Geethikas Anantika
GEETHIKA INFRACON PRIVATE LIMITED AND Mr. A. SANTHOSH KUMAR · Vikarabad · RERA P02100006305
GEETHIKAS ANANTIKA is a plotted development in Dhannaram Revenue Village, Vikarabad Mandal, Vikarabad District, Telangana. It is being developed by GEETHIKA INFRACON PRIVATE LIMITED AND Mr. A. SANTHOSH KUMAR. The project covers 24,659.26 sq.m and its approved tentative layout provides for 90 plots; the supplied records do not state tower or block counts, floors, or plot configurations. It is registered under TG-RERA number P02100006305, with registration from 07/07/2023 to 20/03/2025, and the promoter undertakes completion by 20 March 2025.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
8 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Item | Record |
|---|---|
| Registered project name | GEETHIKAS ANANTIKA RERA record |
| Project type / registered portion | Plotted development; the record identifies the project as a new project, but does not separately describe a phase or phase-wise portion RERA record RERA filing |
| TG-RERA registration | P02100006305; registered from 07/07/2023 to 20/03/2025. The certificate states that validity could be extended by the Authority; the supplied certificate record says no extension is recorded |
| Registered promoter | GEETHIKA INFRACON PRIVATE LIMITED AND Mr. A. SANTHOSH KUMAR RERA record |
| RERA status in supplied record | The certificate records the registration period above. A current registration status after its stated end date is not established by the supplied evidence |
Land and geographic identity
| Item | Record |
|---|---|
| Locality / revenue village | Dhannaram / Dannaram; the layout approval identifies Dhannaram Revenue Village RERA record |
| Mandal / district / PIN | Vikarabad Mandal, Vikarabad District, Telangana; PIN 501101 RERA record |
| Project survey number(s) | Sy. No. 219; no subdivision is stated in the project record Land records |
| Registered site extent | 24,659.26 sq.m is the RERA land-record total/net area; the RERA fields state the same total and net area RERA filing |
| Layout area statement | The layout drawing’s area statement gives 24,659.26 sq.m net layout area Layout record |
| Boundaries | North: R and B Road Dhannaram to Hyderabad; South: agricultural land in Sy. No. 218; East: agricultural land in Sy. No. 198; West: 40 Feet Wide Road RERA filing |
Development identity
| Item | Record |
|---|---|
| Sanctioning authority | Vikarabad Municipality/Municipal Corporation Approvals record |
| Principal approval | Tentative layout approval 0003/LO/3042/2023, dated 20 March 2023; application number 000146/LO/DTCP/3042/0001/2023 Approvals record |
| Development form and scale | Approved tentative layout for 90 plots |
| Approved built-up area | 14,664.50 sq.m is the RERA-filed “Approved Built up Area”; it is not a dwelling-building specification in the supplied records RERA filing |
| Buildings / floors | Tower or block count and building floor configuration are not disclosed in the supplied RERA evidence. The project is a plotted layout, not an evidenced apartment-building scheme RERA filing |
| Parking | Parking-space counts and parking levels are not disclosed in the supplied project-specific evidence RERA filing |
| Plot count | 90 plots, stated in the tentative layout approval |
Offering and status
| Item | Record |
|---|---|
| Unit type | Plots; the layout drawing’s plot schedule contains 90 plots RERA record Layout record |
| Plot-size range | Software-measured from the approved layout drawing: 105.0–300.39 sq.m (125.6–359.3 sq.yd); verify against the drawing Layout record |
| Booked / available | Not established in the supplied project evidence. The RERA-filed allotment and agreement forms are blank or incomplete and do not establish buyer-specific bookings |
| Construction stage | RERA amenity records report progress for several layout works; these are declared progress figures, not independent site verification RERA amenities |
| Completion dates | The promoter’s Form B undertakes completion by 20 March 2025; the RERA certificate also ends on 20/03/2025. These are respectively a promoter-declared completion undertaking and registration validity date, not evidence of completion |
| OC / completion certificate | No project completion certificate or occupancy certificate is identified in the supplied evidence. Scope and current status are therefore not established Document index |
2. The project story
- GEETHIKAS ANANTIKA is registered as a plotted development in Survey No. 219 at Dhannaram/Dannaram, Vikarabad Mandal, Vikarabad District. Its approved tentative layout provides for 90 plots, internal roads, park/open space, utilities and social-infrastructure land. The layout approval places responsibility for the development works on the applicant and describes works including road formation, drainage, water infrastructure, lighting and park development RERA record.
- The project record does not establish how many plots are currently booked or available, or that layout development is complete. TG-RERA’s amenity records report varying progress for roads, water supply, storm-water drains, sewerage, lighting, park/green strip and other works; these figures are promoter-reported progress, not independent verification of site condition RERA amenities.
- The registration certificate’s validity and the promoter’s stated completion undertaking do not themselves establish completion or issuance of a completion/occupancy certificate.
3. Master plan, architecture & building design
This is a plot layout rather than an evidenced apartment or multi-tower project. The supplied layout drawing identifies 90 plots and gives a net layout area of 24,659.26 sq.m. Its stated land-use split is:
| Layout use | Area | Share of net layout area | Evidence |
|---|---|---|---|
| Plots | 14,664.50 sq.m | 59.47% | Software-measured from layout drawing; area statement Layout record |
| Roads | 6,894.05 sq.m | 27.96% | Software-measured from layout drawing; area statement Layout record |
| Parks / open space | 2,231.16 sq.m | 9.05% | Software-measured from layout drawing; area statement Layout record |
| Utilities | 247.44 sq.m | 1.00% | Software-measured from layout drawing; area statement Layout record |
| Social infrastructure | 621.04 sq.m | 2.52% | Software-measured from layout drawing; area statement Layout record |
| Amenities | 0.00 sq.m | 0.00% | Software-measured from layout drawing; area statement Layout record |
- The tentative approval separately describes 90 plots and its own area statement, including the park/open-space, road, utility, social-infrastructure and plotted areas. The drawing-derived plot schedule and land-use measurements are software-read and should be checked against the original drawing Layout record.
- No building arrangement, floors, tower heights, building footprint, apartment circulation or phase-wise building design is established by the supplied evidence.
- The approval identifies a 17.51% mortgage area—specified plots held in favour of the Municipality to secure layout-development obligations. This is an approval-related mortgage, not a description of the plots’ building design.
4. Homes, configurations & floor plans
The project offers plots, not evidenced apartment configurations. The layout schedule identifies 90 plots. Software measurement of the drawing gives the following plot-size bands; the sizes are not RERA-filed unit-area disclosures and should be verified against the drawing Layout record.
| Plot-size band | Plot count |
|---|---|
| 100–150 sq.yd (84–125 sq.m) | 17 |
| 150–200 sq.yd (125–167 sq.m) | 45 |
| 200–250 sq.yd (167–209 sq.m) | 7 |
| 250–300 sq.yd (209–251 sq.m) | 18 |
| 300–400 sq.yd (251–334 sq.m) | 3 |
- The measured smallest, median and largest plot areas are 105.0 sq.m, 140.04 sq.m and 300.39 sq.m, respectively Layout record. These are software-measured drawing figures, not carpet or apartment saleable areas.
- The supplied RERA allotment-letter and agreement-for-sale documents do not contain completed buyer-specific plot details, consideration or payment particulars, so booked and available plot counts cannot be confirmed.
5. Parking & vehicle circulation
The layout provides for 27.96% road area in its area statement, and the tentative approval requires roads to be opened for accessibility to neighbouring sites Layout record. The evidence does not specify parking-space counts, dedicated visitor or accessible parking, parking allocation to individual plots, or a parking structure. A plot purchase should not be treated as carrying an exclusive parking right unless the buyer’s transaction documents establish that allocation.
6. Amenities, recreation & open spaces
The table below summarizes the project’s RERA amenity records. Percentages are reported progress figures, not independently verified completion. The layout approval also describes proposed development works; its requirements or descriptions are not proof that those works have been delivered RERA amenities.
| Description / size | Layout drawing records parks/open space of 2,231.16 sq.m (9.05%) Layout record |
|---|---|
| Evidence source | Layout drawing; RERA amenity record Layout record RERA amenities |
| Declared progress / verified status | 50% declared progress; independent completion not verified RERA amenities |
| Description / size | 621.04 sq.m in the drawing-derived area statement; no specific facility or building is identified Layout record |
|---|---|
| Evidence source | Layout drawing Layout record |
| Declared progress / verified status | RERA amenity record lists community buildings at 0%; no completed facility verified RERA amenities |
| Description / size | No separate delivered facility details supplied beyond the layout park/open-space allocation Layout record |
|---|---|
| Evidence source | RERA amenity record RERA amenities |
| Declared progress / verified status | Aggregate area of recreational open space recorded at 0% progress RERA amenities |
The supplied records do not establish a clubhouse, gym, swimming pool, children’s play area or other indoor/sports facility as an approved or delivered project amenity.
7. Utilities, building services & safety
The tentative layout approval describes infrastructure works to be carried out, including internal water-supply pipelines, an assured water source, overhead tank/sump, underground drainage and common septic tank/STP, storm-water drains, electrical supply lines, street lights, transformer, rainwater-harvesting pits, solid-waste management and park development. These are approval-document requirements/descriptions; they do not independently prove installation or operation.
- Water: RERA amenity record reports 75% progress for water supply RERA amenities. The approval describes internal pipelines, an assured supply source and an overhead tank/sump, but does not provide capacities or establish completed service.
- Sewerage and drainage: RERA amenity record reports 60% for sewerage (chambers, lines, septic tank, STP), 20% for treatment and disposal of sewage/sullage water, and 70% for storm-water drains RERA amenities. The approval describes underground drainage and a common septic tank/STP.
- Electrical: RERA amenity record reports 40% for an electrical meter room/sub-station/receiving station and 30% for street lighting RERA amenities. The approval describes electrical supply lines, street lights and a transformer.
- Rainwater harvesting: RERA amenity record reports 30% progress; the approval describes rainwater-harvesting pits RERA amenities.
- Solid waste: The RERA amenity record reports 0% for solid-waste management and disposal; the approval lists solid-waste management among utilities to be provided RERA amenities.
- Fire safety: The RERA amenity record reports 0% progress for fire protection and fire-safety requirements. No project-specific fire-system design or clearance is supplied RERA amenities.
- Accessibility / security: No project-specific accessible-circulation, CCTV or access-control evidence is established in the supplied RERA project documents.
8. Location, access & connectivity
The registered project location is Dhannaram/Dannaram village, Vikarabad Mandal, Vikarabad District, Telangana, PIN 501101. The parcel record gives a cadastral centroid of 17.340090831953667, 77.9291913389014 RERA record Cadastral map. The layout approval identifies its northern boundary as R and B Road Dhannaram to Hyderabad and western boundary as a 40 Feet Wide Road RERA filing.
The nearest sampled Outer Ring Road interchange is approximately 41.0 km from the parcel centroid Location record. The supplied project evidence does not identify public-transport routes or additional measured distances to landmarks.
9. Developer & development status
- The registered promoter is GEETHIKA INFRACON PRIVATE LIMITED AND Mr. A. SANTHOSH KUMAR; the RERA certificate names the same promoter RERA record.
- The corporate record identifies the entity type as private limited and gives GSTIN 36AAICG5567B1ZL Corporate record. The RERA registration record gives a promoter-office entry in Hyderabad, PIN 500033, but the supplied evidence does not provide a complete registered-office address or official project contact details.
- In Form B, the promoter declares that the project will be completed by 20 March 2025 and makes the stated RERA-related declarations. The RERA amenity record gives partial declared progress for several layout works; no independent site inspection or completed works certificate is supplied here RERA amenities.
- No phase-wise construction schedule or project completion/occupancy certificate is established in the supplied evidence.
10. Approvals, official records & documents
| Record | What the supplied evidence establishes |
|---|---|
| TG-RERA registration certificate | Form C registration for GEETHIKAS ANANTIKA, P02100006305; issued 07/07/2023, with stated validity through 20/03/2025 |
| Tentative layout approval | Approval No. 0003/LO/3042/2023, dated 20 March 2023, for a 90-plot layout in Sy. No. 219, Dhannaram Revenue Village; issued by Vikarabad Municipality/Municipal Corporation |
| Layout application reference | Application No. 000146/LO/DTCP/3042/0001/2023 |
| Layout plan / area statement | Drawing record 321097; four layout sheets, with software-measured plot schedule and land-use areas Layout record |
| Promoter Form B | Form-B affidavit dated 25 April 2023, including the promoter’s stated completion undertaking and project declarations |
| Mortgage document referenced in approval | Mortgage Deed No. 968, dated 22 February 2023, concerning specified layout plots in favour of the Municipality |
| Other approval receipts referenced | TS/0325/2023 and TS/0326/2023, dated 06 January 2023; TS/0352/2023, dated 20 February 2023 |
| Completion / occupancy records | No completion or occupancy certificate is identified in the supplied project evidence Document index |
The registration certificate states the promoter’s obligations concerning agreements for sale, conveyance and the separate-account requirement. The current post-expiry registration status and whether any completion/occupancy certificate has since been issued are not established by the records supplied for this Overview.
1. Project at a glance
Project identity
Registered project name: GEETHIKAS ANANTIKA
Project type / registered portion: Plotted development; the record identifies the project as a new project, but does not separately describe a phase or phase-wise portion
TG-RERA registration: P02100006305; registered from 07/07/2023 to 20/03/2025. The certificate states that validity could be extended by the Authority; the supplied certificate record says no extension is recorded
Registered promoter: GEETHIKA INFRACON PRIVATE LIMITED AND Mr. A. SANTHOSH KUMAR
RERA status in supplied record: The certificate records the registration period above. A current registration status after its stated end date is not established by the supplied evidence
Land and geographic identity
Locality / revenue village: Dhannaram / Dannaram; the layout approval identifies Dhannaram Revenue Village
Mandal / district / PIN: Vikarabad Mandal, Vikarabad District, Telangana; PIN 501101
Project survey number(s): Sy. No. 219; no subdivision is stated in the project record
Registered site extent: 24,659.26 sq.m is the RERA land-record total/net area; the RERA fields state the same total and net area
Layout area statement: The layout drawing’s area statement gives 24,659.26 sq.m net layout area
Boundaries: North: R and B Road Dhannaram to Hyderabad; South: agricultural land in Sy. No. 218; East: agricultural land in Sy. No. 198; West: 40 Feet Wide Road
Development identity
Sanctioning authority: Vikarabad Municipality/Municipal Corporation
Principal approval: Tentative layout approval 0003/LO/3042/2023, dated 20 March 2023; application number 000146/LO/DTCP/3042/0001/2023
Development form and scale: Approved tentative layout for 90 plots
Approved built-up area: 14,664.50 sq.m is the RERA-filed “Approved Built up Area”; it is not a dwelling-building specification in the supplied records
Buildings / floors: Tower or block count and building floor configuration are not disclosed in the supplied RERA evidence. The project is a plotted layout, not an evidenced apartment-building scheme
Parking: Parking-space counts and parking levels are not disclosed in the supplied project-specific evidence
Plot count: 90 plots, stated in the tentative layout approval
Offering and status
Unit type: Plots; the layout drawing’s plot schedule contains 90 plots
Plot-size range: Software-measured from the approved layout drawing: 105.0–300.39 sq.m (125.6–359.3 sq.yd); verify against the drawing
Booked / available: Not established in the supplied project evidence. The RERA-filed allotment and agreement forms are blank or incomplete and do not establish buyer-specific bookings
Construction stage: RERA amenity records report progress for several layout works; these are declared progress figures, not independent site verification
Completion dates: The promoter’s Form B undertakes completion by 20 March 2025; the RERA certificate also ends on 20/03/2025. These are respectively a promoter-declared completion undertaking and registration validity date, not evidence of completion
OC / completion certificate: No project completion certificate or occupancy certificate is identified in the supplied evidence. Scope and current status are therefore not established
2. The project story
- GEETHIKAS ANANTIKA is registered as a plotted development in Survey No. 219 at Dhannaram/Dannaram, Vikarabad Mandal, Vikarabad District. Its approved tentative layout provides for 90 plots, internal roads, park/open space, utilities and social-infrastructure land. The layout approval places responsibility for the development works on the applicant and describes works including road formation, drainage, water infrastructure, lighting and park development.
- The project record does not establish how many plots are currently booked or available, or that layout development is complete. TG-RERA’s amenity records report varying progress for roads, water supply, storm-water drains, sewerage, lighting, park/green strip and other works; these figures are promoter-reported progress, not independent verification of site condition.
- The registration certificate’s validity and the promoter’s stated completion undertaking do not themselves establish completion or issuance of a completion/occupancy certificate.
3. Master plan, architecture & building design
This is a plot layout rather than an evidenced apartment or multi-tower project. The supplied layout drawing identifies 90 plots and gives a net layout area of 24,659.26 sq.m. Its stated land-use split is:
| Layout use | Area | Share of net layout area | Evidence |
|---|---|---|---|
| Plots | 14,664.50 sq.m | 59.47% | Software-measured from layout drawing; area statement |
| Roads | 6,894.05 sq.m | 27.96% | Software-measured from layout drawing; area statement |
| Parks / open space | 2,231.16 sq.m | 9.05% | Software-measured from layout drawing; area statement |
| Utilities | 247.44 sq.m | 1.00% | Software-measured from layout drawing; area statement |
| Social infrastructure | 621.04 sq.m | 2.52% | Software-measured from layout drawing; area statement |
| Amenities | 0.00 sq.m | 0.00% | Software-measured from layout drawing; area statement |
- The tentative approval separately describes 90 plots and its own area statement, including the park/open-space, road, utility, social-infrastructure and plotted areas. The drawing-derived plot schedule and land-use measurements are software-read and should be checked against the original drawing.
- No building arrangement, floors, tower heights, building footprint, apartment circulation or phase-wise building design is established by the supplied evidence.
- The approval identifies a 17.51% mortgage area—specified plots held in favour of the Municipality to secure layout-development obligations. This is an approval-related mortgage, not a description of the plots’ building design.
4. Homes, configurations & floor plans
The project offers plots, not evidenced apartment configurations. The layout schedule identifies 90 plots. Software measurement of the drawing gives the following plot-size bands; the sizes are not RERA-filed unit-area disclosures and should be verified against the drawing.
100–150 sq.yd (84–125 sq.m): 17
150–200 sq.yd (125–167 sq.m): 45
200–250 sq.yd (167–209 sq.m): 7
250–300 sq.yd (209–251 sq.m): 18
300–400 sq.yd (251–334 sq.m): 3
- The measured smallest, median and largest plot areas are 105.0 sq.m, 140.04 sq.m and 300.39 sq.m, respectively. These are software-measured drawing figures, not carpet or apartment saleable areas.
- The supplied RERA allotment-letter and agreement-for-sale documents do not contain completed buyer-specific plot details, consideration or payment particulars, so booked and available plot counts cannot be confirmed.
5. Parking & vehicle circulation
The layout provides for 27.96% road area in its area statement, and the tentative approval requires roads to be opened for accessibility to neighbouring sites. The evidence does not specify parking-space counts, dedicated visitor or accessible parking, parking allocation to individual plots, or a parking structure. A plot purchase should not be treated as carrying an exclusive parking right unless the buyer’s transaction documents establish that allocation.
6. Amenities, recreation & open spaces
The table below summarizes the project’s RERA amenity records. Percentages are reported progress figures, not independently verified completion. The layout approval also describes proposed development works; its requirements or descriptions are not proof that those works have been delivered.
| Description / size | Layout drawing records parks/open space of 2,231.16 sq.m (9.05%) |
|---|---|
| Evidence source | Layout drawing; RERA amenity record |
| Declared progress / verified status | 50% declared progress; independent completion not verified |
| Description / size | 621.04 sq.m in the drawing-derived area statement; no specific facility or building is identified |
|---|---|
| Evidence source | Layout drawing |
| Declared progress / verified status | RERA amenity record lists community buildings at 0%; no completed facility verified |
| Description / size | No separate delivered facility details supplied beyond the layout park/open-space allocation |
|---|---|
| Evidence source | RERA amenity record |
| Declared progress / verified status | Aggregate area of recreational open space recorded at 0% progress |
The supplied records do not establish a clubhouse, gym, swimming pool, children’s play area or other indoor/sports facility as an approved or delivered project amenity.
7. Utilities, building services & safety
The tentative layout approval describes infrastructure works to be carried out, including internal water-supply pipelines, an assured water source, overhead tank/sump, underground drainage and common septic tank/STP, storm-water drains, electrical supply lines, street lights, transformer, rainwater-harvesting pits, solid-waste management and park development. These are approval-document requirements/descriptions; they do not independently prove installation or operation.
- Water: RERA amenity record reports 75% progress for water supply. The approval describes internal pipelines, an assured supply source and an overhead tank/sump, but does not provide capacities or establish completed service.
- Sewerage and drainage: RERA amenity record reports 60% for sewerage (chambers, lines, septic tank, STP), 20% for treatment and disposal of sewage/sullage water, and 70% for storm-water drains. The approval describes underground drainage and a common septic tank/STP.
- Electrical: RERA amenity record reports 40% for an electrical meter room/sub-station/receiving station and 30% for street lighting. The approval describes electrical supply lines, street lights and a transformer.
- Rainwater harvesting: RERA amenity record reports 30% progress; the approval describes rainwater-harvesting pits.
- Solid waste: The RERA amenity record reports 0% for solid-waste management and disposal; the approval lists solid-waste management among utilities to be provided.
- Fire safety: The RERA amenity record reports 0% progress for fire protection and fire-safety requirements. No project-specific fire-system design or clearance is supplied.
- Accessibility / security: No project-specific accessible-circulation, CCTV or access-control evidence is established in the supplied RERA project documents.
8. Location, access & connectivity
The registered project location is Dhannaram/Dannaram village, Vikarabad Mandal, Vikarabad District, Telangana, PIN 501101. The parcel record gives a cadastral centroid of 17.340090831953667, 77.9291913389014. The layout approval identifies its northern boundary as R and B Road Dhannaram to Hyderabad and western boundary as a 40 Feet Wide Road.
The nearest sampled Outer Ring Road interchange is approximately 41.0 km from the parcel centroid. The supplied project evidence does not identify public-transport routes or additional measured distances to landmarks.
9. Developer & development status
- The registered promoter is GEETHIKA INFRACON PRIVATE LIMITED AND Mr. A. SANTHOSH KUMAR; the RERA certificate names the same promoter.
- The corporate record identifies the entity type as private limited and gives GSTIN 36AAICG5567B1ZL. The RERA registration record gives a promoter-office entry in Hyderabad, PIN 500033, but the supplied evidence does not provide a complete registered-office address or official project contact details.
- In Form B, the promoter declares that the project will be completed by 20 March 2025 and makes the stated RERA-related declarations. The RERA amenity record gives partial declared progress for several layout works; no independent site inspection or completed works certificate is supplied here.
- No phase-wise construction schedule or project completion/occupancy certificate is established in the supplied evidence.
10. Approvals, official records & documents
TG-RERA registration certificate: Form C registration for GEETHIKAS ANANTIKA, P02100006305; issued 07/07/2023, with stated validity through 20/03/2025
Tentative layout approval: Approval No. 0003/LO/3042/2023, dated 20 March 2023, for a 90-plot layout in Sy. No. 219, Dhannaram Revenue Village; issued by Vikarabad Municipality/Municipal Corporation
Layout application reference: Application No. 000146/LO/DTCP/3042/0001/2023
Layout plan / area statement: Drawing record 321097; four layout sheets, with software-measured plot schedule and land-use areas
Promoter Form B: Form-B affidavit dated 25 April 2023, including the promoter’s stated completion undertaking and project declarations
Mortgage document referenced in approval: Mortgage Deed No. 968, dated 22 February 2023, concerning specified layout plots in favour of the Municipality
Other approval receipts referenced: TS/0325/2023 and TS/0326/2023, dated 06 January 2023; TS/0352/2023, dated 20 February 2023
Completion / occupancy records: No completion or occupancy certificate is identified in the supplied project evidence
The registration certificate states the promoter’s obligations concerning agreements for sale, conveyance and the separate-account requirement. The current post-expiry registration status and whether any completion/occupancy certificate has since been issued are not established by the records supplied for this Overview.
Frequently asked questions
Is GEETHIKAS ANANTIKA registered with Telangana RERA?
Yes. GEETHIKAS ANANTIKA is registered with the Telangana Real Estate Regulatory Authority as P02100006305; the registration status is New Project.
Who is the developer of GEETHIKAS ANANTIKA?
The promoter named in the RERA registration is GEETHIKA INFRACON PRIVATE LIMITED AND Mr. A. SANTHOSH KUMAR.
Where is GEETHIKAS ANANTIKA located?
GEETHIKAS ANANTIKA is in Dhannaram, Dannaram, Vikarabad, Telangana (501101).
When will GEETHIKAS ANANTIKA be completed?
The promoter's proposed date of completion filed with RERA is 20/03/2025. This is the promoter's declaration, not a guarantee.
More projects in Dannaram