Mgr Layout
MYAKA · Nizamabad · RERA P03100006985
MGR LAYOUT is a plotted development in Mamidipally Village Shivar, Makloor Mandal, Nizamabad District. The registered promoter is Myaka Gangadhar. The project’s total and net land area is 7389.49 sqmts; no plot count, plot-size bands, buildings, floors or plot configurations are stated in the supplied record. It is registered under TG-RERA registration P03100006985, with proposed completion stated as 10/03/2024 and revised proposed completion as 10/03/2023.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
8 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Item | Record |
|---|---|
| Registered project name | MGR LAYOUT RERA record |
| Project type | Plotted development / layout RERA record Approvals record |
| Registered phase or portion | Not separately identified; RERA registration covers the project land stated as Sy. Nos. 203 PART and 207 PART |
| TG-RERA registration | P03100006985 RERA record |
| Registration validity | Certificate states commencement 16/09/2023 and end 10/03/2023, and “0 years”; the supplied record does not establish an extension |
| Registered promoter | Myaka Gangadhar; the project header gives the promoter as MYAKA RERA record Corporate record |
| RERA status | Listed as On-Going Project in the project record RERA record |
Land and geographic identity
| Item | Record |
|---|---|
| Locality | Mamidipally Village Shivar RERA record RERA filing |
| Revenue village | Mamidipalle (also written “Mamidipally” in the filed approval documents) RERA record |
| Mandal / district / PIN | Makloor / Nizamabad / 503223 RERA record |
| Project survey numbers | Sy. Nos. 203 PART and 207 PART RERA record |
| RERA-filed site area | Total area 7389.49 sqmts; net area 7389.49 sqmts RERA filing |
| Boundaries | East: KUNA NADPI GANGARAM LAND; West: OPEN LAND; North: KUNA NADPI GANGARAM LAND; South: 120 FEET ROAD RERA filing |
Development identity
| Item | Record |
|---|---|
| Sanctioning authority | Nizamabad Urban Development Authority (NUDA); the filed letter also records DTCP approval Approvals record |
| Principal layout approval reference | 01/2020/NUDA, Draft Technical Layout Pattern; File No. Lr. Roc.No. 199/NUDA/2019; approved date recorded as 03-2020 Approvals record |
| Approved built-up area | 4139.90 sqmts as recorded in the project fields; the supplied material does not identify the particular layout component represented by this figure RERA filing |
| Site-area basis in approval letter | A.c. 2.00 Gts. |
| Plots / plot count and size bands | Not supplied in the extracted RERA records. The approval letter identifies plots 17, 21, 22 and 23 as mortgaged plots, not as plots available for purchase |
| Buildings and floors | Not applicable to the plotted-layout description in the supplied record; no building or floor schedule is provided RERA record Document index |
| Parking provision | No RERA-filed parking count or parking layout is available in the supplied material Document index |
Offering and status
| Item | Record |
|---|---|
| Offering | Plots in a plotted layout; plot-wise areas, plot count, and inventory are not supplied RERA record Document index |
| RERA saleable area | The project fields record 7389.49 sqmts as total area; no plot-by-plot saleable-area schedule is supplied RERA filing |
| Booked / available counts | Not disclosed in the supplied material Document index |
| Construction / development stage | RERA record labels the project “On-Going Project”; the registration extract does not provide a dated, independently verified construction assessment RERA record RERA amenities |
| Completion dates | Project fields state proposed completion 10/03/2024 and revised proposed completion 10/03/2023. The Form B declaration dated 04-02-2023 undertakes completion on or before 10/03/2023 RERA filing |
| OC / completion certificate | No occupancy or completion certificate is identified in the supplied project documents Document index |
2. The project story
MGR LAYOUT is recorded as a plotted layout in Mamidipally Village Shivar, Makloor Mandal, Nizamabad, on Sy. Nos. 203 PART and 207 PART. Its RERA-filed land record states a total and net area of 7389.49 sqmts. The filed NUDA letter concerns a proposed layout on Sy. Nos. 203 and 207 over A.c. 2.00 Gts. RERA record RERA filing
The layout approval material describes roads, open space, social infrastructure and utilities, and requires development works including road formation, drainage, water-supply infrastructure, electrical lines and street lighting, park development and rainwater-harvesting pits. The RERA amenity entries show several items at 90%, including internal roads and footpaths, water supply, sewerage, green strip/park, street lighting and rainwater harvesting. These are filed progress declarations; no independent completion verification is supplied. RERA amenities
No plot inventory, plot-area schedule, dated site inspection, or occupancy/completion certificate is available in the supplied evidence. Accordingly, the material does not establish which individual plots remain for sale or whether the layout development is complete. Document index RERA amenities
3. Master plan, architecture & building design
This is a plotted layout rather than a building or apartment development in the supplied RERA record. The RERA fields state 7389.49 sqmts total and net land area and 4139.90 sqmts approved built-up area; the supplied records do not define the built-up-area figure’s scope. No building count, floor configuration, apartment arrangement or tower design is provided. RERA record RERA filing RERA filing
The NUDA Draft Technical Layout Pattern letter identifies the following land-use allocations:
| Layout component | Filed area | Filed share | Evidence |
|---|---|---|---|
| Open space | Ac. 0.137 cents | 7.50% | |
| Social Infrastructure | Ac. 0.0457 cents | 2.5% | |
| Roads | Ac. 0.602 cents | 32.96% | |
| Utilities | Ac. 0.0183 cents | 1.0% |
The letter identifies road widths of 18 mts and above and names plots 17, 21, 22 and 23 as mortgaged to NUDA, with a stated extent of 0.16 Cents or 774.40 Sq Yards. These are identified as security plots, not as purchasable inventory. The supplied material does not include an extracted, legible layout drawing from which individual plot arrangement, plot dimensions or internal circulation can be described.
4. Homes, configurations & floor plans
The project is a plotted development. The supplied RERA documents do not include a plot-wise inventory schedule, plot count, plot-size bands, booked or available counts, or individual plot saleable areas. No unit-configuration table can therefore be prepared from the available records. RERA record Document index
Two drawings are recorded, but neither has been measured; both are listed as scans pending. The drawing-review record says any software-measured carpet area would be drawing-based, not a RERA disclosure. No such measurement is available here. Floor plans
5. Parking & vehicle circulation
No sanctioned parking count, visitor or accessible parking provision, parking layout, parking allocation arrangement, or vehicle-entry and exit plan is supplied. The approval letter identifies road widths of 18 mts and above, but does not establish a parking provision or plot-specific parking rights. Document index
6. Amenities, recreation & open spaces
The following are recorded in the RERA amenity data. Percentages are the supplied progress entries, not independent verification of completion.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Internal Roads & Footpaths | No further dimensions supplied | RERA amenities | 90% declared; not independently verified |
| Water Supply | No source, storage capacity or system details supplied in this amenity entry | RERA amenities | 90% declared; not independently verified |
| Sewerage (Chamber, Lines, Septic Tank, STP) | No capacity supplied | RERA amenities | 90% declared; not independently verified |
| Green Strip / TOT LOT / Park | NUDA letter specifies open space of Ac. 0.137 cents (7.50%) | RERA amenities | 90% declared for the amenity entry; not independently verified |
| Street Lighting | No further specifications supplied | RERA amenities | 90% declared; not independently verified |
| Water Conservation / Rainwater Harvesting | Approval letter refers to rainwater-harvesting pits | RERA amenities | 90% declared; not independently verified |
| Community Buildings | No building or description supplied | RERA amenities | 0% recorded |
| Aggregate recreational open space | No separate aggregate figure supplied in the amenity record | RERA amenities | 0% recorded |
The NUDA letter also allocates Ac. 0.0457 cents (2.5%) to social infrastructure and Ac. 0.0183 cents (1.0%) to utilities. Those are layout land-use allocations; the supplied material does not specify a completed community facility or describe its intended use.
7. Utilities, building services & safety
The NUDA layout letter lists proposed layout infrastructure: internal water-supply pipelines, an overhead tank and an assured water-supply source; underground drainage lines and a common septic tank/STP; storm-water drains and nala channelization for storm-water run-off; electrical supply lines, street lights and a transformer; underground ducting for utilities and service lines; and rainwater-harvesting pits. The letter does not provide capacities or establish that these systems have been completed.
The RERA amenity record declares water supply, sewerage, street lighting and rainwater harvesting at 90%, while storm-water drains, sewage/sullage treatment and disposal, solid-waste management, energy management, fire protection and electrical meter/substation/receiving facilities are recorded at 0%. No fire-safety design, emergency access plan, security system or accessibility design is provided in the supplied material. RERA amenities
8. Location, access & connectivity
The registered location is Mamidipally Village Shivar, Makloor Mandal, Nizamabad District, Telangana, PIN 503223. The project-field boundaries identify a 120 FEET ROAD on the south, with KUNA NADPI GANGARAM LAND to the east and north and OPEN LAND to the west. RERA record RERA filing RERA filing
The supplied location record gives the nearest sampled Outer Ring Road interchange as approximately 15.5 km. It provides no public-transport details or other landmark distances. Location record
9. Developer & development status
The registered promoter is identified in the certificate as Myaka Gangadhar; the project header uses MYAKA. The promoter’s legal entity type, corporate registration identifiers, registered office, official contact details and official website are not established in the supplied records. RERA record Corporate record
The Form B affidavit dated 04-02-2023 is a promoter declaration. It states an undertaking to complete the project on or before 10/03/2023 and contains the promoter’s stated title and encumbrance declarations. The project record separately labels the project “On-Going Project”; no independent site-progress report or completion/occupancy certificate is supplied. RERA record Document index
10. Approvals, official records & documents
| Details | Form C; project MGR LAYOUT; registration P03100006985; granted under section 5; issued 16/09/2023 |
|---|
| Details | Draft Technical Layout Pattern 01/2020/NUDA, File No. Lr. Roc.No. 199/NUDA/2019, recorded as approved 03-2020; covers Sy. Nos. 203 and 207 at Mamidipally |
|---|
| Details | Lr. Roc.No.3887/2019/H, dated 13-01-2020 |
|---|
| Details | D.No. 2542/2020, dated 22-02-2020; concerns plots 17, 21, 22 and 23 |
|---|
| Details | Sworn by Sri. Myaka Gangadhar at Armoor on 04-02-2023 |
|---|
| Details | Title report; sale deed; gift/settlement deed; mortgage documents; demarcation certificate; touch map; partial agreement-for-sale templates; encumbrance statements |
|---|
| Details | A layout-plan document is listed, but its extraction is unavailable; the supplied NUDA material describes a draft pattern and conditions for later final layout release |
|---|---|
| Evidence | Document index |
| Details | No such certificate identified in the supplied records |
|---|---|
| Evidence | Document index |
1. Project at a glance
Project identity
Registered project name: MGR LAYOUT
Project type: Plotted development / layout
Registered phase or portion: Not separately identified; RERA registration covers the project land stated as Sy. Nos. 203 PART and 207 PART
TG-RERA registration: P03100006985
Registration validity: Certificate states commencement 16/09/2023 and end 10/03/2023, and “0 years”; the supplied record does not establish an extension
Registered promoter: Myaka Gangadhar; the project header gives the promoter as MYAKA
RERA status: Listed as On-Going Project in the project record
Land and geographic identity
Locality: Mamidipally Village Shivar
Revenue village: Mamidipalle (also written “Mamidipally” in the filed approval documents)
Mandal / district / PIN: Makloor / Nizamabad / 503223
Project survey numbers: Sy. Nos. 203 PART and 207 PART
RERA-filed site area: Total area 7389.49 sqmts; net area 7389.49 sqmts
Boundaries: East: KUNA NADPI GANGARAM LAND; West: OPEN LAND; North: KUNA NADPI GANGARAM LAND; South: 120 FEET ROAD
Development identity
Sanctioning authority: Nizamabad Urban Development Authority (NUDA); the filed letter also records DTCP approval
Principal layout approval reference: 01/2020/NUDA, Draft Technical Layout Pattern; File No. Lr. Roc.No. 199/NUDA/2019; approved date recorded as 03-2020
Approved built-up area: 4139.90 sqmts as recorded in the project fields; the supplied material does not identify the particular layout component represented by this figure
Site-area basis in approval letter: A.c. 2.00 Gts.
Plots / plot count and size bands: Not supplied in the extracted RERA records. The approval letter identifies plots 17, 21, 22 and 23 as mortgaged plots, not as plots available for purchase
Buildings and floors: Not applicable to the plotted-layout description in the supplied record; no building or floor schedule is provided
Parking provision: No RERA-filed parking count or parking layout is available in the supplied material
Offering and status
Offering: Plots in a plotted layout; plot-wise areas, plot count, and inventory are not supplied
RERA saleable area: The project fields record 7389.49 sqmts as total area; no plot-by-plot saleable-area schedule is supplied
Booked / available counts: Not disclosed in the supplied material
Construction / development stage: RERA record labels the project “On-Going Project”; the registration extract does not provide a dated, independently verified construction assessment
Completion dates: Project fields state proposed completion 10/03/2024 and revised proposed completion 10/03/2023. The Form B declaration dated 04-02-2023 undertakes completion on or before 10/03/2023
OC / completion certificate: No occupancy or completion certificate is identified in the supplied project documents
2. The project story
MGR LAYOUT is recorded as a plotted layout in Mamidipally Village Shivar, Makloor Mandal, Nizamabad, on Sy. Nos. 203 PART and 207 PART. Its RERA-filed land record states a total and net area of 7389.49 sqmts. The filed NUDA letter concerns a proposed layout on Sy. Nos. 203 and 207 over A.c. 2.00 Gts.
The layout approval material describes roads, open space, social infrastructure and utilities, and requires development works including road formation, drainage, water-supply infrastructure, electrical lines and street lighting, park development and rainwater-harvesting pits. The RERA amenity entries show several items at 90%, including internal roads and footpaths, water supply, sewerage, green strip/park, street lighting and rainwater harvesting. These are filed progress declarations; no independent completion verification is supplied.
No plot inventory, plot-area schedule, dated site inspection, or occupancy/completion certificate is available in the supplied evidence. Accordingly, the material does not establish which individual plots remain for sale or whether the layout development is complete.
3. Master plan, architecture & building design
This is a plotted layout rather than a building or apartment development in the supplied RERA record. The RERA fields state 7389.49 sqmts total and net land area and 4139.90 sqmts approved built-up area; the supplied records do not define the built-up-area figure’s scope. No building count, floor configuration, apartment arrangement or tower design is provided.
The NUDA Draft Technical Layout Pattern letter identifies the following land-use allocations:
| Layout component | Filed area | Filed share | Evidence |
|---|---|---|---|
| Open space | Ac. 0.137 cents | 7.50% | |
| Social Infrastructure | Ac. 0.0457 cents | 2.5% | |
| Roads | Ac. 0.602 cents | 32.96% | |
| Utilities | Ac. 0.0183 cents | 1.0% |
The letter identifies road widths of 18 mts and above and names plots 17, 21, 22 and 23 as mortgaged to NUDA, with a stated extent of 0.16 Cents or 774.40 Sq Yards. These are identified as security plots, not as purchasable inventory. The supplied material does not include an extracted, legible layout drawing from which individual plot arrangement, plot dimensions or internal circulation can be described.
4. Homes, configurations & floor plans
The project is a plotted development. The supplied RERA documents do not include a plot-wise inventory schedule, plot count, plot-size bands, booked or available counts, or individual plot saleable areas. No unit-configuration table can therefore be prepared from the available records.
Two drawings are recorded, but neither has been measured; both are listed as scans pending. The drawing-review record says any software-measured carpet area would be drawing-based, not a RERA disclosure. No such measurement is available here.
5. Parking & vehicle circulation
No sanctioned parking count, visitor or accessible parking provision, parking layout, parking allocation arrangement, or vehicle-entry and exit plan is supplied. The approval letter identifies road widths of 18 mts and above, but does not establish a parking provision or plot-specific parking rights.
6. Amenities, recreation & open spaces
The following are recorded in the RERA amenity data. Percentages are the supplied progress entries, not independent verification of completion.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Internal Roads & Footpaths | No further dimensions supplied | 90% declared; not independently verified | |
| Water Supply | No source, storage capacity or system details supplied in this amenity entry | 90% declared; not independently verified | |
| Sewerage (Chamber, Lines, Septic Tank, STP) | No capacity supplied | 90% declared; not independently verified | |
| Green Strip / TOT LOT / Park | NUDA letter specifies open space of Ac. 0.137 cents (7.50%) | 90% declared for the amenity entry; not independently verified | |
| Street Lighting | No further specifications supplied | 90% declared; not independently verified | |
| Water Conservation / Rainwater Harvesting | Approval letter refers to rainwater-harvesting pits | 90% declared; not independently verified | |
| Community Buildings | No building or description supplied | 0% recorded | |
| Aggregate recreational open space | No separate aggregate figure supplied in the amenity record | 0% recorded |
The NUDA letter also allocates Ac. 0.0457 cents (2.5%) to social infrastructure and Ac. 0.0183 cents (1.0%) to utilities. Those are layout land-use allocations; the supplied material does not specify a completed community facility or describe its intended use.
7. Utilities, building services & safety
The NUDA layout letter lists proposed layout infrastructure: internal water-supply pipelines, an overhead tank and an assured water-supply source; underground drainage lines and a common septic tank/STP; storm-water drains and nala channelization for storm-water run-off; electrical supply lines, street lights and a transformer; underground ducting for utilities and service lines; and rainwater-harvesting pits. The letter does not provide capacities or establish that these systems have been completed.
The RERA amenity record declares water supply, sewerage, street lighting and rainwater harvesting at 90%, while storm-water drains, sewage/sullage treatment and disposal, solid-waste management, energy management, fire protection and electrical meter/substation/receiving facilities are recorded at 0%. No fire-safety design, emergency access plan, security system or accessibility design is provided in the supplied material.
8. Location, access & connectivity
The registered location is Mamidipally Village Shivar, Makloor Mandal, Nizamabad District, Telangana, PIN 503223. The project-field boundaries identify a 120 FEET ROAD on the south, with KUNA NADPI GANGARAM LAND to the east and north and OPEN LAND to the west.
The supplied location record gives the nearest sampled Outer Ring Road interchange as approximately 15.5 km. It provides no public-transport details or other landmark distances.
9. Developer & development status
The registered promoter is identified in the certificate as Myaka Gangadhar; the project header uses MYAKA. The promoter’s legal entity type, corporate registration identifiers, registered office, official contact details and official website are not established in the supplied records.
The Form B affidavit dated 04-02-2023 is a promoter declaration. It states an undertaking to complete the project on or before 10/03/2023 and contains the promoter’s stated title and encumbrance declarations. The project record separately labels the project “On-Going Project”; no independent site-progress report or completion/occupancy certificate is supplied.
10. Approvals, official records & documents
| Details | Form C; project MGR LAYOUT; registration P03100006985; granted under section 5; issued 16/09/2023 |
|---|
| Details | Draft Technical Layout Pattern 01/2020/NUDA, File No. Lr. Roc.No. 199/NUDA/2019, recorded as approved 03-2020; covers Sy. Nos. 203 and 207 at Mamidipally |
|---|
| Details | Lr. Roc.No.3887/2019/H, dated 13-01-2020 |
|---|
| Details | D.No. 2542/2020, dated 22-02-2020; concerns plots 17, 21, 22 and 23 |
|---|
| Details | Sworn by Sri. Myaka Gangadhar at Armoor on 04-02-2023 |
|---|
| Details | Title report; sale deed; gift/settlement deed; mortgage documents; demarcation certificate; touch map; partial agreement-for-sale templates; encumbrance statements |
|---|
| Details | A layout-plan document is listed, but its extraction is unavailable; the supplied NUDA material describes a draft pattern and conditions for later final layout release |
|---|
| Details | No such certificate identified in the supplied records |
|---|
Frequently asked questions
Is MGR LAYOUT registered with Telangana RERA?
Yes. MGR LAYOUT is registered with the Telangana Real Estate Regulatory Authority as P03100006985; the registration status is On-Going Project.
Who is the developer of MGR LAYOUT?
The promoter named in the RERA registration is MYAKA.
Where is MGR LAYOUT located?
MGR LAYOUT is in MAMIDIPALLY VILLAGE SHIVAR, MAKLOOR MANDAL, NIZAMABAD, Mamidipalle, MAKLOOR, Nizamabad, Telangana (503223).
When will MGR LAYOUT be completed?
The promoter's proposed date of completion filed with RERA is 10/03/2024. This is the promoter's declaration, not a guarantee.