North East

LEVONOR PROJECTS PRIVATE LIMITED · Hyderabad · RERA P02500006167

NORTH EAST is a residential apartment project in Attapur, Rajendranagar mandal, Hyderabad district. It is being developed by registered promoter LEVONOR PROJECTS PRIVATE LIMITED on a net plot area of 2677.72 sq. m, with one residential building comprising 1 Cellar + 1 Stilt + 5 upper floors and 45 3BHK apartments. The project is registered with TG-RERA under registration number P02500006167, and its proposed completion date is 15/03/2026.

01What we found

Period endedTG-RERA registration ran to 15 Mar 2026 - check its extension on TG-RERA
16documents on file - each fact links to its page
1court case on this project's land (survey 95, Attapur)
7items to check - 3 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

7 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

1. Project at a glance

Project identity

ItemProject record
Registered name and typeNORTH EAST; residential apartment project. RERA record RERA filing
Registered portion / phaseThe RERA record identifies one registered project and one building; a separate phase name or phase number is not disclosed. RERA record RERA unit table
TG-RERA registrationP02500006167, Form C, granted 24/04/2023; recorded validity is 24/04/2023–15/03/2026. The certificate says it is subject to extension by the Authority; no extension is recorded in the supplied certificate.
Registered promoterLEVONOR PROJECTS PRIVATE LIMITED. RERA record Corporate record
RERA record statusThe supplied registration certificate establishes registration. Its stated validity ended 15/03/2026; a current post-expiry registration status is not established by the supplied record.

Land and geographic identity

ItemProject record
Locality / revenue villageAttapur locality; revenue village recorded as ATTAPUR / Attapur. RERA record RERA filing
MandalRajendranagar is stated in the GHMC building-permit and OC extractions; the project identity record does not disclose a mandal.
DistrictProject identity record: Hyderabad. The GHMC permit and OC extractions describe the site as in Rangareddy District. RERA record
PIN500048 in the project identity record. RERA record
Survey numbers and subdivisions95/P and 117/P. RERA record
Site extentTotal plot area 3444.3 sq. m; road-affected area 766.58 sq. m; net plot area 2677.72 sq. m. These figures are stated in the GHMC permit/OC records.
BoundariesEast: other land; West: other land; North: other land; South: road. RERA filing

Development identity

ItemProject record
Sanctioning authority and principal approvalGreater Hyderabad Municipal Corporation (GHMC), Building Permit 5588/GHMC/CHR/2023-BP, approved 15 March 2023.
BuildingOne residential building, named Building Name - A in the permit extraction; the OC extraction identifies the building as LEVONOR PROJECT SPVT LTD.
Sanctioned floor configuration1 Cellar + 1 Stilt + 5 upper floors; OC extraction also records 0 ground floors.
Building height14.4 metres in the permit and OC records.
Approved built-up area7,861.40 sq. m in the permit record; the OC records total built-up area of 7861.4 Sq. Metres.
Parking provisionPermit record: total parking area 3302.3 (unit not stated in the extracted parameter). OC record: parking area 3302.3 sq. mts.
Unit countGHMC permit condition refers to the number of units sanctioned but the supplied extraction does not state that count. TG-RERA filing records 45 apartments. RERA unit table
Road-affected areaThe permit records 766.58 sq. m as road-affected and says that portion is to be surrendered to GHMC free of cost.

Offering and status

ItemProject record
RERA-filed configuration3BHK, 45 units; filed saleable area 180.71 sq. m per unit. RERA unit table
Booked / available12 booked; 33 available, as last read from the TG-RERA portal. No as-of date is supplied, so counts are indicative rather than a current inventory confirmation. RERA unit table
Completion datePromoter’s Form B completion undertaking and GHMC permit due date state 15/03/2026.
Occupancy certificateGHMC OC 001041/GHMC/00713/SWOC/CHR1/2025, dated 17/01/2026, covers the residential building at Attapur in survey numbers 95/P and 117/P. The OC records completion date 12/05/2025, zero deviated built-up area and that the building is fit for occupation.
Registration validity versus completionRegistration validity ended 15/03/2026; that is distinct from the stated completion deadline and the OC issued for the building.

2. The project story

  • NORTH EAST is a single-building residential apartment development registered with TG-RERA in Attapur village, on survey numbers 95/P and 117/P. The GHMC permit describes a building with one cellar, one stilt level and five upper floors, for residential use. The RERA filing lists 45 three-bedroom apartments. RERA record RERA unit table
  • The GHMC occupancy certificate is for the residential building on these survey numbers and states that it is fit for occupation. It records completion on 12/05/2025, issuance on 17/01/2026, and zero deviated built-up area. The supplied record therefore documents an OC for the identified building; it does not provide a separate tower- or phase-wise OC breakdown.

3. Master plan, architecture & building design

  • The GHMC permit records a 3444.3 sq. m plot, including 766.58 sq. m affected by road widening, leaving a 2677.72 sq. m net plot area. It records residential built-up area of 7,861.40 sq. m and a 136.83 tot lot (unit not stated in the extracted figure). The building is approved as one residential block with one cellar, one stilt and five upper floors, with a stated height of 14.4 metres.
  • The permit extraction identifies the cellar and stilt as parking levels and states that they are to be used exclusively for vehicle parking. It also requires the tot lot to be fenced and maintained as greenery, periphery greenery and a rainwater-harvesting structure. No supplied drawing-derived record establishes the building footprint, flats per floor, lift or stair counts, internal circulation plan, or residential/common-area distribution.
  • The 7,861.40 sq. m figure is the approved built-up area stated in the permit/OC records; it is not identified here as carpet area or saleable area. The RERA-filed unit saleable area is reported separately below. RERA unit table

4. Homes, configurations & floor plans

  • TG-RERA records 45 3BHK apartments, with 12 booked and 33 available in the portal data supplied; no inventory as-of date is given. The filed saleable area is 180.71 sq. m per unit. RERA unit table
ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
3BHK451233180.71 sq. mSoftware-measured range: 91.2–144.0 sq. m; median 131.0 sq. m27% (software-derived)

The carpet-area figures come from software measurement of floor-plan drawings, not a RERA disclosure, and are flagged as needing review; verify them against the drawing. The measurement set covers 12 3BHK designs. A representative measured plan includes living/dining, kitchen, bedrooms, toilets, balconies and utility; the supplied room measurements include living/dining 7.69 × 3.49 m and kitchen 3.48 × 3.62 m. Balcony and utility areas are excluded from the measured carpet area. Saleable area and measured carpet area are distinct measures; the supplied floor-plan note says saleable area also counts the home’s share of common areas. Floor plans RERA unit details

5. Parking & vehicle circulation

The GHMC permit records 3302.3 as total parking area and approves the cellar and stilt for parking use only. The OC extraction records parking area as 3302.3 sq. mts. The supplied material does not establish the number of car or two-wheeler bays, visitor or accessible spaces, parking allocation to individual apartments, ramp configuration, or EV charging. A parking area in a plan or approval does not by itself establish exclusive parking ownership or a particular unit allocation.

6. Amenities, recreation & open spaces

Landscape/open space
FacilityTot lot / green strip
Description / sizePermit extraction records 136.83 for the tot lot; unit is not stated. Permit requires fencing and maintenance as greenery.
Evidence sourceGHMC permit
Declared progress / verified statusSanction condition; completion status for the tot lot is not separately verified in the supplied record.
Landscape/open space
FacilityPeriphery greenery and tree planting
Description / sizePermit requires a greenery strip and tree plantation along the periphery and front.
Evidence sourceGHMC permit
Declared progress / verified statusRequired by permit; independent completion status not supplied.
Site utility / environmental provision
FacilityRainwater harvesting
Description / sizePermit records 10 rainwater-harvesting pits; OC extraction also records 10, while the permit extraction’s amenities field lists a rainwater-harvesting structure.
Evidence sourceGHMC permit and OC
Declared progress / verified statusRecorded in the OC extraction; no independent operational verification supplied.
Convenience/community
FacilityGarbage house
Description / sizeRequired within the premises by the permit.
Evidence sourceGHMC permit
Declared progress / verified statusPermit condition; completion status not separately stated.
  • The vendor listing also names a swimming pool, gym, children’s play area, clubhouse, park and other facilities, but these are promoter/vendor claims and are not established by the supplied GHMC permit or RERA amenity-progress data. Promoter website
  • The RERA amenity record reports 0% for the listed progress fields, including internal roads and footpaths, green strip/tot lot/park, street lighting and community buildings; the supplied record does not provide an as-of date for those percentages. RERA amenities

7. Utilities, building services & safety

  • The RERA amenity record marks Water Supply, Sewerage (Chamber, Lines, Septic Tank, STP), Water Conservation, Rain water Harvesting, Fire Protection and Fire Safety Requirements, and Electrical Meter Room, Sub-Station, Receiving Station as available “YES”; the same record shows 0% in the progress field for each listed item. These are filed/portal statuses, not independent operational verification. RERA amenities
  • The GHMC permit requires a rainwater-harvesting structure, space for a transformer, a garbage house, qualified technical supervision of services, and fire-fighting installations as stipulated in the National Building Code of India, 2016. It also states that an occupancy fire NOC is to be obtained before issue of the OC. The supplied OC records issuance but does not include the fire NOC itself or details of water storage, STP capacity, backup power, lift count/capacity, CCTV, waste segregation, or accessibility provisions.

8. Location, access & connectivity

  • The registered project location is Attapur, Hyderabad, Telangana; the project record identifies Attapur village and PIN 500048. The GHMC approval records the site on survey numbers 95/P and 117/P, with the southern boundary described as a road. RERA record RERA filing
  • The supplied location data gives the Financial District (Nanakramguda) as an anchor 1.2 km from the cadastral parcel centroid. Location record
  • No further verified approach-road, public-transport, or landmark distances are supplied.

9. Developer & development status

  • The registered promoter is LEVONOR PROJECTS PRIVATE LIMITED, a private limited company, GSTIN 36AACCL2937Q1ZZ. The project record lists its address as Malik Solitaire Building, Road No. 36, Attapur, Hyderabad, PIN 500048. RERA record Corporate record Parties record
  • The promoter’s Form B, signed by authorized signatory Varun Jupally and dated 17/03/2023, declares a completion date of 15/03/2026 and gives the project-fund and approval undertakings in that filing.
  • The GHMC OC is the supplied evidence of occupancy certification for the building; current TG-RERA registration status after the certificate’s stated expiry is not established in the supplied material.

10. Approvals, official records & documents

TG-RERA registration certificate
Reference / dateP02500006167, issued 24/04/2023; stated validity to 15/03/2026
Scope and evidenceForm C for NORTH EAST; survey numbers 95/P and 117/P.
GHMC building permit
Reference / date5588/GHMC/CHR/2023-BP, 15 March 2023; file 006389/GHMC/3191/CHR1/2022-BP
Scope and evidenceResidential building permit for Attapur, survey numbers 95/P and 117/P; includes sanctioned floor configuration and conditions.
GHMC occupancy certificate
Reference / date001041/GHMC/00713/SWOC/CHR1/2025, 17/01/2026
Scope and evidenceOC for the residential building on survey numbers 95/P and 117/P; records completion date 12/05/2025 and zero deviated built-up area.
Architect’s completion certificate
Reference / dateNumber printed in extraction as 001041 / G}J}/C / 00713 / SW OC / CHRI/ 20 25, dated 17/01/2026
Scope and evidenceCertificate states completion in all aspects and refers to the GHMC OC and Form-8.
Promoter’s RERA Form B
Reference / dateDated 17/03/2023
Scope and evidencePromoter declaration for NORTH EAST, including completion undertaking and project-fund declarations.

The supplied evidence includes the building permit, RERA certificate, Form B, architect’s completion certificate and GHMC occupancy certificate. The listed layout-plan document is not extracted in the project evidence, so no additional layout detail is presented here.

Frequently asked questions

Is NORTH EAST registered with Telangana RERA?

Yes. NORTH EAST is registered with the Telangana Real Estate Regulatory Authority as P02500006167; the registration status is New Project.

Who is the developer of NORTH EAST?

The promoter named in the RERA registration is LEVONOR PROJECTS PRIVATE LIMITED.

Where is NORTH EAST located?

NORTH EAST is in ATTAPUR, Hyderabad, Telangana (500048).

When will NORTH EAST be completed?

The promoter's proposed date of completion filed with RERA is 15/03/2026. This is the promoter's declaration, not a guarantee.