Ananda Nilayam

SHILPI MANGALA DEVELOPERS PRIVATE LIMITED · Hyderabad · RERA P02500000779

ANANDA NILAYAM is a residential apartment project at Pakalakunta, Hamlet of Alwal Village, Hyderabad; the mandal is not disclosed. The registered promoter is SHILPI MANGALA DEVELOPERS PRIVATE LIMITED. The project covers 998.18 sq. m and comprises one residential building, Building - A, with a Cellar + Stilt + 5 configuration and 20 apartments: 10 2BHK and 10 3BHK. Its TG-RERA registration number is P02500000779, and its proposed completion date is 23/03/2020.

More from Shilpi Mangala Developers Pvt Ltd · 2 projects →

01What we found

Period endedTG-RERA registration ran to 23 Mar 2020 - check its extension on TG-RERA
13documents on file - each fact links to its page
11court cases on this project's land (survey 552, 554, 556, 561, 570, Pakalakunta)
12items to check - 5 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

12 items to check before you pay, 5 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

Photo from housing.com

1. Project at a glance

Project identity

ItemProject record
Registered project nameANANDA NILAYAM RERA record
Project typeResidential apartment project RERA record RERA filing
Phase / registered portionPhase designation not disclosed. The RERA record describes one building and the land listed below. RERA filing
TG-RERA registrationP02500000779; registered from 25/05/2019 to 23/03/2020. The certificate says it may be extended by the Authority; the supplied certificate records no extension. Approvals record
RERA statusThe project record identifies it as “New Project.” Registration validity ended on 23/03/2020; this is distinct from the completion undertaking and from occupancy certification. RERA filing
Registered promoterSHILPI MANGALA DEVELOPERS PRIVATE LIMITED, company. RERA record Corporate record

Land and geographic identity

ItemProject record
Locality / revenue villagePakalakunta, Hamlet of Alwal Village RERA record RERA filing
MandalNot disclosed Land records
District / PINHyderabad / 500010 RERA record
Project survey numbers552, 553, 554, 556, 557, 558, 561 and 570; subdivisions are not stated in the project identity record. Land records
Plot identifiers111 and 112 RERA filing
Site extent998.18 sq. m total and net area; road-affected area is recorded as 0 sq. m in the building-permit extraction. RERA filing
BoundariesEast: Owners Land; West: 40 feet road; North: 30 feet road; South: plot no 108 109 and 110 RERA filing

Development identity

ItemProject record
Sanctioning authorityGreater Hyderabad Municipal Corporation (GHMC) Approvals record
Principal building approvalBuilding Permit Order 1/C27/15290/2018, dated 23 September, 2018; file no. 1/HO/04284/2018. Approvals record
Approved buildingOne residential building, Building - A
Sanctioned floor configurationCellar + Stilt + 5
Approved built-up area2,326.65 sq. m (residential upper floors); cellar and stilt areas are separately recorded as 570.35 sq. m and 499.70 sq. m. RERA filing
Other plan figuresTot-lot: 52.44 sq. m; sanctioned height: 14.39 m.
Unit count20 RERA-filed units: 10 2BHK and 10 3BHK. The supplied record also lists one total building unit; it does not explain that field’s meaning in relation to the 20 apartments. RERA unit table RERA filing
Parking provisionThe permit requires the cellar and stilt areas approved for parking to be used exclusively for vehicle parking. A parking-space count is not available in the supplied evidence.

Offering and status

ItemProject record
Configurations2BHK and 3BHK apartments RERA unit table
RERA-filed saleable area2BHK: 127.18 sq. m; 3BHK: 151.71 sq. m RERA unit table
Booking availabilityPortal-derived counts show 0 booked and 10 available in each configuration; the portal record has no as-of date, so these counts are indicative. RERA unit table
Completion dateForm B declares a 24-month completion period; it does not give a calendar completion date in the extracted declaration. The project record lists 23/03/2020 as the proposed completion date. RERA record
Construction stageNo independently verified current construction-stage evidence is supplied. The RERA amenities record gives 0% progress for each listed item. RERA amenities
Occupancy / completion certificateNo occupancy or completion certificate is included in the supplied documents; certificate status is therefore not established here. GHMC’s permit says an occupancy certificate is compulsory before occupation. Document index

2. The project story

ANANDA NILAYAM is recorded with TG-RERA as a residential apartment project at plots 111 and 112, Pakalakunta, Hamlet of Alwal Village, Hyderabad. Its RERA and GHMC records describe one building, Building - A, on a site of 998.18 sq. m, with a sanctioned cellar, stilt and five upper floors. RERA record RERA filing

The filed apartment offering comprises ten 2BHK and ten 3BHK units. The RERA portal’s available-unit figures show all 20 as available and none booked, but the figures have no stated retrieval date. The registration record gives a proposed completion date of 23/03/2020, while the Form B declaration states a 24-month completion undertaking. Neither is evidence of current construction progress or completed possession. RERA unit table RERA record

The documents supplied do not establish that the building is complete or occupied. The RERA amenities record reports 0% progress across its listed items, and no occupancy or completion certificate is included in the reviewed material. RERA amenities Document index

3. Master plan, architecture & building design

The GHMC Building Permit Order describes a single residential building, Building - A, on a site of 998.18 sq. m, with Cellar + Stilt + 5 configuration and an approved height of 14.39 m. The order records 2,326.65 sq. m for residential upper floors, separately from 570.35 sq. m for the cellar and 499.70 sq. m for the stilt. These are distinct permit-recorded areas; the supplied evidence does not provide a verified FSI-counted area, carpet area for the whole building, or a building footprint. RERA filing

The permit identifies a 52.44 sq. m tot-lot and requires a strip of greenery on the site periphery. It also requires a transformer space and a garbage house within the premises. The submitted drawing file is identified as a typical plan for floors 2–5 and a first-floor plan, but the supplied evidence does not establish the number of apartments per floor, lift or stair arrangements, or the building’s entries, exits and circulation.

4. Homes, configurations & floor plans

The TG-RERA filing records 20 apartments: ten 2BHK and ten 3BHK. The saleable-area figures below are RERA-filed. The carpet-area figures are software measurements from the approved-plan drawing geometry, not RERA disclosures; the measurements are flagged for review. RERA unit table RERA unit details Floor plans

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
2BHK10010127.18 sq. m82.7–84.2 sq. m; median 82.8 sq. m35%
3BHK10010151.71 sq. m83.0–98.9 sq. m; median 93.4 sq. m38%

For one measured 2BHK drawing, the recorded rooms include a kitchen, two bedrooms, dining and living areas, two toilets, a utility and a balcony. For one measured 3BHK drawing, they include a guest room, two bedrooms, living/dining, three toilets, a puja area, utility and two balconies. Utility and balcony areas are excluded from the supplied drawing-based carpet measurement. Dimensions and room measurements are drawing-derived and should be checked against the plan itself. RERA unit details

Carpet area is not the same as saleable area: the supplied floor-plan note states that saleable area also counts the home’s share of common areas. No separately filed balcony or utility areas are provided here. The portal booking and availability counts have no stated as-of date. Floor plans RERA unit table

5. Parking & vehicle circulation

The GHMC permit identifies the cellar and stilt as parking areas and requires them to remain exclusively for vehicle parking, without partition walls or rolling shutters, and not to be converted or misused. It does not provide a parking-space count in the supplied extraction.

The evidence does not establish resident, visitor or accessible-space counts, parking allocation by apartment, parking ramps or internal driveways, pedestrian separation, or EV charging. A parking area shown or required in a sanctioned plan does not, on this evidence, establish exclusive ownership or allocation to a particular apartment.

6. Amenities, recreation & open spaces

The RERA amenities record lists 14 project elements. The GHMC permit separately specifies a tot-lot, periphery greenery, rainwater harvesting, transformer space and a garbage house. The RERA-recorded progress is 0% for every item in its list; no independently verified completion status is supplied. RERA amenities

Green Strip/TOT LOT/Park
Description / sizePermit specifies tot-lot of 52.44 sq. m and requires it to be fenced and maintained as greenery; periphery greenery is also required.
Evidence sourceRERA amenities; GHMC permit
Declared progress / verified statusRERA progress: 0%; completion not independently verified. RERA amenities
Internal roads and footpaths
Description / sizeListed in the RERA project-amenities record; no dimensions supplied.
Evidence sourceRERA amenities
Declared progress / verified statusProgress: 0%. RERA amenities
Community buildings
Description / sizeListed in the RERA project-amenities record; no details or size supplied.
Evidence sourceRERA amenities
Declared progress / verified statusProgress: 0%. RERA amenities
Street lighting
Description / sizeListed in the RERA project-amenities record.
Evidence sourceRERA amenities
Declared progress / verified statusProgress: 0%. RERA amenities
Sports, clubhouse, pool, gym and indoor play facilities
Description / sizeNot established in the supplied RERA amenities or GHMC permit evidence.
Evidence sourceNo project-specific supporting record supplied
Declared progress / verified statusNot established.

7. Utilities, building services & safety

Water
Evidence in the project recordWater Supply is marked “YES” in the RERA amenities record.
Status / limitationSource, storage, treatment and capacity are not supplied; recorded progress is 0%. RERA amenities
Sewerage and drainage
Evidence in the project recordSewerage and Storm Water Drains are marked “YES”; the RERA record also lists treatment and disposal of sewage and sullage water. The permit requires an ETP.
Status / limitationNo treatment capacity, operating status or completion evidence is supplied; recorded progress is 0%. RERA amenities
Water conservation
Evidence in the project recordRainwater harvesting is marked “YES” in the RERA record; GHMC requires a rainwater-harvesting structure (percolation pit).
Status / limitationCompletion is not independently verified; recorded progress is 0%. RERA amenities
Electrical
Evidence in the project recordThe RERA record lists an electrical meter room, sub-station or receiving station. GHMC requires transformer space.
Status / limitationSupply, backup, transformer capacity and completion status are not supplied; recorded progress is 0% for the RERA-listed item. RERA amenities
Vertical transportation
Evidence in the project recordLift or service-lift details and capacities are not disclosed in the supplied evidence.
Status / limitationNot established.
Fire and life safety
Evidence in the project recordFire protection and fire-safety requirements are listed in the RERA amenities record. The GHMC permit places responsibility for structural and fire-safety requirements on the owner, builder/developer, architect and structural engineer.
Status / limitationNo system specifications or completion evidence are supplied; recorded progress is 0%. The record does not establish compliance by itself. RERA amenities
Waste management
Evidence in the project recordRERA lists solid-waste management and disposal; the permit requires a garbage house within the premises.
Status / limitationNo system details or completed status supplied; RERA progress is 0%. RERA amenities
Accessibility and security
Evidence in the project recordAccessible circulation, CCTV and access-control details are not supplied.
Status / limitationNot established.

8. Location, access & connectivity

The registered project location is Pakalakunta, Hamlet of Alwal Village, Hyderabad, Telangana, PIN 500010. The project records identify roads on the west and north boundaries as a 40 feet road and a 30 feet road respectively. RERA record RERA filing The supplied location record provides a cadastral-parcel centroid of 17.41528, 78.35459 and lists Financial District (Nanakramguda) at 1.2 km. Location record

No project-specific public-transport routes, bus-stop or railway-station distances, or journey times are provided in the RERA location evidence.

9. Developer & development status

The registered promoter is SHILPI MANGALA DEVELOPERS PRIVATE LIMITED, a company. The project record identifies M Keshava Rao as director and authorised signatory, and T V Raghunandan Rao as director. Corporate record Parties record The registration certificate gives a promoter-office entry with district Hyderabad and PIN 500055, while the project record lists a Pakalakunta, Hyderabad address with PIN 500010; the full registered-office particulars are not consistently available in the supplied extracts. Parties record

The Form B declaration, dated 31 January 2019, states a 24-month project-completion undertaking and declares that the land is free from encumbrances. These are promoter declarations, not independent confirmation of title or completion. The supplied RERA amenities progress is 0%, and current construction progress and OC status are not established by the documents provided. RERA amenities Document index

10. Approvals, official records & documents

RecordDetails
TG-RERA registration certificateForm C records ANANDA NILAYAM, registration P02500000779, effective 25/05/2019–23/03/2020.
GHMC building permitBuilding Permit Order 1/C27/15290/2018, file no. 1/HO/04284/2018, dated 23 September, 2018; authorises Building - A (Residence) on the listed project survey numbers.
RERA Form B declarationPromoter declaration dated 31 January 2019, including the 24-month completion undertaking and project-account declarations.
Floor-plan materialRERA document 36578 is referenced for the measured 2BHK and 3BHK plan geometry; one of two drawing records is measured and one remains pending scan review. Floor plans
Layout approvalNo layout-plan approval number or separate approved-layout document is established in the supplied evidence. RERA filing Document index
Occupancy / completion certificateNo certificate is included in the supplied documents. The GHMC permit states that an occupancy certificate is compulsory before occupation. Document index

Frequently asked questions

Is ANANDA NILAYAM registered with Telangana RERA?

Yes. ANANDA NILAYAM is registered with the Telangana Real Estate Regulatory Authority as P02500000779; the registration status is New Project.

Who is the developer of ANANDA NILAYAM?

The promoter named in the RERA registration is SHILPI MANGALA DEVELOPERS PRIVATE LIMITED.

Where is ANANDA NILAYAM located?

ANANDA NILAYAM is in Pakalakunta, Hamlet of Alwal Village, Hyderabad, Telangana (500010).

When will ANANDA NILAYAM be completed?

The promoter's proposed date of completion filed with RERA is 23/03/2020. This is the promoter's declaration, not a guarantee.