MEERA SHANTIVANAM PHASE 3 PLOT 8 is a residential apartment project in Chegur Village, Nandigama Mandal, Ranga Reddy District, developed by MEERA SHANTIVANAM PRIVATE LIMITED. The registered site area is 5,461.58 sq. m, with four residential blocks—3E, 3F, 3G and 3H—each with 1 stilt + 5 upper floors, and 80 3BHK units. Its TG-RERA registration number is P02400007644, and the proposed completion date is 14 September 2029.

More from Meera Shantivanam Pvt Ltd · 14 projects →

01What we found

RegisteredTG-RERA - valid till 14 Sep 2029
25documents on file - each fact links to its page
1court case on this project's land (survey 112, Chegur)
9items to check - 3 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

9 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

1. Project at a glance

Project identity

ItemRecord
Registered project nameMEERA SHANTIVANAM PHASE 3 PLOT 8 RERA record [REGCERT-53918 p1]
Project typeResidential apartment project; the TG-RERA certificate classifies it as “plotted,” while the filed HMDA building approval and occupancy certificate describe residential buildings. RERA record [REGCERT-53918 p1]
Phase / registered portionPhase 3, Plot 8; the registered site is identified as Plot Nos. 1 to 14. RERA record
TG-RERA registrationP02400007644 RERA record [REGCERT-53918 p1]
Registration validity29 January 2024 to 14 September 2029; this is the registration period, not the completion deadline or evidence of occupancy. RERA record [REGCERT-53918 p1]
Registered promoterMEERA SHANTIVANAM PRIVATE LIMITED RERA record [REGCERT-53918 p1]
RERA statusRegistered as a new project. The registration record was captured on 10 September 2026. RERA record Approvals record

Land and geographic identity

ItemRecord
Locality / revenue villageChegur Village; the RERA address also identifies Chegur. RERA record RERA filing
MandalNandigama RERA record RERA filing
DistrictRanga Reddy (also rendered “Rangareddy” in approval records) RERA record
PIN509325 RERA record RERA filing
All project survey numbers112/105, 112/106, 112/122, 112/123, 112/124, 112/126, 112/129, 112/130, 112/131, 112/132, 112/133, 13P and 14P RERA record [REGCERT-53918 p1]
Registered site extent5,461.58 sq. m RERA filing
Net / total site areaRERA land details report total and net area both as 5,461.58 sq. m; the occupancy certificate gives net site area as 5,461.58 sq. m. RERA filing
Plot referencePlot Nos. 1 to 14 RERA filing
Boundaries (RERA filing)North, south, east and west: “NEIGHBOURS LAND.” RERA filing

Development identity

ItemRecord
Sanctioning authorityHyderabad Metropolitan Development Authority (HMDA) Approvals record
Principal building approval061333/SMD/R1/U6/HMDA/20062023, dated 14 September 2023 Approvals record
Approved building arrangementFour residential blocks—3E, 3F, 3G and 3H—each recorded in the occupancy certificate as 1 stilt + 5 upper floors.
HeightsOccupancy certificate: 15.0 metres for each building. The technical approval also records 15.00 mt. excluding stilt floor and 17.95 mt. from GL in its parameter text.
Approved built-up areaThe occupancy certificate lists 3E and 3F at 3,417.8 sq. m each, and 3G and 3H at 2,873.1 sq. m each. The technical approval separately records total built-up area 12,581.8 sq. m and proposed built-up area 15,573.92 sq. m.
Building area figures in the technical approvalThe approval extract contains multiple area labels, including “Residential Net BUA 15,101.06,” “Proposed Net BUA Area 15,195.92,” “Total Proposed Net BUA Area 12,679.56,” “Total Built Up Area 15,573.92 Sq.mt.” and “Total Net BUA Area 12,676.68 Sq.mt.” These are reproduced as labelled; the supplied extract does not reconcile the labels.
ParkingStilt/cellar is specified for vehicle parking. The technical approval records required parking area 1,384.32 sq. m and proposed parking area 2,521.00 sq. m; no parking-space count is supplied.
Unit countsTG-RERA filing: 80 3BHK units. The approval extract records “Dwelling Units: 20” in a parameter entry and also lists “num_units: 80.00”; the occupancy certificate confirms four buildings but does not state a unit count. RERA unit table

Offering and status

ItemRecord
Unit type3BHK apartments; the RERA filing records 80 units. RERA unit table RERA unit details
RERA-filed saleable area17.85 sq. m as recorded for the 3BHK configuration. This is the supplied filing figure and is not a measured carpet-area figure. RERA unit table RERA unit details
Booked / available0 booked / 80 available, as last read from the TG-RERA portal; the record has no as-of date, so treat these counts as indicative. RERA unit table RERA unit details
Construction / completionAn HMDA occupancy certificate is recorded for the four buildings; the architect’s Form 1A also certifies completion of the registered project. This is not merely a proposed or under-construction status.
Completion datesForm B undertakes completion by 14 September 2029. The occupancy-certificate extract records completion date 15 September 2026, and the architect’s certificate is dated 17 October 2026.
Occupancy certificateHMDA Occupancy Certificate 025002/HMDA/05336/SWOC/SKP1/2026, issued 5 October 2026, covers residential blocks 3E, 3F, 3G and 3H on the listed site; the certificate reports no deviated built-up area for the listed blocks.

2. The project story

This is a residential apartment development registered under TG-RERA as MEERA SHANTIVANAM PHASE 3 PLOT 8, at Plot Nos. 1 to 14 in Chegur Village, Nandigama Mandal, Ranga Reddy District. The registered parcel covers 5,461.58 sq. m and is identified by the 13 survey numbers listed above. RERA record RERA filing [REGCERT-53918 p1]

HMDA’s filed technical approval describes residential buildings, and the occupancy certificate identifies four completed blocks—3E, 3F, 3G and 3H—with stilt parking and five upper floors each. The occupancy certificate says the inspected buildings are fit for occupation and records no deviated built-up area for those blocks; an architect’s Form 1A separately certifies overall project completion. These records establish the stated certificate scope, rather than independently verifying current site condition.

The TG-RERA filing lists 80 3BHK units, with 0 booked and 80 available in the portal snapshot, which carries no as-of date. RERA unit table RERA unit details

3. Master plan, architecture & building design

The registered project site is 5,461.58 sq. m. HMDA’s technical approval describes a residential building development on Plot Nos. 1 to 14; the subsequent occupancy certificate names four blocks, 3E–3H, each with 1 stilt + 5 upper floors. RERA filing

The approval extract records a proposed coverage area of 2,601.92 sq. m and contains several separately labelled built-up and net-BUA figures. Because the supplied approval extract presents multiple area labels without reconciling them, they should be read under their original labels rather than treated as interchangeable measures. The occupancy certificate provides block-level built-up areas: 3,417.8 sq. m each for 3E and 3F, and 2,873.1 sq. m each for 3G and 3H.

The technical approval lists a tot-lot, lift, staircase and service shafts, along with STP, sump, septic tank and underground drainage. The supplied material does not establish flats per floor, lift count or capacity, circulation and entry arrangements, or detailed landscape design.

4. Homes, configurations & floor plans

The TG-RERA filing records 80 3BHK units. No measured carpet area, room dimensions or measured flat design is available in the supplied drawing-derived record; the floor-plan review reports zero measured flat designs for this configuration. RERA unit table RERA unit details Floor plans

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
3BHK8008017.85 sq. mNot measured in the supplied drawing reviewNot supplied

The saleable-area value above is reproduced as filed with TG-RERA. The supplied evidence does not provide a measured carpet area or a loading figure, so those cannot be inferred from it. RERA unit details Floor plans

5. Parking & vehicle circulation

The HMDA technical approval specifies stilt/cellar areas for vehicle parking and records 2,521.00 sq. m of proposed parking area against 1,384.32 sq. m required parking area. It does not provide a count of parking bays or distinguish resident, visitor or accessible spaces.

The approval states that the stilt/cellar floor is to be used exclusively for parking and that parking or construction must not be placed in setback areas. The occupancy certificate identifies stilt parking in each of blocks 3E–3H. No parking allocation to individual apartments, exclusive ownership of bays, ramp arrangement, EV charging provision or two-wheeler count is established by the supplied records.

6. Amenities, recreation & open spaces

The RERA amenity record lists 14 project infrastructure and facility categories. It marks several items “YES,” but the supplied progress percentages are 0 and do not establish construction or delivery status. The approval extract also lists a tot-lot and site utilities. RERA amenities

FacilityDescription / sizeEvidence sourceDeclared progress / verified status
Tot-lot / green stripNo size suppliedRERA amenitiesNamed in approval extract; completion status not established
Internal roads and footpathsSize not suppliedRERA amenities“YES”; progress shown as 0
Community buildingsSize or facility details not suppliedRERA amenitiesListed; progress shown as 0
Aggregate recreational open spaceArea not supplied for this registered projectRERA amenitiesListed; progress shown as 0

No clubhouse, indoor recreation or sports facility is established in the supplied project-specific records. Site utilities are described in the next section. RERA amenities

7. Utilities, building services & safety

The RERA amenity record marks water supply, sewerage, storm-water drains, fire protection and electrical meter room/sub-station/receiving station as “YES”; its progress fields show 0, so this filing alone does not establish completed service provision. It also lists water conservation/rainwater harvesting, energy management and solid-waste management, without capacities or completion status. RERA amenities

HMDA’s technical approval lists an STP, sump, septic tank and underground drainage, as well as a transformer and rainwater-harvesting structure/percolation pit. It directs the developer to provide sump, septic tank and underground drainage to applicable standards and to develop rainwater-harvesting structures. The supplied records do not specify water source or storage capacity, STP capacity, treated-water reuse, electrical load or backup-generator capacity.

The approval extract lists a lift, staircase, fire extinguishers and automatic sprinkler system; it specifies sprinklers if basement area exceeds 200 sq. m and includes fire-safety and structural-safety conditions. These are approval provisions, not evidence in this pack that each system has been installed or independently tested. The supplied records do not state lift capacity/count, accessible circulation, CCTV, security arrangements or waste-processing capacity.

8. Location, access & connectivity

The registered location is Chegur Village, Nandigama Mandal, Ranga Reddy District, Telangana, PIN 509325. The cadastral parcel centroid is recorded at 17.17366418164597, 78.22346160878622. RERA record RERA filing Cadastral map

The supplied connectivity record gives the nearest sampled Outer Ring Road interchange at approximately 22.8 km. HMDA approval extracts refer to access-road widths of 15.0 m, 12.19 m and 30.00 m in the building approval materials; the supplied records do not identify a public-transport service or provide verified travel times to landmarks. Location record

9. Developer & development status

The registered legal promoter is MEERA SHANTIVANAM PRIVATE LIMITED, a company. The project filing gives GSTIN 36AAMCM1835C1ZM and lists the promoter’s address as MEERASHANTIVANAM APARTMENTS, CHEGUR, CHEGUR VILLAGE, Nandigama, Ranga Reddy, 509325. Corporate record RERA filing Parties record

TG-RERA records Siva Kumar Ivaturi as an authorized signatory and director, alongside directors Bhuvaneswari Devi Ravala and A Balasubrahmanyam. The Form B declaration, signed by an authorized signatory, undertakes completion by 14 September 2029 and states that the project land is free from encumbrances; these are promoter declarations. Parties record

The project’s four apartment blocks have an HMDA occupancy certificate dated 5 October 2026; the architect’s Form 1A dated 17 October 2026 certifies completion. The registration remains valid until 14 September 2029 unless extended; that validity is separate from the completion undertaking and the occupancy certificate. [REGCERT-53918 p1]

10. Approvals, official records & documents

RecordDetails and scope
TG-RERA registrationForm C certificate for MEERA SHANTIVANAM PHASE 3 PLOT 8, registration P02400007644, promoter Meera Shantivanan Private Limited; valid 29 January 2024–14 September 2029. [REGCERT-53918 p1]
HMDA building technical approval061333/SMD/R1/U6/HMDA/20062023, dated 14 September 2023, for residential development on Plot Nos. 1–14 and the listed survey numbers at Chegur Village; the approval calls for building sanction by the Executive Authority in conformity with HMDA’s technical approval.
Building-plan and approval drawingFiled approval-plan material with HMDA references, site and building information, and area figures; the OCR does not provide a fully legible approval heading or primary permit number for this drawing.
HMDA layout recordLayout Permit 000129/LO/Plg/HMDA/2021, dated 27 February 2021, for the larger residential open layout. The filed drawing records plots 75–91, 12,852 sq. m, as mortgaged to HMDA pending completion/release of layout works; the project-specific extent is separately stated in the building and occupancy records.
HMDA Occupancy Certificate025002/HMDA/05336/SWOC/SKP1/2026, issued 5 October 2026, covering blocks 3E, 3F, 3G and 3H at the listed project site. The certificate reports no deviated built-up area for the listed blocks.
Architect’s Form 1ADated 17 October 2026; records the occupancy-certificate number and certifies completion of the registered project.
Promoter Form B declarationDated 9 November 2023; includes the promoter’s title, encumbrance and completion declarations.
RERA-filed title reportAdvocate’s title opinion dated 22 August 2023, identifying the proposed apartment land as Plot Nos. 1–14 and stating the advocate’s conclusion on title. It is a filed opinion, not a substitute for the underlying title instruments.

The HMDA layout record concerns a larger plotted layout, while the building and occupancy records identify the apartment development on the registered 5,461.58 sq. m site. The supplied evidence does not include an independently verified site inspection or current utility commissioning records.

Frequently asked questions

Is MEERA SHANTIVANAM PHASE 3 PLOT 8 registered with Telangana RERA?

Yes. MEERA SHANTIVANAM PHASE 3 PLOT 8 is registered with the Telangana Real Estate Regulatory Authority as P02400007644; the registration status is New Project.

Who is the developer of MEERA SHANTIVANAM PHASE 3 PLOT 8?

The promoter named in the RERA registration is MEERA SHANTIVANAM PRIVATE LIMITED.

Where is MEERA SHANTIVANAM PHASE 3 PLOT 8 located?

MEERA SHANTIVANAM PHASE 3 PLOT 8 is in CHEGUR VILLAGE, Nandigama, Rangareddy, Telangana (509325).

When will MEERA SHANTIVANAM PHASE 3 PLOT 8 be completed?

The promoter's proposed date of completion filed with RERA is 14/01/2030. This is the promoter's declaration, not a guarantee.