Sign in

Aditya Residency

KRITHI BUILDERS AND DEVELOPERS · Mahabubnagar · RERA P01400010872

Aditya Residency is a residential apartment project in Venkateshwara Colony, Mahabubnagar Urban mandal, Mahabubnagar district, developed by the registered promoter KRITHI BUILDERS AND DEVELOPERS. It covers 747.28 sq. m and comprises one residential apartment building with 1 stilt + 5 floors and 20 homes: ten 2BHK and ten 3BHK. The project is registered under TG-RERA number P01400010872, with proposed completion before 03 February 2029.

01What we found

RegisteredTG-RERA - valid till 3 Feb 2029
29documents on file - each fact links to its page
0court cases on this project's land in the court records searched
8items to check - 4 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

8 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

1. Project at a glance

Project identity

FieldProject record
Registered project nameAditya Residency RERA record
Project typeResidential apartment project RERA record
Phase / registered portionPhase not separately identified; registration concerns the site at Survey No. 222/1, Plot Nos. 33, 34, 43 & 44
TG-RERA registration numberP01400010872 Approvals record
Registration validity3 February 2026 to 3 February 2029 Approvals record
Registered promoterKRITHI BUILDERS AND DEVELOPERS RERA record
RERA statusRegistered; the certificate records the registration and validity period

Land and geographic identity

FieldProject record
LocalityVenkateshwara Colony
Revenue villageVenkateshwara Colony PPUnit Mahabubnagar, as recorded in the TG-RERA certificate
Mandal / district / PINMahabubnagar Urban / Mahabubnagar / 509001
Survey number(s) and subdivision(s)Survey No. 222/1; no further subdivision is stated in the project identity
Site plotsPlot Nos. 33, 34, 43 & 44
Registered site extent747.28 sq. m
Sanction-plan land areaGross plot area 747.28 sq. m; net plot area 747.28 sq. m
BoundariesEast: 33 Wide Road; West: Plot Nos. 43 and 44; North: Plot Nos. 32 and 45; South: Plot Nos. 35 and 42 RERA filing

Development identity

FieldProject record
Sanctioning authorityDTCP, as named on the filed building-permission plan
Principal approval number / dateFile No. 002605/MAHB/00006/SWBP/2025, approved 03/02/2026 Approvals record
Building permit order number0049/MAHB/SWBP/2026, approved 03/02/2026 Approvals record
Approved built-up area1,832.3 sq. m excluding parking; 2,187.8 sq. m including parking
Building countOne residential apartment building RERA record
Sanctioned floor configuration1 stilt + 5 floors
Parking19 car parking spaces; proposed parking area 355.50 sq. m. The plan separately records visitor parking area of 56.25 sq. m
Unit count20 units shown in the RERA unit record and in the filed plan RERA unit table

Offering and status

FieldProject record
Configurations2BHK and 3BHK RERA unit table
RERA-filed saleable areas2BHK: 96.71 sq. m; 3BHK: 130.99 sq. m RERA unit table
Portal booking / availability0 booked and 10 available in each configuration (20 total); portal record has no stated as-of date, so counts are indicative RERA unit table
Construction stageNo construction-progress percentage or independently verified site-stage record is supplied. The filed RERA amenity-progress entries are 0% RERA amenities
Completion datesPromoter’s Form B states completion before 03 February 2029; the building-permit order states completion before 03/02/2029
Registration deadlineRegistration is valid to 03/02/2029 unless extended by the Authority; this is the registration-validity date, not an occupancy certificate
Occupancy / completion certificateNo completion or occupancy certificate is recorded in the supplied project documents; the filed plan says an OC is required before occupation or delivery of possession

2. The project story

Aditya Residency is registered as a residential apartment project on a 747.28 sq. m site in Venkateshwara Colony, Mahabubnagar, identified in the RERA certificate as Survey No. 222/1 and Plot Nos. 33, 34, 43 & 44. The filed plan describes one building with stilt parking and five floors, comprising 20 apartments.

The RERA unit record lists ten 2BHK and ten 3BHK homes. The portal shows all 20 as available and none booked, but supplies no as-of date for those counts. No construction progress has been independently verified in the supplied evidence; the project’s filed amenity progress entries show 0%. The promoter’s completion undertaking and the permit both state a 3 February 2029 completion date. No OC or completion certificate is supplied, and the permit requires an OC before occupation or possession. RERA unit table RERA amenities

3. Master plan, architecture & building design

The filed plan records a gross and net plot area of 747.28 sq. m, no area deductions, proposed coverage of 411.75 sq. m (55.00%), and vacant plot area of 333.92 sq. m. Proposed built-up area is recorded separately as 1,832.3 sq. m excluding parking and 2,187.8 sq. m including parking; these are plan figures, not RERA-filed apartment saleable areas.

The building is shown as one residential block with 1 stilt + 5 floors. The plan records a total height of 20 m, height from ground level of 17.5 m, and height excluding stilt of 15 m. It also shows a 4.5 m wide driveway and a 2.5 m wide corridor. The supplied evidence does not specify flats per floor, lift or stair details, or a phase-wise building arrangement.

The plan’s listed site provisions include a transformer, garbage facility, drinking-water sump, rainwater harvesting and percolation pit. The separate permit record specifies two rainwater-harvesting pits and 30 trees; the plan also requires peripheral greenery and a tot-lot, while its area entry for tot-lot is 0 sq. m. These are sanctioned-plan or permit-record provisions, not evidence that they have been completed.

4. Homes, configurations & floor plans

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
2BHK1001096.71 sq. m58.9–63.2 sq. m; median 59.0 sq. m39%
3BHK10010130.99 sq. m76.3–78.3 sq. m; median 77.4 sq. m41%

Unit counts, booking counts and saleable areas are from the TG-RERA unit record; booking counts are indicative because the portal record has no as-of date. Carpet-area measurements are software-measured from the filed drawing geometry, not RERA disclosures, and are flagged as requiring review. Saleable area and carpet area are distinct measures; the supplied drawing analysis notes that saleable area also includes the home’s share of common areas. Verify any drawing-measured area against the filed plan and the agreement for the specific unit. RERA unit table Floor plans RERA unit details

The measured drawing sample shows a 2BHK arrangement with two bedrooms, hall, dining, kitchen, two toilets and two balconies. A measured 3BHK arrangement shows three bedrooms, hall, dining, kitchen, three toilets and two balconies. These are room labels and dimensions taken from individual drawing examples, not a statement that every unit has an identical layout. RERA unit details

5. Parking & vehicle circulation

The sanctioned plan records 19 car parking spaces, 355.50 sq. m proposed parking area, and 56.25 sq. m visitor parking area. It identifies the stilt as a parking level and specifies that approved stilt parking must remain for vehicle parking and not be partitioned or repurposed. The plan also shows a 4.5 m wide driveway. No two-wheeler count, accessible-space count, EV charger quantity, ramp details, or unit-by-unit parking allocation is supplied. A drawn or sanctioned parking space does not by itself establish exclusive allocation or ownership.

The plan requires parking areas to have electric-vehicle charging infrastructure. This is a permit condition; the supplied record does not establish installation or completion.

6. Amenities, recreation & open spaces

The RERA amenity schedule records the following items, each with progress shown as 0%. The filed permit adds specific plan requirements and quantities; none of the supplied records independently verifies completion. RERA amenities

FacilityDescription / sizeEvidence sourceDeclared progress / verified status
Internal roads and footpathsListed; no size statedRERA amenity record RERA amenities0%; completion not independently verified
Water supplyListed as available: YES; no source or capacity statedRERA amenity record RERA amenities0%; completion not independently verified
Sewerage / sewage and sullage treatment and disposalListed as available: YES; system and capacity not specifiedRERA amenity record RERA amenities0%; completion not independently verified
Storm-water drainsListed; no dimensions statedRERA amenity record RERA amenities0%; completion not independently verified
Green strip / tot-lot / parkListed; permit requires greenery and a fenced tot-lot; plan records tot-lot area as 0 sq. mRERA amenity record RERA amenities; filed plan0%; completion not independently verified
Trees30 trees stated in the permit recordRequired/listed; planting not independently verified
Street lightingListed; no quantity statedRERA amenity record RERA amenities0%; completion not independently verified
Community buildingsListed; no building or size specifiedRERA amenity record RERA amenities0%; completion not independently verified
Solid-waste management and disposalListed; method and capacity not statedRERA amenity record RERA amenities0%; completion not independently verified
Water conservation / rainwater harvestingListed; permit specifies two rainwater-harvesting pits and a percolation pitRERA amenity record RERA amenities0% in RERA amenity record; completion not independently verified
Energy managementListed; no system specifiedRERA amenity record RERA amenities0%; completion not independently verified
Fire protection and fire-safety requirementsListed as available: YES; specific installed systems are not detailed in the supplied recordRERA amenity record RERA amenities0%; completion not independently verified
Electrical meter room / sub-station / receiving stationListed; permit requires transformer spaceRERA amenity record RERA amenities0%; completion not independently verified
Recreational open spaceListed; aggregate area not stated in the amenity recordRERA amenity record RERA amenities0%; completion not independently verified

7. Utilities, building services & safety

The RERA amenity schedule lists water supply, sewerage, storm-water drainage, sewage/sullage treatment and disposal, water conservation/rainwater harvesting, electrical facilities and fire protection; it does not provide system capacities or establish that these services are complete. The permit records a drinking-water sump, transformer space, garbage facility, and two rainwater-harvesting pits. It also requires a percolation pit. RERA amenities

The permit makes an occupancy fire NOC a condition before issuance of an occupancy certificate and requires the relevant fire-fighting installation and means-of-escape safety provisions. The supplied project evidence does not include a fire NOC, an OC, lift details, backup-power arrangements, security systems, accessibility provisions, or evidence that utility and safety works have been installed and commissioned.

8. Location, access & connectivity

The TG-RERA certificate places the project at Survey No. 222/1, Plot Nos. 33, 34, 43 & 44, Venkateshwara Colony PPUnit Mahabubnagar, Mahabubnagar Urban mandal, Mahabubnagar district, PIN 509001. The filed plan identifies the locality as Venkateshwara Colony, Mahabubnagar Town; its boundary description records a 33 Wide Road to the east. RERA filing

A supplied geocode places the location at 16.7567534, 78.0185656. The location record lists the nearest sampled Outer Ring Road interchange at approximately 68.4 km; this is a supplied sampled distance, not a travel-time estimate. No public-transport information or additional verified landmark distances are provided. Location record

9. Developer & development status

The registered promoter is KRITHI BUILDERS AND DEVELOPERS, identified in the RERA filing as a partnership. The supplied corporate identifier is GSTIN 36AAYFK7503L1ZM. The project documents name ACHCHUGATLA CHANDRASHEKAR as authorised signatory; the RERA certificate names him as the promoter’s representative. RERA record Corporate record

The Form B declaration, dated March 2026, states that the project is to be completed before 03 February 2029. The permit records construction to commence before 02/08/2026 and completion before 03/02/2029. No site inspection, verified construction percentage, or occupancy certificate is included in the supplied evidence. The registration certificate is valid to 03/02/2029 unless extended; registration validity, the stated completion date and the required OC are separate matters.

10. Approvals, official records & documents

RecordSupplied evidence
TG-RERA registrationForm C certificate for Aditya Residency, P01400010872, valid 03/02/2026–03/02/2029
Building-permission planFiled plan names DTCP, File No. 002605/MAHB/00006/SWBP/2025, approved 03/02/2026
Building permit orderBuilding Permit Order No. 0049/MAHB/SWBP/2026, approved 03/02/2026; states 20 units and 1 stilt + 5 floors
Form B declarationPromoter’s affidavit-cum-declaration for Aditya Residency; includes land, account and completion undertakings
Mortgage recordPermit documents refer to Mortgage Deed No. 10060/2025, dated 02/08/2025, for the second-floor area of 253.69 sq. m
Occupancy / completion certificateNot present in the supplied documents; the filed plan requires an OC before occupation or delivery of possession

The filed plan also specifies that the sanctioned plan is to be followed, that a commencement notice is required before construction, and that a completion notice and occupancy certificate are required after completion. This index identifies the supplied records; it does not independently verify construction progress or certificate issuance.

Frequently asked questions

Is Aditya Residency registered with Telangana RERA?

Yes. Aditya Residency is registered with the Telangana Real Estate Regulatory Authority as P01400010872; the registration status is New Project.

Who is the developer of Aditya Residency?

The promoter named in the RERA registration is KRITHI BUILDERS AND DEVELOPERS.

Where is Aditya Residency located?

Aditya Residency is in Mahabubnagar, Venkateshwara Colony PPUnit Mahabubnagar, Mahabubnagar Urban, Telangana (509001).

When will Aditya Residency be completed?

The promoter's proposed date of completion filed with RERA is 03/06/2029. This is the promoter's declaration, not a guarantee.