Royal Sai Gowthami Residency
SAI CONSTRUCTION · Hyderabad · RERA P02500007998
ROYAL SAI GOWTHAMI RESIDENCY is a residential apartment building in Zamistanpur, Secunderabad Mandal, Hyderabad District, developed by the registered promoter SAI CONSTRUCTION. The registered site area is 851.91 sq. m., and the project comprises one building with 1 Cellar + 1 Stilt + 5 upper floors and 20 3BHK apartments. It is registered under TG-RERA P02500007998, with registration valid from 2 April 2024 to 15 October 2026, unless extended; the promoter’s Form B declares completion by 16 October 2025.
More from Sai Construction · 3 projects →
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
6 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Field | Record |
|---|---|
| Registered project name | ROYAL SAI GOWTHAMI RESIDENCY RERA record |
| Project type / use | Residential apartment building RERA record |
| Phase / registered portion | Phase not separately identified; registration concerns the project at Survey No. 15, with site extent recorded as 851.91 sq. m. Land records |
| TG-RERA registration | P02500007998 RERA record |
| Registration validity | 2 April 2024 to 15 October 2026, unless extended by the Authority |
| Registered promoter | SAI CONSTRUCTION (also styled “Sai Construction” / “M/s. Sai Constructions” in the filed records); entity type: proprietorship RERA record Corporate record |
| RERA status | Registered; the supplied certificate states the validity dates above. Current extension or post-expiry status is not established by the supplied record. |
Land and geographic identity
| Field | Record |
|---|---|
| Locality / address | Zamistanpur; Plot Nos. 75 and 76, H. No. 6-1-132/76 and 6-1-132/76/A to 6-1-132/76/K RERA record |
| Revenue village | Zamistanpur Village |
| Mandal / district / PIN | Secunderabad / Hyderabad / 500020 RERA record |
| Survey identity | Survey No. 15; title records also identify Old Survey No. 30/2. No subdivision is stated. Land records |
| Registered site extent | 851.91 sq. m. net area RERA record Land records |
| Plan-record site areas | 854.55 sq. m. plot area (minimum); 851.91 sq. m. net plot area; 2.64 sq. m. splay area |
| Boundaries | North: 40 wide road; South: Plot Nos. 77 and 78; East: 40 wide road; West: Plot No. 74 RERA filing |
| Road-affected area | RERA land details record 0 sq. m.; the drawing extraction separately records a road-surrender condition and a 2.64 sq. m. splay area. RERA filing |
Development identity
| Field | Record |
|---|---|
| Sanctioning authority | Greater Hyderabad Municipal Corporation (GHMC) |
| Principal building-permit references | TS/014722/2023, dated 23 February 2023, in the drawing extraction; GHMC permit no. 3901/GHMC/SEC/2023-BP, dated 16 October 2023 Approvals record |
| Building arrangement and floors | One proposed residential building: 1 Cellar + 1 Stilt + 5 upper floors |
| Approved area figures | Approved built-up area in RERA fields: 2,889.70 sq. m. The drawing extraction labels 2,035.50 sq. m. as net residential BUA and 2,889.70 sq. m. as total proposed BUA including parking; it also separately lists total BUA of 2,960.08 sq. m. RERA filing |
| Parking provision in drawing extraction | 22 proposed parkings; cellar and stilt designated for parking |
| Units | 20 residential units in the GHMC drawing extraction and 20 units in the TG-RERA filing RERA unit table |
Offering and status
| Field | Record |
|---|---|
| Configuration | 3BHK apartments RERA unit table |
| RERA-filed saleable area | 135.63 sq. m. per unit RERA unit table |
| Booked / available | 0 booked and 20 available in the portal data supplied; that record has no as-of date, so these counts are indicative, not a live inventory confirmation. RERA unit table |
| RERA completion undertaking | The promoter’s Form B declares completion by 16 October 2025. |
| RERA registration validity | 2 April 2024–15 October 2026, unless extended |
| Construction stage | No independently verified construction-progress evidence is supplied. The RERA amenity/progress record lists 0% for its progress entries; this is a filed record, not a site inspection. RERA amenities |
| Occupancy / completion certificate | No occupancy or completion certificate is identified in the supplied documents. GHMC permit conditions require an occupancy certificate before occupation. |
2. The project story
ROYAL SAI GOWTHAMI RESIDENCY is registered as a residential apartment project on Plot Nos. 75 and 76 in Zamistanpur Village, Survey No. 15 (also referenced in the title material as Old Survey No. 30/2), Secunderabad Mandal, Hyderabad District. The registered site is 851.91 sq. m. net area. RERA record Land records
The GHMC-filed plan describes one building with a cellar, stilt and five upper floors, intended for residential use, with 20 apartments. The RERA filing lists 20 3BHK units. The promoter’s Form B gives a completion undertaking ending 16 October 2025; that is a declared timeline, not evidence that the building was completed. The supplied material does not establish the current construction stage or issuance of an occupancy certificate. RERA unit table
The GHMC permit states that occupation requires an occupancy certificate. Its conditions also designate the cellar and stilt for vehicle parking and identify a tot-lot and building services in the plan record.
3. Master plan, architecture & building design
- The GHMC drawing extraction describes a single residential building on a net plot area of 851.91 sq. m., with proposed coverage of 426.72 sq. m. (49.93%) and vacant plot area of 425.19 sq. m. It records 1 Cellar + 1 Stilt + 5 upper floors, six floors in its floor-count field, and a building height of 14.49 m; it separately lists total height of 17.99 m and head-room height of 20.49 m.
- The area labels in the drawing are distinct: 2,035.50 sq. m. net residential BUA; 2,889.70 sq. m. total proposed BUA including parking; and 2,960.08 sq. m. listed as “Total BUA.” The RERA project fields record approved built-up area as 2,889.70 sq. m. These are document labels; no FSI-counted area is supplied. RERA filing
- The drawing extraction records 20 residential units and five upper-floor area entries of 407.10 sq. m. each. The available material does not establish a verified flat-per-floor schedule, number of lifts or stairs, or detailed circulation and access arrangement.
- The approved-plan extraction lists a tot-lot, transformer space, rainwater harvesting, percolation pit, septic tank, sump and garbage house. It also states that cellar and stilt areas are for parking. No independent completion or site-verification evidence is supplied for these features.
4. Homes, configurations & floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 3BHK | 20 | 0 | 20 | 135.63 sq. m. | 83.3–88.7 sq. m. (software-measured range; median 87.0 sq. m.) | 36% |
RERA-filed unit counts and saleable area are from the project filing. Booking and availability figures are the supplied portal snapshot, with no as-of date, and should be confirmed directly before purchase. RERA unit table RERA unit details
Carpet measurements were software-measured from approved floor-plan drawing geometry for eight 3BHK designs and are marked as needing review; they are not RERA-filed areas. The drawings label rooms including bedrooms, drawing room, dining/kitchen, toilets, wash area and a utility area. In the measured example, the utility area is identified as excluded from carpet area. Floor plans RERA unit details
The RERA saleable area is not interchangeable with carpet area: the supplied drawing-measurement note says saleable area includes the home’s share of common areas. No unit-specific registered agreement or allotment is supplied to establish a particular apartment’s final area or allocation. Floor plans
5. Parking & vehicle circulation
The GHMC drawing extraction records 22 proposed parking spaces, with cellar and stilt approved for vehicle parking. It lists 854.20 sq. m. as proposed parking area and 189.91 sq. m. as visitor parking, against 61.07 sq. m. visitor parking required and 671.73 sq. m. total parking required.
The separate GHMC permit extraction lists total parking area as 879.1 sq. m. The supplied material does not establish unit-wise parking allocations, exclusive ownership rights, accessible parking provision, two-wheeler counts, ramp or driveway details, or EV-charging provision. A drawn parking bay does not itself establish an exclusive unit entitlement.
6. Amenities, recreation & open spaces
The RERA amenity record includes the facilities below. Its progress entries are shown as 0%; this is a portal-recorded figure, not independent verification of site condition. RERA amenities
| Description / size | GHMC drawing extraction lists a tot-lot of 43.55; unit not specified in that entry. The plan requires fencing and maintenance as greenery. |
|---|---|
| Declared progress / verified status | RERA amenity record lists green strip/tot-lot/park at 0%; not independently verified. RERA amenities |
| Description / size | No area supplied in the RERA amenity record. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | Progress recorded as 0%; not independently verified. |
| Description / size | No facility or size details supplied. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | Progress recorded as 0%; not independently verified. |
| Description / size | The plan requires tree planting and maintenance of a peripheral greenery strip. |
|---|---|
| Declared progress / verified status | Required by plan conditions; delivery not independently verified. |
No clubhouse or specific indoor or sports facility is documented in the supplied RERA amenity or plan records. The vendor record lists security, fire safety, waste management and a sewage treatment plant; those are vendor-attributed claims, not evidence of sanctioned or delivered recreational amenities. Promoter website
7. Utilities, building services & safety
| Service | Supplied evidence |
|---|---|
| Water | The RERA amenity record marks water supply “YES”; the GHMC drawing extraction lists a sump. No source, storage capacity or treatment capacity is supplied. RERA amenities |
| Sewerage / drainage | The RERA amenity record marks sewerage “YES” and lists treatment and disposal of sewage/sullage water, but records progress as 0%. The drawing extraction lists a septic tank. The vendor separately claims an STP; the supplied material does not establish that an STP is approved or completed. RERA amenities Promoter website |
| Rainwater | The plan lists rainwater harvesting and a percolation pit; the GHMC permit extraction lists four rainwater-harvesting pits. The amenity record marks water conservation/rainwater harvesting “YES” and progress 0%. RERA amenities |
| Electrical | The plan lists transformer space; the RERA amenity record marks electrical meter room/sub-station/receiving station “YES,” with progress 0%. No capacity or commissioned status is supplied. RERA amenities |
| Fire and life safety | RERA records fire protection and fire-safety requirements, with progress 0%. The GHMC permit requires an Occupancy Fire NOC from the Director (EV&DM) before issue of an occupancy certificate. No Fire NOC is supplied. RERA amenities |
| Waste | The plan requires a garbage house within the premises; the vendor lists waste management. The supplied records do not verify completion or operating arrangements. Promoter website |
| Lifts, access and accessibility | The plan conditions refer to lifts and require services to be executed under qualified technical personnel, but no lift count, capacity, accessibility features or completed installation details are supplied. |
8. Location, access & connectivity
The registered location is Plot Nos. 75 and 76, Zamistanpur Village, Secunderabad Mandal, Hyderabad District, PIN 500020; the plan identifies the locality as Sri Ranga Nagar Colony, Chilkalaguda Extension, Secunderabad. RERA record
The filed land-boundary description identifies 40 wide roads to the north and east, Plot No. 74 to the west, and Plot Nos. 77 and 78 to the south. The drawing extraction also refers to existing and proposed 12.00 m-wide roads and other road-width labels; no verified access-road route or public-transport detail is supplied. RERA filing
A supplied location record lists Financial District (Nanakramguda) at 1.2 km from its stated cadastral parcel centroid. The record does not provide a route or travel time. Location record The vendor’s “nearest landmark” description is Zamistanpur. Promoter website
9. Developer & development status
The registered promoter is SAI CONSTRUCTION, described in the RERA project record as a proprietorship. The supplied promoter address is B, Prem Nagar Colony, Sri Ranga Nagar Colony, Zamistanpur, Secunderabad, Hyderabad, 500020. NIMMALA VIJAYANAND RAVENDER is identified as authorized signatory, and the Form B declaration names him as deponent for M/s. Sai Constructions. Corporate record Parties record
The registration certificate gives a separate promoter address with PIN 500010. No corporate registration number, official contact details or promoter website is supplied.
The GHMC permit identifies SAI CONSTRUCTIONS as developer/builder. The RERA fields describe one building and 20 proposed units; the supplied records do not independently verify construction progress or occupancy. The promoter’s Form B undertaking states completion by 16 October 2025; TG-RERA registration validity is separately stated as ending 15 October 2026 unless extended. RERA record
10. Approvals, official records & documents
| Reference / scope | ROYAL SAI GOWTHAMI RESIDENCY; P02500007998; valid 2 April 2024 to 15 October 2026 unless extended |
|---|
| Reference / scope | TS/014722/2023; dated 23 February 2023; proposed residential building on Survey No. 15 |
|---|
| Reference / scope | 3901/GHMC/SEC/2023-BP; dated 16 October 2023; identifies 1 Cellar + 1 Stilt + 5 upper floors |
|---|
| Reference / scope | Approved Layout No. / LRS Proceeding No. / Subdivision No. recorded as 190/1983; no separate approved-layout document is identified in the supplied material |
|---|
| Reference / scope | Advocate title report and investigation report, plus filed deeds and development agreement material; the detailed title review is outside this Overview |
|---|
| Reference / scope | Form B affidavit-cum-declaration dated 16 March 2024, including promoter declarations and completion undertaking |
|---|
| Reference / scope | No occupancy or completion certificate supplied; the GHMC permit conditions require an occupancy certificate before occupation |
|---|
1. Project at a glance
Project identity
Registered project name: ROYAL SAI GOWTHAMI RESIDENCY
Project type / use: Residential apartment building
Phase / registered portion: Phase not separately identified; registration concerns the project at Survey No. 15, with site extent recorded as 851.91 sq. m.
TG-RERA registration: P02500007998
Registration validity: 2 April 2024 to 15 October 2026, unless extended by the Authority
Registered promoter: SAI CONSTRUCTION (also styled “Sai Construction” / “M/s. Sai Constructions” in the filed records); entity type: proprietorship
RERA status: Registered; the supplied certificate states the validity dates above. Current extension or post-expiry status is not established by the supplied record.
Land and geographic identity
Locality / address: Zamistanpur; Plot Nos. 75 and 76, H. No. 6-1-132/76 and 6-1-132/76/A to 6-1-132/76/K
Revenue village: Zamistanpur Village
Mandal / district / PIN: Secunderabad / Hyderabad / 500020
Survey identity: Survey No. 15; title records also identify Old Survey No. 30/2. No subdivision is stated.
Registered site extent: 851.91 sq. m. net area
Plan-record site areas: 854.55 sq. m. plot area (minimum); 851.91 sq. m. net plot area; 2.64 sq. m. splay area
Boundaries: North: 40 wide road; South: Plot Nos. 77 and 78; East: 40 wide road; West: Plot No. 74
Road-affected area: RERA land details record 0 sq. m.; the drawing extraction separately records a road-surrender condition and a 2.64 sq. m. splay area.
Development identity
Sanctioning authority: Greater Hyderabad Municipal Corporation (GHMC)
Principal building-permit references: TS/014722/2023, dated 23 February 2023, in the drawing extraction; GHMC permit no. 3901/GHMC/SEC/2023-BP, dated 16 October 2023
Building arrangement and floors: One proposed residential building: 1 Cellar + 1 Stilt + 5 upper floors
Approved area figures: Approved built-up area in RERA fields: 2,889.70 sq. m. The drawing extraction labels 2,035.50 sq. m. as net residential BUA and 2,889.70 sq. m. as total proposed BUA including parking; it also separately lists total BUA of 2,960.08 sq. m.
Parking provision in drawing extraction: 22 proposed parkings; cellar and stilt designated for parking
Units: 20 residential units in the GHMC drawing extraction and 20 units in the TG-RERA filing
Offering and status
Configuration: 3BHK apartments
RERA-filed saleable area: 135.63 sq. m. per unit
Booked / available: 0 booked and 20 available in the portal data supplied; that record has no as-of date, so these counts are indicative, not a live inventory confirmation.
RERA completion undertaking: The promoter’s Form B declares completion by 16 October 2025.
RERA registration validity: 2 April 2024–15 October 2026, unless extended
Construction stage: No independently verified construction-progress evidence is supplied. The RERA amenity/progress record lists 0% for its progress entries; this is a filed record, not a site inspection.
Occupancy / completion certificate: No occupancy or completion certificate is identified in the supplied documents. GHMC permit conditions require an occupancy certificate before occupation.
2. The project story
ROYAL SAI GOWTHAMI RESIDENCY is registered as a residential apartment project on Plot Nos. 75 and 76 in Zamistanpur Village, Survey No. 15 (also referenced in the title material as Old Survey No. 30/2), Secunderabad Mandal, Hyderabad District. The registered site is 851.91 sq. m. net area.
The GHMC-filed plan describes one building with a cellar, stilt and five upper floors, intended for residential use, with 20 apartments. The RERA filing lists 20 3BHK units. The promoter’s Form B gives a completion undertaking ending 16 October 2025; that is a declared timeline, not evidence that the building was completed. The supplied material does not establish the current construction stage or issuance of an occupancy certificate.
The GHMC permit states that occupation requires an occupancy certificate. Its conditions also designate the cellar and stilt for vehicle parking and identify a tot-lot and building services in the plan record.
3. Master plan, architecture & building design
- The GHMC drawing extraction describes a single residential building on a net plot area of 851.91 sq. m., with proposed coverage of 426.72 sq. m. (49.93%) and vacant plot area of 425.19 sq. m. It records 1 Cellar + 1 Stilt + 5 upper floors, six floors in its floor-count field, and a building height of 14.49 m; it separately lists total height of 17.99 m and head-room height of 20.49 m.
- The area labels in the drawing are distinct: 2,035.50 sq. m. net residential BUA; 2,889.70 sq. m. total proposed BUA including parking; and 2,960.08 sq. m. listed as “Total BUA.” The RERA project fields record approved built-up area as 2,889.70 sq. m. These are document labels; no FSI-counted area is supplied.
- The drawing extraction records 20 residential units and five upper-floor area entries of 407.10 sq. m. each. The available material does not establish a verified flat-per-floor schedule, number of lifts or stairs, or detailed circulation and access arrangement.
- The approved-plan extraction lists a tot-lot, transformer space, rainwater harvesting, percolation pit, septic tank, sump and garbage house. It also states that cellar and stilt areas are for parking. No independent completion or site-verification evidence is supplied for these features.
4. Homes, configurations & floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 3BHK | 20 | 0 | 20 | 135.63 sq. m. | 83.3–88.7 sq. m. (software-measured range; median 87.0 sq. m.) | 36% |
RERA-filed unit counts and saleable area are from the project filing. Booking and availability figures are the supplied portal snapshot, with no as-of date, and should be confirmed directly before purchase.
Carpet measurements were software-measured from approved floor-plan drawing geometry for eight 3BHK designs and are marked as needing review; they are not RERA-filed areas. The drawings label rooms including bedrooms, drawing room, dining/kitchen, toilets, wash area and a utility area. In the measured example, the utility area is identified as excluded from carpet area.
The RERA saleable area is not interchangeable with carpet area: the supplied drawing-measurement note says saleable area includes the home’s share of common areas. No unit-specific registered agreement or allotment is supplied to establish a particular apartment’s final area or allocation.
5. Parking & vehicle circulation
The GHMC drawing extraction records 22 proposed parking spaces, with cellar and stilt approved for vehicle parking. It lists 854.20 sq. m. as proposed parking area and 189.91 sq. m. as visitor parking, against 61.07 sq. m. visitor parking required and 671.73 sq. m. total parking required.
The separate GHMC permit extraction lists total parking area as 879.1 sq. m. The supplied material does not establish unit-wise parking allocations, exclusive ownership rights, accessible parking provision, two-wheeler counts, ramp or driveway details, or EV-charging provision. A drawn parking bay does not itself establish an exclusive unit entitlement.
6. Amenities, recreation & open spaces
The RERA amenity record includes the facilities below. Its progress entries are shown as 0%; this is a portal-recorded figure, not independent verification of site condition.
| Description / size | GHMC drawing extraction lists a tot-lot of 43.55; unit not specified in that entry. The plan requires fencing and maintenance as greenery. |
|---|---|
| Declared progress / verified status | RERA amenity record lists green strip/tot-lot/park at 0%; not independently verified. |
| Description / size | No area supplied in the RERA amenity record. |
|---|---|
| Declared progress / verified status | Progress recorded as 0%; not independently verified. |
| Description / size | No facility or size details supplied. |
|---|---|
| Declared progress / verified status | Progress recorded as 0%; not independently verified. |
| Description / size | The plan requires tree planting and maintenance of a peripheral greenery strip. |
|---|---|
| Declared progress / verified status | Required by plan conditions; delivery not independently verified. |
No clubhouse or specific indoor or sports facility is documented in the supplied RERA amenity or plan records. The vendor record lists security, fire safety, waste management and a sewage treatment plant; those are vendor-attributed claims, not evidence of sanctioned or delivered recreational amenities.
7. Utilities, building services & safety
Water: The RERA amenity record marks water supply “YES”; the GHMC drawing extraction lists a sump. No source, storage capacity or treatment capacity is supplied.
Sewerage / drainage: The RERA amenity record marks sewerage “YES” and lists treatment and disposal of sewage/sullage water, but records progress as 0%. The drawing extraction lists a septic tank. The vendor separately claims an STP; the supplied material does not establish that an STP is approved or completed.
Rainwater: The plan lists rainwater harvesting and a percolation pit; the GHMC permit extraction lists four rainwater-harvesting pits. The amenity record marks water conservation/rainwater harvesting “YES” and progress 0%.
Electrical: The plan lists transformer space; the RERA amenity record marks electrical meter room/sub-station/receiving station “YES,” with progress 0%. No capacity or commissioned status is supplied.
Fire and life safety: RERA records fire protection and fire-safety requirements, with progress 0%. The GHMC permit requires an Occupancy Fire NOC from the Director (EV&DM) before issue of an occupancy certificate. No Fire NOC is supplied.
Waste: The plan requires a garbage house within the premises; the vendor lists waste management. The supplied records do not verify completion or operating arrangements.
Lifts, access and accessibility: The plan conditions refer to lifts and require services to be executed under qualified technical personnel, but no lift count, capacity, accessibility features or completed installation details are supplied.
8. Location, access & connectivity
The registered location is Plot Nos. 75 and 76, Zamistanpur Village, Secunderabad Mandal, Hyderabad District, PIN 500020; the plan identifies the locality as Sri Ranga Nagar Colony, Chilkalaguda Extension, Secunderabad.
The filed land-boundary description identifies 40 wide roads to the north and east, Plot No. 74 to the west, and Plot Nos. 77 and 78 to the south. The drawing extraction also refers to existing and proposed 12.00 m-wide roads and other road-width labels; no verified access-road route or public-transport detail is supplied.
A supplied location record lists Financial District (Nanakramguda) at 1.2 km from its stated cadastral parcel centroid. The record does not provide a route or travel time. The vendor’s “nearest landmark” description is Zamistanpur.
9. Developer & development status
The registered promoter is SAI CONSTRUCTION, described in the RERA project record as a proprietorship. The supplied promoter address is B, Prem Nagar Colony, Sri Ranga Nagar Colony, Zamistanpur, Secunderabad, Hyderabad, 500020. NIMMALA VIJAYANAND RAVENDER is identified as authorized signatory, and the Form B declaration names him as deponent for M/s. Sai Constructions.
The registration certificate gives a separate promoter address with PIN 500010. No corporate registration number, official contact details or promoter website is supplied.
The GHMC permit identifies SAI CONSTRUCTIONS as developer/builder. The RERA fields describe one building and 20 proposed units; the supplied records do not independently verify construction progress or occupancy. The promoter’s Form B undertaking states completion by 16 October 2025; TG-RERA registration validity is separately stated as ending 15 October 2026 unless extended.
10. Approvals, official records & documents
| Reference / scope | ROYAL SAI GOWTHAMI RESIDENCY; P02500007998; valid 2 April 2024 to 15 October 2026 unless extended |
|---|
| Reference / scope | TS/014722/2023; dated 23 February 2023; proposed residential building on Survey No. 15 |
|---|
| Reference / scope | 3901/GHMC/SEC/2023-BP; dated 16 October 2023; identifies 1 Cellar + 1 Stilt + 5 upper floors |
|---|
| Reference / scope | Approved Layout No. / LRS Proceeding No. / Subdivision No. recorded as 190/1983; no separate approved-layout document is identified in the supplied material |
|---|
| Reference / scope | Advocate title report and investigation report, plus filed deeds and development agreement material; the detailed title review is outside this Overview |
|---|
| Reference / scope | Form B affidavit-cum-declaration dated 16 March 2024, including promoter declarations and completion undertaking |
|---|
| Reference / scope | No occupancy or completion certificate supplied; the GHMC permit conditions require an occupancy certificate before occupation |
|---|
Frequently asked questions
Is ROYAL SAI GOWTHAMI RESIDENCY registered with Telangana RERA?
Yes. ROYAL SAI GOWTHAMI RESIDENCY is registered with the Telangana Real Estate Regulatory Authority as P02500007998; the registration status is New Project.
Who is the developer of ROYAL SAI GOWTHAMI RESIDENCY?
The promoter named in the RERA registration is SAI CONSTRUCTION.
Where is ROYAL SAI GOWTHAMI RESIDENCY located?
ROYAL SAI GOWTHAMI RESIDENCY is in ZAMISTANPUR, Secunderabad, Hyderabad, Telangana (500020).
When will ROYAL SAI GOWTHAMI RESIDENCY be completed?
The promoter's proposed date of completion filed with RERA is 15/02/2027. This is the promoter's declaration, not a guarantee.
More projects in Secunderabad