CHAITRA LAKE BREEZE is a residential apartment project in Ameenpur, Ameenpur mandal, Sangareddy district, developed by the registered promoter Chaitra Constructions & Developers. The project has a site area of 334.45 sq. m and one building with 1 stilt + 5 upper floors, comprising 10 2BHK homes. It is registered with TG-RERA under P01100006929, with a proposed completion date of 2 August 2026.

More from Chaitra Constructions & Developers · 5 projects →

01What we found

Period endedTG-RERA registration ran to 2 Aug 2026 - check its extension on TG-RERA
12documents on file - each fact links to its page
5court cases on this project's land (survey 329, Ameenpur)
8items to check - 6 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

8 items to check before you pay, 6 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

1. Project at a glance

Project identity

FieldRecord
Registered project nameCHAITRA LAKE BREEZE RERA record
Project typeResidential apartment project RERA record RERA filing
Phase / registered portionPhase not separately identified; the registration covers the project on Survey No. 329/PART Land records
TG-RERA registrationP01100006929
Registration validity11 September 2023 to 2 August 2026; the certificate states two years and no extension is recorded in the supplied material
Registered promoterChaitra Constructions & Developers
RERA statusThe project is recorded as registered. Registration validity is distinct from the proposed completion date; no occupancy certificate is recorded in the supplied project documents.

Land and geographic identity

FieldRecord
Locality / site descriptionAmeenpur; the building-permit extraction describes Plot Nos. 752 and 753 and also gives the site locality as “PLOT NO. 313, STREET NO. 22, HMT SWARNAPURI COLONY, AMEENPUR.” RERA filing
Revenue villageAmeenpur Land records
MandalAmeenpur, as stated in the building-permit extraction
DistrictSangareddy (also rendered “Sanga Reddy” in the permit extraction) RERA record
PIN502032 RERA record
Survey number / subdivisionSurvey No. 329/PART; title and encumbrance materials also refer to Survey No. 329/P. Land records
Registered site extent334.45 sq. m RERA filing
Total / net areaBoth recorded as 334.45 sq. m; affected area is recorded as 00 sq. m. RERA filing
BoundariesEast: Plot No. 751; West: Plot No. 754; North: 30-wide road; South: Plot Nos. 756 and 757 RERA filing

Development identity

FieldRecord
Sanctioning authorityHMDA Approvals record
Principal building-permit number and date002701/BP/HMDA/0557/SKP/2023; 2 August 2023 Approvals record
Approved built-up area1,106.35 sq. m in the permit extraction
Building countOne building is recorded in the RERA land details RERA filing
Sanctioned floor configuration1 stilt + 5 upper floors; building height recorded as 14.49 (unit not stated in the extracted figure)
Parking levelsNo separate parking level or parking-space count is established in the supplied extracted records. The permit says no parking or construction in setback areas.
Unit count10 units in the RERA unit record; the RERA land-details field separately records “Total Building Units” and “Proposed Building Units” as 1 each, without defining those field labels further. RERA unit table RERA filing
Entry / exitPermit extraction records one entry and one exit, minimum width 4.5 m and height clearance 5 m

Offering and status

FieldRecord
Configuration2BHK RERA unit table
RERA-filed saleable area111.48 sq. m RERA unit table
Booked / available0 booked; 10 available in the portal-derived unit record. The record carries no as-of date, so counts are indicative. RERA unit table
Construction stageNot established by the supplied evidence; no independently verified site-progress information is provided. Document index
Completion datePromoter-declared completion undertaking: 2 August 2026
Occupancy certificateNo occupancy or completion certificate is recorded in the supplied material; the building-permit document says an occupancy certificate is compulsory before occupation.

2. The project story

CHAITRA LAKE BREEZE is recorded with TG-RERA as a residential apartment project on Plot Nos. 752 and 753, Survey No. 329/PART, in Ameenpur village, Sangareddy district. The RERA land record gives a site area of 334.45 sq. m, and the HMDA building-permit extraction describes a single residential building with a stilt and five upper floors. RERA record Land records

The RERA unit record lists ten 2BHK homes, all shown as available and none booked in the portal-derived snapshot; that snapshot has no as-of date. The supplied documents establish a building permit and a promoter completion undertaking, but do not establish construction progress, completed portions, or an issued occupancy certificate. The permit requires an occupancy certificate before occupation. RERA unit table

3. Master plan, architecture & building design

The project record describes one residential building on 334.45 sq. m, with approved built-up area of 1,106.35 sq. m. The permit extraction specifies 1 stilt + 5 upper floors and a building height of 14.49, without stating the unit for that height. These are permit-record details, not independent measurements of the completed building. RERA filing

The filed RERA configuration is 2BHK. The supplied drawing-derived review records floor-plan measurements for four flat designs, but does not provide a complete architectural description of the building’s common areas, floor-by-floor unit arrangement, lifts, staircases, or building footprint. The HMDA permit extraction records one entry and one exit and requires a minimum 4.5 m approach road, with a 5 m height clearance. RERA unit table Floor plans

4. Homes, configurations & floor plans

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
2BHK10010111.48 sq. mSoftware-measured range: 54.2–77.6 sq. m; median 64.6 sq. m42%

The saleable-area and unit-count figures are from the RERA unit record; the booking snapshot has no as-of date. Carpet-area figures are software measurements from floor-plan drawing geometry, not RERA-filed disclosures, and are marked as needing review. The drawing review measured four flat designs and flags one for review. RERA unit table Floor plans RERA unit details

The drawing extraction for one flat on the “FIFTH FLOOR PLAN,” identified as flat 02, lists a kitchen, two bedrooms, two toilets and a wash area. The supplied room measurements are drawing-derived; they should be checked against the original plan and are not a substitute for the registered agreement or a verified unit measurement. RERA unit details

Saleable area and carpet area are distinct measures: the drawing review says saleable area also includes the home’s share of common areas. The supplied data does not provide a separate balcony, utility, or common-area breakdown for each home. Floor plans

5. Parking & vehicle circulation

The building-permit extraction records one entry and one exit, each with a minimum width of 4.5 m and height clearance of 5 m, and states that parking or construction is not permitted in setback areas. The RERA unit record marks the configuration as mortgaged, but does not establish a parking-space count or unit-specific parking allocation. RERA unit table

The available records do not establish resident or visitor parking counts, accessible parking, parking levels, ramps, internal driveways, pedestrian separation, EV charging, or legally documented exclusive parking allocations. RERA unit table

6. Amenities, recreation & open spaces

The RERA amenities record lists 14 site-development and service categories. Each is recorded with 0% progress; where an availability field says “YES,” that is a filed availability entry, not evidence of completed or independently verified delivery. RERA amenities

FacilityDescription / sizeEvidence sourceDeclared progress / verified status
Green strip / tot lot / parkSize not statedRERA amenities record RERA amenities0%; completion not independently verified
Aggregate recreational open spaceArea not statedRERA amenities record RERA amenities0%; completion not independently verified
Community buildingsDetails and size not statedRERA amenities record RERA amenities0%; completion not independently verified
Internal roads and footpathsDetails not statedRERA amenities record RERA amenities0%; completion not independently verified
Street lightingDetails not statedRERA amenities record RERA amenities0%; completion not independently verified

The permit extraction also identifies a transformer, garbage house, STP and rainwater-harvesting structures as site provisions. It requires rainwater harvesting and an STP, but the supplied record does not establish their completed or independently verified status.

7. Utilities, building services & safety

The RERA amenities record marks water supply, sewerage (including chamber, lines, septic tank and STP), treatment and disposal of sewage and sullage water, solid-waste management and disposal, water conservation/rainwater harvesting, energy management, fire protection and fire-safety requirements, and an electrical meter room/substation/receiving station as “YES”; each is recorded at 0% progress. These are filed entries, not confirmation of completed facilities or statutory compliance. RERA amenities

The HMDA permit extraction identifies a transformer, garbage house, STP and rainwater-harvesting structures, and requires CCTV cameras. It also requires an approach road to be developed and maintained as a black-topped road before release of the occupancy certificate. The supplied documents do not state water source or storage capacity, STP capacity, reuse arrangements, backup-power provision, lift count or capacity, fire-system specifications, waste-segregation arrangements, security arrangements, or accessibility provisions.

8. Location, access & connectivity

The registered project location is Ameenpur village, Ameenpur mandal, Sangareddy district, Telangana 502032; the project parcel is identified as Survey No. 329/PART. The RERA land record gives the northern boundary as a 30-wide road. The HMDA permit extraction records a minimum 4.5 m approach road and specifies that it is to be developed and maintained as a black-topped road before occupancy-certificate release. RERA record Land records

A supplied location record places the project’s cadastral parcel centroid at 17.41528, 78.35459 and lists Financial District (Nanakramguda) at 1.2 km. No public-transport routes, travel times, or other measured connectivity distances are supplied. Location record

9. Developer & development status

The registered promoter is Chaitra Constructions & Developers, recorded as a partnership in the project information. The promoter’s GSTIN is 36AAOFC4110H1ZO. The project record names Gantala Harika Reddy as authorized signatory and Adavalli Prathima as partner. Parties record Corporate record

The RERA certificate gives the promoter office as Village Miyapur, Mandal Serilingampally, District Ranga Reddy, PIN 500049. No official telephone number, email address, or website is supplied.

The promoter’s Form B undertaking states a completion period of 2 August 2026. No construction-progress evidence or occupancy certificate is supplied, so the completion undertaking should not be read as evidence that construction is complete or the building is occupiable.

10. Approvals, official records & documents

RecordSupplied evidence
TG-RERA registrationFORM “C” certificate for CHAITRA LAKE BREEZE, P01100006929; issued 11 September 2023, valid to 2 August 2026
Building permitHMDA permit order 002701/BP/HMDA/0557/SKP/2023, dated 2 August 2023; covers a residential building on Plot Nos. 752 and 753, Survey No. 329/PART, Ameenpur
Title materialRERA-filed title report, development agreement-cum-GPA, sale-deed material and related title documents are listed in the project evidence pack Document index
Layout planA RERA document entry requests a layout-plan copy or an applicable declaration/equivalent document; the supplied extraction does not establish a separate approved layout document. Document index
Occupancy / completion certificateNone recorded in the supplied documents; the permit requires an occupancy certificate before occupation. Document index

The building permit includes stated conditions concerning construction to approved plans, commencement and completion notices, rainwater harvesting, CCTV, an STP, approach-road works, and occupancy certification. This overview records the existence of the permit and the extracted project particulars; it is not a complete review of all permit conditions.

Frequently asked questions

Is CHAITRA LAKE BREEZE registered with Telangana RERA?

Yes. CHAITRA LAKE BREEZE is registered with the Telangana Real Estate Regulatory Authority as P01100006929; the registration status is New Project.

Who is the developer of CHAITRA LAKE BREEZE?

The promoter named in the RERA registration is CHAITRA CONSTRUCTIONS & DEVELOPERS.

Where is CHAITRA LAKE BREEZE located?

CHAITRA LAKE BREEZE is in AMEENPUR, Sangareddy, Telangana (502032).

When will CHAITRA LAKE BREEZE be completed?

The promoter's proposed date of completion filed with RERA is 02/12/2026. This is the promoter's declaration, not a guarantee.