Hari Hara Hibiscus
HARI HARA INFRA · Medchal-Malkajgiri · RERA P02200010836
HARI HARA HIBISCUS is a residential apartment project in Bachupally, Bachupally mandal, Medchal-Malkajgiri district. The registered promoter developing it is HARI HARA INFRA. The project covers 3,872.01 sq.m and comprises one building with 1 Stilt + 5 Floors and 95 apartments: 80 2BHK and 15 3BHK. It is registered under TG-RERA number P02200010836, with proposed completion recorded as 24/03/2029.
More from Hari Hara Infra · 5 projects →
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
7 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Item | Project record |
|---|---|
| Registered project name | HARI HARA HIBISCUS RERA record |
| Project type | Residential apartment project RERA record |
| Phase / registered portion | One registered project; the registration record identifies the listed Bachupally survey land. No separate phase name is disclosed. |
| TG-RERA registration | P02200010836 |
| Registration validity | 24 November 2025 to 24 November 2028. This is the registration period, not the building-permit completion deadline. RERA record |
| Registered promoter | HARI HARA INFRA RERA record |
| RERA status | The certificate records registration; no extension or later status change is supplied. |
Land and geographic identity
| Item | Project record |
|---|---|
| Locality | Bachupally RERA record |
| Revenue village | Bachupally RERA record |
| Mandal | Bachupally RERA record |
| District | Medchal-Malkajgiri RERA record |
| PIN | 500090 RERA record |
| Project survey numbers | 407/A, 407/B, 419, 420 and 421 |
| Registered site extent | 3,872.01 sq.m RERA filing |
| Sanctioned gross / net plot area | Gross Plot Area 3,872.01 sq.m; Net Plot Area 3,872.01 sq.m. The plan records zero deductions for road affected area, nala widening, water bodies, splay, peripheral road and total plot deductions. |
| Boundaries | East: LAND IN SY NO 420 P; West: 30 FEET WIDE ROAD; North: NEIGHBOURS LAND IN SY NO 473 AND 479; South: 30 FEET WIDE ROAD. RERA filing |
Development identity
| Item | Project record |
|---|---|
| Sanctioning authority | Hyderabad Metropolitan Development Authority (HMDA); the permit records delegation to Nizampet Municipal Corporation for release of proceedings/plans. Approvals record |
| Principal approval | Building permit file 008100/HMDA/02397/SWBP/MDL1/2025, approved 24/11/2025. Approvals record |
| Approved built-up area | 10,007.3 sq.m excluding parking; 12,302.16 sq.m including parking, as recorded in the plan. |
| Building count and configuration | One residential building; sanctioned as 1 Stilt + 5 Floors. RERA filing |
| Height | The permit extraction records Total Height 21.96 m, Height from GL 17.95 m, Excluding Stilt 15 m, and a separate sanctioned-parameter entry of Height of the Building (m) 15.0. |
| Parking provision | 65.00 Car Parking Spaces; Visitor Parking Area 241.95 (12.09 %). The permit also records Total Parking Area 2052.91 Sq. Mtrs. |
| Units | Sanctioned plan: 95 units; TG-RERA filing: 95 total units. RERA unit table |
Offering and status
| Item | Project record |
|---|---|
| Configurations | 2BHK and 3BHK apartments. RERA unit table |
| TG-RERA saleable area | 2BHK: 105.82 sq.m; 3BHK: 157.93 sq.m. RERA unit table |
| Booked / available | 2BHK: 0 booked, 80 available; 3BHK: 0 booked, 15 available. These portal counts have no supplied as-of date and are indicative. RERA unit table |
| Construction stage | Not established by the supplied evidence. The permit describes proposed construction; no independently verified site-progress report is provided. |
| Completion dates | The Form B declaration undertakes completion by 24-11-2028; the building permit states construction to be completed before 24/11/2028. The project header records proposed completion as 24/03/2029. RERA record |
| Occupancy / completion certificate | No occupancy or completion certificate is supplied; the building permit requires the promoter to approach HMDA for an occupancy certificate after construction. |
2. The project story
HARI HARA HIBISCUS is registered as a residential apartment development at Bachupally, on the combined project land identified in the filing as survey numbers 407/A, 407/B, 419, 420 and 421. The RERA certificate identifies Bachupally village and mandal, Medchal-Malkajgiri district, and PIN 500090.
The filed plan describes one building, configured as 1 Stilt + 5 Floors, with 95 sanctioned units. The RERA unit schedule lists 80 two-bedroom and 15 three-bedroom apartments. The plan is for proposed construction, and the supplied evidence does not establish construction progress or completion at site. RERA unit table
The promoter’s Form B declaration states a completion undertaking of 24-11-2028. The permit also gives 24/11/2028 as the construction completion deadline; the project header separately records a proposed completion date of 24/03/2029. No occupancy certificate is included in the supplied documents. RERA record
3. Master plan, architecture & building design
The HMDA plan records a gross and net plot area of 3,872.01 sq.m, proposed coverage of 2,315.76 sq.m (60%), and vacant plot area of 1,501.75 sq.m. These are plan figures; “vacant plot area” is not described as a specific landscaped or recreational area.
The development is a single residential building, shown as 1 Stilt + 5 Floors. The plan records 10,007.3 sq.m proposed built-up area excluding parking and 12,302.16 sq.m including parking. It records no commercial area.
The plan specifies 197.71 sq.m for the tot-lot and three green strips of 119.76 sq.m, 38.21 sq.m, and 62.83 sq.m. It also records setbacks: front 3.0 m, rear 6.0 m, and each side 6.0 m. These are plan entries, not evidence that the spaces or landscaping have been completed.
The supplied extracts do not establish floor-by-floor apartment counts, building footprint drawings, lift or stair details, or the number and arrangement of entrances and exits. RERA saleable area and software-measured carpet area are set out separately below; the documents do not identify a separate FSI-counted area. Floor plans RERA unit details
4. Homes, configurations & floor plans
The TG-RERA filing lists 95 apartments: 80 2BHK and 15 3BHK. Its saleable-area figures are separate from the software measurements made from the filed floor-plan drawings. RERA unit table RERA unit details Floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK | 80 | 0 | 80 | 105.82 sq.m | Software-measured range: 66.8–82.4 sq.m; median 75.3 sq.m (811 sq.ft median) | 29% |
| 3BHK | 15 | 0 | 15 | 157.93 sq.m | Software-measured range: 91.8–122.1 sq.m; median 113.9 sq.m (1,226 sq.ft median) | 28% |
Carpet-area measurements were software-measured from the approved-drawing geometry in document 673573, are marked as needing review, and are not RERA disclosures. The drawing set has four drawings, of which two were measured and two remain scans pending; the configuration measurements cover 32 2BHK designs and 6 3BHK designs. Floor plans
The extracted typical 2BHK plan includes living/dining, bedrooms, kitchen, toilets, puja space, wash area and an open-to-air balcony. The 3BHK example includes living/dining, bedrooms, kitchen, toilets, wash area and open-to-air balconies. Room dimensions in the extraction are drawing-measured and not RERA-filed; they should be checked against the drawing. Balcony space is excluded from the supplied carpet-area measurement. RERA unit details
“Saleable area” is the RERA-filed figure; the drawing-based carpet measurements are a different measurement and should not be treated as interchangeable. The supplied data does not provide a separate RERA-filed carpet area. RERA unit table Floor plans
5. Parking & vehicle circulation
The HMDA plan records 65.00 car parking spaces, visitor parking area of 241.95 (12.09 %), and total parking area of 2052.91 Sq. Mtrs. The building permit identifies the stilt as a parking level and requires the approved stilt/cellar parking provision to be used exclusively for vehicle parking, without partition walls or rolling shutters. The supplied plan summary does not identify a separate basement level.
The plan also lists road widths of 9.0 m, 9m Wide Main Road, 9m Wide Sub Road, 4.5m Wide Drive Way, 5.08m Wide Drive Way, and 9.0 M (30'0"). The supplied evidence does not specify resident versus visitor bay counts beyond the visitor parking area, two-wheeler spaces, accessible parking, mechanical parking, EV charging, or a unit-by-unit parking allocation. A plan bay does not itself establish exclusive ownership.
6. Amenities, recreation & open spaces
The RERA amenity schedule marks several project infrastructure items as available, but records 0% progress for each listed entry. “Available” in this schedule is therefore presented as a filed status, not as independently verified completion. RERA amenities
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Green strip / tot-lot / park | Plan records Tot-lot 197.71 sq.m and green strips of 119.76 sq.m, 38.21 sq.m, and 62.83 sq.m. | RERA amenities | Plan provision; amenity schedule marks Green Strip/TOT LOT/Park “YES” and 0%; completion not independently verified. |
| Community buildings | No size or facility details supplied. | RERA amenities | No “available” value stated; 0% recorded. |
| Recreational open space | No separate aggregate area stated in the amenity schedule. | RERA amenities | 0% recorded. |
The plan conditions require the tot-lot to be fenced and maintained as greenery before issue of the occupancy certificate, and require tree planting along the periphery and in front of the premises. No completed landscaping is independently verified.
7. Utilities, building services & safety
The building-permit plan lists a 90KLD sewage treatment plant for Phase 1, a 9.1X3.30M sump, a 2.3X5.1M septic tank and a 7.0X6.0M pump room. It also identifies rainwater harvesting, transformer space and a garbage house. These are plan provisions; the supplied material does not establish installation, commissioning, or operational status.
The permit extraction specifies 3 rainwater-harvesting pits and 185 trees. It requires a rainwater-harvesting structure (percolation pit), transformer space, and a garbage house within the premises.
The RERA amenity schedule marks water supply, sewerage, storm-water drains, street lighting, fire protection and fire safety requirements, and electrical meter room/sub-station/receiving station as “YES”, each with 0% progress. No water source, storage or treatment capacity beyond the listed sump; sewage-reuse arrangements; electrical backup; lift capacities; installed fire systems; security/CCTV; waste-segregation process; or accessibility provisions are established by the supplied material. RERA amenities
The permit states that an occupancy fire NOC is to be obtained before issue of an occupancy certificate, and that occupancy certification is compulsory before occupation. These are permit conditions, not evidence that the NOC or certificate has been obtained.
8. Location, access & connectivity
The registered location is Bachupally village, Bachupally mandal, Medchal-Malkajgiri district, Telangana 500090. The project boundaries recorded in the filing include 30-foot-wide roads on the west and south sides. RERA record RERA filing
The location data provides one connectivity reference: HITEC City — 10.9 km. No route, travel time or public-transport connection is supplied in that record. Location record
9. Developer & development status
The registered promoter is HARI HARA INFRA, identified in the project records as a partnership. The RERA certificate gives its address as Bachupally, Bachupally, Medchal-Malkajgiri, PIN 500090. The supplied corporate identifier is GSTIN 36AANFH4838G1Z3. RERA record Corporate record
The RERA certificate names KANDI RAGHAVA REDDY as representing the promoter. The project filing also identifies landowners and HARI HARA INFRA as the development-agreement-cum-GPA holder.
The available records describe proposed construction and include no independently verified construction-progress figure. The promoter’s Form B declaration gives a completion undertaking of 24-11-2028; the permit states construction is to be completed before 24/11/2028. No occupancy certificate is supplied.
10. Approvals, official records & documents
| Record | What the supplied document establishes |
|---|---|
| TG-RERA certificate — P02200010836 | Form C registration for HARI HARA HIBISCUS; validity from 24/11/2025 to 24/11/2028. |
| HMDA building permit — 008100/HMDA/02397/SWBP/MDL1/2025 | Approved 24/11/2025; proposed residential building of 1 Stilt + 5 Floors on the listed Bachupally survey land, with sanctioned parameters and conditions. |
| HMDA plan drawing | Plan records the proposed building, land area, built-up areas, coverage, tot-lot, green strips, parking and utilities. |
| HMDA technical approval — same file number | Technical approval forwarded to the Municipal Commissioner, Nizampet Municipal Corporation, for release of proceedings and plans; the document does not itself state that those proceedings and plans were released. |
| Form B declaration | Promoter declaration and completion undertaking of 24-11-2028. |
| Occupancy / completion certificate | Not supplied in the reviewed project documents. The permit calls for application for an occupancy certificate after construction. |
| Layout approval record | The supplied permit is a building-permission plan; no separate layout-approval certificate is identified in the supplied evidence. |
The reviewed overview evidence is limited to the supplied project documents and extracts; it does not establish on-site completion or independently verify the listed facilities.
1. Project at a glance
Project identity
Registered project name: HARI HARA HIBISCUS
Project type: Residential apartment project
Phase / registered portion: One registered project; the registration record identifies the listed Bachupally survey land. No separate phase name is disclosed.
TG-RERA registration: P02200010836
Registration validity: 24 November 2025 to 24 November 2028. This is the registration period, not the building-permit completion deadline.
Registered promoter: HARI HARA INFRA
RERA status: The certificate records registration; no extension or later status change is supplied.
Land and geographic identity
Locality: Bachupally
Revenue village: Bachupally
Mandal: Bachupally
District: Medchal-Malkajgiri
PIN: 500090
Project survey numbers: 407/A, 407/B, 419, 420 and 421
Registered site extent: 3,872.01 sq.m
Sanctioned gross / net plot area: Gross Plot Area 3,872.01 sq.m; Net Plot Area 3,872.01 sq.m. The plan records zero deductions for road affected area, nala widening, water bodies, splay, peripheral road and total plot deductions.
Boundaries: East: LAND IN SY NO 420 P; West: 30 FEET WIDE ROAD; North: NEIGHBOURS LAND IN SY NO 473 AND 479; South: 30 FEET WIDE ROAD.
Development identity
Sanctioning authority: Hyderabad Metropolitan Development Authority (HMDA); the permit records delegation to Nizampet Municipal Corporation for release of proceedings/plans.
Principal approval: Building permit file 008100/HMDA/02397/SWBP/MDL1/2025, approved 24/11/2025.
Approved built-up area: 10,007.3 sq.m excluding parking; 12,302.16 sq.m including parking, as recorded in the plan.
Building count and configuration: One residential building; sanctioned as 1 Stilt + 5 Floors.
Height: The permit extraction records Total Height 21.96 m, Height from GL 17.95 m, Excluding Stilt 15 m, and a separate sanctioned-parameter entry of Height of the Building (m) 15.0.
Parking provision: 65.00 Car Parking Spaces; Visitor Parking Area 241.95 (12.09 %). The permit also records Total Parking Area 2052.91 Sq. Mtrs.
Units: Sanctioned plan: 95 units; TG-RERA filing: 95 total units.
Offering and status
Configurations: 2BHK and 3BHK apartments.
TG-RERA saleable area: 2BHK: 105.82 sq.m; 3BHK: 157.93 sq.m.
Booked / available: 2BHK: 0 booked, 80 available; 3BHK: 0 booked, 15 available. These portal counts have no supplied as-of date and are indicative.
Construction stage: Not established by the supplied evidence. The permit describes proposed construction; no independently verified site-progress report is provided.
Completion dates: The Form B declaration undertakes completion by 24-11-2028; the building permit states construction to be completed before 24/11/2028. The project header records proposed completion as 24/03/2029.
Occupancy / completion certificate: No occupancy or completion certificate is supplied; the building permit requires the promoter to approach HMDA for an occupancy certificate after construction.
2. The project story
HARI HARA HIBISCUS is registered as a residential apartment development at Bachupally, on the combined project land identified in the filing as survey numbers 407/A, 407/B, 419, 420 and 421. The RERA certificate identifies Bachupally village and mandal, Medchal-Malkajgiri district, and PIN 500090.
The filed plan describes one building, configured as 1 Stilt + 5 Floors, with 95 sanctioned units. The RERA unit schedule lists 80 two-bedroom and 15 three-bedroom apartments. The plan is for proposed construction, and the supplied evidence does not establish construction progress or completion at site.
The promoter’s Form B declaration states a completion undertaking of 24-11-2028. The permit also gives 24/11/2028 as the construction completion deadline; the project header separately records a proposed completion date of 24/03/2029. No occupancy certificate is included in the supplied documents.
3. Master plan, architecture & building design
The HMDA plan records a gross and net plot area of 3,872.01 sq.m, proposed coverage of 2,315.76 sq.m (60%), and vacant plot area of 1,501.75 sq.m. These are plan figures; “vacant plot area” is not described as a specific landscaped or recreational area.
The development is a single residential building, shown as 1 Stilt + 5 Floors. The plan records 10,007.3 sq.m proposed built-up area excluding parking and 12,302.16 sq.m including parking. It records no commercial area.
The plan specifies 197.71 sq.m for the tot-lot and three green strips of 119.76 sq.m, 38.21 sq.m, and 62.83 sq.m. It also records setbacks: front 3.0 m, rear 6.0 m, and each side 6.0 m. These are plan entries, not evidence that the spaces or landscaping have been completed.
The supplied extracts do not establish floor-by-floor apartment counts, building footprint drawings, lift or stair details, or the number and arrangement of entrances and exits. RERA saleable area and software-measured carpet area are set out separately below; the documents do not identify a separate FSI-counted area.
4. Homes, configurations & floor plans
The TG-RERA filing lists 95 apartments: 80 2BHK and 15 3BHK. Its saleable-area figures are separate from the software measurements made from the filed floor-plan drawings.
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK | 80 | 0 | 80 | 105.82 sq.m | Software-measured range: 66.8–82.4 sq.m; median 75.3 sq.m (811 sq.ft median) | 29% |
| 3BHK | 15 | 0 | 15 | 157.93 sq.m | Software-measured range: 91.8–122.1 sq.m; median 113.9 sq.m (1,226 sq.ft median) | 28% |
Carpet-area measurements were software-measured from the approved-drawing geometry in document 673573, are marked as needing review, and are not RERA disclosures. The drawing set has four drawings, of which two were measured and two remain scans pending; the configuration measurements cover 32 2BHK designs and 6 3BHK designs.
The extracted typical 2BHK plan includes living/dining, bedrooms, kitchen, toilets, puja space, wash area and an open-to-air balcony. The 3BHK example includes living/dining, bedrooms, kitchen, toilets, wash area and open-to-air balconies. Room dimensions in the extraction are drawing-measured and not RERA-filed; they should be checked against the drawing. Balcony space is excluded from the supplied carpet-area measurement.
“Saleable area” is the RERA-filed figure; the drawing-based carpet measurements are a different measurement and should not be treated as interchangeable. The supplied data does not provide a separate RERA-filed carpet area.
5. Parking & vehicle circulation
The HMDA plan records 65.00 car parking spaces, visitor parking area of 241.95 (12.09 %), and total parking area of 2052.91 Sq. Mtrs. The building permit identifies the stilt as a parking level and requires the approved stilt/cellar parking provision to be used exclusively for vehicle parking, without partition walls or rolling shutters. The supplied plan summary does not identify a separate basement level.
The plan also lists road widths of 9.0 m, 9m Wide Main Road, 9m Wide Sub Road, 4.5m Wide Drive Way, 5.08m Wide Drive Way, and 9.0 M (30'0"). The supplied evidence does not specify resident versus visitor bay counts beyond the visitor parking area, two-wheeler spaces, accessible parking, mechanical parking, EV charging, or a unit-by-unit parking allocation. A plan bay does not itself establish exclusive ownership.
6. Amenities, recreation & open spaces
The RERA amenity schedule marks several project infrastructure items as available, but records 0% progress for each listed entry. “Available” in this schedule is therefore presented as a filed status, not as independently verified completion.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Green strip / tot-lot / park | Plan records Tot-lot 197.71 sq.m and green strips of 119.76 sq.m, 38.21 sq.m, and 62.83 sq.m. | Plan provision; amenity schedule marks Green Strip/TOT LOT/Park “YES” and 0%; completion not independently verified. | |
| Community buildings | No size or facility details supplied. | No “available” value stated; 0% recorded. | |
| Recreational open space | No separate aggregate area stated in the amenity schedule. | 0% recorded. |
The plan conditions require the tot-lot to be fenced and maintained as greenery before issue of the occupancy certificate, and require tree planting along the periphery and in front of the premises. No completed landscaping is independently verified.
7. Utilities, building services & safety
The building-permit plan lists a 90KLD sewage treatment plant for Phase 1, a 9.1X3.30M sump, a 2.3X5.1M septic tank and a 7.0X6.0M pump room. It also identifies rainwater harvesting, transformer space and a garbage house. These are plan provisions; the supplied material does not establish installation, commissioning, or operational status.
The permit extraction specifies 3 rainwater-harvesting pits and 185 trees. It requires a rainwater-harvesting structure (percolation pit), transformer space, and a garbage house within the premises.
The RERA amenity schedule marks water supply, sewerage, storm-water drains, street lighting, fire protection and fire safety requirements, and electrical meter room/sub-station/receiving station as “YES”, each with 0% progress. No water source, storage or treatment capacity beyond the listed sump; sewage-reuse arrangements; electrical backup; lift capacities; installed fire systems; security/CCTV; waste-segregation process; or accessibility provisions are established by the supplied material.
The permit states that an occupancy fire NOC is to be obtained before issue of an occupancy certificate, and that occupancy certification is compulsory before occupation. These are permit conditions, not evidence that the NOC or certificate has been obtained.
8. Location, access & connectivity
The registered location is Bachupally village, Bachupally mandal, Medchal-Malkajgiri district, Telangana 500090. The project boundaries recorded in the filing include 30-foot-wide roads on the west and south sides.
The location data provides one connectivity reference: HITEC City — 10.9 km. No route, travel time or public-transport connection is supplied in that record.
9. Developer & development status
The registered promoter is HARI HARA INFRA, identified in the project records as a partnership. The RERA certificate gives its address as Bachupally, Bachupally, Medchal-Malkajgiri, PIN 500090. The supplied corporate identifier is GSTIN 36AANFH4838G1Z3.
The RERA certificate names KANDI RAGHAVA REDDY as representing the promoter. The project filing also identifies landowners and HARI HARA INFRA as the development-agreement-cum-GPA holder.
The available records describe proposed construction and include no independently verified construction-progress figure. The promoter’s Form B declaration gives a completion undertaking of 24-11-2028; the permit states construction is to be completed before 24/11/2028. No occupancy certificate is supplied.
10. Approvals, official records & documents
TG-RERA certificate — P02200010836: Form C registration for HARI HARA HIBISCUS; validity from 24/11/2025 to 24/11/2028.
HMDA building permit — 008100/HMDA/02397/SWBP/MDL1/2025: Approved 24/11/2025; proposed residential building of 1 Stilt + 5 Floors on the listed Bachupally survey land, with sanctioned parameters and conditions.
HMDA plan drawing: Plan records the proposed building, land area, built-up areas, coverage, tot-lot, green strips, parking and utilities.
HMDA technical approval — same file number: Technical approval forwarded to the Municipal Commissioner, Nizampet Municipal Corporation, for release of proceedings and plans; the document does not itself state that those proceedings and plans were released.
Form B declaration: Promoter declaration and completion undertaking of 24-11-2028.
Occupancy / completion certificate: Not supplied in the reviewed project documents. The permit calls for application for an occupancy certificate after construction.
Layout approval record: The supplied permit is a building-permission plan; no separate layout-approval certificate is identified in the supplied evidence.
The reviewed overview evidence is limited to the supplied project documents and extracts; it does not establish on-site completion or independently verify the listed facilities.
Frequently asked questions
Is HARI HARA HIBISCUS registered with Telangana RERA?
Yes. HARI HARA HIBISCUS is registered with the Telangana Real Estate Regulatory Authority as P02200010836; the registration status is New Project.
Who is the developer of HARI HARA HIBISCUS?
The promoter named in the RERA registration is HARI HARA INFRA.
Where is HARI HARA HIBISCUS located?
HARI HARA HIBISCUS is in BACHUPALLY, Medchal-Malkajgiri, Telangana (500090).
When will HARI HARA HIBISCUS be completed?
The promoter's proposed date of completion filed with RERA is 24/03/2029. This is the promoter's declaration, not a guarantee.