Sign in

Soras Sanctuary Block A

Padmaja Infra Developers · Rangareddy · RERA P02400008840

Soras Sanctuary Block A is a residential apartment project in Madhava Hills, Phase-II, Kondapur Village, Serilingampally Mandal, Ranga Reddy District, developed by registered promoter Padmaja Infra Developers. The registered site extent is 480.20 sq. m., with one residential building of 1 Stilt + 5 upper floors and 10 3BHK units, each with a RERA-filed saleable area of 167.22 sq. m. Its TG-RERA registration number is P02400008840, and the proposed and revised completion date is 30 July 2027.

More from Padmaja Infra Developers · 3 projects →

01What we found

RegisteredTG-RERA - valid till 30 Jul 2027
14documents on file - each fact links to its page
27court cases on this project's land (survey 218, Kondapur)
7items to check - 2 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

7 items to check before you pay, 2 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

1. Project at a glance

Project identity

FieldProject record
Registered nameSoras Sanctuary Block A RERA record
Project type / registered portionResidential apartment project; Block A is the registered project portion. One residential building is identified in the filed approval and project records. RERA record RERA filing
TG-RERA registrationP02400008840; valid from 30 July 2024 to 30 July 2027. Registration validity is distinct from the stated project completion deadline. RERA record
Registered promoterPadmaja Infra Developers; entity type: partnership. RERA record Corporate record RERA filing
RERA statusListed as “On-Going Project” in the project record. An occupancy certificate is also on file for Block A; see the scope note below. RERA filing

Land and geographic identity

FieldProject record
Locality / revenue villageMadhava Hills, Phase-II / Kondapur Village.
Mandal / district / PINSerilingampally / Ranga Reddy / 500084. RERA record RERA filing
Project survey number(s)Survey No. 218/3. RERA record Land records
Other survey number appearing in filed layout materialSurvey No. 106 also appears in the survey-number list in the layout-plan extraction; the supplied records do not identify it as an additional project parcel.
Registered site extent480.20 sq. m. in the building-permit/layout records; the occupancy certificate records net site area of 480.22 sq. m.
Total / net area and affected areaBuilding-permit record: plot area 480.2 sq. m., road-affected area 0.0, nala-affected area 0.0, net plot area 480.2 sq. m. The occupancy certificate records road-affected area 0.0 and net site area 480.22 sq. m.
BoundariesNorth: Main Road; South, East and West: Others Land. RERA filing

Development identity

FieldProject record
Sanctioning authorityGreater Hyderabad Municipal Corporation (GHMC); an occupancy certificate is recorded as issued by Cyberabad Municipal Corporation. Approvals record
Principal building approvalBuilding Permit No. 2361/GHMC/SLP/2024-BP, dated 30 July 2024; file No. 005732/GHMC/2760/SLP2/2024-BP. Approvals record
Approved built-up area1,352.05 sq. m. in the building-permit and layout records. The occupancy certificate records 1,352.05 sq. m. sanctioned and 1,420.35 sq. m. in the completion plan.
Building count / configurationOne residential building, identified as Soras Sanctuary Block A; sanctioned as 1 Stilt + 5 upper floors. RERA filing
Height14.99 metres in the sanctioned and completion-plan details.
Parking levels / areaOne parking floor; the filed permit records parking floor area of 255.9 sq. m. and total parking area of 270.4 sq. m. The occupancy certificate records parking area of 270.41 sq. m. sanctioned and 282.39 sq. m. in the completion plan. A number of parking spaces is not supplied.
Unit counts10 units in the layout-plan extraction and RERA unit record; all are listed as 3BHK. The permit extraction itself does not state a unit count. RERA unit table RERA unit details

Offering and status

FieldProject record
Unit type and filed saleable area3BHK; RERA-filed saleable area 167.22 sq. m. per unit. RERA unit table RERA unit details
Booked / available0 booked and 10 available in the portal-derived unit record; no as-of date is provided, so these counts are indicative rather than a current availability confirmation. RERA unit table RERA unit details
Construction stageThe RERA project record labels the project “On-Going Project.” The submitted occupancy certificate records Block A as inspected and fit for occupation; the supplied evidence does not establish that all units have been handed over or sold. RERA filing
Completion datesRERA registration record: proposed and revised completion date 30 July 2027. The building permit also states construction to be completed before 30 July 2027. RERA record RERA filing
Occupancy certificateCertificate No. 020607/CMC/01663/SWOC/SLP2/2026, issued 11 July 2026, for Soras Sanctuary Block A at Plot No. 49 Eastern Part, Survey No. 218/3. It records completion date 11 June 2026. This is a Block A certificate; the evidence does not identify another project phase or tower. Approvals record
Architect’s completion certificateForm–1A dated 30 June 2026 states that Soras Sanctuary Block A was completed in all aspects and identifies the above occupancy-certificate number.

2. The project story

Soras Sanctuary Block A is a single-building residential apartment project recorded at Madhava Hills, Phase-II, Kondapur Village, Serilingampally Mandal, Ranga Reddy District. The project parcel is identified as Survey No. 218/3, and the building-permit record describes a 480.2 sq. m. plot with a residential building of stilt plus five upper floors. The layout-plan extraction also lists Survey No. 106, but the supplied material does not explain its relationship to the project parcel. RERA record Land records

The RERA unit record lists 10 3BHK units. It shows none booked and all 10 available, but does not carry an as-of date. The project’s proposed and revised RERA completion date is 30 July 2027. Separately, the submitted municipal occupancy certificate identifies Block A as fit for occupation, with a completion date of 11 June 2026; the architect’s Form–1A also states completion. These records concern Block A, and should not be read as a unit-by-unit handover or current sales-status confirmation. RERA unit table RERA unit details RERA record

3. Master plan, architecture & building design

The filed building permit describes a new residential building with 1 Stilt + 5 upper floors, a height of 14.99 metres, and 1,352.05 sq. m. of upper-floor area. It records 255.9 sq. m. as parking-floor area and 270.4 sq. m. as total parking area. The layout-plan extraction separately records proposed built-up area excluding parking of 1,352.05 sq. m., including parking of 1,622.45 sq. m., total BUA of 1,638.66 sq. m., deductions of 16.21 sq. m. and net BUA of 1,352.05 sq. m.; these are the distinct labels as supplied in that record.

The occupancy certificate records 1,352.05 sq. m. as the sanctioned-plan built-up area and 1,420.35 sq. m. in the completion plan, with a total deviated built-up area for the block of 68.3. It records the building height as 14.99 metres in both plans.

The layout-plan extraction identifies one entry and one exit, each subject to a minimum width of 4.5 metres and height clearance of 5 metres. It also records setbacks and a 14.9 sq. m. Tot Lot in the building-permit extraction. No floor-by-floor unit arrangement, number of flats per floor, lift count, stair count, or detailed internal circulation description is supplied.

The layout material lists the HUDA final layout approval proceedings as 6/MP2/H/2001, dated 17 September 2001, and related layout references 6/MP2/PLG/HUDA/2001, 9273/MP2/H/1999, and G/177/LP/426/96-97. These references are included here as filed identifiers; this Overview does not assess their legal effect.

4. Homes, configurations & floor plans

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
3BHK10010167.22 sq. m.89.0–98.3 sq. m.; median 94.5 sq. m.43%

RERA-filed unit information lists 10 3BHK units and a saleable area of 167.22 sq. m. per unit. The booked and available counts are portal-derived and have no supplied as-of date. RERA unit details RERA unit table

The carpet-area figures above are software-measured from the filed floor-plan drawing, not RERA-filed measurements. The measurement record covers four flat designs and marks one for review. It gives a median of 94.5 sq. m. (1,018 sq. ft.) and a range of 89.0–98.3 sq. m. (959–1,059 sq. ft.). The drawing also labels a 1.20 m-wide balcony, other balcony space and a utility area; these are excluded from the software-measured carpet area. Floor plans RERA unit details

Carpet area and saleable area are different measures: the software-measured carpet figure is taken from drawing geometry, while the RERA-filed saleable figure is the registered unit-area disclosure. Confirm drawing-based dimensions against the approved drawing and the specific unit documents. The supplied material does not provide a unit-specific floor plan or verified room-area schedule for every home. Floor plans RERA unit details

5. Parking & vehicle circulation

The building-permit extraction records one parking floor, a parking-floor area of 255.9 sq. m. and total parking area of 270.4 sq. m. The occupancy certificate records 270.41 sq. m. in the sanctioned plan and 282.39 sq. m. in the completion plan. These are area figures, not counts of parking spaces.

The building-permit conditions say the stilt and any cellar approved for parking must be used exclusively for vehicle parking and not partitioned or converted to another use. The layout-plan material also refers to an entry and exit with minimum dimensions of 4.5 metres wide and 5 metres of height clearance. The supplied records do not establish the number of car or two-wheeler spaces, visitor or accessible-space provision, EV charger installation, or the parking allocation attached to any particular apartment. A parking area shown in approval records does not by itself establish exclusive ownership or allocation to a buyer.

6. Amenities, recreation & open spaces

The RERA amenities record lists 14 project-infrastructure items. The listed progress percentages are 0 where supplied; no independent completion verification is provided for these items. The occupancy certificate separately records four rainwater-harvesting pits in both the sanctioned plan and completion plan. RERA amenities

Green strip / Tot Lot / park
Description / sizeBuilding-permit extraction records a 14.9 sq. m. Tot Lot.
Evidence sourceRERA-filed permit and amenities record RERA amenities
Declared progress / verified statusAmenities record: available “YES,” progress 0%; no independent completion verification supplied.
Aggregate recreational open space
Description / sizeListed as available “YES”; no area stated in the supplied amenities record.
Evidence sourceRERA amenities record RERA amenities
Declared progress / verified statusProgress 0%; no independent completion verification supplied.
Community buildings
Description / sizeListed in the amenities record; no size or facility detail supplied.
Evidence sourceRERA amenities record RERA amenities
Declared progress / verified statusProgress 0%; no independent completion verification supplied.
Rainwater harvesting
Description / sizeBuilding-permit extraction lists 7 rainwater-harvesting pits; occupancy certificate records 4 pits in the sanctioned and completion plans.
Evidence sourceRERA-filed permit and occupancy certificate
Declared progress / verified statusOccupancy certificate records the pits in the completion plan; no separate operational verification supplied.
Landscape / tree planting
Description / sizeBuilding-permit extraction records 8 trees and requires greenery to be maintained; no landscape-area figure is supplied.
Evidence sourceRERA-filed permit
Declared progress / verified statusRequirement recorded; no independent completion verification supplied.

The vendor data also lists children’s play areas, indoor games, parks, central greens and landscaped gardens. These are vendor-listed features, not established here as RERA-declared, sanctioned or delivered facilities. Promoter website

7. Utilities, building services & safety

The filed layout-plan material lists a separate underground static water storage tank of 25,000 litres and a separate terrace tank of 25,000 litres. It lists a bore well, water-supply line, sewerage line, septic tank, STP, sump, storm-water line, percolation pit, transformer, garbage house, lift and parking. The RERA amenities record marks water supply, sewerage and rainwater harvesting as available “YES,” while its supplied progress entries are 0%; independent operational verification is not included. RERA amenities

The building-permit conditions specify rainwater harvesting, a transformer space, a garbage house, tree planting and fire NOC from the Director (EV&DM) before issue of the occupancy certificate. The occupancy certificate is on file, but the supplied extracts do not include a separate Fire NOC or operational test reports for utilities and safety systems. The layout-plan material also lists fire-protection and fire-safety requirements, but an illustration or condition alone does not establish the installed system.

No capacities or specifications are supplied for lifts, backup power, sewage-treatment capacity, water-treatment facilities, CCTV, access control, waste segregation, accessible circulation or EV charging. Vendor-listed claims such as power backup, 24-hour water, CCTV and fire-fighting systems are not treated here as verified project provisions. Promoter website

8. Location, access & connectivity

The registered project location is Kondapur, Serilingampally Mandal, Ranga Reddy District, PIN 500084, on Survey No. 218/3. The filed building permit places the site at Madhava Hills; the layout document identifies Madhava Hills, Phase-II. The boundary entry records Main Road to the north and other land to the south, east and west. RERA record RERA filing RERA filing

The supplied location record identifies HITEC City at a measured distance of 5.4 km from the cadastral parcel centroid. No other verified road, public-transport or landmark distances are supplied. Vendor connectivity statements about nearby IT hubs, schools, colleges, hospitals, malls and a metro station are not independently measured in the available project records. Location record Promoter website

9. Developer & development status

The registered promoter is Padmaja Infra Developers, identified in the project record as a partnership. Its listed GSTIN is 36ABBFP9912G1Z4. The supplied promoter address is Mythri Nagar, Madhava Hills, Phase II, Kondapur, Serilingampally, Ranga Reddy, 500084. The RERA registration certificate gives a different abbreviated address and identifies the same promoter; the supplied records do not include an official contact number, email address or promoter website. Corporate record Parties record

The building permit identifies M/s.R.S. Builders & Developers as developer/builder in that permit record. The registered RERA promoter remains Padmaja Infra Developers. RERA record

The RERA record gives a proposed and revised completion date of 30 July 2027. The Form B declaration dated 20 August 2024 also contains a completion undertaking, but the extracted date is truncated (“30-07ot”), so it is not quoted as a complete date. The RERA portal-derived unit record lists 10 units, 0 booked and 10 available, without an as-of date. RERA record RERA unit details

For Block A, an occupancy certificate dated 11 July 2026 records the building as fit for occupation and a completion date of 11 June 2026. An architect’s Form–1A dated 30 June 2026 states the block was completed in all aspects and cites that certificate. These records establish the stated certificate and architect’s certification for Block A; they do not establish individual buyer handovers.

10. Approvals, official records & documents

TG-RERA registration certificate
Identifier / dateP02400008840; valid 30 July 2024–30 July 2027
Scope and sourceForm C certificate for Soras Sanctuary Block A, identifying Padmaja Infra Developers as promoter.
GHMC building permit
Identifier / date2361/GHMC/SLP/2024-BP; 30 July 2024; file No. 005732/GHMC/2760/SLP2/2024-BP
Scope and sourceBuilding permit for a residential building at Survey No. 218/3, Kondapur.
Layout / building-plan material
Identifier / dateHUDA final layout proceedings 6/MP2/H/2001; related references also include 6/MP2/PLG/HUDA/2001, 9273/MP2/H/1999 and G/177/LP/426/96-97
Scope and sourceLayout-plan and approval material filed with the project.
Occupancy certificate
Identifier / date020607/CMC/01663/SWOC/SLP2/2026; issued 11 July 2026; completion date recorded as 11 June 2026
Scope and sourceCyberabad Municipal Corporation certificate for Soras Sanctuary Block A, Plot No. 49 Eastern Part, Survey No. 218/3.
Architect’s completion certificate
Identifier / dateForm–1A dated 30 June 2026
Scope and sourceStates that Soras Sanctuary Block A was completed in all aspects and identifies the occupancy-certificate number.
Form B declaration
Identifier / date20 August 2024
Scope and sourcePromoter declaration covering title basis, encumbrance statement, project-fund and audit undertakings, approvals and completion undertaking. The extracted completion date is truncated.
Title documents filed
Identifier / dateSale Deed No. 5700/2024; title report dated 2 September 2024; mortgage deed No. 13690 of 2024 is cited in the title report
Scope and sourceFiled title and mortgage material relating to Survey No. 218/3; full title and encumbrance review is addressed separately.
Layout lookup limitation
Identifier / dateHMDA DPMS approved-layout lookup is recorded as unavailable through the public channel
Scope and sourceThis is a portal-access limitation, not evidence of refusal or absence of an approval. HMDA

Other registrations of Soras Sanctuary

Frequently asked questions

Is Soras Sanctuary Block A registered with Telangana RERA?

Yes. Soras Sanctuary Block A is registered with the Telangana Real Estate Regulatory Authority as P02400008840; the registration status is On-Going Project.

Who is the developer of Soras Sanctuary Block A?

The promoter named in the RERA registration is Padmaja Infra Developers.

Where is Soras Sanctuary Block A located?

Soras Sanctuary Block A is in Kondapur, Serilingampally, Rangareddy, Telangana (500084).

When will Soras Sanctuary Block A be completed?

The promoter's proposed date of completion filed with RERA is 30/07/2027. This is the promoter's declaration, not a guarantee.

More projects in Kondapur