Sathya Abode

SATHYA INFRATECH · Sangareddy · RERA P01100010254

SATHYA ABODE is a residential apartment project in Ameenpur, AMEENPUR mandal, Sangareddy district. The registered promoter developing it is SATHYA INFRATECH, partnership. The project covers 446.13 sq.m and comprises 1 building sanctioned as 1 Stilt + 5 Floors, with 15 2BHK apartments, each with a saleable area of 71.69 sq.m. It is registered under TG-RERA number P01100010254, and the proposed completion date recorded in the project header is 22/01/2029.

More from Sathya Infratech · 4 projects →

01What we found

RegisteredTG-RERA - valid till 22 Sep 2028
19documents on file - each fact links to its page
0court cases on this project's land in the court records searched
8items to check - 3 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

8 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

1. Project at a glance

Project identity

FieldProject record
Registered project nameSATHYA ABODE RERA record [REGCERT-71681]
Project type / phaseResidential apartment project; phase or separately identified registered portion is not specified in the supplied record. RERA record RERA filing
TG-RERA registrationP01100010254 [REGCERT-71681]
Registration validity22/09/2025 to 22/09/2028, unless extended by the Authority. This is the registration-validity period, not the building’s completion deadline. [REGCERT-71681 p1]
Registered promoterSATHYA INFRATECH, partnership. [REGCERT-71681] Corporate record
RERA statusRegistered project; the registration record states that quarterly updates are to be submitted. The supplied registration certificate does not establish an occupancy certificate. [REGCERT-71681 p1]

Land and geographic identity

FieldProject record
LocalityAmeenpur / Ameenpur Municipality RERA record
Revenue villageAMEENAPUR (also rendered “Ameenpur” in the building-permit extracts). RERA record [REGCERT-71681]
MandalAMEENPUR RERA record [REGCERT-71681]
DistrictSangareddy RERA record [REGCERT-71681]
PIN502032 RERA record [REGCERT-71681]
Project survey numbers128, 129 AND 130 PARTS; the filed building plan specifies Survey Nos. 128, 129 & 130 PARTS. The supplied record does not identify the relevant subdivisions within each survey number. RERA record
PlotsPlot Nos. 429 and 430
Registered / sanctioned site extent446.13 sq.m: the building-permit extract records gross and net plot area as 446.13 sq.m.
Boundaries in RERA filingEast: 33FT WIDE ROAD; West: PLOT NO S 421 AND 422; North: PLOT NO 428; South: 40FT WIDE ROAD. RERA filing

Development identity

FieldProject record
Sanctioning authorityHyderabad Metropolitan Development Authority (HMDA); the permit is addressed/delegated to Ameenpur Municipality.
Principal building-permit number / date006218/HMDA/01875/SWBP/SKP2/2025, approved 22/09/2025.
Municipality permit number0644/HMDA/SWBP/2025, approved 22/09/2025.
Approved built-up area1255.4 sq.m excluding parking; 1506.48 sq.m including parking, as recorded in the filed plan.
Building count and configuration1 building; sanctioned as 1 Stilt + 5 Floors.
Height recorded in permit extractBuilding height 14.5 m; total height 19.65 m.
ParkingSanctioned parking area 251.08 sq.m; the plan extract records Car Parking Spaces: 2.00.
Unit count15 dwelling units in the approved-plan extract and 15 apartments in the RERA unit record. RERA unit table

Offering and status

FieldProject record
RERA-filed configuration2BHK, 15 units; saleable area 71.69 sq.m per unit. RERA unit table RERA unit table
Booked / available4 booked; 11 available, as last read from the TG-RERA portal. The portal record supplied here has no as-of date; treat these counts as indicative. RERA unit table
Construction stageRERA filing records Water Supply: 40%, Sewerage: 20%, and Water Conservation, Rain water Harvesting: 20%; other listed infrastructure items show 0% or no reported percentage. These are filed progress figures, not independent site verification. RERA amenities
Completion deadlineThe RERA registration certificate is valid to 22/09/2028; the Form B declaration also undertakes completion by 22/09/2028. [REGCERT-71681 p1]
Other completion date shown in project recordThe project header records proposed completion 22/01/2029. RERA record
Occupancy / completion certificateNo occupancy or completion certificate is evidenced in the supplied documents; the building-permit extract records completion certification as false.

2. The project story

SATHYA ABODE is a single-building residential apartment project on Plot Nos. 429 and 430, within Survey Nos. 128, 129 AND 130 PARTS, in revenue village AMEENAPUR, Ameenpur mandal, Sangareddy district. The RERA-filed site extent is 446.13 sq.m. The project’s sanctioned form is one building with a stilt level and five floors, with 15 dwelling units. RERA record RERA unit table

The RERA unit record lists 15 2BHK apartments. It shows four booked and eleven available, but provides no as-of date for those counts. The project is registered through 22/09/2028, and the promoter’s Form B declaration states a completion target of 22/09/2028. No occupancy or completion certificate is present in the supplied evidence. The filed infrastructure progress figures are limited to the items shown in the Overview tables; they are not independent confirmation of on-site work. RERA unit table [REGCERT-71681 p1] RERA amenities

3. Master plan, architecture & building design

The filed building plan identifies a gross and net plot area of 446.13 sq.m, with proposed coverage of 251.08 sq.m (56.00%) and vacant plot area of 180.06 sq.m. It records total proposed built-up area as 1255.4 sq.m excluding parking and 1506.48 sq.m including parking. These are the plan’s stated areas; no separate FSI-counted area or carpet-area total is supplied.

The sanctioned building is 1 Stilt + 5 Floors. The filed plan records a 2.5 m wide corridor and 4.5 m wide driveway. The permit extract specifies front setback of 3.0 m, rear setback of 2.5 m, and side setbacks of 2.5 m each. The supplied extracted records do not establish the number of flats per floor, lift or stair configuration, or floor-by-floor common-area arrangement.

The plan lists a tot-lot and greenery-related conditions, but the commencement-certificate extract records “Tot Lot” as 0 sq.m. The supplied evidence does not provide a quantified landscaped/open-space schedule beyond those entries.

4. Homes, configurations & floor plans

The RERA filing records 15 2BHK apartments, each with a saleable area of 71.69 sq.m. The table distinguishes that filed saleable area from carpet-area measurements taken by software from the approved-plan drawing geometry. The drawing measurements are not RERA disclosures and are marked as needing review; the supplied recommendation says to verify measured areas against the drawing. RERA unit table RERA unit details Floor plans

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
2BHK1541171.69 sq.m52.8 sq.m (software-measured; not RERA-filed)26% (software-derived from drawing record)

Carpet area refers to the drawing-measured internal unit area in the supplied software record; saleable area is the RERA-filed figure and includes the home’s share of common areas according to the supplied floor-plan caveat. The supplied drawing extract identifies two bedrooms, kitchen/dining, living space, two toilets, and a balcony for a measured 2BHK design; the balcony is excluded from the measured carpet area. RERA unit details Floor plans

5. Parking & vehicle circulation

The approved-plan extract records 251.08 sq.m of parking area and Car Parking Spaces: 2.00. It states that stilt parking approved in the plan is to be used exclusively for vehicle parking and not converted or misused. The extracted records do not specify resident-versus-visitor allocation, accessible spaces, two-wheeler counts, EV charging quantities, or unit-wise parking allotments. A drawn or sanctioned parking provision does not, by itself, establish exclusive allocation to a particular apartment.

The plan extract records a 4.5m Wide Drive Way and a 2.5m Wide Corridor. The supplied material does not establish the number or arrangement of vehicle entry/exit points or a separate pedestrian route.

6. Amenities, recreation & open spaces

The RERA amenities record contains filed infrastructure items and progress percentages. The following table separates those entries from conditions or facilities stated in the building permit; no independent completion verification is supplied. RERA amenities

FacilityDescription / sizeEvidence sourceDeclared progress / verified status
Tot-lot / green stripPermit condition requires a fenced tot-lot maintained as greenery; plan extract lists vacant plot area as 180.06 sq.m but gives no tot-lot size.RERA amenities record: 0% for Green Strip/TOT LOT/Park; not independently verified. RERA amenities
Trees / peripheral greeneryPermit extract records 15 trees and requires tree plantation and maintenance of a peripheral greenery strip.Required/recorded in permit; completion not established.
Community buildingsNo size or facility description supplied.RERA amenitiesRERA amenities record: 0%.
Internal roads and footpathsNo facility dimensions supplied in the RERA amenities record.RERA amenities0%.
Street lightingNo further description supplied.RERA amenities0%.

No clubhouse, indoor recreation facility, swimming pool, or other sports facility is established by the supplied RERA filing or extracted permit evidence.

7. Utilities, building services & safety

Water
Evidence in the project recordRERA amenities record marks Water Supply YES and reports 40% progress. The permit requires public water-supply connections only after an occupancy certificate. No source, storage capacity, or treatment capacity is established in the supplied RERA documents. RERA amenities
Status indicatedFiled progress; not independently verified.
Sewerage / drainage
Evidence in the project recordRERA amenities record marks “Sewerage (Chamber, Lines, Septic Tank, STP)” YES with 20% progress. The plan extract lists septic/septic tank; no STP capacity is supplied. Storm-water drains are recorded at 0%. RERA amenities
Status indicatedFiled progress; no independent completion verification.
Rainwater harvesting
Evidence in the project recordThe permit requires a rainwater-harvesting structure/percolation pit and records 2 rainwater-harvesting pits. RERA reports water conservation/rainwater harvesting at 20%. RERA amenities
Status indicatedRequired and reported progress; completion not verified.
Electrical
Evidence in the project recordPermit records space for a transformer. The RERA amenities record marks an electrical meter room/sub-station/receiving station YES, at 0%. RERA amenities
Status indicatedProvision recorded; progress reported at 0%.
Lifts
Evidence in the project recordThe plan/permit material lists a lift, but does not provide quantity, capacity, or service-lift details.
Status indicatedNo completion status established.
Fire and life safety
Evidence in the project recordThe permit conditions require fire-fighting installations and an occupancy Fire NOC before issuance of an occupancy certificate. RERA amenities record fire protection/fire safety at 0%. RERA amenities
Status indicatedCondition and filed progress; statutory compliance or completion is not established by the supplied record.
Waste
Evidence in the project recordPermit requires a garbage house; the building-permit extract also directs that construction and demolition waste be transferred to a designated collection point. RERA solid-waste management/disposal is recorded at 0%. RERA amenities
Status indicatedRequired; project progress recorded at 0% for solid-waste management.
EV charging
Evidence in the project recordThe building permit includes a condition concerning EV charging infrastructure in parking places. No number of chargers or installed status is supplied.
Status indicatedPermit condition; installation not established.
Accessibility
Evidence in the project recordNo project-specific accessible route or accessibility facilities are evidenced in the supplied extracted records.
Status indicatedNot established.

8. Location, access & connectivity

The registered site location is AMEENAPUR, AMEENPUR, Sangareddy, 502032, on Plot Nos. 429 and 430 in Survey Nos. 128, 129 AND 130 PARTS. The filed boundaries identify 33-foot-wide and 40-foot-wide roads to the east and south respectively. [REGCERT-71681] RERA filing

The location dataset records the nearest sampled Outer Ring Road interchange at approximately 8.4 km. The distance is an approximate mapped measurement, not a promoter travel-time claim. No additional verified public-transport distances or landmark measurements are supplied. Location record

9. Developer & development status

The registered promoter is SATHYA INFRATECH, identified as a partnership in the project record. The supplied corporate record lists GSTIN 36AEEFS2890C1Z1 and an office address in Shankar Nagar, Ameenpur, Sangareddy, 502032. The Form C certificate separately lists the promoter address as Hyderabad, PIN 500050; this Overview identifies the registered entity and does not infer that either address is a project-site address. Corporate record Parties record [REGCERT-71681]

The RERA filing names GURKA VENKATA REDDY as authorized signatory and CHEGIREDDY ESHWARA SATHYA PRASAD REDDY as partner. The building-permit extract identifies SUDHAVENI PRASHANTH as developer/builder. Parties record

The promoter’s Form B affidavit declares a completion target of 22/09/2028. The project header also records proposed completion 22/01/2029. The supplied documents do not establish that construction is complete, and no occupancy or completion certificate is provided. The RERA amenities progress figures are promoter-filed records, not independent site verification. RERA record RERA amenities

10. Approvals, official records & documents

TG-RERA Form C registration certificate
Identifier / dateP01100010254; valid 22/09/2025–22/09/2028 unless extended
What it establishesRegistration of SATHYA ABODE and stated promoter obligations. [REGCERT-71681 p1]
HMDA building permit order
Identifier / date006218/HMDA/01875/SWBP/SKP2/2025; 22/09/2025
What it establishesTechnical approval for a residential 1 Stilt + 5 Floors building on Plot Nos. 429 and 430 in Survey Nos. 128, 129 and 130 parts.
Ameenpur Municipality building-permit record
Identifier / date0644/HMDA/SWBP/2025; 22/09/2025
What it establishesBuilding-permit record for the same residential building and site particulars.
Filed plan / approval drawing
Identifier / dateDocument 610057; approval number 006218/HMDA/01875/SWBP/SKP2/2025
What it establishesPlan-derived site, building, area, unit and permit-condition details.
Approved layout reference appearing in permit extract
Identifier / date1294/HUDA/MP2/93
What it establishesReference recorded in the building-permit extract; a separate approved-layout document is not established in the supplied evidence.
Form B promoter declaration
Identifier / date10·10·2Q25 as extracted; completion undertaking 22/09/2028
What it establishesPromoter declarations concerning title basis, encumbrances, fund handling and completion.
Occupancy/completion certificate
Identifier / dateNot supplied; permit extract records completion certified as false
What it establishesNo occupancy or completion certification is established by this evidence set.

Frequently asked questions

Is SATHYA ABODE registered with Telangana RERA?

Yes. SATHYA ABODE is registered with the Telangana Real Estate Regulatory Authority as P01100010254; the registration status is New Project.

Who is the developer of SATHYA ABODE?

The promoter named in the RERA registration is SATHYA INFRATECH.

Where is SATHYA ABODE located?

SATHYA ABODE is in AMEENPUR, AMEENAPUR, Sangareddy, Telangana (502032).

When will SATHYA ABODE be completed?

The promoter's proposed date of completion filed with RERA is 22/01/2029. This is the promoter's declaration, not a guarantee.