BILVA HEIGHTS is a residential apartment project in Kompally-Ncl Colony, Dundigal Gandimaisamma, Medchal-Malkajgiri. The registered promoter is BILVA TREE CONSTRUCTIONS AND DEVELOPERS. The project occupies 671.88 sq. m. and comprises 1 building with 1 Stilt + 5 upper floors and 15 apartments: 5 × 2BHK with saleable areas of 101.72 sq. m. and 10 × 3BHK with saleable areas of 140.32 sq. m. It is registered under TG-RERA registration P02200007491, and the promoter’s Form B declares completion by 01.02.2025.

More from Bilva Tree Constructions And Developers · 2 projects →

01What we found

Period endedTG-RERA registration ran to 1 Feb 2025 - check its extension on TG-RERA
21documents on file - each fact links to its page
21court cases on this project's land (survey 150, Kompally-Ncl Colony)
7items to check - 2 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

7 items to check before you pay, 2 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

1. Project at a glance

Project identity

ItemRecord
Registered project nameBILVA HEIGHTS RERA record
Project type / phaseResidential apartment project; phase or separately named registered portion: not disclosed. The registration certificate identifies the project as an apartment project. RERA record
TG-RERA registrationP02200007491 RERA record
Registration validity02/01/2024–01/02/2025, as recorded on the TG-RERA certificate. This is registration validity, not the completion date or an occupancy certificate. RERA record
Registered promoterBILVA TREE CONSTRUCTIONS AND DEVELOPERS RERA record
RERA status in supplied recordRegistration certificate records registration. No extension instrument is included here; a later architect’s completion certificate is included below.

Land and geographic identity

ItemRecord
LocalityKompally; the RERA certificate’s location field says Kompally-Ncl Colony. RERA record
Revenue villageKompally-Ncl Colony in the RERA registration record; building-permission documents describe Kompally Village. RERA record
Mandal / district / PINDundigal Gandimaisamma / Medchal-Malkajgiri / 500014 RERA record
Survey number and subdivisionSy.No. 150/A; no further survey subdivision is specified in the registration certificate. RERA record
Registered site extent671.88 sq. m. RERA filing
Total / net area671.88 sq. m. total area and 671.88 sq. m. net area in the RERA land fields. RERA filing
Boundaries in RERA recordEast: Neghibour land; West: 40 wide road; North: plot no 367; South: Neghibour land. RERA filing

Development identity

ItemRecord
Sanctioning authorityHyderabad Metropolitan Development Authority (HMDA); the building-permit order records release through Kompally Municipality / Municipal Corporation.
Principal building approval001507/BP/HMDA/0142/MED/2021, dated 02 February, 2022. Approvals record
Building count / configuration1 building; 1 Stilt + 5 upper floors. The building-permit extract states NO OF FLOORS: 6.
HeightThe filing extract gives 14.90 MT. and also records 19.00mt. Total Ht., 18.00 mt. from GL, and 14.90 mt. Excluding Stilt Floor.
Approved built-up areaThe building-plan extract lists 1628.00 as “built up area”; the HMDA approval extract separately lists 1,970.70 sq. m. total built up area and 1,605.45 sq. m. proposed built-up area. These are retained under their respective document labels; the supplied material does not reconcile the different area labels. RERA filing
ParkingThe building-plan details state PROPOSED NUMBER OF PARKINGS 7. Stilt is designated for parking in the permit conditions.
Units15 total units in the RERA unit record: 5 × 2BHK and 10 × 3BHK. RERA unit table

Offering and status

ItemRecord
RERA-filed configurations and saleable areas2BHK: 101.72 sq. m.; 3BHK: 140.32 sq. m. RERA unit table
Booked / availablePortal-derived RERA counts show 0 booked and 5 available 2BHK units, and 0 booked and 10 available 3BHK units. The portal snapshot has no as-of date, so counts are indicative. RERA unit table
Completion undertakingForm B declares completion by 01.02.2025.
Occupancy certificate / completion evidenceAn architect’s Form–1A records an HMDA occupancy certificate for one building, dated 06/01/2026, and certifies overall project completion; the certificate extract gives completion date 28.03.2026. The supplied extract does not state a separate phase or tower scope beyond the single building.
Construction-stage evidenceThe supplied Form–1A records completion; no independent site inspection or site-progress measurement is supplied.

2. The project story

  • BILVA HEIGHTS is registered as a residential apartment project on Sy.No. 150/A, at Kompally in Dundigal Gandimaisamma mandal, Medchal-Malkajgiri district. The registered site extent is 671.88 sq. m.; the registration record identifies the location as Kompally-Ncl Colony, while the building-permission document refers to Kompally Village. RERA record RERA filing
  • The sanctioned development is one residential building with 1 Stilt + 5 upper floors. RERA unit records list 15 apartments: five 2BHK and ten 3BHK homes. The RERA portal snapshot lists all 15 as available, but has no as-of date. RERA unit table
  • The promoter’s Form B undertook completion by 01.02.2025. A later architect’s Form–1A records an HMDA occupancy certificate dated 06/01/2026 for one building and certifies project completion; the supplied extract states 28.03.2026 as the completion date. This is certificate evidence, not an independent site inspection.

3. Master plan, architecture & building design

  • The supplied building-plan material describes one residential building on a 671.88 sq. m. site, with 1 Stilt + 5 upper floors. It records 315.66 SQ.MT. vacant plot area and 356.21 SQ.MT. proposed coverage area (53.02 %). The plan extract also lists 1605.45 SQ.MT. net BUA residential, 1628.00 built up area and 1970.70 total built up area; these remain as stated labels in the submitted material rather than interchangeable area measures.
  • HMDA’s technical approval extract records a total built-up area of 1,970.70 sq. m., proposed built-up area of 1,605.45 sq. m., and a building height of 14.90. The plan extract separately states 19.00mt. Total Ht., 18.00 mt. from GL and 14.90 mt. Excluding Stilt Floor.
  • The plan extract notes a 1.0MT GREENERY STRIP, 2.00 mt. Wide Passage, 12.00 MT WIDE EXISTING ROAD, 12.00 MT WIDE PROPOSED ROAD and 4.5M WIDE DRIVE WAY. The building-permit order describes one entry and one exit, each with minimum width 4.5mts. and height clearance 5mts. The supplied extracts do not provide a detailed floor-by-floor common-area schedule, lift count, stair arrangement, or apartment distribution by floor.

4. Homes, configurations & floor plans

RERA-filed saleable areas are presented below separately from software measurements made from the approved floor-plan drawings. The software measurements are drawing-based, not RERA disclosures, and are not independent measurements of completed apartments. Saleable area includes the home’s share of common areas; the supplied material does not provide a RERA-filed carpet-area figure. RERA unit table Floor plans

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
2BHK505101.72 sq. m.70.6–75.7 sq. m.; median 73.1 sq. m. (software-measured)28%
3BHK10010140.32 sq. m.86.6–94.8 sq. m.; median 94.6 sq. m. (software-measured)33%

The drawing-derived measurements cover two 2BHK designs and three 3BHK designs in document 355362. One measured 2BHK plan shows living/dining, kitchen, wash area, two bedrooms, toilet and a utility area; the utility area is marked excluded from carpet measurement. One measured 3BHK plan shows living/dining, kitchen, wash area, foyer, three bedrooms, toilets and a utility area, also excluded from carpet measurement. Room dimensions and drawing-derived areas are available in the supplied unit-detail record; they should be checked against the plan drawing. RERA unit details

5. Parking & vehicle circulation

  • The building-plan extract states PROPOSED NUMBER OF PARKINGS 7 and identifies the stilt floor for vehicle parking. The permit order also specifies that stilt/cellar (where applicable) is to be used exclusively for parking; it does not establish individual parking allocations to units. No visitor, accessible, two-wheeler, mechanical or EV-charging counts are supplied, and no legally documented unit-wise parking allocation is included.
  • The permit extract records one entry and one exit, each with minimum width 4.5mts. and height clearance 5mts. It also records a 4.5M WIDE DRIVE WAY in the building-plan details.

6. Amenities, recreation & open spaces

The RERA amenity record marks water supply, rainwater harvesting and electrical meter room/sub-station/receiving station at 100%; other listed amenity categories are recorded at 0%. These are portal declarations, not independent verification of completion. RERA amenities

FacilityDescription / sizeEvidence sourceDeclared progress / verified status
Water supplyRERA record: YESRERA amenities100% declared; not independently verified
Water conservation / rainwater harvestingPlan lists RWH; RERA record: YESRERA amenities100% declared; not independently verified
Green strip / tot lot / parkNo size statedRERA amenitiesRERA record 0%
Community buildingsNo details statedRERA amenitiesRERA record 0%
Internal roads and footpathsNo facility details or size statedRERA amenitiesRERA record 0%
Street lightingNo details statedRERA amenitiesRERA record 0%

The building-plan document also lists a gate, lift and parking, but provides no amenity-area or capacity schedule.

7. Utilities, building services & safety

  • The building-plan and permit extracts list a sump, rainwater harvesting, septic tank, STP, transformer and transformer yard. HMDA’s approval extract specifies a separate underground static water storage tank of 25, 000 lts. and a separate residential terrace tank of 25,000 lts. The permit extract also lists a garbage house and ETP. These are approval/document-listed provisions; the supplied material does not establish their installed condition or operational capacity beyond the stated tank capacities.
  • The approval conditions require fire-safety and structural-stability requirements to be addressed and state that automatic sprinklers are to be provided if basement area exceeds 200 Sq. Mtrs. The supplied records do not establish fire-system installation, clearances, lift capacity or quantity, backup-power capacity, waste-handling performance, CCTV installation, or accessibility provisions.

8. Location, access & connectivity

The registered location is Kompally-Ncl Colony, Dundigal Gandimaisamma, Medchal-Malkajgiri, 500014; the building-permit documents describe the site as Kompally Village. The plan records a 12.00 MT WIDE EXISTING ROAD, a 12.00 MT WIDE PROPOSED ROAD and a 4.5M WIDE DRIVE WAY. RERA record

A supplied location record gives the nearest sampled Outer Ring Road interchange at approximately 42.8 km. This is a location-record measurement; no travel time or public-transport service details are supplied. Location record

9. Developer & development status

The registered promoter is BILVA TREE CONSTRUCTIONS AND DEVELOPERS, identified as a proprietorship in the project record. The RERA certificate gives a promoter address of Village: Mandal: Secunderabad, District: Hyderabad, Pin: 500011; the project record separately lists the promoter’s address as MANIRATNAM RESIDENCY, MALLIKARJUNA COLONY, kompally, kompally, Dundigal Gandimaisamma, Medchal-Malkajgiri, 500014. Corporate record Parties record

The project record names NAKKA SANTOSH KUMAR as authorized signatory. Form B, dated 12.09.2023, declares completion by 01.02.2025. The architect’s Form–1A records one building with an HMDA occupancy certificate dated 06/01/2026 and certifies overall completion, with completion date 28.03.2026 stated in the extract. No independent site-progress verification is supplied. Parties record

10. Approvals, official records & documents

RecordSupplied evidence
TG-RERA registrationForm C for BILVA HEIGHTS, registration P02200007491, valid 02/01/2024–01/02/2025.
Principal building approvalHMDA technical approval 001507/BP/HMDA/0142/MED/2021, dated 02 February, 2022, for one building with 1 Stilt + 5 upper floors.
Building permit orderKompally Municipality / Municipal Corporation order 000241/BP/HMDA/MED/2022, dated 12 February, 2022. Approvals record
Building-plan documentBuilding-plan details identify Sy.No. 150/A, one residential building and plan conditions; the plan extract includes the building configuration, site-area and parking details summarized above.
Occupancy / completion evidenceArchitect’s Form–1A records HMDA occupancy certificate 009725/HMDA/02864/SWOC/MDL1/2025, dated 06/01/2026, for one building, and certifies overall project completion.
Promoter declarationForm B dated 12.09.2023, including the promoter’s completion undertaking and project-fund declarations.

The supplied record does not include a separate approved-layout lookup result or an independent site-completion inspection.

Frequently asked questions

Is BILVA HEIGHTS registered with Telangana RERA?

Yes. BILVA HEIGHTS is registered with the Telangana Real Estate Regulatory Authority as P02200007491; the registration status is New Project.

Who is the developer of BILVA HEIGHTS?

The promoter named in the RERA registration is BILVA TREE CONSTRUCTIONS AND DEVELOPERS.

Where is BILVA HEIGHTS located?

BILVA HEIGHTS is in kompally, Kompally-Ncl Colony, Dundigal Gandimaisamma, Medchal-Malkajgiri, Telangana (500014).

When will BILVA HEIGHTS be completed?

The promoter's proposed date of completion filed with RERA is 01/02/2025. This is the promoter's declaration, not a guarantee.

More projects in Kompally Ncl Colony