Sri Ayyappa Sai Ram And Jagannadh Residency
SASR INFRASTRUCTURE PRIVATE LIMITED · Sangareddy · RERA P01100007145
SRI AYYAPPA SAI RAM AND JAGANNADH RESIDENCY is a residential apartment project in Sultanpur, Ameenpur mandal, Sangareddy district, developed by registered promoter SASR INFRASTRUCTURE PRIVATE LIMITED. The project has a land area of 4,739.42 sq.m and one building of I Stilt + 5 Upper floors, with 99 apartments: 84 2BHK and 15 3BHK. It is registered with TG-RERA under P01100007145, and the RERA header records proposed completion as 13/07/2029.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
10 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Item | Project record |
|---|---|
| Registered project name | SRI AYYAPPA SAI RAM AND JAGANNADH RESIDENCY RERA record |
| Project type | Residential apartment project RERA record RERA filing |
| Phase / registered portion | New Project; the supplied record describes one building. Separate phase name or phase number is not disclosed. RERA record RERA filing RERA unit table |
| TG-RERA registration | P01100007145; registration issued 21/10/2023 and recorded as valid through 13/03/2029. The certificate states a five-year validity, subject to extension under the Act and rules; no extension is recorded in the supplied certificate. Registration validity is not the project-completion deadline. RERA record |
| Registered legal promoter | SASR INFRASTRUCTURE PRIVATE LIMITED RERA record Corporate record |
| RERA status | The project is recorded as “New Project”; the registration certificate is supplied. RERA record |
Land and geographic identity
| Item | Project record |
|---|---|
| Locality / revenue village | Sultanpur; the project record and filed approvals refer to SULTANPUR / Sultanpur-ORRGC Village. RERA record RERA filing |
| Mandal / district / PIN | Ameenpur mandal; Sangareddy district; PIN 502319. RERA record RERA filing |
| Project survey identifiers | Sy. No. 30/22 (recorded as “30/22 (The Survey No - 30/22 is Known as ie OLD Survey No - 30/2)”) and Sy. No. 30/2. A filed Gram Panchayat permission also lists Sy. No. 30/32; that identifier is reproduced as recorded. RERA record RERA filing |
| Site extent | RERA land details: total 4,739.42 sq.m, area affected by road widening/FTL/Nala widening 72.70 sq.m, and net area 4,666.72 sq.m. HMDA technical approval and Gram Panchayat permission each state 4,666.71 sq.m. RERA filing |
| Boundaries (RERA-filed) | North: land of Sudhakar Rao in Sy. No. 30 by 23; south: land of Janga Reddy Vijaya Kumar Reddy and others; east: neighbours’ property; west: 100 Feet Road, petrol pump and other land. RERA filing |
Development identity
| Item | Project record |
|---|---|
| Principal technical approval | HMDA technical approval 047962/SKP/R1/U6/HMDA/05082021, dated 13/03/2023. The approval states that the plans require sanction by the local Executive Authority in conformity with the technical approval. Approvals record |
| Local building permission | Gram Panchayat–Dayara proceedings GPD/BA/2023, dated 29.09.2023, for a residential building. Approvals record |
| Approved built-up area | 9,874.75 sq.m is recorded as “Built up Area” in the HMDA technical approval parameters. The same document separately records 12,451.69 as “Proposed Built-up Area”; the supplied extraction does not state a unit for that latter figure. |
| Building arrangement | One residential building / one tower is recorded. RERA unit table |
| Floor configuration | The filed building permissions describe I Stilt + 5 Upper floors. Basement, podium and separate parking-floor counts are not disclosed in the supplied records. |
| Units | 99 total in the RERA-derived unit schedule: 84 2BHK and 15 3BHK. RERA unit table RERA unit details |
| Parking | HMDA approval refers to cellar and stilt areas approved for parking, but the supplied records do not give a sanctioned space count. |
Offering and status
| Item | Project record |
|---|---|
| Configurations | 2BHK and 3BHK apartments. RERA unit table RERA unit details |
| RERA-filed saleable areas | 2BHK: 104.76 sq.m; 3BHK: 139.82 sq.m. RERA unit table RERA unit details |
| Booked / available | 2BHK: 9 booked / 75 available; 3BHK: 1 booked / 14 available. Portal counts are indicative: the supplied record gives no as-of date for these counts. RERA unit table RERA unit details |
| Construction stage | A current construction-stage or site-progress report is not supplied. The amenity progress entries supplied are recorded as 0%; they do not establish overall building progress. RERA amenities |
| Completion dates | The RERA header records proposed completion 13/07/2029; the Form B declaration states completion by 13 March 2029. RERA record |
| Occupancy / completion certificate | No occupancy or completion certificate is supplied in the reviewed project documents. The HMDA approval says an occupancy certificate is required before occupation. Document index |
2. The project story
This is a residential apartment development registered with TG-RERA as SRI AYYAPPA SAI RAM AND JAGANNADH RESIDENCY, in Sultanpur, Ameenpur mandal, Sangareddy district. The project record identifies Sy. No. 30/22, with the old-survey reference Sy. No. 30/2; the filed local permission also lists Sy. No. 30/32. The RERA land schedule states a total site area of 4,739.42 sq.m and net area of 4,666.72 sq.m. RERA record RERA filing
The filed approvals describe one residential building of I Stilt + 5 Upper floors. The RERA unit schedule records 99 apartments: 84 2BHK and 15 3BHK. The supplied evidence does not establish the building’s current physical construction stage, and no occupancy or completion certificate is included. Accordingly, the registration and stated completion dates should not be read as evidence that construction is complete or that occupation is certified. RERA unit table Document index
The Form B declaration gives a completion undertaking of 13 March 2029; the RERA header separately records proposed completion as 13/07/2029. These are recorded here as separate filed values. The registration certificate records registration validity through 13/03/2029; that is a distinct registration-validity date. RERA record
3. Master plan, architecture & building design
The HMDA technical approval records a residential building on 4,666.71 Sq. Mt. and identifies a proposed structure of 1 Stilt + 5 floors. The approval parameters list “Built up Area 9874.75” and separately “Proposed Built-up Area 12451.69”; the supplied extraction does not specify a unit for the latter entry. The RERA land schedule records total area 4,739.42 sq.m, affected area 72.70 sq.m, and net area 4,666.72 sq.m. RERA filing
The project record identifies one building and one tower. The supplied material does not provide a readable approved floor-plan extraction establishing floor-by-floor apartment arrangement, number of flats per floor, building footprint, lift or stair count, or the distribution of common and private areas. The layout-plan item in the RERA file is not extracted, so internal roads, landscaping dimensions and open-space area cannot be described from the available drawing record. RERA unit table Document index
The approval lists a mortgage of 988 sq.m of built-up area in the first floor in favour of HMDA and records a separate 72.70 Sq.mtrs area affected by the proposed 30-metre master-plan road as gifted to the Gram Panchayat.
4. Homes, configurations & floor plans
RERA configuration counts and saleable areas are shown below. The carpet figures are software-measured from floor-plan drawing geometry, not RERA-filed carpet-area declarations; the drawing-derived measurement itself is identified as requiring review. RERA saleable area is a different measure and includes the home’s share of common areas, so the two figures should not be treated as interchangeable. RERA unit table RERA unit details Floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK | 84 | 9 | 75 | 104.76 sq.m | 60.0–76.5 sq.m; median 68.4 sq.m | 35% |
| 3BHK | 15 | 1 | 14 | 139.82 sq.m | 88.7–100.2 sq.m; median 98.7 sq.m | 29% |
The drawing measurement covers 14 2BHK designs and 3 3BHK designs. One measured example labelled 2BHK records a hall, two bedrooms, kitchen and wash area; one measured 3BHK example records a hall, three bedrooms and kitchen. These are software readings from the first-floor plan, not a guarantee that every unit has identical room dimensions or layout. RERA unit details Floor plans
5. Parking & vehicle circulation
The HMDA approval says cellar and stilt areas approved for parking must be used exclusively for vehicle parking and not converted to another use. It also requires one entry and one exit, each with a minimum width of 4.5mts and height clearance of 5mts. The filed approval does not provide a parking-space count, visitor or accessible-space count, or a unit-by-unit parking allocation.
No evidence in the supplied project record establishes an EV-charging provision, parking allotment terms for a particular apartment, or whether any drawn bay is exclusively allocated to a buyer. The approval identifies 988 sq.m of first-floor built-up area as mortgaged to HMDA; that is not a parking allocation.
6. Amenities, recreation & open spaces
The RERA amenities schedule lists the following items and records 0% progress for each listed entry. “Available: YES” in that schedule is a recorded availability field, not independent confirmation of completion or current operation. The HMDA technical approval separately names certain site features as conditions or provisions. RERA amenities
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Green strip / tot lot / park | Size not supplied; HMDA approval also lists a “Tot-lot.” | RERA amenities schedule; HMDA technical approval RERA amenities | RERA schedule: 0%; completion not independently verified |
| Community buildings | No size or capacity supplied | RERA amenities schedule RERA amenities | 0%; completion not independently verified |
| Aggregate recreational open space | Area not supplied | RERA amenities schedule RERA amenities | 0%; completion not independently verified |
The vendor record also lists a clubhouse, swimming pool, gym, indoor games and children’s play area, among other advertised amenities; no corresponding project-specific approved size or completion evidence is supplied here. Those vendor-listed items are not treated as confirmed, sanctioned or delivered facilities. Promoter website
7. Utilities, building services & safety
The HMDA technical approval requires rainwater-harvesting structures, an ETP, a transformer and a garbage house. It also specifies separate underground and terrace water-storage tanks of 25,000 lts. capacity each for residential buildings. These are approval conditions or requirements; the supplied evidence does not verify installation or operation.
The RERA amenities schedule marks water supply, sewerage, storm-water drains, rainwater harvesting/water conservation and an electrical meter room/sub-station/receiving station as “YES,” while recording 0% progress for the listed schedule items. The record does not provide water-source details, treatment capacity, STP capacity, reuse arrangements, electrical load, generator capacity, lift specifications, CCTV or access-control details as project-filed service specifications. RERA amenities
The HMDA approval requires compliance with Fire Service department norms, provides for automatic sprinklers if basement area exceeds 200 Sq.mts, and requires structural and construction-worker safety measures. These approval conditions do not establish that the relevant systems have been installed or that statutory clearances have been obtained. The available material does not state whether the basement threshold applies to this building.
8. Location, access & connectivity
The registered location is Sultanpur village, Ameenpur mandal, Sangareddy district, PIN 502319. The project boundaries recorded in the RERA land schedule include a 100 Feet Road and Petrol Pump and Others Land on the west. HMDA’s technical approval refers to a proposed 30 mts wide Master plan road affecting 72.70 Sq.mtrs and records that area as gifted to the Gram Panchayat. RERA record RERA filing
A software-derived location point is recorded as parcel centroid 17.57000, 78.31124. The nearest sampled Outer Ring Road interchange is listed at approximately 7.0 km; this is a measured connectivity record, not a travel-time claim. No public-transport route, named access-road sequence or verified travel time is supplied. Location record Cadastral map
9. Developer & development status
The registered promoter is SASR INFRASTRUCTURE PRIVATE LIMITED, a private limited company; the supplied corporate identifier is 36AAWCS6955P1Z0 (GSTIN). The RERA record gives the promoter’s address as H No 1-57/PP/305, Madinaguda, Sultanpur, Ameenpur, Sangareddy, 502319. Corporate record Parties record RERA filing
The Form B affidavit is made by Sri. S. Venkata Ramana Reddy, stated to be authorised by the promoter. The filing identifies landowners Sara Ramesh alias Boreda Ramesh and Boreda Sai Kiran and refers to Development cum General Power of Attorney No. 15738/2023 for the development arrangement.
A current construction-progress certificate or independently verified site report is not supplied. The project’s RERA header records proposed completion as 13/07/2029, while Form B states 13 March 2029; the registration certificate separately records validity through 13/03/2029. No occupancy or completion certificate is included in the reviewed documents. RERA record Document index
10. Approvals, official records & documents
| Identifier / date | P01100007145; issued 21/10/2023 |
|---|---|
| What the supplied record establishes | Registration for the named project, with validity recorded through 13/03/2029, subject to the certificate’s conditions. |
| Identifier / date | 047962/SKP/R1/U6/HMDA/05082021; 13/03/2023 |
|---|---|
| What the supplied record establishes | Technical approval for a residential building on the stated survey land; the document says local Executive Authority sanction is required in conformity with the technical plans. |
| Identifier / date | GPD/BA/2023; 29.09.2023 |
|---|---|
| What the supplied record establishes | Building permission for a residential I Stilt + 5 Upper floors building, subject to stated conditions. |
| Identifier / date | October 2023 |
|---|---|
| What the supplied record establishes | Promoter declaration includes a completion undertaking of 13th MARCH 2029 and RERA-related undertakings. |
| Identifier / date | RERA-filed item 361137 |
|---|---|
| What the supplied record establishes | The layout-plan item is not extracted; drawing-based unit measurements are available, but are software measurements and require review. Document index |
| Identifier / date | Not supplied |
|---|---|
| What the supplied record establishes | No such certificate is included in the reviewed project documents. Document index |
The RERA registration certificate includes quarterly-update and separate-account conditions. The approval documents also specify conditions for construction, parking, road access, utilities and occupancy; the full conditions remain in the cited source documents.
1. Project at a glance
Project identity
Registered project name: SRI AYYAPPA SAI RAM AND JAGANNADH RESIDENCY
Project type: Residential apartment project
Phase / registered portion: New Project; the supplied record describes one building. Separate phase name or phase number is not disclosed.
TG-RERA registration: P01100007145; registration issued 21/10/2023 and recorded as valid through 13/03/2029. The certificate states a five-year validity, subject to extension under the Act and rules; no extension is recorded in the supplied certificate. Registration validity is not the project-completion deadline.
Registered legal promoter: SASR INFRASTRUCTURE PRIVATE LIMITED
RERA status: The project is recorded as “New Project”; the registration certificate is supplied.
Land and geographic identity
Locality / revenue village: Sultanpur; the project record and filed approvals refer to SULTANPUR / Sultanpur-ORRGC Village.
Mandal / district / PIN: Ameenpur mandal; Sangareddy district; PIN 502319.
Project survey identifiers: Sy. No. 30/22 (recorded as “30/22 (The Survey No - 30/22 is Known as ie OLD Survey No - 30/2)”) and Sy. No. 30/2. A filed Gram Panchayat permission also lists Sy. No. 30/32; that identifier is reproduced as recorded.
Site extent: RERA land details: total 4,739.42 sq.m, area affected by road widening/FTL/Nala widening 72.70 sq.m, and net area 4,666.72 sq.m. HMDA technical approval and Gram Panchayat permission each state 4,666.71 sq.m.
Boundaries (RERA-filed): North: land of Sudhakar Rao in Sy. No. 30 by 23; south: land of Janga Reddy Vijaya Kumar Reddy and others; east: neighbours’ property; west: 100 Feet Road, petrol pump and other land.
Development identity
Principal technical approval: HMDA technical approval 047962/SKP/R1/U6/HMDA/05082021, dated 13/03/2023. The approval states that the plans require sanction by the local Executive Authority in conformity with the technical approval.
Local building permission: Gram Panchayat–Dayara proceedings GPD/BA/2023, dated 29.09.2023, for a residential building.
Approved built-up area: 9,874.75 sq.m is recorded as “Built up Area” in the HMDA technical approval parameters. The same document separately records 12,451.69 as “Proposed Built-up Area”; the supplied extraction does not state a unit for that latter figure.
Building arrangement: One residential building / one tower is recorded.
Floor configuration: The filed building permissions describe I Stilt + 5 Upper floors. Basement, podium and separate parking-floor counts are not disclosed in the supplied records.
Units: 99 total in the RERA-derived unit schedule: 84 2BHK and 15 3BHK.
Parking: HMDA approval refers to cellar and stilt areas approved for parking, but the supplied records do not give a sanctioned space count.
Offering and status
Configurations: 2BHK and 3BHK apartments.
RERA-filed saleable areas: 2BHK: 104.76 sq.m; 3BHK: 139.82 sq.m.
Booked / available: 2BHK: 9 booked / 75 available; 3BHK: 1 booked / 14 available. Portal counts are indicative: the supplied record gives no as-of date for these counts.
Construction stage: A current construction-stage or site-progress report is not supplied. The amenity progress entries supplied are recorded as 0%; they do not establish overall building progress.
Completion dates: The RERA header records proposed completion 13/07/2029; the Form B declaration states completion by 13 March 2029.
Occupancy / completion certificate: No occupancy or completion certificate is supplied in the reviewed project documents. The HMDA approval says an occupancy certificate is required before occupation.
2. The project story
This is a residential apartment development registered with TG-RERA as SRI AYYAPPA SAI RAM AND JAGANNADH RESIDENCY, in Sultanpur, Ameenpur mandal, Sangareddy district. The project record identifies Sy. No. 30/22, with the old-survey reference Sy. No. 30/2; the filed local permission also lists Sy. No. 30/32. The RERA land schedule states a total site area of 4,739.42 sq.m and net area of 4,666.72 sq.m.
The filed approvals describe one residential building of I Stilt + 5 Upper floors. The RERA unit schedule records 99 apartments: 84 2BHK and 15 3BHK. The supplied evidence does not establish the building’s current physical construction stage, and no occupancy or completion certificate is included. Accordingly, the registration and stated completion dates should not be read as evidence that construction is complete or that occupation is certified.
The Form B declaration gives a completion undertaking of 13 March 2029; the RERA header separately records proposed completion as 13/07/2029. These are recorded here as separate filed values. The registration certificate records registration validity through 13/03/2029; that is a distinct registration-validity date.
3. Master plan, architecture & building design
The HMDA technical approval records a residential building on 4,666.71 Sq. Mt. and identifies a proposed structure of 1 Stilt + 5 floors. The approval parameters list “Built up Area 9874.75” and separately “Proposed Built-up Area 12451.69”; the supplied extraction does not specify a unit for the latter entry. The RERA land schedule records total area 4,739.42 sq.m, affected area 72.70 sq.m, and net area 4,666.72 sq.m.
The project record identifies one building and one tower. The supplied material does not provide a readable approved floor-plan extraction establishing floor-by-floor apartment arrangement, number of flats per floor, building footprint, lift or stair count, or the distribution of common and private areas. The layout-plan item in the RERA file is not extracted, so internal roads, landscaping dimensions and open-space area cannot be described from the available drawing record.
The approval lists a mortgage of 988 sq.m of built-up area in the first floor in favour of HMDA and records a separate 72.70 Sq.mtrs area affected by the proposed 30-metre master-plan road as gifted to the Gram Panchayat.
4. Homes, configurations & floor plans
RERA configuration counts and saleable areas are shown below. The carpet figures are software-measured from floor-plan drawing geometry, not RERA-filed carpet-area declarations; the drawing-derived measurement itself is identified as requiring review. RERA saleable area is a different measure and includes the home’s share of common areas, so the two figures should not be treated as interchangeable.
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK | 84 | 9 | 75 | 104.76 sq.m | 60.0–76.5 sq.m; median 68.4 sq.m | 35% |
| 3BHK | 15 | 1 | 14 | 139.82 sq.m | 88.7–100.2 sq.m; median 98.7 sq.m | 29% |
The drawing measurement covers 14 2BHK designs and 3 3BHK designs. One measured example labelled 2BHK records a hall, two bedrooms, kitchen and wash area; one measured 3BHK example records a hall, three bedrooms and kitchen. These are software readings from the first-floor plan, not a guarantee that every unit has identical room dimensions or layout.
5. Parking & vehicle circulation
The HMDA approval says cellar and stilt areas approved for parking must be used exclusively for vehicle parking and not converted to another use. It also requires one entry and one exit, each with a minimum width of 4.5mts and height clearance of 5mts. The filed approval does not provide a parking-space count, visitor or accessible-space count, or a unit-by-unit parking allocation.
No evidence in the supplied project record establishes an EV-charging provision, parking allotment terms for a particular apartment, or whether any drawn bay is exclusively allocated to a buyer. The approval identifies 988 sq.m of first-floor built-up area as mortgaged to HMDA; that is not a parking allocation.
6. Amenities, recreation & open spaces
The RERA amenities schedule lists the following items and records 0% progress for each listed entry. “Available: YES” in that schedule is a recorded availability field, not independent confirmation of completion or current operation. The HMDA technical approval separately names certain site features as conditions or provisions.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Green strip / tot lot / park | Size not supplied; HMDA approval also lists a “Tot-lot.” | RERA amenities schedule; HMDA technical approval | RERA schedule: 0%; completion not independently verified |
| Community buildings | No size or capacity supplied | RERA amenities schedule | 0%; completion not independently verified |
| Aggregate recreational open space | Area not supplied | RERA amenities schedule | 0%; completion not independently verified |
The vendor record also lists a clubhouse, swimming pool, gym, indoor games and children’s play area, among other advertised amenities; no corresponding project-specific approved size or completion evidence is supplied here. Those vendor-listed items are not treated as confirmed, sanctioned or delivered facilities.
7. Utilities, building services & safety
The HMDA technical approval requires rainwater-harvesting structures, an ETP, a transformer and a garbage house. It also specifies separate underground and terrace water-storage tanks of 25,000 lts. capacity each for residential buildings. These are approval conditions or requirements; the supplied evidence does not verify installation or operation.
The RERA amenities schedule marks water supply, sewerage, storm-water drains, rainwater harvesting/water conservation and an electrical meter room/sub-station/receiving station as “YES,” while recording 0% progress for the listed schedule items. The record does not provide water-source details, treatment capacity, STP capacity, reuse arrangements, electrical load, generator capacity, lift specifications, CCTV or access-control details as project-filed service specifications.
The HMDA approval requires compliance with Fire Service department norms, provides for automatic sprinklers if basement area exceeds 200 Sq.mts, and requires structural and construction-worker safety measures. These approval conditions do not establish that the relevant systems have been installed or that statutory clearances have been obtained. The available material does not state whether the basement threshold applies to this building.
8. Location, access & connectivity
The registered location is Sultanpur village, Ameenpur mandal, Sangareddy district, PIN 502319. The project boundaries recorded in the RERA land schedule include a 100 Feet Road and Petrol Pump and Others Land on the west. HMDA’s technical approval refers to a proposed 30 mts wide Master plan road affecting 72.70 Sq.mtrs and records that area as gifted to the Gram Panchayat.
A software-derived location point is recorded as parcel centroid 17.57000, 78.31124. The nearest sampled Outer Ring Road interchange is listed at approximately 7.0 km; this is a measured connectivity record, not a travel-time claim. No public-transport route, named access-road sequence or verified travel time is supplied.
9. Developer & development status
The registered promoter is SASR INFRASTRUCTURE PRIVATE LIMITED, a private limited company; the supplied corporate identifier is 36AAWCS6955P1Z0 (GSTIN). The RERA record gives the promoter’s address as H No 1-57/PP/305, Madinaguda, Sultanpur, Ameenpur, Sangareddy, 502319.
The Form B affidavit is made by Sri. S. Venkata Ramana Reddy, stated to be authorised by the promoter. The filing identifies landowners Sara Ramesh alias Boreda Ramesh and Boreda Sai Kiran and refers to Development cum General Power of Attorney No. 15738/2023 for the development arrangement.
A current construction-progress certificate or independently verified site report is not supplied. The project’s RERA header records proposed completion as 13/07/2029, while Form B states 13 March 2029; the registration certificate separately records validity through 13/03/2029. No occupancy or completion certificate is included in the reviewed documents.
10. Approvals, official records & documents
| Identifier / date | P01100007145; issued 21/10/2023 |
|---|---|
| What the supplied record establishes | Registration for the named project, with validity recorded through 13/03/2029, subject to the certificate’s conditions. |
| Identifier / date | 047962/SKP/R1/U6/HMDA/05082021; 13/03/2023 |
|---|---|
| What the supplied record establishes | Technical approval for a residential building on the stated survey land; the document says local Executive Authority sanction is required in conformity with the technical plans. |
| Identifier / date | GPD/BA/2023; 29.09.2023 |
|---|---|
| What the supplied record establishes | Building permission for a residential I Stilt + 5 Upper floors building, subject to stated conditions. |
| Identifier / date | October 2023 |
|---|---|
| What the supplied record establishes | Promoter declaration includes a completion undertaking of 13th MARCH 2029 and RERA-related undertakings. |
| Identifier / date | RERA-filed item 361137 |
|---|---|
| What the supplied record establishes | The layout-plan item is not extracted; drawing-based unit measurements are available, but are software measurements and require review. |
| Identifier / date | Not supplied |
|---|---|
| What the supplied record establishes | No such certificate is included in the reviewed project documents. |
The RERA registration certificate includes quarterly-update and separate-account conditions. The approval documents also specify conditions for construction, parking, road access, utilities and occupancy; the full conditions remain in the cited source documents.
Frequently asked questions
Is SRI AYYAPPA SAI RAM AND JAGANNADH RESIDENCY registered with Telangana RERA?
Yes. SRI AYYAPPA SAI RAM AND JAGANNADH RESIDENCY is registered with the Telangana Real Estate Regulatory Authority as P01100007145; the registration status is New Project.
Who is the developer of SRI AYYAPPA SAI RAM AND JAGANNADH RESIDENCY?
The promoter named in the RERA registration is SASR INFRASTRUCTURE PRIVATE LIMITED.
Where is SRI AYYAPPA SAI RAM AND JAGANNADH RESIDENCY located?
SRI AYYAPPA SAI RAM AND JAGANNADH RESIDENCY is in Sultanpur, AMEENPUR, Sangareddy, Telangana (502319).
When will SRI AYYAPPA SAI RAM AND JAGANNADH RESIDENCY be completed?
The promoter's proposed date of completion filed with RERA is 13/07/2029. This is the promoter's declaration, not a guarantee.
More projects in Sultanpur