Thirumala Residency
THIRUMALA CONSTRUCTIONS DEVELOPERS · Medchal-Malkajgiri · RERA P02200003015
THIRUMALA RESIDENCY is a residential apartment project in Uppal, Uppal mandal, Medchal-Malkajgiri district. It is being developed by registered promoter THIRUMALA CONSTRUCTIONS DEVELOPERS. The project covers 745.3 m² and comprises one proposed residential building with 1 Stilt + 5 upper floors and 15 homes, filed at saleable areas of 86.36 m² or 108.72 m²; bedroom configurations are not disclosed in the RERA filing. Its TG-RERA registration number is P02200003015, and the proposed completion date is 22/04/2027.
More from Thirumala Constructions Developers · 6 projects →
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
9 items to check before you pay, 2 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Item | Project record |
|---|---|
| Registered name / type | THIRUMALA RESIDENCY — residential apartment project. RERA record |
| Registered portion / phase | Phase designation not disclosed in the supplied registration record. RERA record |
| TG-RERA registration | P02200003015; granted 17 June 2021; shown as valid through 22 December 2026. The certificate states “5 years” and names the same start and end dates. RERA record |
| Registered promoter | THIRUMALA CONSTRUCTIONS DEVELOPERS; partnership. RERA record RERA filing |
| RERA status | The project evidence identifies it as a “New Project”; registration is recorded. A current portal status beyond the registration validity details is not supplied. RERA record |
Land and geographic identity
| Item | Project record |
|---|---|
| Locality / revenue village | Locality: Uppal; revenue village in the project filing: Uppal. The building permit describes the site as UPPAL KHALSA, Swaroop Nagar, Uppal. RERA record RERA filing |
| Mandal / district / PIN | Uppal mandal; Medchal-Malkajgiri district; PIN 500092. RERA record |
| Project survey numbers | 60/1, 61, 62, 63 and 64. No project survey subdivisions are specified in the registration certificate or supplied project identity. RERA record Land records |
| Plot description | 33/B PART AND 34-B/2 PART. RERA filing |
| Registered site extent | Registration certificate gives the plot description but not an extent in the supplied extract. The RERA land filing and building-permit parameters state 745.3 m²; the title/development-agreement material describes 894 sq.yds. or 747.47 sq.mtrs. RERA filing |
| Total / net area and affected area | RERA land filing: total 745.3 sq.mts, net 745.30 sq.mts, affected area 0 sq.mts. Building permit: net area 745.3 m², road-affected area 0, nala-affected area 0. RERA filing |
| Boundaries in RERA filing | East: PLOT NO 33 B 1; west: PLOT NO 34 B 1; north: NEIGHBOURS; south: PLOT 33 BPART AND B 2 PART. RERA filing |
Development identity
| Item | Project record |
|---|---|
| Sanctioning authority | Greater Hyderabad Municipal Corporation (GHMC). Approvals record |
| Principal building approval | Approval no. 2/C2/12868/2020, dated 23 December 2020; permit file no. 2/C2/10025/2020. Approvals record |
| Building | One proposed residential building, Building - RESI-1 (PROP). |
| Sanctioned configuration | 1 Stilt + 5 upper floors; stated height 14.5 m. Upper-floor residential area: 1,407.20 m²; stilt-parking area: 301.10 m². The record does not separately provide an approved built-up-area total in the supplied permit extraction. |
| Approved / filed unit count | Building permit: no. of units sanctioned is subject to the permit condition against increasing the sanctioned number without GHMC approval; a count is not stated in the supplied permit extraction. RERA filing lists 15 unit entries. RERA unit table |
| Parking / site features in permit | Stilt approved for parking; parking count and allocation are not supplied. Permit also lists a 154.34 m² tot-lot and 35 trees. |
Offering and status
| Item | Project record |
|---|---|
| RERA-filed units | 15 unit entries, filed as door numbers 101–103, 201–203, 301–303, 401–403 and 501–503. The filing does not state their bedroom configurations. RERA unit table RERA unit details |
| RERA-filed saleable areas | Entries filed at 86.36 m² or 108.72 m² saleable area. RERA unit table RERA unit table |
| Booked / available | The supplied portal-derived unit table reports 0 booked and 15 available. It carries no as-of date, so these counts are indicative. RERA unit table |
| Construction stage | No independently verified site-progress information is supplied. The building permit provides construction and completion conditions; it does not establish current construction stage. |
| Completion dates | Promoter’s Form B declares completion by 22 December 2026; the project header gives proposed completion as 22/04/2027. RERA record |
| Occupancy / completion certificate | No occupancy or completion certificate is supplied. The building permit states that an occupancy certificate is compulsory before occupation. Its stated permit validity is through 23 December 2026. |
2. The project story
THIRUMALA RESIDENCY is registered as a residential apartment project on the RERA-identified site in Uppal, Uppal mandal, Medchal-Malkajgiri district. Its registered land record identifies survey numbers 60/1, 61, 62, 63 and 64, with plot description 33/B PART AND 34-B/2 PART. The project is organized as one proposed residential building, rather than a multi-tower development. RERA record RERA filing
The GHMC building permit describes one stilt and five upper floors, with stilt parking. The project’s RERA unit table contains 15 door-number entries; it reports no bookings and all 15 as available, but no as-of date is provided. The RERA filing does not identify bedroom configurations for these entries. No construction-progress report or certificate establishing completed or occupied portions is included in the supplied evidence. RERA unit table RERA unit details
The promoter’s Form B gives 22 December 2026 as the completion undertaking, while the project header records 22 April 2027 as proposed completion. These are the supplied completion-date records; neither is evidence that the building has been completed. The supplied permit requires an occupancy certificate before occupation, and no such certificate is present in the reviewed documents. RERA record
3. Master plan, architecture & building design
The GHMC building permit identifies a single residential building, Building - RESI-1 (PROP), on a site with net area 745.3 m². It specifies 1 Stilt + 5 upper floors, a stated height of 14.5 m, 1,407.20 m² of residential upper-floor area and 301.10 m² of stilt-parking area. These are permit parameters; the supplied extraction does not separately state an approved built-up-area total or FSI-counted area.
The permit lists a 154.34 m² tot-lot, 35 trees, a compound wall of 142.54 RM, and two rainwater-harvesting structures (RWHPs). It also specifies a transformer space, garbage house, rainwater-harvesting structure/percolation pit and ETP. The supplied drawing record does not provide enough extracted detail to describe the building footprint, flat arrangement by floor, lifts, stairs, entrances, exits, landscaping plan or common-area distribution.
The RERA filing identifies 15 units, but the supplied permit extraction does not state a sanctioned unit total. No separate phase-wise organization is disclosed. RERA unit table
4. Homes, configurations & floor plans
The RERA unit list records door-number entries and saleable areas, not bedroom configurations. The table below groups the filed entries by area; booked and available counts are as shown in the supplied portal-derived data, without an as-of date. RERA unit table RERA unit table
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| Configuration not disclosed; entries at 86.36 m² | 10 | 0 | 10 | 86.36 m² each | Not mapped to RERA entries | Not supplied |
| Configuration not disclosed; entries at 108.72 m² | 5 | 0 | 5 | 108.72 m² each | Not mapped to RERA entries | Not supplied |
Software measurement of the approved floor-plan drawing identifies 1BHK and 2BHK layouts, but these are drawing-based measurements, not RERA-filed configuration or carpet-area disclosures. The measured carpet-area ranges are 70.9–71.0 m² for 1BHK and 73.7–74.0 m² for 2BHK; the measured designs are not matched to the RERA unit entries. The measurement source states that its drawing geometry needs review. Carpet area is distinct from RERA saleable area, which includes the home’s share of common areas; no loading figure is supplied. RERA unit details Floor plans
The measured drawing extract gives one example of room dimensions for each layout: for the 1BHK, hall 3.51 × 5.82 m, dining 3.0 × 3.28 m, kitchen 2.43 × 3.0 m and master bedroom 3.5 × 4.51 m; for the 2BHK, bedroom 3.35 × 3.75 m, hall 3.85 × 5.36 m, toilet 1.5 × 2.0 m, master bedroom 3.35 × 3.52 m and kitchen 2.21 × 3.85 m. These are software-measured drawing figures, not RERA disclosures. RERA unit details
5. Parking & vehicle circulation
The GHMC permit identifies stilt parking and states that the approved stilt and cellar areas for parking must be used exclusively for vehicle parking without partition walls or rolling shutters. The permit’s extracted parameters give a 301.10 m² stilt-parking area; they do not state a parking-space count. The supplied evidence does not establish visitor or accessible parking, two-wheeler provision, mechanical parking, a basement/cellar level, ramp or driveway arrangement, EV charging, or unit-wise parking allocation. A drawn or sanctioned parking provision does not by itself establish an exclusive allocation to a particular home.
6. Amenities, recreation & open spaces
The RERA amenities record lists 14 project facilities or infrastructure categories and shows 0% progress for each category where a progress figure is supplied. The permit separately requires a tot-lot to be fenced and maintained as greenery before an occupancy certificate is issued. No independent evidence of completed amenities is supplied. RERA amenities
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Tot-lot / green area | Permit states 154.34 m²; to be fenced and maintained as greenery before issue of OC | GHMC building permit | Permit requirement; completion not independently verified. |
| Green strip / tot-lot / park | Listed as a RERA amenity; no size supplied in that entry | RERA amenities record | 0% recorded. RERA amenities |
| Community buildings | Listed; no description or size supplied | RERA amenities record | 0% recorded. RERA amenities |
| Aggregate recreational open space | Listed; area not supplied in the RERA amenities entry | RERA amenities record | 0% recorded. RERA amenities |
| Internal roads and footpaths | Listed; dimensions not supplied | RERA amenities record | 0% recorded. RERA amenities |
| Street lighting | Listed; specifications not supplied | RERA amenities record | 0% recorded. RERA amenities |
The supplied RERA amenities record does not provide a clubhouse, swimming pool, gym or other indoor/sports facility as a project-declared amenity. No independent completion verification is available. RERA amenities
7. Utilities, building services & safety
The RERA amenities record marks water supply, sewerage and rainwater harvesting as “YES,” but records 0% progress for those categories. The building permit specifies an ETP, a garbage house, a transformer space and a rainwater-harvesting structure/percolation pit; it also lists two RWHPs. These are filed or permitted provisions, not evidence that the systems are installed or operational. RERA amenities
| Service | Supplied evidence |
|---|---|
| Water | RERA amenities record: water supply marked “YES”; source, storage, treatment and capacity are not supplied. RERA amenities |
| Sewerage / drainage | RERA amenities record lists sewerage (chamber, lines, septic tank, STP) and treatment/disposal of sewage and sullage water; sewerage is marked “YES.” The permit specifies an ETP. System design, capacity and completion status are not supplied. RERA amenities |
| Storm water / harvesting | Storm-water drains are listed in the RERA record; rainwater harvesting is marked “YES.” The permit lists two RWHPs and a percolation pit. RERA amenities |
| Electrical | Electrical meter room/sub-station/receiving station is marked “YES” in the RERA record; the permit requires transformer space. Supply capacity and backup are not supplied. RERA amenities |
| Fire and life safety | Fire protection and fire safety requirements are listed in the RERA amenities record. The permit requires an occupancy Fire NOC from the Director (EV&DM) before issue of an occupancy certificate. No Fire NOC is supplied. RERA amenities |
| Waste | Solid-waste management and disposal are listed in the RERA amenities record; the permit requires a garbage house within the premises. Waste-system details and completion are not supplied. RERA amenities |
| Lifts / accessibility / security | Lift count and capacity, accessible circulation, ramps, CCTV and access-control arrangements are not supplied in the reviewed records. Document index |
8. Location, access & connectivity
The registered project location is Uppal, Uppal mandal, Medchal-Malkajgiri district, PIN 500092. The RERA land record identifies survey numbers 60/1, 61, 62, 63 and 64 and plot description 33/B PART AND 34-B/2 PART. The building permit describes the site as Uppal Khalsa, Swaroop Nagar, Uppal, and identifies a 40 FT WIDE ROAD and 18 mt. road widths in its extracted road details. RERA record RERA filing
The supplied location record gives a distance of 2.0 km to Financial District (Nanakramguda). It does not provide a route, measurement method, travel time, public-transport service or other verified connectivity details. Location record
9. Developer & development status
The registered promoter is THIRUMALA CONSTRUCTIONS DEVELOPERS, recorded as a partnership. The project filing gives GSTIN 36AAGFT3933P1ZL. The supplied registration certificate lists the promoter office as Village: Mandal: Abdullapurmet, District: Ranga Reddy, PIN 500039; the project filing separately gives a promoter address at Survey No. 37, Peerzadiguda, Swaroop Nagar, Uppal, Medchal-Malkajgiri, PIN 500092. These are the addresses stated in the supplied project records; no official contact number, email or website is supplied. RERA filing Corporate record
The Form B affidavit is signed by Gattamaneni Venkata Sudhakar Rao as authorized signatory for the promoter and declares completion by 22 December 2026. The project header records proposed completion as 22 April 2027. The evidence provided does not establish current construction progress or an occupancy-certificate date. RERA record
10. Approvals, official records & documents
| Record | Supplied evidence |
|---|---|
| TG-RERA registration | Form C for THIRUMALA RESIDENCY, registration no. P02200003015, granted 17 June 2021; shown valid through 22 December 2026. |
| GHMC building permit | Building Permit Order; approval no. 2/C2/12868/2020, file no. 2/C2/10025/2020, dated 23 December 2020; one residential building, 1 stilt + 5 upper floors. |
| Approved drawing | RERA-filed drawing document 158650; floor-plan software measurements are based on its drawings and are not RERA-filed area disclosures. The supplied extraction does not provide a complete drawing schedule. Floor plans |
| Promoter declaration | Form B affidavit by Gattamaneni Venkata Sudhakar Rao, dated 3 April 2021, including the stated completion undertaking and project-fund declarations. |
| Occupancy / completion certificate | No OC or completion certificate is included in the supplied documents. The building permit states that an occupancy certificate is compulsory before occupation. |
The GHMC permit also states that the sanctioned plan is to be followed, that a commencement notice is to be submitted before construction, and that a completion notice and occupancy certificate are required. It records conditions concerning the tot-lot, parking use, ETP, transformer space and fire NOC.
1. Project at a glance
Project identity
Registered name / type: THIRUMALA RESIDENCY — residential apartment project.
Registered portion / phase: Phase designation not disclosed in the supplied registration record.
TG-RERA registration: P02200003015; granted 17 June 2021; shown as valid through 22 December 2026. The certificate states “5 years” and names the same start and end dates.
Registered promoter: THIRUMALA CONSTRUCTIONS DEVELOPERS; partnership.
RERA status: The project evidence identifies it as a “New Project”; registration is recorded. A current portal status beyond the registration validity details is not supplied.
Land and geographic identity
Locality / revenue village: Locality: Uppal; revenue village in the project filing: Uppal. The building permit describes the site as UPPAL KHALSA, Swaroop Nagar, Uppal.
Mandal / district / PIN: Uppal mandal; Medchal-Malkajgiri district; PIN 500092.
Project survey numbers: 60/1, 61, 62, 63 and 64. No project survey subdivisions are specified in the registration certificate or supplied project identity.
Plot description: 33/B PART AND 34-B/2 PART.
Registered site extent: Registration certificate gives the plot description but not an extent in the supplied extract. The RERA land filing and building-permit parameters state 745.3 m²; the title/development-agreement material describes 894 sq.yds. or 747.47 sq.mtrs.
Total / net area and affected area: RERA land filing: total 745.3 sq.mts, net 745.30 sq.mts, affected area 0 sq.mts. Building permit: net area 745.3 m², road-affected area 0, nala-affected area 0.
Boundaries in RERA filing: East: PLOT NO 33 B 1; west: PLOT NO 34 B 1; north: NEIGHBOURS; south: PLOT 33 BPART AND B 2 PART.
Development identity
Sanctioning authority: Greater Hyderabad Municipal Corporation (GHMC).
Principal building approval: Approval no. 2/C2/12868/2020, dated 23 December 2020; permit file no. 2/C2/10025/2020.
Building: One proposed residential building, Building - RESI-1 (PROP).
Sanctioned configuration: 1 Stilt + 5 upper floors; stated height 14.5 m. Upper-floor residential area: 1,407.20 m²; stilt-parking area: 301.10 m². The record does not separately provide an approved built-up-area total in the supplied permit extraction.
Approved / filed unit count: Building permit: no. of units sanctioned is subject to the permit condition against increasing the sanctioned number without GHMC approval; a count is not stated in the supplied permit extraction. RERA filing lists 15 unit entries.
Parking / site features in permit: Stilt approved for parking; parking count and allocation are not supplied. Permit also lists a 154.34 m² tot-lot and 35 trees.
Offering and status
RERA-filed units: 15 unit entries, filed as door numbers 101–103, 201–203, 301–303, 401–403 and 501–503. The filing does not state their bedroom configurations.
RERA-filed saleable areas: Entries filed at 86.36 m² or 108.72 m² saleable area.
Booked / available: The supplied portal-derived unit table reports 0 booked and 15 available. It carries no as-of date, so these counts are indicative.
Construction stage: No independently verified site-progress information is supplied. The building permit provides construction and completion conditions; it does not establish current construction stage.
Completion dates: Promoter’s Form B declares completion by 22 December 2026; the project header gives proposed completion as 22/04/2027.
Occupancy / completion certificate: No occupancy or completion certificate is supplied. The building permit states that an occupancy certificate is compulsory before occupation. Its stated permit validity is through 23 December 2026.
2. The project story
THIRUMALA RESIDENCY is registered as a residential apartment project on the RERA-identified site in Uppal, Uppal mandal, Medchal-Malkajgiri district. Its registered land record identifies survey numbers 60/1, 61, 62, 63 and 64, with plot description 33/B PART AND 34-B/2 PART. The project is organized as one proposed residential building, rather than a multi-tower development.
The GHMC building permit describes one stilt and five upper floors, with stilt parking. The project’s RERA unit table contains 15 door-number entries; it reports no bookings and all 15 as available, but no as-of date is provided. The RERA filing does not identify bedroom configurations for these entries. No construction-progress report or certificate establishing completed or occupied portions is included in the supplied evidence.
The promoter’s Form B gives 22 December 2026 as the completion undertaking, while the project header records 22 April 2027 as proposed completion. These are the supplied completion-date records; neither is evidence that the building has been completed. The supplied permit requires an occupancy certificate before occupation, and no such certificate is present in the reviewed documents.
3. Master plan, architecture & building design
The GHMC building permit identifies a single residential building, Building - RESI-1 (PROP), on a site with net area 745.3 m². It specifies 1 Stilt + 5 upper floors, a stated height of 14.5 m, 1,407.20 m² of residential upper-floor area and 301.10 m² of stilt-parking area. These are permit parameters; the supplied extraction does not separately state an approved built-up-area total or FSI-counted area.
The permit lists a 154.34 m² tot-lot, 35 trees, a compound wall of 142.54 RM, and two rainwater-harvesting structures (RWHPs). It also specifies a transformer space, garbage house, rainwater-harvesting structure/percolation pit and ETP. The supplied drawing record does not provide enough extracted detail to describe the building footprint, flat arrangement by floor, lifts, stairs, entrances, exits, landscaping plan or common-area distribution.
The RERA filing identifies 15 units, but the supplied permit extraction does not state a sanctioned unit total. No separate phase-wise organization is disclosed.
4. Homes, configurations & floor plans
The RERA unit list records door-number entries and saleable areas, not bedroom configurations. The table below groups the filed entries by area; booked and available counts are as shown in the supplied portal-derived data, without an as-of date.
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| Configuration not disclosed; entries at 86.36 m² | 10 | 0 | 10 | 86.36 m² each | Not mapped to RERA entries | Not supplied |
| Configuration not disclosed; entries at 108.72 m² | 5 | 0 | 5 | 108.72 m² each | Not mapped to RERA entries | Not supplied |
Software measurement of the approved floor-plan drawing identifies 1BHK and 2BHK layouts, but these are drawing-based measurements, not RERA-filed configuration or carpet-area disclosures. The measured carpet-area ranges are 70.9–71.0 m² for 1BHK and 73.7–74.0 m² for 2BHK; the measured designs are not matched to the RERA unit entries. The measurement source states that its drawing geometry needs review. Carpet area is distinct from RERA saleable area, which includes the home’s share of common areas; no loading figure is supplied.
The measured drawing extract gives one example of room dimensions for each layout: for the 1BHK, hall 3.51 × 5.82 m, dining 3.0 × 3.28 m, kitchen 2.43 × 3.0 m and master bedroom 3.5 × 4.51 m; for the 2BHK, bedroom 3.35 × 3.75 m, hall 3.85 × 5.36 m, toilet 1.5 × 2.0 m, master bedroom 3.35 × 3.52 m and kitchen 2.21 × 3.85 m. These are software-measured drawing figures, not RERA disclosures.
5. Parking & vehicle circulation
The GHMC permit identifies stilt parking and states that the approved stilt and cellar areas for parking must be used exclusively for vehicle parking without partition walls or rolling shutters. The permit’s extracted parameters give a 301.10 m² stilt-parking area; they do not state a parking-space count. The supplied evidence does not establish visitor or accessible parking, two-wheeler provision, mechanical parking, a basement/cellar level, ramp or driveway arrangement, EV charging, or unit-wise parking allocation. A drawn or sanctioned parking provision does not by itself establish an exclusive allocation to a particular home.
6. Amenities, recreation & open spaces
The RERA amenities record lists 14 project facilities or infrastructure categories and shows 0% progress for each category where a progress figure is supplied. The permit separately requires a tot-lot to be fenced and maintained as greenery before an occupancy certificate is issued. No independent evidence of completed amenities is supplied.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Tot-lot / green area | Permit states 154.34 m²; to be fenced and maintained as greenery before issue of OC | GHMC building permit | Permit requirement; completion not independently verified. |
| Green strip / tot-lot / park | Listed as a RERA amenity; no size supplied in that entry | RERA amenities record | 0% recorded. |
| Community buildings | Listed; no description or size supplied | RERA amenities record | 0% recorded. |
| Aggregate recreational open space | Listed; area not supplied in the RERA amenities entry | RERA amenities record | 0% recorded. |
| Internal roads and footpaths | Listed; dimensions not supplied | RERA amenities record | 0% recorded. |
| Street lighting | Listed; specifications not supplied | RERA amenities record | 0% recorded. |
The supplied RERA amenities record does not provide a clubhouse, swimming pool, gym or other indoor/sports facility as a project-declared amenity. No independent completion verification is available.
7. Utilities, building services & safety
The RERA amenities record marks water supply, sewerage and rainwater harvesting as “YES,” but records 0% progress for those categories. The building permit specifies an ETP, a garbage house, a transformer space and a rainwater-harvesting structure/percolation pit; it also lists two RWHPs. These are filed or permitted provisions, not evidence that the systems are installed or operational.
Water: RERA amenities record: water supply marked “YES”; source, storage, treatment and capacity are not supplied.
Sewerage / drainage: RERA amenities record lists sewerage (chamber, lines, septic tank, STP) and treatment/disposal of sewage and sullage water; sewerage is marked “YES.” The permit specifies an ETP. System design, capacity and completion status are not supplied.
Storm water / harvesting: Storm-water drains are listed in the RERA record; rainwater harvesting is marked “YES.” The permit lists two RWHPs and a percolation pit.
Electrical: Electrical meter room/sub-station/receiving station is marked “YES” in the RERA record; the permit requires transformer space. Supply capacity and backup are not supplied.
Fire and life safety: Fire protection and fire safety requirements are listed in the RERA amenities record. The permit requires an occupancy Fire NOC from the Director (EV&DM) before issue of an occupancy certificate. No Fire NOC is supplied.
Waste: Solid-waste management and disposal are listed in the RERA amenities record; the permit requires a garbage house within the premises. Waste-system details and completion are not supplied.
Lifts / accessibility / security: Lift count and capacity, accessible circulation, ramps, CCTV and access-control arrangements are not supplied in the reviewed records.
8. Location, access & connectivity
The registered project location is Uppal, Uppal mandal, Medchal-Malkajgiri district, PIN 500092. The RERA land record identifies survey numbers 60/1, 61, 62, 63 and 64 and plot description 33/B PART AND 34-B/2 PART. The building permit describes the site as Uppal Khalsa, Swaroop Nagar, Uppal, and identifies a 40 FT WIDE ROAD and 18 mt. road widths in its extracted road details.
The supplied location record gives a distance of 2.0 km to Financial District (Nanakramguda). It does not provide a route, measurement method, travel time, public-transport service or other verified connectivity details.
9. Developer & development status
The registered promoter is THIRUMALA CONSTRUCTIONS DEVELOPERS, recorded as a partnership. The project filing gives GSTIN 36AAGFT3933P1ZL. The supplied registration certificate lists the promoter office as Village: Mandal: Abdullapurmet, District: Ranga Reddy, PIN 500039; the project filing separately gives a promoter address at Survey No. 37, Peerzadiguda, Swaroop Nagar, Uppal, Medchal-Malkajgiri, PIN 500092. These are the addresses stated in the supplied project records; no official contact number, email or website is supplied.
The Form B affidavit is signed by Gattamaneni Venkata Sudhakar Rao as authorized signatory for the promoter and declares completion by 22 December 2026. The project header records proposed completion as 22 April 2027. The evidence provided does not establish current construction progress or an occupancy-certificate date.
10. Approvals, official records & documents
TG-RERA registration: Form C for THIRUMALA RESIDENCY, registration no. P02200003015, granted 17 June 2021; shown valid through 22 December 2026.
GHMC building permit: Building Permit Order; approval no. 2/C2/12868/2020, file no. 2/C2/10025/2020, dated 23 December 2020; one residential building, 1 stilt + 5 upper floors.
Approved drawing: RERA-filed drawing document 158650; floor-plan software measurements are based on its drawings and are not RERA-filed area disclosures. The supplied extraction does not provide a complete drawing schedule.
Promoter declaration: Form B affidavit by Gattamaneni Venkata Sudhakar Rao, dated 3 April 2021, including the stated completion undertaking and project-fund declarations.
Occupancy / completion certificate: No OC or completion certificate is included in the supplied documents. The building permit states that an occupancy certificate is compulsory before occupation.
The GHMC permit also states that the sanctioned plan is to be followed, that a commencement notice is to be submitted before construction, and that a completion notice and occupancy certificate are required. It records conditions concerning the tot-lot, parking use, ETP, transformer space and fire NOC.
Frequently asked questions
Is THIRUMALA RESIDENCY registered with Telangana RERA?
Yes. THIRUMALA RESIDENCY is registered with the Telangana Real Estate Regulatory Authority as P02200003015; the registration status is New Project.
Who is the developer of THIRUMALA RESIDENCY?
The promoter named in the RERA registration is THIRUMALA CONSTRUCTIONS DEVELOPERS.
Where is THIRUMALA RESIDENCY located?
THIRUMALA RESIDENCY is in Uppal, Medchal-Malkajgiri, Telangana (500092).
When will THIRUMALA RESIDENCY be completed?
The promoter's proposed date of completion filed with RERA is 22/04/2027. This is the promoter's declaration, not a guarantee.