Khyathi Homes
KHYATHI INFRA DEVELOPERS · Yadadri Bhuvanagiri · RERA P02000008407
KHYATHI HOMES is a plotted development at RAIGIRI REVENUE, Bhongir Mandal, Yadadri Bhuvanagiri District, developed by registered promoter KHYATHI INFRA DEVELOPERS. The RERA land record gives the site extent as 30,353.93 sq m, and the tentative layout approval states 86 plots; buildings, towers and floors are not disclosed. The plots range from 152.95 sq m to 524.75 sq m in the layout drawing schedule. The TG-RERA registration number is P02000008407, and the promoter’s Form B declares completion by 14/12/2025.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
9 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Field | Project record |
|---|---|
| Registered project name | KHYATHI HOMES RERA record |
| Project type | Plotted development / residential layout RERA record RERA filing |
| Phase / registered portion | No phase designation is disclosed; registration is for the project identified as KHYATHI HOMES. RERA record |
| TG-RERA registration | P02000008407 Approvals record |
| Registration validity | 22 June 2024 to 14 December 2025, unless extended by the Authority. This is the registration-validity period stated on the certificate; it is separate from the completion undertaking. Approvals record |
| Registered promoter | KHYATHI INFRA DEVELOPERS, a partnership Corporate record RERA filing |
| Status in supplied record | The project is recorded as a “New Project.” The registration certificate states the validity period above; no extension order or current registration-status confirmation is supplied. RERA record |
Land and geographic identity
| Field | Project record |
|---|---|
| Locality / revenue village | Raigiri Revenue Village; locality recorded as RAIGIRI REVENUE RERA record RERA filing |
| Mandal | Bhongir / Bhongir Mandal RERA record |
| District | Yadadri Bhuvanagiri; the layout document styles this as Yadadri-Bhuvanagiri District RERA record |
| PIN | 508116 RERA record RERA filing |
| Survey numbers in RERA project record | 775P and 776P RERA record Land records |
| Subdivisions | No project subdivision numbers are disclosed in the RERA identity fields; the layout approval identifies the land as 775P and 776P. Land records |
| Registered site extent | The RERA land record states 30,353.93 sq m. RERA filing |
| Total / net land area | RERA land details record total and net area each as 30,353.93 sq m, with affected area shown as 0 sq m. The layout drawing’s area statement gives net layout area as 30,352.69 sq m. RERA filing Layout record |
| Boundaries | North, south, east and west: EXISTING ROAD RERA filing |
Development identity
| Field | Project record |
|---|---|
| Sanctioning authority | BHONGIR Municipality/Municipal Corporation Approvals record |
| Principal layout approval | Tentative layout plan 0002/LO/3153/2023, dated 15 December 2023; application 009387/LO/DTCP/3153/0004/2023. Approvals record |
| Approved built-up area | 18,818.71 sq m is recorded in the RERA fields. It is a filed built-up-area figure, not an indication of plotted sale area. RERA filing |
| Buildings / floors | Not disclosed; the approved development is a plotted layout, not a building scheme in the supplied records. |
| Plot count | 86 plots are stated in the tentative layout approval and layout drawing schedule. Layout record |
| Parking | A plot-layout parking count, parking level or parking-allocation schedule is not disclosed in the supplied records. Layout record |
Offering and status
| Field | Project record |
|---|---|
| Unit type | Plots RERA record |
| Plot areas | The layout drawing schedule contains 86 plots, with sizes software-read from the drawing ranging from 152.95 sq m to 524.75 sq m; the schedule and measurements should be checked against the drawing. Layout record |
| Booked / available | Not supplied. RERA record Layout record |
| Construction / development stage | The RERA record labels the project “New Project”; no independently verified site-progress measurement is supplied. RERA record |
| Completion date | Promoter’s Form B declares completion by 14/12/2025. |
| Occupancy / completion certificate | No occupancy or completion certificate is included in the supplied records. The tentative layout approval is not an occupancy or completion certificate. |
2. The project story
KHYATHI HOMES is registered as a plotted residential development at Raigiri Revenue Village, Bhongir Mandal, Yadadri Bhuvanagiri District, PIN 508116, covering project survey numbers 775P and 776P. The RERA-filed land details record a site extent of 30,353.93 sq m; the tentative layout plan describes 86 plots and allocates land for roads, park/open space, utilities and social infrastructure. RERA record Land records Layout record
The layout approval is explicitly tentative. It places responsibility for infrastructure and amenities on the applicant/developer and describes requirements for road formation, drainage, water supply, electrical works, plantation, park development and rainwater-harvesting pits. No construction-progress evidence or independent site inspection result is supplied here, so the project’s physical completion cannot be confirmed from this Overview.
3. Master plan, architecture & building design
The filed development is a plotted layout, not a multi-storey building project in the supplied records. The tentative layout approval identifies 86 plots on survey numbers 775P and 776P. The software-read plot schedule reports areas from 152.95 sq m to 524.75 sq m, with a median of 183.13 sq m; these measurements are drawing-derived and should be checked against the approved drawing. Layout record
The layout drawing’s land-use statement allocates the 30,352.69 sq m net layout area as follows:
| Use | Area | Share of net layout area | Evidence |
|---|---|---|---|
| Plots | 18,817.82 sq m | 62.00% | Software-read layout area statement Layout record |
| Roads | 7,707.36 sq m | 25.39% | Software-read layout area statement Layout record |
| Parks / open space | 2,749.07 sq m | 9.06% | Software-read layout area statement Layout record |
| Utilities | 313.44 sq m | 1.03% | Software-read layout area statement Layout record |
| Social infrastructure | 764.95 sq m | 2.52% | Software-read layout area statement Layout record |
| Amenities | 0.00 sq m | 0.00% | Software-read layout area statement Layout record |
The tentative approval separately describes road area, open space, social infrastructure, utility land and plotted area, and records 14 plots reserved as mortgage security in favour of Bhongir Municipality/Municipal Corporation. The approval states that the mortgage land and other layout plots are not to receive building permission or development allowance until required development works are completed, the mortgage is released and the final layout is released.
No building footprint, floor configuration, building height, apartment arrangement or building-level phase plan is evidenced for this plotted layout. The supplied records do not establish a released final layout.
4. Homes, configurations & floor plans
The RERA-filed offering is plots, not apartments. No RERA plot-type inventory with booked/available counts or unit-wise saleable areas is supplied. The approved layout drawing’s plot schedule gives 86 plots; areas below are software-measured from that drawing, not RERA-filed saleable-area figures. Layout record
| Plot-size band | Plot count | Evidence |
|---|---|---|
| 150–200 sq yd (125–167 sq m) | 19 | Software-read drawing schedule Layout record |
| 200–250 sq yd (167–209 sq m) | 41 | Software-read drawing schedule Layout record |
| 250–300 sq yd (209–251 sq m) | 7 | Software-read drawing schedule Layout record |
| 300–400 sq yd (251–334 sq m) | 8 | Software-read drawing schedule Layout record |
| 400–500 sq yd (334–418 sq m) | 4 | Software-read drawing schedule Layout record |
| 500–1000 sq yd (418–836 sq m) | 7 | Software-read drawing schedule Layout record |
The layout records the plot area, but no apartment carpet area, balcony area, common-area loading or plot-wise booking status is provided. The supplied floor-plan analysis reports two layout sheets and no flat floor plans; it therefore does not support descriptions of home interiors or room configurations. Floor plans Layout record
5. Parking & vehicle circulation
The layout drawing and supplied RERA fields do not disclose a parking-space count, visitor or accessible parking provision, parking levels, vehicle ramps, EV charging, or a plot-wise parking allocation. The tentative layout approval requires roads to remain open for access to neighbouring sites and prohibits a compound wall or fencing around the site; it does not establish any exclusive parking right for an individual plot. Layout record
6. Amenities, recreation & open spaces
The tentative layout approval describes common development works and facilities. Its amenity and infrastructure list is not evidence that each item has been completed; no independent completion verification is supplied.
| Description / size | 0 Acer 27.17 Gts; 3,288 sq yd; 9.06% in the approval; layout drawing records 2,749.07 sq m. |
|---|---|
| Evidence source | Tentative layout approval and drawing Layout record |
| Declared progress / verified status | Provided for in the layout record; completion not independently verified. |
| Description / size | 0 Acer 7.56 Gts; 915 sq yd; 2.52% in the approval; layout drawing records 764.95 sq m. |
|---|---|
| Evidence source | Tentative layout approval and drawing Layout record |
| Declared progress / verified status | Provided for in the layout record; facility type and delivery status are not specified. |
| Description / size | No size or quantity supplied. |
|---|---|
| Evidence source | RERA amenity record RERA amenities |
| Declared progress / verified status | No progress or completion evidence supplied. |
| Description / size | Approval specifies road formation with black top; road area is recorded as 1 Acer 36.18 Gts; 9,218 sq yd; 25.39% in the approval and 7,707.36 sq m in the drawing. |
|---|---|
| Evidence source | Tentative layout approval and drawing Layout record |
| Declared progress / verified status | Required in the approval; completion not independently verified. |
| Description / size | No quantity or area supplied. |
|---|---|
| Evidence source | Tentative layout approval |
| Declared progress / verified status | Required in the approval; completion not independently verified. |
No clubhouse or indoor recreation facilities are identified in the supplied RERA documents. RERA amenities
7. Utilities, building services & safety
The tentative layout approval lists infrastructure to be provided by the applicant/developer. These are approval requirements or stated development works, not confirmation that the facilities have been delivered.
| Evidence in the project record | Internal water-supply pipelines, assured water-supply source, overhead tank and water reservoir are specified. |
|---|---|
| Status evidenced | Required/described in the tentative layout approval; source capacity and completed status are not supplied. |
| Evidence in the project record | Underground drainage lines, storm-water drains and a common septic tank / STP are specified. |
|---|---|
| Status evidenced | Required/described in the tentative layout approval; capacity, treatment performance and completion status are not supplied. |
| Evidence in the project record | Rainwater-harvesting pits are specified. |
|---|---|
| Status evidenced | Required/described; quantity and completed status are not supplied. |
| Evidence in the project record | Electrical supply lines, street lights and a transformer are specified; the RERA amenity record lists an electrical meter room/sub-station/receiving station. |
|---|---|
| Status evidenced | Provided for in the records; capacity and completed status are not supplied. RERA amenities |
| Evidence in the project record | Solid-waste management is listed among the utilities in the approval. |
|---|---|
| Status evidenced | Listed as required development work; system details and completed status are not supplied. |
| Evidence in the project record | The RERA amenity record has a fire-protection/fire-safety field, but no facility details or capacity are supplied for this plotted layout. |
|---|---|
| Status evidenced | No specific system or completion evidence established. RERA amenities |
No lift, building-level accessibility or emergency-vehicle access details are applicable or evidenced in the supplied layout records. RERA amenities
8. Location, access & connectivity
The registered location is Raigiri Revenue Village, Bhongir Mandal, Yadadri Bhuvanagiri District, PIN 508116. The project record identifies survey numbers 775P and 776P; all four recorded site boundaries are described as existing roads. RERA record RERA filing RERA filing
The parcel centroid is recorded at 17.538316009983905, 78.92523486615968. The supplied location data lists the nearest sampled Outer Ring Road interchange at approximately 27.8 km. No route, travel time, public-transport service or additional landmark information is supplied. Cadastral map Location record
9. Developer & development status
The registered promoter is KHYATHI INFRA DEVELOPERS, identified in the RERA fields as a partnership; its GSTIN is 36ABAFK6621Q1ZX. The RERA address record lists Flat No-5C, 2/91/4, Sri Rams Asheervad Apartments, Sri Bagh Colony, Raigiri Revenue, Raigiri, Bhongir, Yadadri Bhuvanagiri, 508116. The registration certificate separately records a promoter address in Ranga Reddy District, PIN 500084; a registered-office confirmation is not supplied. Corporate record RERA filing RERA filing
The RERA records name KAYETHI ANISH REDDY and BANDARU MALLESH as partners, and CHALLAGULLA SRINI MOHAN as authorized signatory. Form B, dated 1Th day of May 2024 as extracted, declares completion by 14/12/2025 and makes other promoter declarations concerning the project. Parties record
The project is recorded as a new plotted development. No quarterly physical-progress figures, independent site verification, completion certificate or occupancy certificate is included in the supplied evidence. RERA record Approvals record Document index
10. Approvals, official records & documents
| Identifier / date | P02000008407; valid 22/06/2024–14/12/2025, unless extended |
|---|---|
| What the supplied record establishes | Form C certificate for KHYATHI HOMES and Khyathi Infra Developers; includes registration conditions. |
| Identifier / date | 0002/LO/3153/2023, dated 15 December 2023 |
|---|---|
| What the supplied record establishes | Tentative residential layout approval by BHONGIR Municipality/Municipal Corporation for survey numbers 775P and 776P; states 86 plots and layout-development conditions. |
| Identifier / date | 009387/LO/DTCP/3153/0004/2023 |
|---|---|
| What the supplied record establishes | Application number recorded on the tentative layout approval. |
| Identifier / date | 10024/2023, dated 12 December 2023 |
|---|---|
| What the supplied record establishes | Approval records a mortgage of 14 identified plots, totalling 0 Acer 28.29 Gts / 3,424 sq yd, in favour of Bhongir Municipality/Municipal Corporation. |
| Identifier / date | 10025/2023, dated 12 December 2023 |
|---|---|
| What the supplied record establishes | The supplied title-document extraction describes a gift in favour of the Commissioner of Bhongir Municipality for road, open-space and utility land. |
| Identifier / date | Form B, dated 1Th day of May 2024 as extracted |
|---|---|
| What the supplied record establishes | Promoter declaration including the stated completion undertaking and project-fund commitments. |
| Identifier / date | Not supplied |
|---|---|
| What the supplied record establishes | No such certificate is included in the available project documents. Document index |
The layout approval calls for development works and later release of the final layout; no final-layout release or completion certificate is included in the supplied documents.
1. Project at a glance
Project identity
Registered project name: KHYATHI HOMES
Project type: Plotted development / residential layout
Phase / registered portion: No phase designation is disclosed; registration is for the project identified as KHYATHI HOMES.
TG-RERA registration: P02000008407
Registration validity: 22 June 2024 to 14 December 2025, unless extended by the Authority. This is the registration-validity period stated on the certificate; it is separate from the completion undertaking.
Registered promoter: KHYATHI INFRA DEVELOPERS, a partnership
Status in supplied record: The project is recorded as a “New Project.” The registration certificate states the validity period above; no extension order or current registration-status confirmation is supplied.
Land and geographic identity
Locality / revenue village: Raigiri Revenue Village; locality recorded as RAIGIRI REVENUE
Mandal: Bhongir / Bhongir Mandal
District: Yadadri Bhuvanagiri; the layout document styles this as Yadadri-Bhuvanagiri District
PIN: 508116
Survey numbers in RERA project record: 775P and 776P
Subdivisions: No project subdivision numbers are disclosed in the RERA identity fields; the layout approval identifies the land as 775P and 776P.
Registered site extent: The RERA land record states 30,353.93 sq m.
Total / net land area: RERA land details record total and net area each as 30,353.93 sq m, with affected area shown as 0 sq m. The layout drawing’s area statement gives net layout area as 30,352.69 sq m.
Boundaries: North, south, east and west: EXISTING ROAD
Development identity
Sanctioning authority: BHONGIR Municipality/Municipal Corporation
Principal layout approval: Tentative layout plan 0002/LO/3153/2023, dated 15 December 2023; application 009387/LO/DTCP/3153/0004/2023.
Approved built-up area: 18,818.71 sq m is recorded in the RERA fields. It is a filed built-up-area figure, not an indication of plotted sale area.
Buildings / floors: Not disclosed; the approved development is a plotted layout, not a building scheme in the supplied records.
Plot count: 86 plots are stated in the tentative layout approval and layout drawing schedule.
Parking: A plot-layout parking count, parking level or parking-allocation schedule is not disclosed in the supplied records.
Offering and status
Unit type: Plots
Plot areas: The layout drawing schedule contains 86 plots, with sizes software-read from the drawing ranging from 152.95 sq m to 524.75 sq m; the schedule and measurements should be checked against the drawing.
Booked / available: Not supplied.
Construction / development stage: The RERA record labels the project “New Project”; no independently verified site-progress measurement is supplied.
Completion date: Promoter’s Form B declares completion by 14/12/2025.
Occupancy / completion certificate: No occupancy or completion certificate is included in the supplied records. The tentative layout approval is not an occupancy or completion certificate.
2. The project story
KHYATHI HOMES is registered as a plotted residential development at Raigiri Revenue Village, Bhongir Mandal, Yadadri Bhuvanagiri District, PIN 508116, covering project survey numbers 775P and 776P. The RERA-filed land details record a site extent of 30,353.93 sq m; the tentative layout plan describes 86 plots and allocates land for roads, park/open space, utilities and social infrastructure.
The layout approval is explicitly tentative. It places responsibility for infrastructure and amenities on the applicant/developer and describes requirements for road formation, drainage, water supply, electrical works, plantation, park development and rainwater-harvesting pits. No construction-progress evidence or independent site inspection result is supplied here, so the project’s physical completion cannot be confirmed from this Overview.
3. Master plan, architecture & building design
The filed development is a plotted layout, not a multi-storey building project in the supplied records. The tentative layout approval identifies 86 plots on survey numbers 775P and 776P. The software-read plot schedule reports areas from 152.95 sq m to 524.75 sq m, with a median of 183.13 sq m; these measurements are drawing-derived and should be checked against the approved drawing.
The layout drawing’s land-use statement allocates the 30,352.69 sq m net layout area as follows:
| Use | Area | Share of net layout area | Evidence |
|---|---|---|---|
| Plots | 18,817.82 sq m | 62.00% | Software-read layout area statement |
| Roads | 7,707.36 sq m | 25.39% | Software-read layout area statement |
| Parks / open space | 2,749.07 sq m | 9.06% | Software-read layout area statement |
| Utilities | 313.44 sq m | 1.03% | Software-read layout area statement |
| Social infrastructure | 764.95 sq m | 2.52% | Software-read layout area statement |
| Amenities | 0.00 sq m | 0.00% | Software-read layout area statement |
The tentative approval separately describes road area, open space, social infrastructure, utility land and plotted area, and records 14 plots reserved as mortgage security in favour of Bhongir Municipality/Municipal Corporation. The approval states that the mortgage land and other layout plots are not to receive building permission or development allowance until required development works are completed, the mortgage is released and the final layout is released.
No building footprint, floor configuration, building height, apartment arrangement or building-level phase plan is evidenced for this plotted layout. The supplied records do not establish a released final layout.
4. Homes, configurations & floor plans
The RERA-filed offering is plots, not apartments. No RERA plot-type inventory with booked/available counts or unit-wise saleable areas is supplied. The approved layout drawing’s plot schedule gives 86 plots; areas below are software-measured from that drawing, not RERA-filed saleable-area figures.
| Plot-size band | Plot count | Evidence |
|---|---|---|
| 150–200 sq yd (125–167 sq m) | 19 | Software-read drawing schedule |
| 200–250 sq yd (167–209 sq m) | 41 | Software-read drawing schedule |
| 250–300 sq yd (209–251 sq m) | 7 | Software-read drawing schedule |
| 300–400 sq yd (251–334 sq m) | 8 | Software-read drawing schedule |
| 400–500 sq yd (334–418 sq m) | 4 | Software-read drawing schedule |
| 500–1000 sq yd (418–836 sq m) | 7 | Software-read drawing schedule |
The layout records the plot area, but no apartment carpet area, balcony area, common-area loading or plot-wise booking status is provided. The supplied floor-plan analysis reports two layout sheets and no flat floor plans; it therefore does not support descriptions of home interiors or room configurations.
5. Parking & vehicle circulation
The layout drawing and supplied RERA fields do not disclose a parking-space count, visitor or accessible parking provision, parking levels, vehicle ramps, EV charging, or a plot-wise parking allocation. The tentative layout approval requires roads to remain open for access to neighbouring sites and prohibits a compound wall or fencing around the site; it does not establish any exclusive parking right for an individual plot.
6. Amenities, recreation & open spaces
The tentative layout approval describes common development works and facilities. Its amenity and infrastructure list is not evidence that each item has been completed; no independent completion verification is supplied.
| Description / size | 0 Acer 27.17 Gts; 3,288 sq yd; 9.06% in the approval; layout drawing records 2,749.07 sq m. |
|---|---|
| Evidence source | Tentative layout approval and drawing |
| Declared progress / verified status | Provided for in the layout record; completion not independently verified. |
| Description / size | 0 Acer 7.56 Gts; 915 sq yd; 2.52% in the approval; layout drawing records 764.95 sq m. |
|---|---|
| Evidence source | Tentative layout approval and drawing |
| Declared progress / verified status | Provided for in the layout record; facility type and delivery status are not specified. |
| Description / size | No size or quantity supplied. |
|---|---|
| Evidence source | RERA amenity record |
| Declared progress / verified status | No progress or completion evidence supplied. |
| Description / size | Approval specifies road formation with black top; road area is recorded as 1 Acer 36.18 Gts; 9,218 sq yd; 25.39% in the approval and 7,707.36 sq m in the drawing. |
|---|---|
| Evidence source | Tentative layout approval and drawing |
| Declared progress / verified status | Required in the approval; completion not independently verified. |
| Description / size | No quantity or area supplied. |
|---|---|
| Evidence source | Tentative layout approval |
| Declared progress / verified status | Required in the approval; completion not independently verified. |
No clubhouse or indoor recreation facilities are identified in the supplied RERA documents.
7. Utilities, building services & safety
The tentative layout approval lists infrastructure to be provided by the applicant/developer. These are approval requirements or stated development works, not confirmation that the facilities have been delivered.
| Evidence in the project record | Internal water-supply pipelines, assured water-supply source, overhead tank and water reservoir are specified. |
|---|---|
| Status evidenced | Required/described in the tentative layout approval; source capacity and completed status are not supplied. |
| Evidence in the project record | Underground drainage lines, storm-water drains and a common septic tank / STP are specified. |
|---|---|
| Status evidenced | Required/described in the tentative layout approval; capacity, treatment performance and completion status are not supplied. |
| Evidence in the project record | Rainwater-harvesting pits are specified. |
|---|---|
| Status evidenced | Required/described; quantity and completed status are not supplied. |
| Evidence in the project record | Electrical supply lines, street lights and a transformer are specified; the RERA amenity record lists an electrical meter room/sub-station/receiving station. |
|---|---|
| Status evidenced | Provided for in the records; capacity and completed status are not supplied. |
| Evidence in the project record | Solid-waste management is listed among the utilities in the approval. |
|---|---|
| Status evidenced | Listed as required development work; system details and completed status are not supplied. |
| Evidence in the project record | The RERA amenity record has a fire-protection/fire-safety field, but no facility details or capacity are supplied for this plotted layout. |
|---|---|
| Status evidenced | No specific system or completion evidence established. |
No lift, building-level accessibility or emergency-vehicle access details are applicable or evidenced in the supplied layout records.
8. Location, access & connectivity
The registered location is Raigiri Revenue Village, Bhongir Mandal, Yadadri Bhuvanagiri District, PIN 508116. The project record identifies survey numbers 775P and 776P; all four recorded site boundaries are described as existing roads.
The parcel centroid is recorded at 17.538316009983905, 78.92523486615968. The supplied location data lists the nearest sampled Outer Ring Road interchange at approximately 27.8 km. No route, travel time, public-transport service or additional landmark information is supplied.
9. Developer & development status
The registered promoter is KHYATHI INFRA DEVELOPERS, identified in the RERA fields as a partnership; its GSTIN is 36ABAFK6621Q1ZX. The RERA address record lists Flat No-5C, 2/91/4, Sri Rams Asheervad Apartments, Sri Bagh Colony, Raigiri Revenue, Raigiri, Bhongir, Yadadri Bhuvanagiri, 508116. The registration certificate separately records a promoter address in Ranga Reddy District, PIN 500084; a registered-office confirmation is not supplied.
The RERA records name KAYETHI ANISH REDDY and BANDARU MALLESH as partners, and CHALLAGULLA SRINI MOHAN as authorized signatory. Form B, dated 1Th day of May 2024 as extracted, declares completion by 14/12/2025 and makes other promoter declarations concerning the project.
The project is recorded as a new plotted development. No quarterly physical-progress figures, independent site verification, completion certificate or occupancy certificate is included in the supplied evidence.
10. Approvals, official records & documents
| Identifier / date | P02000008407; valid 22/06/2024–14/12/2025, unless extended |
|---|---|
| What the supplied record establishes | Form C certificate for KHYATHI HOMES and Khyathi Infra Developers; includes registration conditions. |
| Identifier / date | 0002/LO/3153/2023, dated 15 December 2023 |
|---|---|
| What the supplied record establishes | Tentative residential layout approval by BHONGIR Municipality/Municipal Corporation for survey numbers 775P and 776P; states 86 plots and layout-development conditions. |
| Identifier / date | 009387/LO/DTCP/3153/0004/2023 |
|---|---|
| What the supplied record establishes | Application number recorded on the tentative layout approval. |
| Identifier / date | 10024/2023, dated 12 December 2023 |
|---|---|
| What the supplied record establishes | Approval records a mortgage of 14 identified plots, totalling 0 Acer 28.29 Gts / 3,424 sq yd, in favour of Bhongir Municipality/Municipal Corporation. |
| Identifier / date | 10025/2023, dated 12 December 2023 |
|---|---|
| What the supplied record establishes | The supplied title-document extraction describes a gift in favour of the Commissioner of Bhongir Municipality for road, open-space and utility land. |
| Identifier / date | Form B, dated 1Th day of May 2024 as extracted |
|---|---|
| What the supplied record establishes | Promoter declaration including the stated completion undertaking and project-fund commitments. |
| Identifier / date | Not supplied |
|---|---|
| What the supplied record establishes | No such certificate is included in the available project documents. |
The layout approval calls for development works and later release of the final layout; no final-layout release or completion certificate is included in the supplied documents.
Frequently asked questions
Is KHYATHI HOMES registered with Telangana RERA?
Yes. KHYATHI HOMES is registered with the Telangana Real Estate Regulatory Authority as P02000008407; the registration status is New Project.
Who is the developer of KHYATHI HOMES?
The promoter named in the RERA registration is KHYATHI INFRA DEVELOPERS.
Where is KHYATHI HOMES located?
KHYATHI HOMES is in RAIGIRI REVENUE, Raigiri, Bhongir, Yadadri Bhuvanagiri, Telangana (508116).
When will KHYATHI HOMES be completed?
The promoter's proposed date of completion filed with RERA is 14/12/2025. This is the promoter's declaration, not a guarantee.