JB INFRA PROJECTS , PHASE 4 is a residential plotted development in Ibrahimpatnam, Ibrahimpatnam Mandal, Ranga Reddy District, developed by the registered promoter JB INFRA PROJECTS. The registered site extent is 427175.34 Sq.m, and the project offers residential plots; the supplied RERA material does not establish the plot count or plot-size range. It is registered with TG-RERA under P02400002334, and the promoter-declared completion date is 29-1-2025.

01What we found

Period endedTG-RERA registration ran to 29 Jan 2025 - check its extension on TG-RERA
26documents on file - each fact links to its page
0court cases on this project's land in the court records searched
13items to check - 4 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

13 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

Project at a glance

Project identity

FieldProject record
Registered project nameJB INFRA PROJECTS, PHASE 4
Project typePlotted development / open-plot layout RERA record
Phase / registered portionPhase 4; the registration certificate identifies this project as “PHASE 4”
TG-RERA registrationP02400002334, granted under section 5; issued 12/11/2020
Registration validityCertificate states four years, from 12/11/2020 to 29/01/2025; no extension is recorded in the supplied certificate
Registered promoterJB INFRA PROJECTS
RERA status shown in the recordHeader labels the project “New Project.” The stated registration period has ended; the evidence supplied here does not establish a later extension or current registration status RERA record

Land and geographic identity

FieldProject record
LocalityIbrahimpatnam; RERA registration certificate PIN: 501506
Revenue villageIbrahimpatnam (Khalsa) Village; the title materials also use “Khalsa Ibrahimpatnam Village”
Mandal / districtIbrahimpatnam Mandal, Ranga Reddy District
Project survey numbers and subdivisions, as filed632P, 633p, 634p, 635, 636, 637P, 638P, 639P, 651, 652, 653P, 660 to 668P, 670, 671P to 677p, 679P, 682
Registered site extent427175.34 Sq.m
Total / net site areaTotal Site area: 427175.34 sq.m; Net Site Area: 427175.34 sq.m, in the draft layout area statement
Filed boundariesEast: neighbours’ land; West: neighbours’ land; North: “NAIGHBOURS LANDV” as recorded; South: neighbours’ land RERA filing

Development identity

FieldProject record
Sanctioning authorityHyderabad Metropolitan Development Authority (HMDA)
Principal layout approvalFinal Layout Permit 000023/LO/Plg/HMDA/2019, dated 29 January, 2019; final layout release recorded 21 January, 2021
Approved built-up area247440.97 sq.m is recorded as “Approved Built up Area” in the RERA project fields; the layout drawing labels this figure “Plotted Area,” not building floor area RERA filing Layout record
Building / tower count and floorsNot disclosed in the supplied evidence. This is a plotted layout, not a building or apartment scheme
ParkingNo project-wide car or two-wheeler parking count or parking-level arrangement is established in the supplied record
Layout land-use figures in the drawing-derived recordPlotted Area: 247440.97 sq.m; Road Area: 128801.88 sq.m; park area: 39131.08 sq.m; Social Infrastructure Area: 11800.06 sq.m; Amenity Area: 0.00 sq.m Layout record

Offering and status

FieldProject record
Unit typeResidential plots / open plots
RERA-filed plot count and plot-size rangeNot established in the supplied RERA material Document index
Drawing-derived count831 plot numbers, identified from numbers printed 1 to 831; software/drawing-derived and to be verified against the layout drawing Layout record
Booked / available countsNot available in the supplied evidence Document index
Construction / development stageNo current, independently verified site-progress assessment is supplied. The filing records approved layout infrastructure and a final layout release RERA amenities
Promoter-declared completion date29-1-2025 in Form B
Registration validity end date29/01/2025; this is separate from the promoter’s completion undertaking
Occupancy / completion certificateHMDA’s final-layout letter is recorded as dated 21 January, 2021 and as an “Occupancy Certificate Number” in the extracted record; its stated scope is the final plotted layout, not a building- or individual-plot occupancy certificate

The project story

  • This is a residential open-plot layout registered as JB INFRA PROJECTS, PHASE 4, in Ibrahimpatnam (Khalsa) Village, Ibrahimpatnam Mandal, Ranga Reddy District. The RERA registration and HMDA layout documents identify the same project survey schedule: 632P, 633p, 634p, 635, 636, 637P, 638P, 639P, 651, 652, 653P, 660 to 668P, 670, 671P to 677p, 679P and 682.
  • HMDA’s final-layout letter describes a residential layout with open plots and records a final layout release dated 21 January, 2021. It states that building sites are for residential dwelling houses, with individual building permissions to be considered separately under the applicable building rules. Thus, the supplied approvals establish a plotted layout; they do not document houses or apartment buildings being constructed as part of this registration.
  • The RERA registration certificate runs to 29/01/2025, and the promoter’s Form B gives 29-1-2025 as its completion undertaking. The supplied material does not include a current site inspection or verified construction-progress report. Accordingly, the approval and completion dates should not be read as proof that all layout works or individual plots are completed or occupied.

Master plan, architecture & building design

  • The project is a plotted layout, so building configuration, tower heights, floor arrangements and apartment plans are not applicable on the evidence supplied. HMDA’s final-layout letter identifies a residential open-plot layout and leaves individual building permission for later consideration; it also states that a building site is for residential dwelling use.
  • The layout-drawing-derived area statement gives a total and net site area of 427175.34 sq.m. Its listed allocation is 247440.97 sq.m for plotted area, 128801.88 sq.m for layout roads, 39131.08 sq.m for park area, and 11800.06 sq.m for social infrastructure. The separate amenity-area figure is 0.00 sq.m. These are layout land-use figures, not building floor area, saleable area or carpet area. Layout record
  • The RERA fields list “Approved Built up Area” as 247440.97 sq.m, while the drawing-derived layout record labels that same figure “Plotted Area.” The evidence does not supply a separate building-area schedule; the figure is therefore reported as filed and not treated here as verified building floor area. RERA filing Layout record
  • The drawing-derived record identifies plot numbers 1 to 831, but reports that plot sizes are not completely extracted and no plot-size measurements are available from that record. The extracted draft layout letter separately identifies 164 plots—Nos. 514 to 540 and 695 to 831—as mortgaged to HMDA for development obligations. Layout record

Homes, configurations & floor plans

This registration concerns plots rather than apartments or villas. No RERA-filed plot-size range, plot-wise inventory, booked count, available count or unit-level price schedule is included in the supplied evidence. Document index

Residential open plots
UnitsNot established in the supplied RERA material; drawing-derived plot-number count is 831 (numbers 1 to 831), requiring verification against the drawing
BookedNot available
AvailableNot available
RERA saleable areaNot supplied
Measured carpet areaNot applicable
Loading (if supplied)Not supplied

Two layout sheets are identified in the drawing-derived record; the software extraction reports no plot sizes measured and says the plot extraction is incomplete. Layout record No apartment floor plans or measured home areas are supplied. Floor plans

Parking & vehicle circulation

  • The approval material does not establish a count of resident, visitor, accessible or two-wheeler parking spaces, nor a dedicated parking level, ramp arrangement or plot-wise parking allocation. The layout is served by internal roads; the draft HMDA letter specifies road widths of 18 mts and above. It also says roads are to remain open for access to neighbouring sites, and the final-layout conditions require free public access on the roads.
  • The drawing-derived record identifies 164 plots mortgaged to HMDA as a layout-development security condition; this is not a parking provision or an allotment of plots to buyers. Layout record

Amenities, recreation & open spaces

Internal roads and footpaths
Description / sizeLayout roads: 128801.88 sq.m in the area statement; draft letter specifies road widths of 18 mts and above
Declared progress / verified statusHMDA final-layout letter records layout release; no independent present-condition inspection is supplied
Parks / open space
Description / sizePark area: 39131.08 sq.m; separate open-space line: 11800.06 sq.m in the draft layout area statement
Evidence sourceLayout record
Declared progress / verified statusFinal-layout letter says roads and open spaces were taken over by the Local Authority under registered Gift Deed 12681/2020 dated 30-12-2020
Social infrastructure
Description / size11800.06 sq.m in the layout drawing-derived land-use split; the draft letter’s area statement labels 11800.06 as “Open space,” while the final letter refers to social infrastructure among areas handed over
Evidence sourceLayout record
Declared progress / verified statusGift-deed handover is stated in the final-layout letter; no current physical-condition verification is supplied
Community buildings
Description / sizeRERA amenity schedule lists “Community Buildings” without a supplied size or quantity
Evidence sourceRERA amenities
Declared progress / verified statusProgress field is 0%; completion is not independently verified RERA amenities
Green strip / TOT lot / park
Description / sizeListed in the RERA amenity schedule without a supplied size or quantity
Evidence sourceRERA amenities
Declared progress / verified statusListed as available “YES”; progress field is 0%, and no independent completion verification is supplied RERA amenities
Street lighting
Description / sizeListed in the RERA amenity schedule without a supplied quantity
Evidence sourceRERA amenities
Declared progress / verified statusListed as available “YES”; progress field is 0%, and no independent completion verification is supplied RERA amenities
  • The promoter’s Form B also refers to amenities including storm-water drains, underground drainage lines, a common septic tank / STP, internal water-supply pipelines, an overhead tank, electrical supply lines, street lights, a transformer, avenue plantation, park development, rainwater-harvesting pits, social infrastructure and a utilities area. These are promoter-filed declarations; no supplied evidence verifies their present operational status.

Utilities, building services & safety

  • HMDA’s draft layout letter lists storm-water drains, underground drainage lines, a common septic tank / STP, internal water-supply pipelines, an overhead tank, electrical supply lines, street lights, a transformer, avenue plantation, park development, rainwater-harvesting pits, social infrastructure and a utilities area. The supplied material does not state capacities, water source, treatment performance, electrical backup or service commissioning status.
  • The final-layout letter describes the layout as provided with water supply, sewerage and drainage disposal systems, street lighting, rainwater-harvesting structure and other civic amenities; it assigns maintenance of those services to the local body. This is an approval-document statement, not a current operational inspection.
  • The RERA amenity schedule lists water supply, sewerage, storm-water drains, treatment and disposal of sewage and sullage water, solid-waste management and disposal, water conservation/rainwater harvesting, energy management, fire protection and fire-safety requirements, and an electrical meter room/sub-station/receiving station. It supplies no capacities or completion evidence for these items; several progress fields are recorded as 0%. RERA amenities
  • No project-specific lift, accessible-circulation, security-system, fire-clearance or emergency-access details are established in the supplied evidence. The final-layout conditions specify a minimum safety distance of 3m (10’0”) between a building and high-tension electricity lines when individual residential building permissions are considered.

Location, access & connectivity

  • The registered location is Ibrahimpatnam (Khalsa) Village, Ibrahimpatnam Mandal, Ranga Reddy District, PIN 501506. The supplied cadastral geocode identifies the parcel centroid as 17.333019634344925, 78.12807441006096. Location record
  • A sampled connectivity record places the nearest sampled Outer Ring Road interchange approximately 24.5 km away. This is a measured distance in the supplied location data; no travel time or public-transport connection is established there. Location record
  • HMDA’s draft layout letter requires roads to be opened for accessibility to neighbouring sites; the final-layout letter requires roads to remain open for free access to the general public. The supplied evidence does not identify the names of approach roads or confirm a public-transport service or nearby landmark.

Developer & development status

  • The registered promoter is JB INFRA PROJECTS, identified in the RERA record as a partnership. The supplied RERA fields name B. Manohar Reddy as authorised signatory; the project registration certificate gives a promoter office at B.N. Reddy Nagar, Hayathnagar Mandal, Ranga Reddy District, PIN 500070. Corporate record RERA filing
  • The promoter’s Form B declares a completion undertaking of 29-1-2025 and states that the land is free from encumbrances. These are promoter declarations in the registration filing. The registration certificate states validity to 29/01/2025 and the supplied certificate does not record an extension.
  • No current independently verified development-progress percentage, plot-wise booking information or completed-works inspection is supplied. The developer-site documents in the evidence pack describe other named JB projects; they are not used here to establish this registered Phase 4 project’s plot sizes, amenities or progress. Document index Promoter website

Approvals, official records & documents

TG-RERA Form C registration certificate
Identifier / dateP02400002334; issued 12/11/2020; stated validity to 29/01/2025
Scope and evidenceRegisters JB INFRA PROJECTS, PHASE 4; includes the filed survey schedule and registration conditions
HMDA draft layout letter
Identifier / dateApproval 000023/LO/Plg/HMDA/2019; dated 29 January, 2019; application 016241/SMD/LT/U6/HMDA/11102018
Scope and evidenceDraft open-plot layout proposal; records land extent, survey schedule, area statement, development conditions and HMDA mortgage of 164 plots
HMDA final layout letter
Identifier / dateFinal layout release recorded 21 January, 2021; file 040223/LT/SMD/FLT/U6/HMDA/02112020
Scope and evidenceRecords final residential open-plot layout approval and conditions
Registered Gift Deed
Identifier / date12681/2020, dated 30-12-2020
Scope and evidenceFinal-layout letter states roads, open spaces and social infrastructure were handed over to the Local Authority by registered gift deed
Relinquishment Deed
Identifier / date1307/2021, dated 19/1/2021
Scope and evidenceFinal-layout letter records a relinquishment deed concerning the mortgaged plots
Promoter Form B declaration
Identifier / dateDeclaration in Form B; completion undertaking 29-1-2025
Scope and evidencePromoter-filed title, encumbrance and project undertakings
RERA-filed amenity schedule
Identifier / date14 listed items
Scope and evidenceIncludes infrastructure and safety categories; progress fields and “available” entries are recorded in the filing schedule RERA amenities
Layout drawing-derived record
Identifier / dateTwo layout sheets; source document 73625
Scope and evidenceSoftware extraction reports 831 plot numbers and land-use figures; plot-size extraction is incomplete Layout record

The supplied document set does not include a separate building plan, building commencement certificate, individual building occupancy certificate, or current works-completion verification for this plotted layout. The final-layout letter’s “Occupancy Certificate Number” entry is recorded at layout scope and should not be read as an occupancy certificate for a house or other building.

Frequently asked questions

Is JB INFRA PROJECTS , PHASE 4 registered with Telangana RERA?

Yes. JB INFRA PROJECTS , PHASE 4 is registered with the Telangana Real Estate Regulatory Authority as P02400002334; the registration status is New Project.

Who is the developer of JB INFRA PROJECTS , PHASE 4?

The promoter named in the RERA registration is JB INFRA PROJECTS.

Where is JB INFRA PROJECTS , PHASE 4 located?

JB INFRA PROJECTS , PHASE 4 is in kalsa, Ibrahimpatnam, Rangareddy, Telangana (501506).

When will JB INFRA PROJECTS , PHASE 4 be completed?

The promoter's proposed date of completion filed with RERA is 29/01/2025. This is the promoter's declaration, not a guarantee.