J. P s EAST WEST RESIDENCY
EAST WEST DEVELOPERS · Medchal-Malkajgiri · RERA P02200002975
J. P s EAST WEST RESIDENCY is a residential apartments project in Kompally, Dundigal Gandimaisamma Mandal, Medchal-Malkajgiri District, developed by EAST WEST DEVELOPERS. The project covers 967.21 sq. m and comprises 1 building with 1 cellar, 1 stilt and 5 upper floors, with 20 homes: 10 2BHK and 10 3BHK. Its TG-RERA registration number is P02200002975, registered from 20/05/2021 to 14/04/2027, and its proposed completion date is 14/08/2027.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
10 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Field | Project record |
|---|---|
| Registered project name | J. P s EAST WEST RESIDENCY RERA record |
| Project type | Residential apartments RERA record RERA filing |
| Phase / registered portion | No separate phase name is disclosed; registration is for the project, with one building recorded RERA record RERA filing |
| TG-RERA registration | P02200002975; registered from 20/05/2021 to 14/04/2027 Approvals record |
| RERA status | New Project; certificate records registration under section 5. The registration term is separate from the project’s completion undertaking. RERA record |
| Registered promoter | EAST WEST DEVELOPERS RERA record Corporate record |
Land and geographic identity
| Field | Project record |
|---|---|
| Locality / revenue village | Kompally / Kompally Village; the HMDA technical approval also spells the village “Kompalle.” RERA record RERA filing |
| Mandal | Dundigal Gandimaisamma RERA record RERA filing |
| District | Medchal-Malkajgiri RERA record RERA filing |
| PIN | 500047 RERA record |
| Survey number(s) / subdivision(s) | Survey No. 150; no subdivision is identified in the supplied project record. Land records |
| Site extent | RERA land details state 967.21 sq. m total and 967.21 sq. m net; affected area is recorded as 0. RERA filing |
| Boundaries as filed | East: Plot No. 357; West: Plot No. 360; North: Road width – 15; South: CTS No. – RERA filing |
| Plot reference | Plot Nos. 358 and 359 RERA filing |
Development identity
| Field | Project record |
|---|---|
| Sanctioning authorities | HMDA technical approval, followed by a Kompally Municipality building permit order Approvals record |
| Principal approval identifiers | HMDA technical approval 024503/MED/R1/U6/HMDA/10062019, dated 16/05/2020; Kompally Municipality building permit 0005/21-22, dated 15.04.2021, File No. 03402/TP/KM/2021 Approvals record |
| Approved built-up area | 2335.85 sq. m in the Kompally Municipality building permit order |
| Buildings / blocks | 1 building is recorded in the RERA land details. RERA filing |
| Sanctioned floor configuration | HMDA technical approval: 1 cellar + 1 stilt + 5 upper floors. The municipal permit records “Residential 5.” |
| Parking levels / area | Municipal permit records cellar and stilt parking area of 1066.94 sq. m; the HMDA approval says the cellar and stilt are for parking. Parking-space count is not stated. |
| Units | 20 RERA-filed units: 10 2BHK and 10 3BHK. The filed building-unit count is 1; the record does not state a separate approved apartment count in the supplied sanction extracts. RERA unit table RERA unit table RERA filing |
Offering and status
| Field | Project record |
|---|---|
| Configurations | 2BHK and 3BHK RERA unit table |
| RERA-filed saleable areas | 2BHK: 43.81 sq. m; 3BHK: 59.24 sq. m RERA unit table |
| Booked / available | Portal-read figures: 2BHK 0 booked / 10 available; 3BHK 0 booked / 10 available. The portal record has no as-of date, so these counts are indicative. RERA unit table RERA unit table |
| Construction stage | No verified construction-progress percentage or site-stage report is supplied. The listed amenity progress figures are 0%; they do not establish overall construction progress. RERA amenities |
| Completion dates | RERA Form B records a promoter completion undertaking of 15/04/2026; the project header gives proposed completion 14/08/2027. RERA record |
| Registration validity | 14/04/2027 is the certificate’s registration end date; it is not itself a construction completion date. |
| Occupancy / completion certificate | No occupancy or completion certificate is included in the supplied records. The HMDA approval states an Occupancy Certificate is compulsory before occupation. Document index |
The project record identifies one residential apartment building on Plot Nos. 358 and 359 in Survey No. 150, Kompally Village. RERA records 20 homes across two configurations. The project’s declared completion timing and the registration validity are separate matters; the supplied documents do not establish that construction is complete or that an occupancy certificate has been issued. RERA record Land records RERA unit table
2. The project story
J. P s EAST WEST RESIDENCY is registered as a residential apartment project in Kompally Village, Dundigal Gandimaisamma Mandal, Medchal-Malkajgiri District. The project land record identifies Survey No. 150, Plot Nos. 358 and 359, and a site extent of 967.21 sq. m. The recorded boundaries are Plot No. 357 to the east, Plot No. 360 to the west, a road of width 15 to the north, and an unspecified CTS reference to the south. RERA record RERA filing
The project’s filing describes one building and 20 apartments: ten 2BHK and ten 3BHK homes. The HMDA technical approval describes a cellar, stilt and five upper floors; the municipal building permit records a five-level residential building and cellar/stilt parking. These are descriptions in the approval documents, not independent confirmation of the building’s present physical condition. RERA filing RERA unit table
No construction-progress evidence, completion certificate or occupancy certificate is supplied. Accordingly, the current completion stage and whether any part is ready for occupation cannot be established from this record. The promoter’s Form B states a completion undertaking date of 15/04/2026; the project header records a proposed completion date of 14/08/2027. RERA amenities Document index RERA record
3. Master plan, architecture & building design
The RERA filing records a total and net site area of 967.21 sq. m, an approved built-up area of 2335.85 sq. m, and one building. The Kompally Municipality permit records a 50.54 “Tot-lot” area, while its road-affected-area field is illegible; these are figures as recorded in the permit extract. RERA filing
The HMDA technical approval describes 1 cellar + 1 stilt + 5 upper floors. The municipal permit records a residential building of five levels and a cellar-plus-stilt area of 1066.94 sq. m, identified as parking area. The HMDA document also records a building height of 14.2; its unit is not shown in the supplied extracted parameter text.
The available extracts do not establish the building footprint, apartments per floor, lift or stair layout, entry and exit arrangement, internal circulation, landscaping plan, or residential/common-area allocation. A separate proposed-building-plan file is present, but its extracted text does not provide a readable approval decision or usable design detail. The floor-plan drawings have not been software-measured: two drawings are recorded, with zero measured and two scans pending. Floor plans
4. Homes, configurations & floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK | 10 | 0 | 10 | 43.81 sq. m | Not available; drawings pending measurement | Not supplied |
| 3BHK | 10 | 0 | 10 | 59.24 sq. m | Not available; drawings pending measurement | Not supplied |
The unit counts, booking figures and saleable areas above are from the RERA-filed unit record. Booked and available counts are a portal read without an as-of date and should be treated as indicative. RERA unit table RERA unit table
No software-measured carpet areas or room dimensions are available: the two drawing records remain scans pending measurement. RERA saleable area is reported separately from carpet area; the supplied evidence does not provide a carpet-area figure or a quantified common-area loading for either configuration. Floor plans RERA unit details
5. Parking & vehicle circulation
The municipal building permit records 1066.94 sq. m as parking area for the cellar and stilt. The HMDA technical approval states that the cellar and stilt approved for parking are to be used exclusively for vehicle parking and not converted or misused for another purpose.
The supplied records do not establish the number of car or two-wheeler spaces, visitor or accessible spaces, parking allocation to individual homes, ramp design, internal driveway arrangement, pedestrian separation or EV-charging provision. A parking-space ratio cannot be stated from the available evidence.
6. Amenities, recreation & open spaces
The RERA amenities record lists 14 project infrastructure and facility items. Listed progress is 0% for each item; the record does not establish independent completion. The building permit separately requires transformer and garbage-house provision, and the HMDA approval refers to rainwater-harvesting structures. RERA amenities
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Internal Roads & Footpaths | Size not stated | RERA amenities filing RERA amenities | 0%; not independently verified |
| Green Strip / TOT LOT / Park | Municipal permit records TOT LOT 50.54; unit not shown in the extract | RERA amenities filing RERA amenities; building permit | RERA amenity progress 0%; completion not verified |
| Community Buildings | No further description or size supplied | RERA amenities filing RERA amenities | 0%; not independently verified |
| Water Supply | Listed as available: YES; details not supplied | RERA amenities filing RERA amenities | Progress recorded as 0%; completion not verified |
| Sewerage, chambers, lines, septic tank / STP | Listed as available: YES; facility details not supplied | RERA amenities filing RERA amenities | Progress recorded as 0%; completion not verified |
| Treatment and disposal of sewage and sullage water | Size and system details not supplied | RERA amenities filing RERA amenities | 0%; not independently verified |
| Storm-water drains | Details not supplied | RERA amenities filing RERA amenities | 0%; not independently verified |
| Water conservation / rainwater harvesting | Listed as available: YES; HMDA approval also requires rainwater-harvesting structures | RERA amenities filing RERA amenities | Progress recorded as 0%; completion not verified |
| Solid-waste management and disposal | Details not supplied; building permit also provides for a garbage house | RERA amenities filing RERA amenities | 0%; not independently verified |
| Street lighting | Details not supplied | RERA amenities filing RERA amenities | 0%; not independently verified |
| Energy management | Details not supplied | RERA amenities filing RERA amenities | 0%; not independently verified |
| Electrical meter room / sub-station / receiving station | Listed as available: YES; building permit also requires transformer provision | RERA amenities filing RERA amenities | Progress recorded as 0%; completion not verified |
| Fire protection and fire-safety requirements | Specific systems and capacities not supplied | RERA amenities filing RERA amenities | 0%; not independently verified |
| Aggregate recreational open space | Area not supplied | RERA amenities filing RERA amenities | 0%; not independently verified |
7. Utilities, building services & safety
Water and drainage: The RERA amenities record lists water supply, sewerage and storm-water drains; it also lists water conservation and rainwater harvesting. It does not provide water sources, storage or treatment capacities, STP capacity, reuse arrangements or drainage design. The HMDA approval requires rainwater-harvesting structures. RERA amenities
Electrical and waste: The RERA record lists an electrical meter room/sub-station/receiving station, and the municipal permit requires transformer and garbage-house provision. No supply capacity, backup system, waste-segregation arrangement or operating status is supplied. RERA amenities
Vertical transport, fire safety and accessibility: No lift information, lift capacity, service lift, escape-stair details, fire-system specifications, accessibility features, CCTV or access-control details are established by the supplied project filing and approval extracts. The RERA amenities record lists fire protection and fire-safety requirements, but provides no system details or evidence of completion. RERA amenities
8. Location, access & connectivity
The registered location is Kompally Village, Dundigal Gandimaisamma Mandal, Medchal-Malkajgiri District, PIN 500047. The project land record identifies a road of width 15 along the north boundary; the supplied record does not identify that road by name. RERA record RERA filing
No project-specific road-network description, public-transport service details or measured distances to landmarks are supplied in the RERA location evidence. The available location record contains coordinates labelled as a “cadastral parcel centroid,” but does not establish the project’s access route or nearby connectivity. Location record
9. Developer & development status
The registered promoter is EAST WEST DEVELOPERS, recorded as a partnership. Its GSTIN is 36AACFE3657K2Z8. The project filing names DANNAMANENI PRAVEEN RAO as authorized signatory and lists BOORLA AMARNATH and SARIDENA KRISHNA as partners. RERA record Corporate record Parties record
The registration certificate gives the promoter’s office as “Village: Mandal: District: Hyderabad, Pin: 500076,” without village or mandal names in the supplied extract. The project address is separately recorded as B, Karthikeya Nagar, Kompally Village, Dundigal Gandimaisamma, Medchal-Malkajgiri, 500047. Parties record
The promoter’s Form B declares a completion undertaking date of 15/04/2026. The project header records 14/08/2027 as the proposed completion date. No independent construction-progress evidence or occupancy/completion certificate is supplied. TG-RERA registration is recorded through 14/04/2027; that validity date is distinct from the completion dates. RERA record Document index
10. Approvals, official records & documents
| Record | What the supplied evidence shows |
|---|---|
| TG-RERA registration certificate | Form C records project J. P s EAST WEST RESIDENCY, registration P02200002975, issued 20/05/2021, valid through 14/04/2027; it identifies Survey No. 150 and Plot Nos. 358 and 359. |
| HMDA technical approval | HMDA technical approval 024503/MED/R1/U6/HMDA/10062019, dated 16/05/2020, for a residential building on Survey No. 150; extract describes 1 cellar, 1 stilt and 5 upper floors. |
| Kompally Municipality building permit | Permit 0005/21-22, File No. 03402/TP/KM/2021, dated 15.04.2021; records a residential building with approved built-up area 2335.85 sq. m. |
| RERA-filed title / development document | Development Agreement Cum General Power of Attorney dated 21 March 2020, filed as document 166987, for development of Plot Nos. 358 and 359 in Survey No. 150. |
| RERA-filed title report | Sale deed material filed as document 166999, relating to Plot Nos. 358 and 359 in Survey No. 150. |
| Form B promoter declaration | Document 166996 records the promoter’s declarations, including its completion undertaking date of 15/04/2026. |
| Proposed building plan | Document 166991 is described as a proposed building plan; the supplied extraction does not show a readable approval decision. |
| Occupancy / completion certificate | None supplied in the reviewed project documents. Document index |
| Location and project-specific official records | The supplied location record provides a cadastral parcel-centroid label but no measured connectivity distances. The HMDA master-plan land-use sheet could not be confidently assigned, and the public HMDA DPMS approved-layout lookup is recorded as unavailable. Location record HMDA |
1. Project at a glance
Project identity
Registered project name: J. P s EAST WEST RESIDENCY
Project type: Residential apartments
Phase / registered portion: No separate phase name is disclosed; registration is for the project, with one building recorded
TG-RERA registration: P02200002975; registered from 20/05/2021 to 14/04/2027
RERA status: New Project; certificate records registration under section 5. The registration term is separate from the project’s completion undertaking.
Registered promoter: EAST WEST DEVELOPERS
Land and geographic identity
Locality / revenue village: Kompally / Kompally Village; the HMDA technical approval also spells the village “Kompalle.”
Mandal: Dundigal Gandimaisamma
District: Medchal-Malkajgiri
PIN: 500047
Survey number(s) / subdivision(s): Survey No. 150; no subdivision is identified in the supplied project record.
Site extent: RERA land details state 967.21 sq. m total and 967.21 sq. m net; affected area is recorded as 0.
Boundaries as filed: East: Plot No. 357; West: Plot No. 360; North: Road width – 15; South: CTS No. –
Plot reference: Plot Nos. 358 and 359
Development identity
Sanctioning authorities: HMDA technical approval, followed by a Kompally Municipality building permit order
Principal approval identifiers: HMDA technical approval 024503/MED/R1/U6/HMDA/10062019, dated 16/05/2020; Kompally Municipality building permit 0005/21-22, dated 15.04.2021, File No. 03402/TP/KM/2021
Approved built-up area: 2335.85 sq. m in the Kompally Municipality building permit order
Buildings / blocks: 1 building is recorded in the RERA land details.
Sanctioned floor configuration: HMDA technical approval: 1 cellar + 1 stilt + 5 upper floors. The municipal permit records “Residential 5.”
Parking levels / area: Municipal permit records cellar and stilt parking area of 1066.94 sq. m; the HMDA approval says the cellar and stilt are for parking. Parking-space count is not stated.
Units: 20 RERA-filed units: 10 2BHK and 10 3BHK. The filed building-unit count is 1; the record does not state a separate approved apartment count in the supplied sanction extracts.
Offering and status
Configurations: 2BHK and 3BHK
RERA-filed saleable areas: 2BHK: 43.81 sq. m; 3BHK: 59.24 sq. m
Booked / available: Portal-read figures: 2BHK 0 booked / 10 available; 3BHK 0 booked / 10 available. The portal record has no as-of date, so these counts are indicative.
Construction stage: No verified construction-progress percentage or site-stage report is supplied. The listed amenity progress figures are 0%; they do not establish overall construction progress.
Completion dates: RERA Form B records a promoter completion undertaking of 15/04/2026; the project header gives proposed completion 14/08/2027.
Registration validity: 14/04/2027 is the certificate’s registration end date; it is not itself a construction completion date.
Occupancy / completion certificate: No occupancy or completion certificate is included in the supplied records. The HMDA approval states an Occupancy Certificate is compulsory before occupation.
The project record identifies one residential apartment building on Plot Nos. 358 and 359 in Survey No. 150, Kompally Village. RERA records 20 homes across two configurations. The project’s declared completion timing and the registration validity are separate matters; the supplied documents do not establish that construction is complete or that an occupancy certificate has been issued.
2. The project story
J. P s EAST WEST RESIDENCY is registered as a residential apartment project in Kompally Village, Dundigal Gandimaisamma Mandal, Medchal-Malkajgiri District. The project land record identifies Survey No. 150, Plot Nos. 358 and 359, and a site extent of 967.21 sq. m. The recorded boundaries are Plot No. 357 to the east, Plot No. 360 to the west, a road of width 15 to the north, and an unspecified CTS reference to the south.
The project’s filing describes one building and 20 apartments: ten 2BHK and ten 3BHK homes. The HMDA technical approval describes a cellar, stilt and five upper floors; the municipal building permit records a five-level residential building and cellar/stilt parking. These are descriptions in the approval documents, not independent confirmation of the building’s present physical condition.
No construction-progress evidence, completion certificate or occupancy certificate is supplied. Accordingly, the current completion stage and whether any part is ready for occupation cannot be established from this record. The promoter’s Form B states a completion undertaking date of 15/04/2026; the project header records a proposed completion date of 14/08/2027.
3. Master plan, architecture & building design
The RERA filing records a total and net site area of 967.21 sq. m, an approved built-up area of 2335.85 sq. m, and one building. The Kompally Municipality permit records a 50.54 “Tot-lot” area, while its road-affected-area field is illegible; these are figures as recorded in the permit extract.
The HMDA technical approval describes 1 cellar + 1 stilt + 5 upper floors. The municipal permit records a residential building of five levels and a cellar-plus-stilt area of 1066.94 sq. m, identified as parking area. The HMDA document also records a building height of 14.2; its unit is not shown in the supplied extracted parameter text.
The available extracts do not establish the building footprint, apartments per floor, lift or stair layout, entry and exit arrangement, internal circulation, landscaping plan, or residential/common-area allocation. A separate proposed-building-plan file is present, but its extracted text does not provide a readable approval decision or usable design detail. The floor-plan drawings have not been software-measured: two drawings are recorded, with zero measured and two scans pending.
4. Homes, configurations & floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK | 10 | 0 | 10 | 43.81 sq. m | Not available; drawings pending measurement | Not supplied |
| 3BHK | 10 | 0 | 10 | 59.24 sq. m | Not available; drawings pending measurement | Not supplied |
The unit counts, booking figures and saleable areas above are from the RERA-filed unit record. Booked and available counts are a portal read without an as-of date and should be treated as indicative.
No software-measured carpet areas or room dimensions are available: the two drawing records remain scans pending measurement. RERA saleable area is reported separately from carpet area; the supplied evidence does not provide a carpet-area figure or a quantified common-area loading for either configuration.
5. Parking & vehicle circulation
The municipal building permit records 1066.94 sq. m as parking area for the cellar and stilt. The HMDA technical approval states that the cellar and stilt approved for parking are to be used exclusively for vehicle parking and not converted or misused for another purpose.
The supplied records do not establish the number of car or two-wheeler spaces, visitor or accessible spaces, parking allocation to individual homes, ramp design, internal driveway arrangement, pedestrian separation or EV-charging provision. A parking-space ratio cannot be stated from the available evidence.
6. Amenities, recreation & open spaces
The RERA amenities record lists 14 project infrastructure and facility items. Listed progress is 0% for each item; the record does not establish independent completion. The building permit separately requires transformer and garbage-house provision, and the HMDA approval refers to rainwater-harvesting structures.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Internal Roads & Footpaths | Size not stated | RERA amenities filing | 0%; not independently verified |
| Green Strip / TOT LOT / Park | Municipal permit records TOT LOT 50.54; unit not shown in the extract | RERA amenities filing; building permit | RERA amenity progress 0%; completion not verified |
| Community Buildings | No further description or size supplied | RERA amenities filing | 0%; not independently verified |
| Water Supply | Listed as available: YES; details not supplied | RERA amenities filing | Progress recorded as 0%; completion not verified |
| Sewerage, chambers, lines, septic tank / STP | Listed as available: YES; facility details not supplied | RERA amenities filing | Progress recorded as 0%; completion not verified |
| Treatment and disposal of sewage and sullage water | Size and system details not supplied | RERA amenities filing | 0%; not independently verified |
| Storm-water drains | Details not supplied | RERA amenities filing | 0%; not independently verified |
| Water conservation / rainwater harvesting | Listed as available: YES; HMDA approval also requires rainwater-harvesting structures | RERA amenities filing | Progress recorded as 0%; completion not verified |
| Solid-waste management and disposal | Details not supplied; building permit also provides for a garbage house | RERA amenities filing | 0%; not independently verified |
| Street lighting | Details not supplied | RERA amenities filing | 0%; not independently verified |
| Energy management | Details not supplied | RERA amenities filing | 0%; not independently verified |
| Electrical meter room / sub-station / receiving station | Listed as available: YES; building permit also requires transformer provision | RERA amenities filing | Progress recorded as 0%; completion not verified |
| Fire protection and fire-safety requirements | Specific systems and capacities not supplied | RERA amenities filing | 0%; not independently verified |
| Aggregate recreational open space | Area not supplied | RERA amenities filing | 0%; not independently verified |
7. Utilities, building services & safety
Water and drainage: The RERA amenities record lists water supply, sewerage and storm-water drains; it also lists water conservation and rainwater harvesting. It does not provide water sources, storage or treatment capacities, STP capacity, reuse arrangements or drainage design. The HMDA approval requires rainwater-harvesting structures.
Electrical and waste: The RERA record lists an electrical meter room/sub-station/receiving station, and the municipal permit requires transformer and garbage-house provision. No supply capacity, backup system, waste-segregation arrangement or operating status is supplied.
Vertical transport, fire safety and accessibility: No lift information, lift capacity, service lift, escape-stair details, fire-system specifications, accessibility features, CCTV or access-control details are established by the supplied project filing and approval extracts. The RERA amenities record lists fire protection and fire-safety requirements, but provides no system details or evidence of completion.
8. Location, access & connectivity
The registered location is Kompally Village, Dundigal Gandimaisamma Mandal, Medchal-Malkajgiri District, PIN 500047. The project land record identifies a road of width 15 along the north boundary; the supplied record does not identify that road by name.
No project-specific road-network description, public-transport service details or measured distances to landmarks are supplied in the RERA location evidence. The available location record contains coordinates labelled as a “cadastral parcel centroid,” but does not establish the project’s access route or nearby connectivity.
9. Developer & development status
The registered promoter is EAST WEST DEVELOPERS, recorded as a partnership. Its GSTIN is 36AACFE3657K2Z8. The project filing names DANNAMANENI PRAVEEN RAO as authorized signatory and lists BOORLA AMARNATH and SARIDENA KRISHNA as partners.
The registration certificate gives the promoter’s office as “Village: Mandal: District: Hyderabad, Pin: 500076,” without village or mandal names in the supplied extract. The project address is separately recorded as B, Karthikeya Nagar, Kompally Village, Dundigal Gandimaisamma, Medchal-Malkajgiri, 500047.
The promoter’s Form B declares a completion undertaking date of 15/04/2026. The project header records 14/08/2027 as the proposed completion date. No independent construction-progress evidence or occupancy/completion certificate is supplied. TG-RERA registration is recorded through 14/04/2027; that validity date is distinct from the completion dates.
10. Approvals, official records & documents
TG-RERA registration certificate: Form C records project J. P s EAST WEST RESIDENCY, registration P02200002975, issued 20/05/2021, valid through 14/04/2027; it identifies Survey No. 150 and Plot Nos. 358 and 359.
HMDA technical approval: HMDA technical approval 024503/MED/R1/U6/HMDA/10062019, dated 16/05/2020, for a residential building on Survey No. 150; extract describes 1 cellar, 1 stilt and 5 upper floors.
Kompally Municipality building permit: Permit 0005/21-22, File No. 03402/TP/KM/2021, dated 15.04.2021; records a residential building with approved built-up area 2335.85 sq. m.
RERA-filed title / development document: Development Agreement Cum General Power of Attorney dated 21 March 2020, filed as document 166987, for development of Plot Nos. 358 and 359 in Survey No. 150.
RERA-filed title report: Sale deed material filed as document 166999, relating to Plot Nos. 358 and 359 in Survey No. 150.
Form B promoter declaration: Document 166996 records the promoter’s declarations, including its completion undertaking date of 15/04/2026.
Proposed building plan: Document 166991 is described as a proposed building plan; the supplied extraction does not show a readable approval decision.
Occupancy / completion certificate: None supplied in the reviewed project documents.
Location and project-specific official records: The supplied location record provides a cadastral parcel-centroid label but no measured connectivity distances. The HMDA master-plan land-use sheet could not be confidently assigned, and the public HMDA DPMS approved-layout lookup is recorded as unavailable.
Frequently asked questions
Is J. P s EAST WEST RESIDENCY registered with Telangana RERA?
Yes. J. P s EAST WEST RESIDENCY is registered with the Telangana Real Estate Regulatory Authority as P02200002975; the registration status is New Project.
Who is the developer of J. P s EAST WEST RESIDENCY?
The promoter named in the RERA registration is EAST WEST DEVELOPERS.
Where is J. P s EAST WEST RESIDENCY located?
J. P s EAST WEST RESIDENCY is in KOMPALLY VILLAGE, Dundigal Gandimaisamma, Medchal-Malkajgiri, Telangana (500047).
When will J. P s EAST WEST RESIDENCY be completed?
The promoter's proposed date of completion filed with RERA is 14/08/2027. This is the promoter's declaration, not a guarantee.
More projects in Kompally