HARMONY HEIGHTS is a residential apartment project in an HMDA layout at Plot No./House No. 776 EP, Uppal, Uppal mandal, Medchal-Malkajgiri district. The registered promoter is ALTERRA PROJECTS PRIVATE LIMITED. The project record states a land area of 597.33 sq m, one building and 10 homes, all configured as 3BHK; the GHMC permit describes the building as 1 Stilt + 5 upper floors. Its TG-RERA registration is P02200008818, and its proposed and revised proposed completion date is 30/09/2027.

More from Alterra Projects Pvt Ltd · 3 projects →

01What we found

RegisteredTG-RERA
13documents on file - each fact links to its page
16court cases on this project's land (survey 1, 9, Uppal) or naming the project
7items to check - 2 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

7 items to check before you pay, 2 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

1. Project at a glance

Project identity

FieldProject record
Registered project nameHARMONY HEIGHTS RERA record
Project typeResidential apartment project RERA record RERA filing
Registered portion / phaseThe RERA record describes the registered site as Plot 776 EP in Uppal; no separately named phase is disclosed. One building is recorded. RERA filing RERA filing
TG-RERA registrationP02200008818; registration effective 12 June 2024. The Form C certificate states validity from 12/06/2024 to 31/05/2027, unless extended by the Authority. RERA record
Registered promoterALTERRA PROJECTS PRIVATE LIMITED RERA record Corporate record
RERA statusOn-Going Project RERA filing
Completion deadlineThe RERA project record gives 30/09/2027 as both proposed and revised proposed completion. This is separate from the registration-validity date. RERA record RERA filing
Occupancy/completion certificateNo occupancy or completion certificate is recorded in the supplied project evidence. The later GHMC building-permit record states “completion_certified: false”; its scope is the Uppal building permit described below.

Land and geographic identity

FieldProject record
Locality / plot descriptionHMDA layout; Plot No./House No. 776 EP RERA filing RERA filing
Revenue villageUppal RERA record RERA filing
MandalUppal RERA record RERA filing
District / PINMedchal-Malkajgiri / 500039 RERA record RERA filing
Project survey numbers and subdivisions, as filed1 TO 40; 282 TO 368; 369(P); 370 TO 373; 374(P); 375 TO 387; 395 TO 401; 454; 456 TO 459; 505(P); 510 TO 564 RERA filing
Site areaRERA land details state total area 597.33 sq m and net area 597.33 sq m; affected area is recorded as 0 sq m. The GHMC permit gives 499.36 sq m as the plot and net plot area for the permitted building. RERA filing
Boundaries in the RERA land recordNorth: 60 FEET ROAD; South: PLOT NO 783; East: PLOT NO 777; West: REMAINING PART OF PLOT NO 776 RERA filing

Development identity

FieldProject record
Sanctioning authorityGreater Hyderabad Municipal Corporation (GHMC) Approvals record
Principal building permitPermit No. 1575/GHMC/LBN/2024-BP, dated 12 June 2024; file No. 004835/GHMC/2352/LBN2/2024-BP Approvals record
Approved building configuration1 Stilt + 5 upper floors; residential building
Approved built-up area1,565.80 sq m total proposed built-up area including parking; 1,314.70 sq m excluding parking (net built-up area); 251.10 sq m parking area.
Building countOne building in the RERA land record RERA filing
Approved versus RERA-declared homesGHMC permit plan: 10 units; RERA filing: 10 units RERA unit table
ParkingThe permit records 251.10 sq m of parking area, including stilt parking. A parking-space count is not established in the supplied Uppal permit extract.

Offering and status

FieldProject record
RERA-filed unit type3BHK; 10 units RERA unit table
RERA-filed saleable area158.86 sq m per unit RERA unit table
Booked / available0 booked and 10 available in the portal data supplied; the record has no as-of date, so these counts are indicative. RERA unit table
Construction stageThe project is recorded as on-going. No independently verified site-progress measurement is supplied. RERA filing
Completion datesProposed and revised proposed completion: 30/09/2027 RERA filing
OC statusNo OC is supplied for the project. The GHMC permit requires an OC before occupation; this is a permit condition, not evidence that an OC has been issued.

2. The project story

HARMONY HEIGHTS is registered with TG-RERA as a residential apartment project on Plot 776 EP, in the Uppal revenue village and mandal, Medchal-Malkajgiri district. The project record identifies one building and 10 RERA-filed 3BHK homes. Its registered completion target is 30 September 2027. The supplied record describes the project as on-going, but does not provide a verified construction-progress percentage or a site-inspection report. RERA record RERA filing RERA filing RERA unit table

GHMC’s permit for the Uppal site sanctions a residential building with one stilt and five upper floors on a stated 499.36 sq m site; the permit extract records 10 units. The RERA filing also records 10 units. The evidence supplied does not include a project-specific occupancy certificate.

3. Master plan, architecture & building design

The project’s GHMC building-permit extract describes a single residential building on the Uppal site, with 1 Stilt + 5 upper floors and total height 15.00 M. It records 1,314.70 sq m of residential floor area, 236.06 sq m of stilt area, 251.10 sq m of parking area, and 1,565.80 sq m total proposed built-up area including parking. These are distinct permit figures; no FSI-counted area or gross built-up-area figure is supplied for this Uppal building.

The RERA registration record identifies one building and a site area of 597.33 sq m, while the GHMC permit extract identifies a 499.36 sq m plot for the permitted building. The permit extract also refers to approved layout No. 14741/PLG/HMDA/2018 and an 18 m road width. RERA filing

No complete floor-plan geometry, unit-by-floor schedule, lift or stair count, entry/exit arrangement, circulation plan, or landscaping-area schedule for the Uppal building is available in the supplied drawing-derived evidence. The permit lists a tot-lot and a rainwater-harvesting pit; it does not provide a tot-lot area in that extract.

4. Homes, configurations & floor plans

The RERA unit record lists 10 3BHK homes, each with a saleable area of 158.86 sq m. Booked and available counts are shown as 0 and 10, respectively, but the supplied portal record has no as-of date. RERA unit table

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
3BHK10010158.86 sq mNot established for this Uppal building in the supplied drawing measurementsNot supplied

The supplied software-measured drawing data includes 3BHK measurements from documents 294614 and 478743, but those records identify different site descriptions and do not establish that those drawings are for this RERA-registered Uppal building. Accordingly, no drawing-measured carpet-area figure is attributed here to the registered Uppal homes. The RERA saleable area and a software-measured carpet area are different measures; the supplied evidence does not provide a verified carpet-area figure for this building. RERA unit details Floor plans

5. Parking & vehicle circulation

The GHMC permit extract records 251.10 sq m of parking area, including 236.06 sq m of stilt area. A count of sanctioned parking spaces, visitor or accessible bays, parking allocation by unit, and the vehicle-entry, ramp or driveway arrangement are not established in the supplied Uppal-building record.

The permit condition says parking places in buildings are to include electric-vehicle charging infrastructure as applicable; the supplied extract does not document installed EV chargers or a project-specific parking-allotment arrangement. A drawn or permitted parking area does not by itself establish exclusive ownership or allocation to a particular unit.

6. Amenities, recreation & open spaces

The RERA amenities record marks water supply, green strip/tot-lot/park, and water conservation/rainwater harvesting as “YES”; it lists 14 project-infrastructure categories, each with 0% progress. The permit extract separately lists a tot-lot and one rainwater-harvesting pit. No independent completion verification is supplied. RERA amenities

Landscape/open space — Tot-lot
Description / sizeGHMC permit lists a tot-lot; no area is given in the Uppal permit extract.
Declared progress / verified statusPermit-listed; completion not independently verified.
Landscape/open space — Green strip / tot-lot / park
Description / sizeRERA amenities record marks “YES”; no size is supplied.
Evidence sourceRERA amenities
Declared progress / verified statusRERA-listed as available; progress shown as 0%; no independent completion verification.
Utilities-adjacent — Rainwater harvesting
Description / sizePermit lists 1 rainwater-harvesting pit; RERA amenities record marks water conservation/rainwater harvesting “YES”.
Evidence sourceRERA amenities
Declared progress / verified statusPermit/RERA-listed; progress shown as 0% in the amenities record; no independent completion verification.

No project-specific evidence supplied for the Uppal building confirms a clubhouse, indoor recreation facilities, swimming pool, gym, or other recreational facilities. RERA amenities Document index

7. Utilities, building services & safety

ServiceEvidence in the project record
WaterRERA amenities record marks water supply “YES.” The supplied Uppal permit extract does not state a project water source, storage capacity, or treatment arrangement. RERA amenities
Sewerage and drainageThe RERA amenities record lists sewerage and treatment/disposal categories, but shows 0% progress and does not specify an STP capacity or reuse system for this building. RERA amenities
Storm-water and harvestingThe amenities record lists storm-water drains and marks water conservation/rainwater harvesting “YES”; the permit lists one rainwater-harvesting pit. No completion verification is supplied. RERA amenities
ElectricalThe permit requires space for a transformer. A project-specific installed transformer, power-backup capacity, or completed electrical system is not evidenced.
Vertical transportationLift count, type, capacity and service-lift provision are not established in the supplied Uppal-building evidence.
Fire and life safetyThe permit identifies structural and fire-safety responsibilities and requires an Occupancy Certificate before occupation. The supplied evidence does not establish completed installations, a fire NOC, or an issued OC for this building.
Waste and securityThe permit requires a garbage house. A project-specific waste-management system, CCTV, or access-control installation is not established.
AccessibilityThe supplied Uppal permit extract does not specify accessible routes, ramps, or accessible-unit provision.

8. Location, access & connectivity

The registered location is Uppal, Uppal mandal, Medchal-Malkajgiri district, PIN 500039, in an HMDA layout. The RERA land record identifies Plot 776 EP and the stated boundaries, including a 60-foot road to the north. The GHMC permit extract refers to an 18 m road width and the HMDA layout number 14741/PLG/HMDA/2018. RERA record RERA filing RERA filing

The location data supplied contains one mapped connectivity point: Financial District (Nanakramguda), 2.0 km. It identifies this as a distance from the cadastral parcel centroid; no route, travel time, or public-transport details are supplied. Location record

9. Developer & development status

The registered legal promoter is ALTERRA PROJECTS PRIVATE LIMITED, a private limited company. Its supplied GSTIN is 36AAVCA3013B1Z1. The RERA record identifies BOMMYREDDY ASHOK KUMAR REDDY as an authorized signatory. The company’s supplied address is VAISHNOVI TNR, VASAVI COLONY, Uppal Bhagayath Village, HMDA layout, Uppal, Medchal-Malkajgiri, 500039. Corporate record Parties record

The project is recorded as on-going, with a proposed and revised completion date of 30/09/2027. The supplied evidence does not include independently verified construction progress or an OC for the registered building. RERA filing RERA record

10. Approvals, official records & documents

RecordReference and scope
TG-RERA registration certificateForm C for HARMONY HEIGHTS, registration P02200008818, naming Alterra Projects Private Limited as promoter; states registration validity from 12/06/2024 to 31/05/2027 unless extended.
GHMC building permit1575/GHMC/LBN/2024-BP, dated 12 June 2024; file No. 004835/GHMC/2352/LBN2/2024-BP; permit extract describes the Uppal building as 1 Stilt + 5 upper floors on 499.36 sq m.
Layout reference in permit14741/PLG/HMDA/2018, recorded in the GHMC permit extract.
RERA land and unit recordsRERA filing records Plot 776 EP, the project survey-number string shown above, 597.33 sq m total/net land area, one building, and 10 units. RERA filing RERA filing RERA unit table
Form B declarationAlterra Projects Private Limited’s Form B is dated 11-08-2024 and contains promoter declarations about title basis, encumbrances, project funds, approvals and completion timing. It is a promoter declaration, not an independent verification.

The supplied evidence does not include an occupancy or completion certificate for the registered Uppal building.

Frequently asked questions

Is HARMONY HEIGHTS registered with Telangana RERA?

Yes. HARMONY HEIGHTS is registered with the Telangana Real Estate Regulatory Authority as P02200008818; the registration status is On-Going Project.

Who is the developer of HARMONY HEIGHTS?

The promoter named in the RERA registration is ALTERRA PROJECTS PRIVATE LIMITED.

Where is HARMONY HEIGHTS located?

HARMONY HEIGHTS is in HMDA layout, Uppal, Medchal-Malkajgiri, Telangana (500039).

When will HARMONY HEIGHTS be completed?

The promoter's proposed date of completion filed with RERA is 30/09/2027. This is the promoter's declaration, not a guarantee.