Gk Raj Casa Grande

GK RAJ CONSTRUCTIONS · Medchal-Malkajgiri · RERA P02200002971

GK RAJ CASA GRANDE is a residential apartment project in Yapral, Alwal, Medchal-Malkajgiri district. The registered promoter is GK RAJ CONSTRUCTIONS, a partnership. The registered site area is 23269.23 m2, with eight residential blocks and one amenities building; the residential blocks have Ground + 5 upper floors, except Block 5, which has a cellar, and the amenities building has Ground + 3 upper floors. The RERA filing records 280 homes: 2BHK, 3BHK and 4BHK, with saleable areas of 96.99 sqm, 129.12 sqm and 260.87 sqm, respectively. The TG-RERA registration is P02200002971, and the proposed completion date is 02/04/2027.

01What we found

RegisteredTG-RERA - valid till 2 Dec 2026
15documents on file - each fact links to its page
30court cases on this project's land (survey 49, Yapral)
7items to check - 3 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

7 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

1. Project at a glance

Project identity

FieldRecord
Registered project nameGK RAJ CASA GRANDE RERA record
Project type / phaseResidential apartment project; the registration identifies the project, but a separate phase name or phase boundary is not disclosed. RERA record
TG-RERA registrationP02200002971; issued 20/05/2021, valid until 02/12/2026. The certificate does not record an extension. Registration validity is separate from the project completion deadline and from occupancy certification. RERA record
Registered promoterGK RAJ CONSTRUCTIONS, a partnership. RERA record Corporate record
RERA statusRecorded as New Project; the registration certificate is the supplied evidence of registration. RERA record

Land and geographic identity

FieldRecord
Locality / revenue villageYapral; revenue village stated as Yapral. RERA record RERA filing
Mandal / district / PINAlwal / Medchal-Malkajgiri / 500087. The certificate’s mandal wording is “Malkajgiri”; the project header and filing identify Alwal. RERA record RERA filing
Project survey number and subdivision49/PART; no further project subdivision is identified in the supplied project filing. RERA record Land records
Registered site area23269.23 m2. The permit records Net Area(m2) 22617.24; these are separately stated permit figures.
Boundaries as filedNorth: PART OF SY NO 49; South: PART OF SY NO 49; East: PART SY NO 49; West: 100 WIDE ROAD. RERA filing
Survey-record contextThe cadastral lookup for 49/PART reports 50614.43 sqm for the whole survey, not just the project parcel. Cadastral map

Development identity

FieldRecord
Sanctioning authorityGreater Hyderabad Municipal Corporation (GHMC). Approvals record
Principal building approvalRevised Building Permit Order, approval 1/C28/12171/2020, dated 02 December, 2020; file no. 1/C28/09163/2020. Approvals record
Approved built-up areaProposed Covered builtup area 36,879.30 (permit figure; units not specified in the extracted wording). The project filing separately records approved built-up area 59604.61 Sqmts. These are shown as distinct record entries, not treated as interchangeable measurements. RERA filing
Building count and usePermit describes eight residential blocks—Blocks 1–8—and one amenities building. The project filing records 9 total building units, including 8 homes and 1 amenity block. RERA filing RERA unit table
Sanctioned floor configurationBlocks 1–4 and 6–8: Ground + 5 upper floors; Block 5: Cellar + Ground + 5 upper floors; amenities building: Ground + 3 upper floors.
Parking / cellarPermit records Cellar 2 22,252.20 and requires approved cellar and stilt areas to be used exclusively for parking; the extracted record does not establish a total parking-space count or unit allocations.
Unit countsTG-RERA unit record: 283 total, comprising 280 residential units and 3 amenity/common-area entries; the latter are not homes for sale. RERA unit table RERA unit table

Offering and status

FieldRecord
RERA-filed home configurations2BHK: 2; 3BHK: 231; 4BHK: 47. RERA unit table RERA unit details
RERA-filed saleable areas2BHK 96.99 sqm; 3BHK 129.12 sqm; 4BHK 260.87 sqm. RERA unit table RERA unit details
Booked / available2BHK: 0 / 2; 3BHK: 79 / 152; 4BHK: 12 / 35. Portal counts are indicative: the supplied record has no as-of date. RERA unit table RERA unit details
Construction stageA construction-stage percentage or independently verified site-progress report is not supplied. The RERA amenity-progress schedule reports varying percentages for listed infrastructure and facilities; it is not an independent site inspection. RERA amenities
Completion dateProject header: 02/04/2027 proposed completion. The Form B declaration states 02.12.2026 as the promoter’s completion undertaking. RERA record
Occupancy / completion certificateNo occupancy or completion certificate is supplied. The GHMC permit states that an occupancy certificate is compulsory before occupation.

2. The project story

GK RAJ CASA GRANDE is registered as a residential apartment project in Yapral, Medchal-Malkajgiri district, on project land identified in the filing as Survey No. 49/PART. The GHMC permit describes eight residential blocks and a separate amenities building; the RERA filing records nine building units in total, including the amenity block. RERA record Land records RERA unit table

The permit describes seven residential blocks as Ground plus five upper floors, one block with a cellar as well, and a Ground plus three upper-floor amenities building. The RERA unit schedule lists 280 homes across 2BHK, 3BHK and 4BHK configurations. Portal booking figures are available but undated, so they indicate the status last captured rather than a confirmed current inventory. RERA unit details RERA unit table

The supplied material does not establish construction completion by block, an independently inspected construction percentage, or an issued occupancy certificate for any block or phase. The permit requires an occupancy certificate before occupation; the project’s stated completion dates are recorded separately above. RERA record

3. Master plan, architecture & building design

The GHMC permit records a site area of 23269.23 m2, a net area of 22617.24 m2, Tot-lot (m2) 2240, and eight residential blocks plus an amenities building. It also records Proposed Covered builtup area 36,879.30; the supplied extraction does not specify the unit beside that figure. Separately, the RERA filing lists approved built-up area as 59604.61 Sqmts. RERA filing

BuildingPermit-stated floorsPermit-stated height
Blocks 1–4, 6–8Ground + 5 upper floors17.94 m each
Block 5Cellar + Ground + 5 upper floors17.34 m
Amenities buildingGround + 3 upper floors14.9 m

The permit lists ground and upper-floor residential areas for the blocks, and a commercial ground area of 520.05 m2 plus upper-floor area of 1,560.15 m2 for the amenities building. These are permit-extraction figures; they are not identified as carpet area or RERA saleable area. The project unit table separately includes three “AMINITES” entries of 520.05 sqm each, marked not for sale in the supplied unit record. RERA unit table RERA unit table

The permit records Cellar 2 22,252.20, 22 rain-water-harvesting structures, 1,160 trees, and a tot-lot of 2,240 m2. It also requires periphery greenery and a fenced tot-lot. A building footprint plan, floor-by-floor flat arrangement, internal circulation plan and detailed parking layout are not available in the supplied extracted records.

4. Homes, configurations & floor plans

TG-RERA records three home configurations. No carpet-area measurements were completed from the supplied floor-plan drawings: the drawing dataset contains two drawings, with 0 measured and 2 no_flats. Accordingly, the table presents RERA-filed saleable areas and does not infer carpet area or loading. RERA unit details Floor plans

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
2BHK20296.99 sqmNot measuredNot supplied
3BHK23179152129.12 sqmNot measuredNot supplied
4BHK471235260.87 sqmNot measuredNot supplied

RERA unit details RERA unit table

The booking and availability counts are from the RERA portal record and carry no as-of date, so treat them as indicative. “AMINITES” appears as a separate non-sale entry in the unit table; it is not counted as a home configuration. RERA unit table RERA unit table

Saleable area is the RERA-filed measure. Carpet area is not supplied here as a measured figure; no comparison or loading calculation can therefore be made from this evidence. RERA unit details Floor plans

5. Parking & vehicle circulation

The GHMC permit records a cellar level for Block 5 and states that cellar and stilt areas approved for parking must remain exclusively for vehicle parking, without partition walls or rolling shutters and without conversion to another use. It also records “Cellar 2 22,252.20”; the supplied extraction does not clarify a parking-space count or provide a full parking-level schedule.

A total number of car or two-wheeler spaces, visitor or accessible-space provision, ramps, vehicle entries and exits, mechanical parking, EV charging facilities in the sanctioned plan, and unit-wise parking allocations are not established in the supplied project documents. The permit’s parking condition does not itself establish exclusive parking ownership for any apartment. Document index

6. Amenities, recreation & open spaces

The GHMC permit records a tot-lot, rain-water-harvesting structures, trees and a separate amenities building. The RERA progress schedule provides declared percentages for selected project infrastructure; those percentages are reported as filed, not independently verified completion. RERA amenities

Tot-lot / green strip / park
Description / sizePermit records Tot-lot (m2) 2240 and requires fencing and maintenance as greenery.
Evidence sourceGHMC permit
Declared progress / verified statusRERA schedule: 90% for Green Strip/TOT LOT/Park; not independently verified. RERA amenities
Trees / periphery greenery
Description / sizePermit records 1160 Trees and requires tree plantation and a maintained strip of greenery.
Evidence sourceGHMC permit
Declared progress / verified statusNo completion verification supplied.
Amenities building
Description / sizeOne separate building, Ground + 3 upper floors; permit lists commercial ground area 520.05 m2 and upper-floor area 1,560.15 m2.
Evidence sourceGHMC permit
Declared progress / verified statusRERA schedule: Community Buildings 70%; not independently verified. RERA amenities
Internal roads and footpaths
Description / sizeFacility category recorded; no dimensions supplied.
Evidence sourceRERA amenity schedule
Declared progress / verified status100% declared. RERA amenities
Street lighting
Description / sizeFacility category recorded; no quantity supplied.
Evidence sourceRERA amenity schedule
Declared progress / verified status90% declared. RERA amenities
Water supply
Description / sizeFacility category recorded; details of source and capacity are not established in this schedule.
Evidence sourceRERA amenity schedule
Declared progress / verified status100% declared. RERA amenities
Sewerage (chamber, lines, septic tank, STP)
Description / sizeFacility category recorded; capacity and operating details not supplied.
Evidence sourceRERA amenity schedule
Declared progress / verified status90% declared. RERA amenities
Storm-water drains
Description / sizeFacility category recorded; dimensions not supplied.
Evidence sourceRERA amenity schedule
Declared progress / verified status90% declared. RERA amenities
Water conservation / rain-water harvesting
Description / sizeGHMC permit records 22 RWHPs.
Evidence sourceGHMC permit; RERA amenity schedule
Declared progress / verified statusRERA schedule: 80% declared; not independently verified. RERA amenities
Electrical meter room / sub-station / receiving station
Description / sizePermit requires space for a transformer; the RERA schedule records the electrical room/sub-station category.
Evidence sourceGHMC permit; RERA amenity schedule
Declared progress / verified status90% declared. RERA amenities
Sewage treatment and disposal; solid-waste management; energy management; fire protection; recreational open-space aggregate
Description / sizeCategories appear in the RERA schedule, but no facility description or completed provision is established by the supplied record.
Evidence sourceRERA amenity schedule
Declared progress / verified statusEach listed at 0%; this is a filed progress entry, not an independent inspection. RERA amenities

A clubhouse, pool, gym, theatre and other recreational features appear in promoter-supplied amenity material, not in the extracted GHMC permit or RERA amenity schedule as confirmed delivered facilities. They are therefore not represented here as sanctioned or completed project amenities. Promoter website

7. Utilities, building services & safety

The permit requires a rain-water-harvesting structure, space for a transformer and a garbage house within the premises. It also requires public amenities such as water and electricity connections to be provided only on production of an occupancy certificate. The RERA schedule records water supply at 100%, sewerage at 90%, storm-water drains at 90%, and electrical meter room/sub-station/receiving station at 90%; these are declared progress entries, not independently verified operating status. RERA amenities

The permit requires fire-safety measures, an occupancy Fire NOC before issue of an occupancy certificate, and automatic sprinkler systems in cellar floors before occupancy certification. It also requires services including sanitation, plumbing, fire safety, lifts and electrical installations to be supervised by qualified technical personnel. No issued Fire NOC, occupancy certificate, lift specification or capacity, water-storage or treatment capacity, STP capacity, backup-power capacity, or accessibility design details are established in the supplied project-specific official records.

Promoter-supplied specifications describe centralized water and LPG systems, lifts, power backup, CCTV and access control, among other features. These are promoter-provided descriptions and are not treated here as independently verified installation or operation. Promoter website

8. Location, access & connectivity

The registered project location is Yapral, Alwal mandal, Medchal-Malkajgiri district, Telangana, PIN 500087; the land record identifies Survey No. 49/PART. The GHMC permit describes the locality as “YAPRAL (Circle 17)” and identifies a 100 WIDE ROAD at the west boundary. RERA record Land records RERA filing

The supplied location record gives the nearest sampled Outer Ring Road interchange at approximately 4.3 km from the cadastral parcel centroid. This is a recorded approximate distance, not a travel-time estimate. Location record

Promoter-supplied material lists neighborhood destinations and travel-time claims, but the supplied project evidence does not independently verify those distances or times. No public-transport service details are established in the official project records provided. Promoter website

9. Developer & development status

The registered promoter is GK RAJ CONSTRUCTIONS, recorded as a partnership, with address in G K Colony, Yapral, Alwal, Medchal-Malkajgiri, PIN 500087. The RERA registration certificate separately states the promoter office as “Village: Mandal: Malkajgiri, District: Medchal-Malkajgiri, Pin: 500094.” The supplied evidence does not provide a company registration number or a project-specific official contact number. Corporate record Parties record

The RERA filing identifies KATIKANENI HANUMANTHA RAO as authorized signatory and lists the project’s landowners separately. The GHMC permit names GOPALA KRISHNA BUILDERS as developer/builder; this is the name recorded in that permit, while the TG-RERA registered promoter is GK RAJ CONSTRUCTIONS. Parties record Corporate record

The promoter’s Form B declaration, dated 05.12.2020, states a completion undertaking of 02.12.2026. The project header records 02/04/2027 as the proposed completion date. No block-wise construction progress or occupancy certificate is supplied, so the current physical completion status cannot be established from this record. RERA record RERA amenities

10. Approvals, official records & documents

RecordWhat the supplied evidence establishes
TG-RERA registration certificateForm C registration for GK RAJ CASA GRANDE, registration no. P02200002971, issued 20/05/2021, valid to 02/12/2026.
GHMC building permitRevised Building Permit Order 1/C28/12171/2020, dated 02 December, 2020, file no. 1/C28/09163/2020; includes eight residential blocks and an amenities building.
RERA Form B declarationPromoter declaration by K. Hanumantha Rao, dated 05.12.2020, including the stated title, encumbrance and completion declarations.
Project unit and land recordsRERA filing records Survey No. 49/PART, site area and unit schedule. RERA filing Land records RERA unit table
Layout documentA layout-plan document is listed in the RERA evidence, but no extracted approval content is supplied here. Document index
Occupancy / completion certificateNone supplied in the reviewed project evidence. The GHMC permit requires an occupancy certificate before occupation. Document index
HMDA layout lookupPublic approved-layout lookup is reported unavailable from the supplied evidence; this is an access limitation, not evidence of refusal. HMDA

Frequently asked questions

Is GK RAJ CASA GRANDE registered with Telangana RERA?

Yes. GK RAJ CASA GRANDE is registered with the Telangana Real Estate Regulatory Authority as P02200002971; the registration status is New Project.

Who is the developer of GK RAJ CASA GRANDE?

The promoter named in the RERA registration is GK RAJ CONSTRUCTIONS.

Where is GK RAJ CASA GRANDE located?

GK RAJ CASA GRANDE is in YAPRAL, Alwal, Medchal-Malkajgiri, Telangana (500087).

When will GK RAJ CASA GRANDE be completed?

The promoter's proposed date of completion filed with RERA is 02/04/2027. This is the promoter's declaration, not a guarantee.