SUNRISE CITY is a plotted development in Maripeda, Maripeda Mandal, Mahabubabad District. The registered promoter is RAMASAHAYAM HARIKA, and the RERA land extent is 251214.46 sqmts. The tentative layout approval states 737 plots; no tower or floor configuration is disclosed. The project is registered under TG-RERA number P00700006178, and the promoter’s declared completion date is 02/12/2025.

01What we found

Period endedTG-RERA registration ran to 2 Dec 2025 - check its extension on TG-RERA
25documents on file - each fact links to its page
0court cases on this project's land in the court records searched
10items to check - 3 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

10 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

Maripeda, Maripeda, Mahabubabad · geocoded — approximate.

1. Project at a glance

Project identity

ItemRecord
Registered project nameSUNRISE CITY RERA record
Project typePlotted development RERA record RERA filing
Registered phase/portionNot separately identified in the supplied record; the RERA registration refers to the project and its listed survey numbers. RERA record
TG-RERA registrationP00700006178; granted under section 5.
Registration validity02/12/2022–02/12/2025. The supplied certificate states no extension. This is the registration validity period, not confirmation of completion or occupancy certification.
Registered promoterRAMASAHAYAM HARIKA (also styled Ramasahayam Harika in the certificate). RERA record
RERA statusThe record identifies the project as a “New Project”; no current registration-status update or extension order is supplied. RERA record

Land and geographic identity

ItemRecord
Locality / revenue villageMaripeda; the layout approval identifies MARIPEDA Revenue Village. RERA record
Mandal / district / PINMaripeda Mandal, Mahabubabad District, 506315. RERA record
Project survey numbers and subdivisions516, 517, 518, 520P, 521, 522, 523, 532P, 533P, 534, 535P, 536, 537, 538, 540. RERA record
Registered site extent251214.46 sqmts in the RERA land details. RERA filing
Net / total areaRERA records both total area and net area as 251214.46 sqmts. RERA filing
BoundariesEast: 40 - FEET ROAD; West: OTHERS LAND; North: 30 - FEET ROAD; South: 30 - FEET ROAD. RERA filing

Development identity

ItemRecord
Sanctioning authorityMARIPEDA Municipality/Municipal Corporation; the supplied RERA record also identifies DTCP as the authority name. RERA record Approvals record
Principal layout approvalTentative Layout Plan 0004/LO/3091/2022, dated 02 December, 2022; application 008915/LO/DTCP/3091/0007/2022. Approvals record
Approved layout extent and plot countThe approval document states 62 Acer 3 Gts 300450 Sq. Yds and 737 No's. These are figures stated in the tentative layout approval.
Approved built-up area137049.63 sqmts is recorded in the RERA fields. The supplied material does not identify a building or floor schedule for this plotted development. RERA filing
Building count / floor configurationNot disclosed in the supplied project record. The approval is for a plotted layout, not a building-floor schedule.
Parking“Open Parking” appears in the vendor-supplied record; no sanctioned parking count or plot-specific allocation is provided. Promoter website

Offering and status

ItemRecord
OfferingPlots in a plotted development. The tentative layout approval states 737 No's; a separate drawing-derived record describes 36 plots, but its relationship to the registered project portion is not established in the supplied record. Layout record
RERA unit inventory / booked and available countsNot supplied. RERA record
Plot sizesDrawing-based software extraction identifies 36 plots with sizes from 127.44 sq.m to 434.81 sq.m; this is a drawing-derived count and measurement, not a RERA-filed unit schedule. Layout record
Promoter-declared completion date02/12/2025, in the Form B declaration.
Construction / development stageNo dated, independently verified site-progress evidence is supplied. A third-party vendor record describes the project as completed, but that is not a TG-RERA status or an independently verified site inspection. Promoter website
Occupancy / completion certificateNo occupancy or completion certificate is included in the supplied documents. The project is a plotted layout; no phase- or plot-specific certificate status is established here. Document index

2. The project story

SUNRISE CITY is registered as a plotted-development project in Maripeda, Maripeda Mandal, Mahabubabad District. The registered land description covers survey numbers 516, 517, 518, 520P, 521, 522, 523, 532P, 533P, 534, 535P, 536, 537, 538 and 540. The RERA record gives the project land extent as 251214.46 sqmts. RERA record RERA filing

The file includes tentative layout approval 0004/LO/3091/2022, dated 02 December, 2022. That approval describes a layout of 62 Acer 3 Gts 300450 Sq. Yds and 737 plots, with land reserved for plotted sites, roads, open space, social infrastructure and utilities. The approval makes infrastructure and development works the applicant’s responsibility; the supplied file does not establish the completed status of those works.

The RERA promoter declaration undertakes completion by 02/12/2025. No independent construction-progress inspection, completion certificate or occupancy certificate is supplied. The vendor record’s “completed” description is not treated as verified project progress. Promoter website Document index

3. Master plan, architecture & building design

The principal project-specific drawing evidence is for a plotted layout. The tentative approval allocates the stated layout area as follows: 33 Acer 34.6 Gts 163910 Sq. Yds (54.74%) plotted area; 18 Acer 3.04 Gts 87490 Sq. Yds (29.22%) roads; 5 Acer 23.51 Gts 27045 Sq. Yds (9.03%) open space; 1 Acer 22.09 Gts 7514 Sq. Yds (2.51%) social infrastructure; 0 Acer 26.37 Gts 3191 Sq. Yds (1.07%) utilities; and 0 Acer 220.29 Gts 26655 Sq. Yds (16.22 %) mortgage area, as stated in the approval.

A separate software extraction from layout drawing 318654 describes 36 plots across two layout sheets. It reports plot sizes from 127.44 sq.m to 434.81 sq.m, with the largest number in the 200-250 sq yd band (22 plots). Its own area statement gives a net layout area of 12850.75 sq.m: 7901.4 sq.m plots, 3331.29 sq.m roads, 1159.23 sq.m parks/open space, 129.32 sq.m utilities, and 329.52 sq.m social infrastructure. Plot counts and sizes are software-read from drawing text and should be checked against the drawing; this extraction is not a RERA unit schedule. Layout record

The RERA record lists approved built-up area of 137049.63 sqmts and mortgage area of 22286.97 sqmts. No building count, building footprint, floor configuration, tower-height, or residential floor-plan information is supplied for this plotted project. RERA filing Floor plans

The approval identifies 0 Acer 220.29 Gts 26655 Sq. Yds as mortgage area and lists reserved plots subject to mortgage deed 14276/2022. It states that the mortgage is connected with development-condition compliance and that release/final layout steps follow completion of required works. Approvals record

4. Homes, configurations & floor plans

This is a plotted development; no apartment configuration schedule is provided. The tentative layout approval states 737 No's, while the software extraction from drawing 318654 identifies 36 plots and plot-size bands. The supplied evidence does not establish that the 36 drawing-measured plots represent the complete registered offering, so these counts are reported with their respective source and scope. Layout record

Plot-size band (drawing-derived)Plots
150-200 sq yd (125-167 sq.m)5
200-250 sq yd (167-209 sq.m)22
250-300 sq yd (209-251 sq.m)3
300-400 sq yd (251-334 sq.m)3
400-500 sq yd (334-418 sq.m)2
500-1000 sq yd (418-836 sq.m)1

The software-read drawing gives a smallest plot of 127.44 sq.m (152.4 sq yd), median of 205.43 sq.m (245.7 sq yd) and largest of 434.81 sq.m (520.0 sq yd). These are drawing-derived measurements, not RERA-filed saleable-area figures. Layout record

No booked or available plot counts, plot-specific saleable areas, or executed allotment/sale agreements are included. The supplied floor-plan data contains two layout sheets and no flat plans; carpet-area measurements therefore do not apply to the evidence provided. Floor plans Document index

5. Parking & vehicle circulation

The tentative layout approval provides for roads and requires road formation and access works. It states that roads are to be opened for access to neighbouring sites and that development works include road formation with black top. The supplied material does not include a sanctioned parking-space count, visitor or accessible parking schedule, internal driveway/ramp detail, or plot-specific parking allocation.

“Open Parking” is listed in the vendor record, but no count, approved drawing reference or legally documented exclusive allocation is supplied. A parking bay or general open-parking description does not establish a buyer’s exclusive parking right. Promoter website

6. Amenities, recreation & open spaces

The approval calls for layout infrastructure and amenities, and the RERA amenity record marks several infrastructure categories as available. These are record entries, not independent confirmation that each facility has been completed or handed over. RERA amenities

Park / open space
Description / sizeApproval reserves 5 Acer 23.51 Gts 27045 Sq. Yds (9.03%); drawing extraction reports 1159.23 sq.m. Layout record
Evidence sourceTentative layout approval; software-read drawing
Declared progress / verified statusReserved in the approval/drawing; completion not independently verified.
Green strip / tot lot / park
Description / sizeListed as available at 100% in the RERA amenity data. RERA amenities
Evidence sourceRERA amenity record
Declared progress / verified statusRERA-recorded availability; not independently site-verified.
Social infrastructure
Description / sizeApproval reserves 1 Acer 22.09 Gts 7514 Sq. Yds (2.51%); drawing extraction reports 329.52 sq.m. Layout record
Evidence sourceTentative layout approval; software-read drawing
Declared progress / verified statusLand reservation shown; facility delivery is not established.
Community buildings
Description / sizeAmenity record shows 0%. RERA amenities
Evidence sourceRERA amenity record
Declared progress / verified statusNo progress recorded.

No clubhouse, indoor recreation facility or specific sports facility is identified in the supplied project evidence.

7. Utilities, building services & safety

The tentative layout approval requires the applicant to undertake specified infrastructure works, including internal water supply pipelines, an assured water source, overhead tank/sump, storm-water drains, underground drainage, common septic tank/STP, transformer, street lights, avenue planting and rainwater-harvesting pits. These are stated requirements; the approval text does not by itself establish that the works are complete.

ServiceSupplied record
Water“Water Supply” is marked available at 100% in the RERA amenity data. The approval requires an assured water-supply source, internal pipelines and an overhead tank/sump; capacity and completion verification are not supplied. RERA amenities
Sewerage / drainage“Sewerage (Chamber, Lines, Septic Tank, STP)” and storm-water drains are marked available at 100% in the amenity record. The approval specifies underground drainage, common septic tank/STP and storm-water drains. Treatment capacity and independent completion evidence are not supplied. RERA amenities
Rainwater harvestingThe amenity record marks water conservation/rainwater harvesting at 100%; the approval requires rainwater-harvesting pits. Independent completion evidence is not supplied. RERA amenities
ElectricalThe amenity record marks an electrical meter room/sub-station/receiving station at 100%. The approval requires an electric transformer, supply lines and street lights; capacities and independent completion evidence are not supplied. RERA amenities
Solid wasteThe approval lists solid-waste management among the utilities to be developed. The amenity record shows 0% for solid-waste management and disposal. RERA amenities
Fire and life safetyThe amenity record shows 0% for fire protection and fire-safety requirements. No project-specific fire-system details or clearance are supplied. RERA amenities
Lifts / accessibility / securityNot disclosed in the supplied project evidence. Document index

8. Location, access & connectivity

The registered location is Maripeda, in Maripeda Mandal, Mahabubabad District, PIN 506315. The project boundaries recorded in the RERA land details are 40 - FEET ROAD to the east and 30 - FEET ROAD to the north and south; the west boundary is recorded as OTHERS LAND. RERA record RERA filing

The cadastral parcel centroid supplied for survey 516 is 17.375860475281794, 79.89489439111196; it is a survey-level location reference, not proof of the full project boundary. The only supplied measured connectivity point is an approximate 129.2 km to the nearest sampled Outer Ring Road interchange. No additional public-transport, landmark or route-distance information is provided. Cadastral map Location record

9. Developer & development status

The registered promoter is RAMASAHAYAM HARIKA. The RERA record lists the organization type as Others and does not establish a company or other legal-entity type. The registration certificate gives a promoter-office line of “Village: Mandal: District: Medchal-Malkajgiri, Pin: 500085,” but the village and mandal fields are blank in that line. RERA record RERA filing

Form B for SUNRISE CITY records the promoter’s declaration of legal title basis, states that the land is free from encumbrances, and undertakes completion by 02/12/2025. Those are promoter declarations in the filed document. The supplied evidence does not establish current physical progress, a revised completion date, or completion/occupancy certification. Document index

No registered promoter entity number, official contact details, or official project website is supplied. The third-party vendor record’s “completed” description is not treated as a verified development status. Corporate record Promoter website

10. Approvals, official records & documents

RecordSupplied evidence and scope
TG-RERA registrationFORM ‘C’ registration P00700006178 for SUNRISE CITY under section 5; valid 02/12/2022–02/12/2025, with no extension recorded in the supplied certificate.
Principal tentative layout approval0004/LO/3091/2022, dated 02 December, 2022, issued by MARIPEDA Municipality/Municipal Corporation for the Maripeda layout; application 008915/LO/DTCP/3091/0007/2022.
Approval references recorded in project dataThe project record also lists 0019/LO/3046/2022 and application 008810/LO/DTCP/3046/0026/2022. The supplied approval document 318657 concerns Kodada Revenue Village, Suryapet District, and applicants Arvapally Satyanarayana and Marri Santosh; it does not establish approval of the Maripeda project parcel. Approvals record
Form B declarationPromoter declaration for SUNRISE CITY, including stated completion date 02/12/2025.
Layout drawingDrawing-derived layout record, source document 318654, two layout sheets; plot count and sizes are software-read and require drawing-level verification. Layout record
Completion / occupancy certificateNone supplied. Document index
Other project recordsThe file includes title-report and encumbrance-record materials; their land-title and encumbrance analysis belongs in the dedicated Land & Title and Risk sections. Document index

Frequently asked questions

Is SUNRISE CITY registered with Telangana RERA?

Yes. SUNRISE CITY is registered with the Telangana Real Estate Regulatory Authority as P00700006178; the registration status is New Project.

Who is the developer of SUNRISE CITY?

The promoter named in the RERA registration is RAMASAHAYAM HARIKA.

Where is SUNRISE CITY located?

SUNRISE CITY is in MARIPEDA, Mahabubabad, Telangana (506315).

When will SUNRISE CITY be completed?

The promoter's proposed date of completion filed with RERA is 02/12/2025. This is the promoter's declaration, not a guarantee.