Sign in

Greater Infras Carnation

GREATER INFRA PROJECTS PRIVATE LIMITED · Sangareddy · RERA P01100002703

GREATER INFRAS CARNATION is a residential apartment project in Ameenapur / Ameenpur, Ameenpur mandal, Sangareddy district. It is being developed by the registered promoter, GREATER INFRA PROJECTS PRIVATE LIMITED. The project occupies 3,176.69 sq. m and comprises one building with 1 cellar, 1 stilt and 5 upper floors, containing 80 apartments: 60 2BHK and 20 3BHK, with RERA-filed saleable areas of 102.19 m² and 135.64 m², respectively. It is registered under TG-RERA **P01100002703**, and the promoter-declared completion date is 31 December 2023.

More from Greater Infra Projects Pvt Ltd · 24 projects →

01What we found

Period endedTG-RERA registration ran to 31 Dec 2023 - check its extension on TG-RERA
29documents on file - each fact links to its page
0court cases on this project's land in the court records searched
9items to check - 3 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

9 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

Project photo

1. Project at a glance

Project identity

FieldProject record
Registered project nameGREATER INFRAS CARNATION
Project typeResidential apartment project
Phase / registered portionPhase not separately identified in the supplied record; one residential building is recorded
TG-RERA registrationP01100002703
Registration validity18 March 2021 to 31 December 2023; the certificate states “2 years” and says validity is subject to extension by the Authority
RERA statusRegistration period shown in the supplied certificate has ended; no extension is recorded there
Registered promoterGREATER INFRA PROJECTS PRIVATE LIMITED
Project completion undertakingPromoter-declared completion by 31 December 2023

RERA record

Land and geographic identity

FieldProject record
LocalityAmeenpur / Ameenapur (as stated in the filed and approval records)
Revenue villageAmeenapur; the occupancy record also identifies Ameenpur
MandalAmeenpur
DistrictSangareddy (also rendered “Sanga Reddy” in approval records)
PIN502032
Survey number(s)Survey No. 333; no project subdivision is stated in the RERA identity
Plot numbers in registration certificate110, 111, 112, 113/A, 113/B, 114, 115, 116, 117, 118, 119, 120, 121 Part, 121 Part and 122
Registered site extent3,176.69 sq. m in the RERA project fields
Approval/OC site extent3,177.28 sq. m in HMDA approval and occupancy records
Net / total area in OC recordSite area 3,177.28 m²; net area 3,177.28 m²; road-widening area 0.00
Boundaries filed with RERANorth: 30 FEET WIDE ROAD; South: PLOT NOS 109 AND 123; East: 40 FEET WIDE ROAD; West: NEIGHBOURS LAND

RERA record RERA filing

Development identity

FieldProject record
Sanctioning authorityHyderabad Metropolitan Development Authority (HMDA); approval record says building-plan sanction and release are to be handled by Ameenpur Municipality
Principal building approval033428/SKP/R1/U6/HMDA/29012020, approved 05/01/2021
Building configurationOne building, named CARNATION: 1 cellar, 1 stilt and 5 upper floors; the OC record lists 0 ground floors
Approved built-up areaHMDA technical approval lists proposed built-up area of 11,116.39 m² and “Total Built up Area” of 7,992.8 m². The OC record lists floor area of 7,992.8 m²
Parking area recorded at OC3,027.6 m²; a space count is not supplied
RERA unit count80 apartments: 60 2BHK and 20 3BHK
Approved unit countNot separately established in the supplied approval extracts
Parking levelsCellar and stilt are identified; the technical approval directs that the cellar/stilt be used exclusively for vehicle parking

RERA filing RERA unit table RERA unit details

Offering and status

FieldProject record
Configurations2BHK and 3BHK
RERA-filed saleable areas2BHK: 102.19 m²; 3BHK: 135.64 m²
Booking / availability11 booked and 69 available in the last-read TG-RERA portal record; no as-of date is supplied, so counts are indicative
Construction stageHMDA occupancy certificate records the building as fit for occupation; an architect’s certificate filed with RERA describes the project as completed in all aspects
Completion dates recordedPromoter’s Form B undertaking: 31 December 2023. HMDA OC record gives building completion date as 31 October 2022
Occupancy certificateHMDA OC 002089/OC/HMDA/SKP/2023, dated 02 January 2023; scope stated is the CARNATION residential building on Survey No. 333

RERA unit details RERA unit table

2. The project story

GREATER INFRAS CARNATION is registered as a residential apartment project on Survey No. 333 in Ameenapur/Ameenpur, Sangareddy district. The RERA filing describes 80 homes in one building: 60 two-bedroom apartments and 20 three-bedroom apartments. The HMDA technical approval describes one residential building with a cellar, stilt and five upper floors; its conditions reserve the cellar/stilt for vehicle parking. RERA record RERA filing RERA unit table

The supplied HMDA occupancy record identifies the CARNATION building, records completion on 31 October 2022 and an occupancy certificate issued on 02 January 2023. An architect’s certificate filed with TG-RERA, dated 25 January 2023, says the registered project was completed in all aspects. These records concern the named building/project; the supplied evidence does not identify a separate phase or additional tower.

The RERA portal’s last-read booking figures are 11 booked and 69 available, but the record provides no retrieval date for those counts. They should therefore be treated as indicative rather than a current inventory statement. RERA unit table

3. Master plan, architecture & building design

The RERA filing identifies a 3,176.69 sq. m site in Survey No. 333. HMDA’s technical approval and occupancy record state a site/net area of 3,177.28 m². The RERA filing gives approved built-up area as 11,116.39 m²; the HMDA technical-approval extract separately lists “Total Built up Area” of 7,992.8 m² and proposed built-up area of 11,116.39 m², while the OC record lists floor area of 7,992.8 m². These terms are reproduced as labelled in the records and are not interchangeable measurements. RERA filing

The development is recorded as one residential building, CARNATION, with one cellar, one stilt and five upper floors. The OC record states 0 ground floors. It records a parking area of 3,027.6 m² and building height of 14.95 m; the technical-approval extract lists a height of 14.5. No floor-by-floor apartment arrangement, apartment count per floor, footprint, lift or stair details, or site circulation drawing is available in the supplied evidence.

The HMDA technical approval requires a rainwater-harvesting structure and notes that no parking or construction is to be placed in setback areas. It also records a 10.18% built-up-area mortgage of 813.70 m² on the second floor in favour of HMDA. The supplied records do not provide a complete approved layout or a measured allocation of residential, common and open-space areas.

4. Homes, configurations & floor plans

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
2BHK601050102.19 m²Median 68.7 m²; range 67.9–69.4 m²33%
3BHK20119135.64 m²Not measured in supplied drawingsNot supplied

RERA unit counts, bookings and saleable areas are from the filing; booking counts have no supplied as-of date. The 2BHK carpet measurements are software-measured from the floor-plan drawing in document 147543, not RERA-filed figures, and the source notes that they require review. The drawing records a 2BHK example with two bedrooms, dining, kitchen, two toilets and a balcony; the balcony is excluded from the measured carpet area. RERA unit details Floor plans

Carpet area, saleable area and common-area loading are distinct measures. The RERA-filed saleable area is presented above separately from the drawing-derived carpet estimate; the supplied evidence does not provide a drawing-based 3BHK carpet measurement. RERA unit details Floor plans

5. Parking & vehicle circulation

The HMDA occupancy record lists a parking area of 3,027.6 m², and the technical approval identifies a cellar and stilt and directs that the cellar/stilt be used exclusively for vehicle parking without partition walls or rolling shutters. No sanctioned parking-space count, resident/visitor/accessibility breakdown, two-wheeler count, mechanical-parking provision, ramp details or unit-wise parking allocation is available in the supplied record. A recorded parking area does not by itself establish an exclusive parking allocation to a particular apartment.

The approval identifies the site boundary roads as 30 FEET WIDE ROAD to the north and 40 FEET WIDE ROAD to the east. It also refers to 18 mt. road widths in the technical-approval extract; the supplied record does not establish an internal driveway or pedestrian-vehicle circulation plan. RERA filing

6. Amenities, recreation & open spaces

FacilityDescription / sizeEvidence sourceDeclared progress / verified status
Tot-lot / green stripSize not suppliedHMDA technical approval; RERA amenity filingApproval extract lists a tot-lot; RERA filing marks “Green Strip/TOT LOT/Park” at 100%
Rainwater harvestingSize/capacity not suppliedHMDA technical approval; RERA amenity filing; OC recordRequired by technical approval; RERA filing marks water conservation/rainwater harvesting at 100%; OC record lists RWH
Community buildingsNo facility detail suppliedRERA amenity filingRERA filing records 0%
Aggregate recreational open spaceArea not suppliedRERA amenity filingRERA filing records 0%

The percentages above are promoter/RERA portal declarations, not independent site verification. The supplied evidence does not specify a clubhouse, indoor recreation facilities, sports courts or other recreational facilities. RERA amenities

7. Utilities, building services & safety

Water supply and storage
Evidence in project recordHMDA technical approval lists water supply, an underground static water tank of 25,000 litres and a separate residential terrace tank of 25,000 litres
Status represented by the evidenceApproval provision; no separate completion verification or ongoing supply source is supplied
Sewerage and drainage
Evidence in project recordTechnical approval lists a septic tank and requires water supply, drainage and sewerage disposal arrangements; RERA amenity filing marks “Sewerage (Chamber, Lines, Septic Tank, STP)” at 100%
Status represented by the evidenceApproval requirement and promoter-filed percentage; no capacity or independent operational verification supplied
Storm-water drainage
Evidence in project recordRERA amenity filing records 0% for storm-water drains
Status represented by the evidencePortal declaration
Electrical supply and backup
Evidence in project recordTechnical approval lists a transformer and generator; RERA filing marks the electrical meter room/sub-station/receiving station and generator at 100%
Status represented by the evidenceApproval list and promoter-filed percentages; no capacity or independent verification supplied
Fire and emergency systems
Evidence in project recordTechnical approval lists fire extinguishers, hose reel/down corner, automatic sprinkler system and emergency lighting; it specifies a minimum of four fire extinguishers per floor
Status represented by the evidenceApproval provisions; the supplied extracts do not establish installation or fire-clearance status
Waste
Evidence in project recordTechnical approval lists a garbage house; RERA filing records solid-waste management and disposal at 0%
Status represented by the evidenceApproval list and portal declaration
Security
Evidence in project recordRERA filing marks “CC CAMERAS” at 100%
Status represented by the evidencePortal declaration; no independent verification supplied
Lifts and accessibility
Evidence in project recordNo lift, service-lift, accessible-circulation or ramp details supplied
Status represented by the evidenceNot established in the supplied evidence

RERA amenities

8. Location, access & connectivity

The registered location is Ameenapur/Ameenpur, Ameenpur mandal, Sangareddy district, Telangana, PIN 502032; the registered land is identified as Survey No. 333. The cadastral parcel-centroid coordinate supplied is 17.52587116374659, 78.33948761635529. This is a software/cadastral location reference, not a measured apartment or site-access point. RERA record RERA filing Location record Cadastral map

The supplied location record gives the nearest sampled Outer Ring Road interchange at approximately 8.4 km. No approach-road route, public-transport stop, landmark distance or travel time is supplied. Location record

9. Developer & development status

The registered legal promoter is GREATER INFRA PROJECTS PRIVATE LIMITED, a private limited company. The supplied corporate identifier is GSTIN 36AAHCG8193L1ZX. The promoter address recorded in the project evidence is 217/A, Opp Metro Station, Sree Balaji Nagar, Ameenpur, Ameenpur, Sangareddy, 502032. Corporate record Parties record

The promoter’s Form B affidavit, dated January 2021 and signed by authorized signatory N. Srinivas, undertakes completion by 31 December 2023 and states that pending approvals would be obtained. The project record also contains an HMDA occupancy certificate for the CARNATION building dated 02 January 2023 and an architect’s completion certificate dated 25 January 2023. These documents concern the building/project completion and occupancy record; the TG-RERA registration certificate separately shows validity through 31 December 2023 and no extension in the supplied certificate.

10. Approvals, official records & documents

TG-RERA registration certificate
Identifier / dateP01100002703, issued 18/03/2021; valid through 31/12/2023
Scope and evidenceForm C for GREATER INFRAS CARNATION; Survey No. 333;
HMDA technical building approval
Identifier / date033428/SKP/R1/U6/HMDA/29012020, approved 05/01/2021
Scope and evidenceResidential building on Survey No. 333; technical approval extract records one cellar, one stilt and five upper floors;
HMDA occupancy certificate
Identifier / date002089/OC/HMDA/SKP/2023, dated 02 January 2023
Scope and evidenceCARNATION residential building, Survey No. 333; completion date recorded as 31 October 2022;
Architect’s completion certificate
Identifier / dateDated 25-01-2023; cites OC 002089/OC/HMDA/SKP/2023
Scope and evidenceCertifies overall completion of GREATER INFRAS CARNATION;
Form B promoter declaration
Identifier / dateJanuary 2021
Scope and evidenceProject completion undertaking and project-account/audit commitments;
Floor-plan drawing record
Identifier / dateDocument 147543
Scope and evidenceOne drawing measured for 2BHK carpet-area estimates; software-measured, not a RERA disclosure;

The supplied records identify HMDA as the technical-approval and occupancy-certificate authority and state that building-plan sanction/release is to be handled by Ameenpur Municipality. An approved layout-plan document or a separately extracted municipal building-sanction certificate is not available in the supplied materials.

Frequently asked questions

Is GREATER INFRAS CARNATION registered with Telangana RERA?

Yes. GREATER INFRAS CARNATION is registered with the Telangana Real Estate Regulatory Authority as P01100002703; the registration status is New Project.

Who is the developer of GREATER INFRAS CARNATION?

The promoter named in the RERA registration is GREATER INFRA PROJECTS PRIVATE LIMITED.

Where is GREATER INFRAS CARNATION located?

GREATER INFRAS CARNATION is in AMEENPUR, AMEENAPUR, Sangareddy, Telangana (502032).

When will GREATER INFRAS CARNATION be completed?

The promoter's proposed date of completion filed with RERA is 31/12/2023. This is the promoter's declaration, not a guarantee.

More projects in Ameenapur