Rl City Pragathi Nagar
SRI RL CONSTRUCTIONS · Medchal-Malkajgiri · RERA P02200001983
RL CITY PRAGATHI NAGAR is a residential apartment project in Pragathi Nagar, Bachupally mandal, Medchal-Malkajgiri district, developed by registered promoter SRI RL CONSTRUCTIONS. It is on a site of 1,337.62 sq. m and comprises one residential building with 1 Stilt + 5 Upper floors and 30 apartments: 25 2BHK and 5 3BHK. The project is registered with TG-RERA under P02200001983, with proposed completion on 31/08/2020.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
10 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Item | RERA-filed / recorded detail |
|---|---|
| Registered project name | RL CITY PRAGATHI NAGAR |
| Project type | Residential apartment project |
| Phase / registered portion | Not separately identified in the supplied record; the registration refers to the project as a whole |
| TG-RERA registration number | P02200001983 |
| Registration validity | 06/07/2020 to 31/08/2020; certificate records no extension |
| Registered promoter | SRI RL CONSTRUCTIONS |
| RERA status | Listed as “New Project” in the project record. The registration certificate’s stated validity ended on 31/08/2020; current registration status is not established by the supplied evidence. |
RERA record RERA filing
Land and geographic identity
| Item | RERA-filed / recorded detail |
|---|---|
| Locality | Pragathi Nagar |
| Revenue village | Project record: Pragathi Nagar; HMDA technical approval and title documents refer to Bachupally Village / Bachpalle Village. The revenue-village identity is not reconciled in the supplied material. |
| Mandal | Bachupally |
| District | Medchal-Malkajgiri |
| PIN | 500090 |
| Survey numbers / subdivisions | 151P (also described in title/approval material as 151 (part) or 151part), 152, 153, 154 and 155 |
| Registered / proposed site extent | 1,337.62 sq. m (also stated as 1,337.62 Sq. Mt. in the HMDA technical approval) |
| Total and net land area | 1,337.62 sq. m total and 1,337.62 sq. m net; recorded affected area is 0. |
| Boundaries | East: 30 FEET WIDE ROAD; West: 40 FEET WIDE ROAD; North: PLOT NOS 5 AND 14; South: PLOT NOS 1 AND 18 |
RERA record RERA filing Land records
Development identity
| Item | Recorded detail |
|---|---|
| Sanctioning authority | Hyderabad Metropolitan Development Authority (HMDA); the technical approval directs the Executive Authority to sanction the building plans in conformity with HMDA’s technically approved plans. |
| Principal approval | 012002/MED/R1/U6/HMDA/24052018, approved 23/08/2019 |
| Approved built-up area | 3,114.58 sq. m (HMDA sanctioned parameter). The same approval extraction separately records Proposed Built-up Area 3,806.44; the supplied record does not explain the relationship between these figures. |
| Building count / configuration | One residential building; 1 Stilt + 5 Upper floors in the HMDA technical-approval extraction. |
| Basement / parking levels | No separate basement or parking level is identified in the supplied record. The HMDA approval states that cellar and stilt areas approved for parking are to be used exclusively for vehicle parking; whether a cellar is included in this project’s final plan is not established here. |
| Units | 30 units in the TG-RERA record: 25 2BHK and 5 3BHK. |
| Mortgage recorded in approval | The HMDA approval extraction identifies 319.17 sq. m as the mortgage area in the project record; the approval’s mortgage description refers to 319.17 sq. m of first-floor built-up area in favour of HMDA. |
RERA record RERA filing RERA unit table Approvals record
Offering and status
| Item | RERA-filed / recorded detail |
|---|---|
| Configurations | 2BHK and 3BHK apartments |
| RERA-filed saleable area | 2BHK: 67.64 sq. m; 3BHK: 165.37 sq. m |
| Booked / available | Portal-derived record shows 0 booked and 25 available 2BHK; 0 booked and 5 available 3BHK. The portal record has no as-of date, so counts are indicative. |
| Construction stage | A project-level completeness figure of 80% is recorded, but no dated site inspection or independently verified construction assessment is supplied. |
| Completion dates | Project record gives proposed completion 31/08/2020. The Form B declaration contains a garbled completion-date entry (“315 August, 2020”); it is not treated as a separate reliable date. |
| Occupancy / completion certificate | No occupancy or completion certificate is included in the supplied evidence. The HMDA approval states that an Occupancy Certificate is compulsory before occupation. |
RERA unit table RERA unit details RERA record
2. The project story
RL CITY PRAGATHI NAGAR is recorded with TG-RERA as a residential apartment project by SRI RL CONSTRUCTIONS, on a stated site extent of 1,337.62 sq. m in the survey-number group 151P, 152, 153, 154 and 155. The record identifies one building, with 1 stilt and 5 upper floors, and a total of 30 apartments: 25 two-bedroom and 5 three-bedroom units. RERA record Land records RERA unit table
TG-RERA’s project data records all 30 units as available and none booked, but does not provide an as-of date for that inventory. The project record also gives 80% completeness; this is a recorded progress figure, not independent confirmation of present site conditions. The stated proposed completion date was 31/08/2020. No occupancy or completion certificate is included in the supplied materials, so the evidence does not establish that the building has been completed or is approved for occupation. RERA unit table RERA unit details RERA record
3. Master plan, architecture & building design
The HMDA technical approval extraction describes one residential building, “1Stilt + 5 Upper floors.” It records an approved built-up area of 3,114.58 sq. m and separately lists “Proposed Built-up Area 3806.44”; the supplied information does not define the measurement basis for the latter figure. No floor-by-floor plans, building footprint, flats-per-floor schedule, lift or stair details, or detailed circulation drawings are available in the supplied evidence.
The registered site extent is 1,337.62 sq. m, with the same total and net area and recorded affected area of zero. The HMDA approval refers to a 10% mortgage area and records 476.73 as provided in its sanctioned parameters; its mortgage detail separately describes 319.17 sq. m on the first floor under registered mortgage document 8024/2019. These are approval-record details, not a description of unit ownership or saleable area. Land records
The supplied floor-plan data contains two drawings, but neither has measured units; no software-measured carpet areas or room dimensions are available. The approval calls for a transformer, garbage house, rainwater-harvesting structure (percolation pit) and ETP, but the supplied evidence does not establish their completed condition. Floor plans
4. Homes, configurations & floor plans
TG-RERA’s unit record identifies 30 apartments in two configurations. The floor-plan files supplied for review do not yield measured carpet areas or room layouts, so no drawing-based measurements are reported.
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK | 25 | 0 | 25 | 67.64 sq. m | Not available | Not supplied |
| 3BHK | 5 | 0 | 5 | 165.37 sq. m | Not available | Not supplied |
Booked and available counts are portal-derived and have no stated as-of date. RERA-filed saleable area is distinct from carpet area; no carpet-area figure or loading figure is supplied. The drawing set contains two plans, but the supplied drawing review records zero measured plans and no room measurements. RERA unit table RERA unit details Floor plans
5. Parking & vehicle circulation
The HMDA approval describes the stilt as a parking area and states that cellar and stilt areas approved for parking must remain exclusively for vehicle parking, without partitions or other use. It also requires one entry and one exit with a minimum width of 4.5 m and a height clearance of 5 m. The supplied evidence does not state the sanctioned number of car or two-wheeler spaces, identify visitor or accessible spaces, or establish any unit-specific parking allocation. A drawn or designated parking bay would not, on this evidence alone, establish exclusive ownership.
6. Amenities, recreation & open spaces
The TG-RERA amenity record includes project infrastructure and open-space categories. Its progress percentages are recorded disclosures; the supplied evidence does not independently verify completion.
| Description / size | Green strip / tot lot / park; no size supplied |
|---|---|
| Evidence source | RERA amenity record; HMDA approval conditions |
| Declared progress / verified status | 85% recorded; not independently verified. HMDA approval calls for a fenced tot lot and maintained greenery before occupancy. |
| Description / size | No size or configuration supplied |
|---|---|
| Evidence source | RERA amenity record |
| Declared progress / verified status | 50% recorded; not independently verified. |
| Description / size | No capacity or size supplied |
|---|---|
| Evidence source | RERA amenity record |
| Declared progress / verified status | “YES”; 45% recorded; not independently verified. |
| Description / size | Details not supplied |
|---|---|
| Evidence source | RERA amenity record |
| Declared progress / verified status | “YES”; 50% recorded; not independently verified. |
| Description / size | The record lists these components as a category; no capacity or installed configuration is supplied |
|---|---|
| Evidence source | RERA amenity record |
| Declared progress / verified status | “YES”; 50% recorded; not independently verified. |
| Description / size | No source, storage capacity or treatment details supplied |
|---|---|
| Evidence source | RERA amenity record |
| Declared progress / verified status | “YES”; 0% recorded; not independently verified. |
| Description / size | No extent or specification supplied |
|---|---|
| Evidence source | RERA amenity record |
| Declared progress / verified status | “YES”; 40% recorded; not independently verified. |
| Description / size | HMDA approval calls for a rainwater-harvesting structure (percolation pit); no size supplied |
|---|---|
| Evidence source | RERA amenity record; HMDA approval |
| Declared progress / verified status | “YES”; 0% recorded in the amenity record; not independently verified. |
The amenity record also lists fire protection and fire safety, internal roads and footpaths, storm-water drains, community buildings, treatment and disposal of sewage and sullage water, and solid-waste management and disposal, but records 0% progress for each and gives no facility dimensions or capacities. RERA amenities
7. Utilities, building services & safety
The HMDA technical approval sets out project conditions for water, sewerage, electrical and fire-safety provisions, but the supplied record does not establish that these facilities have been installed, tested or accepted. The RERA amenity record lists water supply and sewerage infrastructure, while giving recorded progress of 0% and 50%, respectively; these figures are not independent site verification. RERA amenities
- Water and sewerage: Approval conditions refer to water-source and sewerage-disposal locations, treatment and discharge arrangements, septic-tank provisions, and a 25,000-litre underground static water tank and 25,000-litre residential terrace tank. The approval also requires rainwater harvesting and refers to an ETP. The supplied record does not confirm completed installation, operational status or service capacities beyond those stated tank capacities.
- Electrical and backup: The approval requires provision for a transformer, a generator as an alternate electricity source, emergency lighting in corridors/common passages and staircases, and electrical fire-safety certification. The RERA record lists an electrical meter room/sub-station/receiving station at 45% progress; installation and commissioning are not independently verified. RERA amenities
- Fire and life safety: The approval specifies fire extinguishers, manual operation and alarm systems, hose reel/down-comer provisions, fire-resistant lift swing doors and an automatic sprinkler system if the basement area exceeds 200 sq. m. It also requires fire-vehicle manoeuvrability through joint open space and prohibits construction or parking in setback areas. The supplied evidence does not establish installed systems, testing, or fire clearance.
- Lifts, access and waste: Lifts are referenced in the approval’s service requirements, but lift count, capacity and service-lift provision are not stated. The approval calls for a garbage house within the premises; its completed status is not established. No accessibility features or accessible circulation details are supplied.
8. Location, access & connectivity
The project record places the site in Pragathi Nagar, Bachupally mandal, Medchal-Malkajgiri district, PIN 500090, on surveys 151P, 152, 153, 154 and 155. The recorded site boundaries identify a 30 FEET WIDE ROAD on the east and a 40 FEET WIDE ROAD on the west. The HMDA technical approval refers to Bachpalle Village, while project and land records use Pragathi Nagar as the village/locality entry; the revenue-village identity is therefore not conclusively established by these supplied records. RERA record Land records
A parcel-centroid location is recorded at 17.41528, 78.35459. The location data lists Financial District (Nanakramguda) at 1.2 km as an anchor. No verified public-transport or travel-time information is supplied. Location record
9. Developer & development status
The registered promoter is SRI RL CONSTRUCTIONS, recorded as a partnership. The partnership deed identifies Talluri Lakshmaiah, Talluri Rama Devi and Nimmagadda Nageswara Babu as partners. The project record names Lakshmaiah Talluri as authorised signatory. The promoter address recorded in the project data is PRASANKA ENCLAVE, PHASE 6, KAKATIYA HILLS PRAGATHI NAGAR ROAD, PRAGATHI NAGAR, Bachupally, Medchal-Malkajgiri, 500090; the RERA certificate separately records the promoter office as Kukatpally, Medchal-Malkajgiri, PIN 500085. RERA filing Corporate record Parties record
The project record gives a completeness figure of 80% and proposed completion date 31/08/2020; no dated, independent site assessment or occupancy/completion certificate is supplied. TG-RERA inventory shows 30 units, all recorded as available, but has no as-of date. These are record disclosures, not confirmation of current construction, sales or possession status. RERA record RERA unit table RERA unit details Document index
10. Approvals, official records & documents
| Record | Supplied evidence |
|---|---|
| TG-RERA registration | Form C for RL CITY PRAGATHI NAGAR, registration P02200001983, issued 06/07/2020; stated validity through 31/08/2020; certificate records no extension. |
| HMDA technical approval | Approval 012002/MED/R1/U6/HMDA/24052018, dated 23/08/2019; technical approval for the residential proposal, with conditions directing local-authority sanction and setting out construction and occupancy requirements. |
| Local-authority building sanction | HMDA approval says plans are to be sanctioned by the Executive Authority in conformity with the technically approved plans. A separate local-authority sanction document is not included in the supplied evidence. |
| Registered mortgage | Mortgage document 8024/2019, dated 1/4/2019, for 319.17 sq. m of first-floor built-up area in favour of the Metropolitan Commissioner, HMDA, as described in the approval extraction. |
| Title and development documents | Advocate’s title search report and title documents are filed, including Development Agreement-cum-General Power of Attorney 8351/2018; a partnership deed is also on file. |
| Promoter declaration | Form B declaration by SRI RL CONSTRUCTIONS, represented by Lakhsmaiah Talluri, dated 10th day of Oct'2019; it contains promoter declarations about title, encumbrances, completion and project obligations. |
| Occupancy / completion certificate | Not present in the supplied documents. HMDA approval states that an Occupancy Certificate is compulsory before occupation. |
The HMDA approval includes conditions concerning approved-plan construction, water and sewerage, rainwater harvesting, fire safety, parking, public display of plans and occupancy certification. This overview records the approval evidence supplied; it does not establish compliance with those conditions or the present status of the local-authority sanction.
1. Project at a glance
Project identity
Registered project name: RL CITY PRAGATHI NAGAR
Project type: Residential apartment project
Phase / registered portion: Not separately identified in the supplied record; the registration refers to the project as a whole
TG-RERA registration number: P02200001983
Registration validity: 06/07/2020 to 31/08/2020; certificate records no extension
Registered promoter: SRI RL CONSTRUCTIONS
RERA status: Listed as “New Project” in the project record. The registration certificate’s stated validity ended on 31/08/2020; current registration status is not established by the supplied evidence.
Land and geographic identity
Locality: Pragathi Nagar
Revenue village: Project record: Pragathi Nagar; HMDA technical approval and title documents refer to Bachupally Village / Bachpalle Village. The revenue-village identity is not reconciled in the supplied material.
Mandal: Bachupally
District: Medchal-Malkajgiri
PIN: 500090
Survey numbers / subdivisions: 151P (also described in title/approval material as 151 (part) or 151part), 152, 153, 154 and 155
Registered / proposed site extent: 1,337.62 sq. m (also stated as 1,337.62 Sq. Mt. in the HMDA technical approval)
Total and net land area: 1,337.62 sq. m total and 1,337.62 sq. m net; recorded affected area is 0.
Boundaries: East: 30 FEET WIDE ROAD; West: 40 FEET WIDE ROAD; North: PLOT NOS 5 AND 14; South: PLOT NOS 1 AND 18
Development identity
Sanctioning authority: Hyderabad Metropolitan Development Authority (HMDA); the technical approval directs the Executive Authority to sanction the building plans in conformity with HMDA’s technically approved plans.
Principal approval: 012002/MED/R1/U6/HMDA/24052018, approved 23/08/2019
Approved built-up area: 3,114.58 sq. m (HMDA sanctioned parameter). The same approval extraction separately records Proposed Built-up Area 3,806.44; the supplied record does not explain the relationship between these figures.
Building count / configuration: One residential building; 1 Stilt + 5 Upper floors in the HMDA technical-approval extraction.
Basement / parking levels: No separate basement or parking level is identified in the supplied record. The HMDA approval states that cellar and stilt areas approved for parking are to be used exclusively for vehicle parking; whether a cellar is included in this project’s final plan is not established here.
Units: 30 units in the TG-RERA record: 25 2BHK and 5 3BHK.
Mortgage recorded in approval: The HMDA approval extraction identifies 319.17 sq. m as the mortgage area in the project record; the approval’s mortgage description refers to 319.17 sq. m of first-floor built-up area in favour of HMDA.
Offering and status
Configurations: 2BHK and 3BHK apartments
RERA-filed saleable area: 2BHK: 67.64 sq. m; 3BHK: 165.37 sq. m
Booked / available: Portal-derived record shows 0 booked and 25 available 2BHK; 0 booked and 5 available 3BHK. The portal record has no as-of date, so counts are indicative.
Construction stage: A project-level completeness figure of 80% is recorded, but no dated site inspection or independently verified construction assessment is supplied.
Completion dates: Project record gives proposed completion 31/08/2020. The Form B declaration contains a garbled completion-date entry (“315 August, 2020”); it is not treated as a separate reliable date.
Occupancy / completion certificate: No occupancy or completion certificate is included in the supplied evidence. The HMDA approval states that an Occupancy Certificate is compulsory before occupation.
2. The project story
RL CITY PRAGATHI NAGAR is recorded with TG-RERA as a residential apartment project by SRI RL CONSTRUCTIONS, on a stated site extent of 1,337.62 sq. m in the survey-number group 151P, 152, 153, 154 and 155. The record identifies one building, with 1 stilt and 5 upper floors, and a total of 30 apartments: 25 two-bedroom and 5 three-bedroom units.
TG-RERA’s project data records all 30 units as available and none booked, but does not provide an as-of date for that inventory. The project record also gives 80% completeness; this is a recorded progress figure, not independent confirmation of present site conditions. The stated proposed completion date was 31/08/2020. No occupancy or completion certificate is included in the supplied materials, so the evidence does not establish that the building has been completed or is approved for occupation.
3. Master plan, architecture & building design
The HMDA technical approval extraction describes one residential building, “1Stilt + 5 Upper floors.” It records an approved built-up area of 3,114.58 sq. m and separately lists “Proposed Built-up Area 3806.44”; the supplied information does not define the measurement basis for the latter figure. No floor-by-floor plans, building footprint, flats-per-floor schedule, lift or stair details, or detailed circulation drawings are available in the supplied evidence.
The registered site extent is 1,337.62 sq. m, with the same total and net area and recorded affected area of zero. The HMDA approval refers to a 10% mortgage area and records 476.73 as provided in its sanctioned parameters; its mortgage detail separately describes 319.17 sq. m on the first floor under registered mortgage document 8024/2019. These are approval-record details, not a description of unit ownership or saleable area.
The supplied floor-plan data contains two drawings, but neither has measured units; no software-measured carpet areas or room dimensions are available. The approval calls for a transformer, garbage house, rainwater-harvesting structure (percolation pit) and ETP, but the supplied evidence does not establish their completed condition.
4. Homes, configurations & floor plans
TG-RERA’s unit record identifies 30 apartments in two configurations. The floor-plan files supplied for review do not yield measured carpet areas or room layouts, so no drawing-based measurements are reported.
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK | 25 | 0 | 25 | 67.64 sq. m | Not available | Not supplied |
| 3BHK | 5 | 0 | 5 | 165.37 sq. m | Not available | Not supplied |
Booked and available counts are portal-derived and have no stated as-of date. RERA-filed saleable area is distinct from carpet area; no carpet-area figure or loading figure is supplied. The drawing set contains two plans, but the supplied drawing review records zero measured plans and no room measurements.
5. Parking & vehicle circulation
The HMDA approval describes the stilt as a parking area and states that cellar and stilt areas approved for parking must remain exclusively for vehicle parking, without partitions or other use. It also requires one entry and one exit with a minimum width of 4.5 m and a height clearance of 5 m. The supplied evidence does not state the sanctioned number of car or two-wheeler spaces, identify visitor or accessible spaces, or establish any unit-specific parking allocation. A drawn or designated parking bay would not, on this evidence alone, establish exclusive ownership.
6. Amenities, recreation & open spaces
The TG-RERA amenity record includes project infrastructure and open-space categories. Its progress percentages are recorded disclosures; the supplied evidence does not independently verify completion.
| Description / size | Green strip / tot lot / park; no size supplied |
|---|---|
| Evidence source | RERA amenity record; HMDA approval conditions |
| Declared progress / verified status | 85% recorded; not independently verified. HMDA approval calls for a fenced tot lot and maintained greenery before occupancy. |
| Description / size | No size or configuration supplied |
|---|---|
| Evidence source | RERA amenity record |
| Declared progress / verified status | 50% recorded; not independently verified. |
| Description / size | No capacity or size supplied |
|---|---|
| Evidence source | RERA amenity record |
| Declared progress / verified status | “YES”; 45% recorded; not independently verified. |
| Description / size | Details not supplied |
|---|---|
| Evidence source | RERA amenity record |
| Declared progress / verified status | “YES”; 50% recorded; not independently verified. |
| Description / size | The record lists these components as a category; no capacity or installed configuration is supplied |
|---|---|
| Evidence source | RERA amenity record |
| Declared progress / verified status | “YES”; 50% recorded; not independently verified. |
| Description / size | No source, storage capacity or treatment details supplied |
|---|---|
| Evidence source | RERA amenity record |
| Declared progress / verified status | “YES”; 0% recorded; not independently verified. |
| Description / size | No extent or specification supplied |
|---|---|
| Evidence source | RERA amenity record |
| Declared progress / verified status | “YES”; 40% recorded; not independently verified. |
| Description / size | HMDA approval calls for a rainwater-harvesting structure (percolation pit); no size supplied |
|---|---|
| Evidence source | RERA amenity record; HMDA approval |
| Declared progress / verified status | “YES”; 0% recorded in the amenity record; not independently verified. |
The amenity record also lists fire protection and fire safety, internal roads and footpaths, storm-water drains, community buildings, treatment and disposal of sewage and sullage water, and solid-waste management and disposal, but records 0% progress for each and gives no facility dimensions or capacities.
7. Utilities, building services & safety
The HMDA technical approval sets out project conditions for water, sewerage, electrical and fire-safety provisions, but the supplied record does not establish that these facilities have been installed, tested or accepted. The RERA amenity record lists water supply and sewerage infrastructure, while giving recorded progress of 0% and 50%, respectively; these figures are not independent site verification.
- Water and sewerage: Approval conditions refer to water-source and sewerage-disposal locations, treatment and discharge arrangements, septic-tank provisions, and a 25,000-litre underground static water tank and 25,000-litre residential terrace tank. The approval also requires rainwater harvesting and refers to an ETP. The supplied record does not confirm completed installation, operational status or service capacities beyond those stated tank capacities.
- Electrical and backup: The approval requires provision for a transformer, a generator as an alternate electricity source, emergency lighting in corridors/common passages and staircases, and electrical fire-safety certification. The RERA record lists an electrical meter room/sub-station/receiving station at 45% progress; installation and commissioning are not independently verified.
- Fire and life safety: The approval specifies fire extinguishers, manual operation and alarm systems, hose reel/down-comer provisions, fire-resistant lift swing doors and an automatic sprinkler system if the basement area exceeds 200 sq. m. It also requires fire-vehicle manoeuvrability through joint open space and prohibits construction or parking in setback areas. The supplied evidence does not establish installed systems, testing, or fire clearance.
- Lifts, access and waste: Lifts are referenced in the approval’s service requirements, but lift count, capacity and service-lift provision are not stated. The approval calls for a garbage house within the premises; its completed status is not established. No accessibility features or accessible circulation details are supplied.
8. Location, access & connectivity
The project record places the site in Pragathi Nagar, Bachupally mandal, Medchal-Malkajgiri district, PIN 500090, on surveys 151P, 152, 153, 154 and 155. The recorded site boundaries identify a 30 FEET WIDE ROAD on the east and a 40 FEET WIDE ROAD on the west. The HMDA technical approval refers to Bachpalle Village, while project and land records use Pragathi Nagar as the village/locality entry; the revenue-village identity is therefore not conclusively established by these supplied records.
A parcel-centroid location is recorded at 17.41528, 78.35459. The location data lists Financial District (Nanakramguda) at 1.2 km as an anchor. No verified public-transport or travel-time information is supplied.
9. Developer & development status
The registered promoter is SRI RL CONSTRUCTIONS, recorded as a partnership. The partnership deed identifies Talluri Lakshmaiah, Talluri Rama Devi and Nimmagadda Nageswara Babu as partners. The project record names Lakshmaiah Talluri as authorised signatory. The promoter address recorded in the project data is PRASANKA ENCLAVE, PHASE 6, KAKATIYA HILLS PRAGATHI NAGAR ROAD, PRAGATHI NAGAR, Bachupally, Medchal-Malkajgiri, 500090; the RERA certificate separately records the promoter office as Kukatpally, Medchal-Malkajgiri, PIN 500085.
The project record gives a completeness figure of 80% and proposed completion date 31/08/2020; no dated, independent site assessment or occupancy/completion certificate is supplied. TG-RERA inventory shows 30 units, all recorded as available, but has no as-of date. These are record disclosures, not confirmation of current construction, sales or possession status.
10. Approvals, official records & documents
TG-RERA registration: Form C for RL CITY PRAGATHI NAGAR, registration P02200001983, issued 06/07/2020; stated validity through 31/08/2020; certificate records no extension.
HMDA technical approval: Approval 012002/MED/R1/U6/HMDA/24052018, dated 23/08/2019; technical approval for the residential proposal, with conditions directing local-authority sanction and setting out construction and occupancy requirements.
Local-authority building sanction: HMDA approval says plans are to be sanctioned by the Executive Authority in conformity with the technically approved plans. A separate local-authority sanction document is not included in the supplied evidence.
Registered mortgage: Mortgage document 8024/2019, dated 1/4/2019, for 319.17 sq. m of first-floor built-up area in favour of the Metropolitan Commissioner, HMDA, as described in the approval extraction.
Title and development documents: Advocate’s title search report and title documents are filed, including Development Agreement-cum-General Power of Attorney 8351/2018; a partnership deed is also on file.
Promoter declaration: Form B declaration by SRI RL CONSTRUCTIONS, represented by Lakhsmaiah Talluri, dated 10th day of Oct'2019; it contains promoter declarations about title, encumbrances, completion and project obligations.
Occupancy / completion certificate: Not present in the supplied documents. HMDA approval states that an Occupancy Certificate is compulsory before occupation.
The HMDA approval includes conditions concerning approved-plan construction, water and sewerage, rainwater harvesting, fire safety, parking, public display of plans and occupancy certification. This overview records the approval evidence supplied; it does not establish compliance with those conditions or the present status of the local-authority sanction.
Frequently asked questions
Is RL CITY PRAGATHI NAGAR registered with Telangana RERA?
Yes. RL CITY PRAGATHI NAGAR is registered with the Telangana Real Estate Regulatory Authority as P02200001983; the registration status is New Project.
Who is the developer of RL CITY PRAGATHI NAGAR?
The promoter named in the RERA registration is SRI RL CONSTRUCTIONS.
Where is RL CITY PRAGATHI NAGAR located?
RL CITY PRAGATHI NAGAR is in PRAGATHI NAGAR, Bachupally, Medchal-Malkajgiri, Telangana (500090).
When will RL CITY PRAGATHI NAGAR be completed?
The promoter's proposed date of completion filed with RERA is 31/08/2020. This is the promoter's declaration, not a guarantee.
More projects in Pragathi Nagar