Square One BLOCK D

VR INFRATECH · Medchal-Malkajgiri · RERA P02200008720

Square One BLOCK D is a residential apartment project in Uppal Bhagayath, Uppal mandal, Medchal-Malkajgiri district, developed by registered promoter VR INFRATECH. The project’s registered site measures 398.83 sq. m.; the RERA filing records one building and 10 homes, configured as 3BHK. It is registered with TG-RERA under P02200008720, with a proposed completion date of 01/06/2026.

More from Vr Infratech · 4 projects →

01What we found

Period endedTG-RERA registration ran to 1 Jun 2026 - check its extension on TG-RERA
15documents on file - each fact links to its page
9court cases on this project's land (survey 1, 282, Uppal)
12items to check - 6 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

12 items to check before you pay, 6 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

1. Project at a glance

Project identity

FieldProject record
Registered project nameSquare One BLOCK D RERA record
Project typeResidential apartment project RERA record RERA filing
Phase / registered portionBlock D is the TG-RERA registered project; the supplied records describe one building. RERA record
TG-RERA registration numberP02200008720 RERA record
Registration validity28 August 2024 to 1 June 2026, as stated on the registration certificate. Validity is distinct from the completion date. RERA record
Registered promoterVR INFRATECH (also rendered “Vr Infratech” / “VR INFRA TECH” in filed documents) RERA record
RERA statusRegistered; the record identifies the project as “New Project.” No extension is evidenced in the supplied data. RERA record RERA filing

Land and geographic identity

FieldProject record
LocalityUppal Bhagayath / Uppal Bagayath; registered location is shown as Uppal Bhagyath. RERA record RERA filing
Revenue villageUppal; the building-plan and architect-certificate records also use Uppal Bhagayath Village. RERA record
MandalUppal RERA record
DistrictMedchal-Malkajgiri RERA record
PIN500039 RERA record
Project survey numbers and subdivisions, as recorded1 TO 40, 282 TO 368, 369P, 370 TO 373, 374P, 375 TO 387, 395 TO 401, 454, 456 TO 459, 505P, 510 TO 564 RERA filing
Site descriptionPlot No. 880 South-West Part (Block-A), as described in the supplied building-plan record. RERA filing
Registered site extent398.83 sq. m RERA filing
Total / net site areaTotal: 398.83 sq. m; net: 398.83 sq. m in the RERA land record and building-permit extraction. RERA filing
Boundaries in RERA land recordNorth: Plot No. 880 Block-B; south: Plot No. 879; east: eastern part of Plot No. 880; west: 40 ft wide road. RERA filing

Development identity

FieldProject record
Sanctioning authorityGreater Hyderabad Municipal Corporation (GHMC) Approvals record
Principal building-permit reference1716/GHMC/LBN/2023-BP, dated 1 June 2023 Approvals record
Other building-permit reference171/ENG/TP10/GHMC/2020-25, approved date recorded as 25 April 2023; application / permit number TS/029235/2023 Approvals record
Approved built-up area1,196.50 sq. m residential upper floors; 1,435.80 sq. m total proposed built-up area including parking, according to the supplied plan extraction.
Building countOne proposed residential building is identified for the registered project. RERA filing
Sanctioned floor configuration1 stilt + 5 upper floors; the plan describes stilt, first, second, third, fourth and fifth floors.
Building height14.95 m in the sanctioned-plan extraction.
Parking in plan recordStilt parking is referenced; the plan extraction records 10 under “TNMTS. PARKING” and 239.30 sq. m parking area, while “PROPOSED NUMBER OF PARKINGS” is recorded as 0. The source labels are reproduced as recorded; a reliable car-space count is not established here.
Unit count10 in the TG-RERA unit record and layout-plan extraction; the building-plan extraction also states 10 units. RERA unit table

Offering and status

FieldProject record
RERA-filed configuration3BHK; 10 units RERA unit table
RERA-filed saleable area75.25 sq. m per unit RERA unit table
Booked / available0 booked / 10 available in the portal-derived record; no as-of date is supplied, so counts are indicative. RERA unit table
Construction stageAn architect’s Form F1 reports 60% excavation and 0% for several listed activities. This is a filed progress certificate, not independent site verification.
Completion date1 June 2026, recorded as the proposed completion date and in the promoter’s Form B completion undertaking. RERA record
Occupancy / completion certificateNo occupancy or completion certificate is evidenced in the supplied documents. The Form F1 is not an OC or completion certificate.

2. The project story

Square One BLOCK D is registered as a residential apartment project in Uppal, with one building on a recorded site of 398.83 sq. m. Its sanctioned configuration is one stilt level with five upper floors; the RERA unit record lists ten 3BHK apartments. RERA record RERA filing RERA unit table

The filed architect’s progress certificate describes excavation at 60% and several other listed activities at 0%. Those percentages are the architect’s filed report; they do not establish independently inspected or verified site progress. The supplied record gives a proposed completion date of 1 June 2026, but contains no OC or completion certificate. RERA record

3. Master plan, architecture & building design

The supplied GHMC building-permit records identify a single residential building on a 398.83 sq. m plot, configured as 1 stilt + 5 upper floors, with a recorded height of 14.95 m. The plan extraction lists 1,196.50 sq. m as net residential built-up area and 1,435.80 sq. m as total proposed built-up area including parking. These are distinct plan-record figures; neither is a carpet-area figure.

The plan identifies Plot No. 880 South-West Part (Block-A), and lists road references of 12.00 MT wide existing road, 12.00 MT wide proposed road, 40' wide road and 80' wide road. The supplied evidence does not establish the building footprint dimensions, flats per floor, lift count, stair arrangement, internal circulation details, or a site-wide phase layout.

The plan includes a tot-lot, perimeter greenery and rainwater-harvesting structure among its conditions and provisions. These are plan-recorded requirements or features, not evidence that they have been completed.

4. Homes, configurations & floor plans

The TG-RERA unit record lists ten 3BHK units, all shown as available and none as booked at the portal-record snapshot; that snapshot has no stated as-of date. RERA saleable area is 75.25 sq. m per unit. RERA unit table

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
3BHK1001075.25 sq. mNot established from the supplied floor-plan measurementsNot supplied

The supplied floor-plan processing record reports two drawings reviewed but zero measured flat designs for 3BHK. Accordingly, no drawing-based carpet area, room dimensions or floor-plan arrangement can be stated. Saleable area is the RERA-filed unit-area figure; it should not be read as a measured carpet area. Floor plans RERA unit details RERA unit table

5. Parking & vehicle circulation

The building-plan record refers to stilt parking and states that stilt areas approved for parking are to be used for vehicles only. Its extracted parameters list 239.30 sq. m parking area and 10 under “TNMTS. PARKING,” but also record “PROPOSED NUMBER OF PARKINGS” as 0. The available extracted labels do not establish a dependable number of car spaces, visitor or accessible spaces, or any unit-specific parking allocation.

The plan provides for one entry and one exit, each with a minimum width of 4.5 m and height clearance of 5 m. No evidence supplied establishes a ramp arrangement, EV charging, pedestrian/vehicle separation or exclusive parking ownership for a particular apartment.

6. Amenities, recreation & open spaces

The TG-RERA amenity record lists 14 items and records 0% progress for each. “YES” denotes availability in the filing record where shown; it does not establish completion. The building-plan record also contains conditions relating to a tot-lot, greenery and building services. RERA amenities

FacilityDescription / sizeEvidence sourceDeclared progress / verified status
Green strip / tot-lot / parkGreenery and tot-lot identified; no size supplied. The plan requires the tot-lot to be fenced and maintained as greenery.RERA amenity record; GHMC plan RERA amenitiesRERA record: 0%; completion not independently verified.
Community buildingsNo further description or size supplied.RERA amenity record RERA amenities0%; completion not independently verified.
Aggregate recreational open spaceArea not supplied.RERA amenity record RERA amenities0%; completion not independently verified.
Internal roads and footpathsNo further details supplied.RERA amenity record RERA amenities0%; completion not independently verified.
Street lightingNo further details supplied.RERA amenity record RERA amenities0%; completion not independently verified.

7. Utilities, building services & safety

The RERA amenity record marks water supply, sewerage (chambers, lines, septic tank/STP), rainwater harvesting and electrical meter room/substation/receiving station as “YES,” but reports 0% progress for the listed amenities. The architect’s certificate also lists water supply, sewerage, landscaping/tree planting, rainwater harvesting and an electrical meter room/substation/receiving station. These are filed disclosures, not confirmation of completed or operational services. RERA amenities

The GHMC plan records requirements or provisions for a rainwater-harvesting structure, transformer space, garbage house, generator, emergency lighting, fire-fighting installations, hose reel/down corner, fire extinguishers, alarm system, underground and terrace water tanks, and automatic sprinklers if basement area exceeds 200 sq. m. The plan states tank capacities of 25,000 litres for the underground static water tank and 25,000 litres for the residential terrace tank. These are plan provisions and conditions; supplied records do not verify installation, operational status, lift capacity, accessibility features, or completion of fire-safety measures.

8. Location, access & connectivity

The registered location is Uppal, Uppal Mandal, Medchal-Malkajgiri District, PIN 500039; the filed building and architect records refer to Uppal Bhagayath / Uppal Bagayath Village. The plan locates the site under Uppal Circle, LB. Nagar Zone, GHMC, Telangana. RERA record

The building-plan extraction lists 12.00 MT wide existing road, 12.00 MT wide proposed road, 40' wide road and 80' wide road. The location data supplies one distance: Financial District (Nanakramguda), 2.0 km, measured from the cadastral parcel centroid. The supplied data does not describe public-transport links or other verified landmark distances. Location record

9. Developer & development status

The registered promoter is VR INFRATECH, recorded as a partnership, with GSTIN 36AATFV7222N1ZC. The promoter record names MUKKA HARI CHARAN as authorized signatory. The supplied registered-address record is Flat No. 405, Mayfair Gardens, Road No. 12, Uppal Bhagyath, Uppal, Medchal-Malkajgiri, PIN 500039. RERA record Corporate record Parties record

The Form B declaration dated 3 July 2024 states a completion undertaking of 1 June 2026 and makes declarations concerning land title, encumbrances, project funds and approvals. These are promoter declarations. The filed architect’s Form F1 reports construction progress, but is not an independent site inspection. No occupancy certificate or completion certificate is included in the supplied project documents.

10. Approvals, official records & documents

RecordSupplied evidence
TG-RERA registrationForm C certificate for Square One BLOCK D, registration P02200008720; validity stated as 28 August 2024 to 1 June 2026.
GHMC building permitBuilding Permit Order 1716/GHMC/LBN/2023-BP, dated 1 June 2023; the extraction identifies one residential building with 1 stilt + 5 upper floors.
Additional GHMC plan reference171/ENG/TP10/GHMC/2020-25; application/permit TS/029235/2023, dated 25 April 2023 in the supplied plan extraction.
Layout / drawing recordSupplied plan document identifies the building proposal and plot description; a separate approved-layout certificate is not established by the supplied material.
Architect’s progress certificateForm F1 for Square One BLOCK D, identifying the project registration number and reporting construction progress; not an approval or OC.
Promoter declarationForm B affidavit dated 3 July 2024, including the promoter’s stated completion date and project undertakings.
Occupancy / completion certificateNot evidenced in the supplied documents. Document index

Other registrations of Square One

Frequently asked questions

Is Square One BLOCK D registered with Telangana RERA?

Yes. Square One BLOCK D is registered with the Telangana Real Estate Regulatory Authority as P02200008720; the registration status is New Project.

Who is the developer of Square One BLOCK D?

The promoter named in the RERA registration is VR INFRATECH.

Where is Square One BLOCK D located?

Square One BLOCK D is in UPPAL BHAGYATH, Uppal, Medchal-Malkajgiri, Telangana (500039).

When will Square One BLOCK D be completed?

The promoter's proposed date of completion filed with RERA is 01/06/2026. This is the promoter's declaration, not a guarantee.