Durga
SRI DURGA DEVELOPERS · Hyderabad · RERA P02500000381
DURGA is a residential apartment project in Begumpet, Hyderabad, Hyderabad district; the mandal is not disclosed. The registered promoter is SRI DURGA DEVELOPERS. The project has a total site area of 1,084.78 sq m and one proposed residential building with a cellar, stilt and 5 residential upper floors, comprising 10 4BHK units. It is registered under TG-RERA number P02500000381, with a proposed completion date of 10-04-2024.
More from Sri Durga Developers · 4 projects →
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
9 items to check before you pay, 2 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Item | TG-RERA record |
|---|---|
| Registered project name | DURGA |
| Project type | Residential apartment project |
| Phase / registered portion | Not separately identified in the supplied record |
| TG-RERA registration | P02500000381 |
| Registration validity | 2 March 2019 to 10 April 2024, unless extended by the Authority; the supplied certificate records no extension |
| Registered promoter | SRI DURGA DEVELOPERS |
| RERA status | The registration certificate’s stated validity ended on 10 April 2024. Current registration status is not established by the supplied certificate. |
| Registered project status | “New Project” in the RERA project record |
RERA record RERA filing Approvals record
Land and geographic identity
| Item | RERA-filed / document record |
|---|---|
| Locality | Begumpet; the building permit describes Cheekoti Garden, Begumpet |
| Revenue village | Begumpet |
| Mandal | Not disclosed |
| District / PIN | Hyderabad / 500016 |
| Survey numbers | 30, 39 & 40; no subdivision numbers are specified in the supplied project identity record |
| Plot / premises references | 1-10-68/B & 1-10-68/C, Plot Nos. 14 & 15 |
| Site extent | Total site area 1,084.78 sq m; road-affected area 59.52 sq m; net area 1,025.26 sq m |
| Boundaries | North: Plot Nos. 13 and 26; South: road; East: Plot No. 16; West: road |
RERA filing RERA filing Land records
Development identity
| Item | Sanctioned / filed record |
|---|---|
| Sanctioning authority | Greater Hyderabad Municipal Corporation (GHMC) |
| Building permit | Permit No. 1/18B/06189/2018, dated 10 April 2018; file No. 1/18B/15015/2017 |
| Approved residential area | 2,642.85 sq m |
| Building count | One proposed residential building, identified in the permit as “Building - A (PROPOSED)” |
| Sanctioned configuration | Cellar + stilt + 5 residential upper floors; stated height 14.84 m |
| Parking levels | Cellar (614.28 sq m) and stilt (691.20 sq m), both identified in the permit for parking |
| Tot-lot | 85.97 sq m |
| Approved versus RERA-declared units | The supplied extract gives no numerical sanctioned unit count. The RERA filing records 10 units. |
Approvals record RERA filing RERA unit table
Offering and status
| Item | RERA-filed record |
|---|---|
| Configuration | 4BHK |
| Units / booking | 10 units; 0 booked and 10 available in the portal data supplied. No as-of date is stated, so counts are indicative. |
| RERA saleable area | 297.29 sq m per unit |
| Construction stage | Not established by the supplied evidence; no independently verified site-progress record is provided. |
| Completion date | Promoter’s Form-B declaration undertakes completion by 10-04-2024. No revised completion date is supplied. |
| Occupancy certificate | No occupancy certificate is included in the supplied records; its issuance or current status is not established. |
RERA unit table RERA unit table Document index
2. The project story
DURGA is registered with TG-RERA as a residential apartment project for the Begumpet site identified by Survey Nos. 30, 39 & 40, at the premises described as 1-10-68/B & 1-10-68/C, Plot Nos. 14 & 15. The GHMC building-permit extract describes one proposed building, Building A, with a cellar, stilt and five upper floors, and a residential area of 2,642.85 sq m. RERA record RERA filing
The RERA unit record describes ten 4BHK units, with 0 booked and 10 available in the supplied portal data; the portal data has no as-of date. The promoter’s Form-B affidavit, dated 28 November 2018, declared a completion undertaking of 10 April 2024. The evidence supplied here does not establish subsequent construction progress, completion, or issuance of an occupancy certificate. The GHMC permit states that an occupancy certificate is compulsory before occupation. RERA unit table RERA unit table
3. Master plan, architecture & building design
The GHMC building-permit extract records the building height as 14.84 m, residential area as 2,642.85 sq m, site area as 1,084.78 sq m, net area as 1,025.26 sq m, and road-affected area as 59.52 sq m. These are permit-extract figures; the supplied materials do not provide a separately labelled FSI-counted area or gross built-up area. RERA filing
The permit lists cellar parking of 614.28 sq m, stilt parking of 691.20 sq m, and an 85.97 sq m tot-lot. It also refers to five rainwater-harvesting structures and 50 trees. The supplied material does not establish the building footprint, number of flats per floor, lifts or stair arrangements, entrances, internal circulation, or detailed common-area distribution.
The supplied RERA unit schedule records ten 4BHK units. No approved drawing extraction establishing the apartment-by-apartment arrangement is available in the evidence presented here. RERA unit table RERA unit table
4. Homes, configurations & floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 4BHK | 10 | 0 | 10 | 297.29 sq m | Not available in the supplied measurements | Not supplied |
RERA unit table RERA unit table
The supplied drawing-measurement data covers 2BHK and 3BHK layouts, not the RERA-filed 4BHK configuration; it therefore does not provide a measured carpet area for the units reported in this table. In general, saleable area and carpet area are distinct measures; no project-specific loading figure is supplied. RERA unit details Floor plans
5. Parking & vehicle circulation
The GHMC permit identifies a cellar parking level of 614.28 sq m and a stilt parking level of 691.20 sq m, and states that both are to be used exclusively for vehicle parking. It does not provide the number of parking spaces, their allocation by unit, visitor or accessible parking counts, or information about ramps, vehicle entries, or internal driveways. The supplied RERA unit record marks the units as mortgaged; it does not establish any buyer-specific parking allocation. RERA unit table RERA unit table
6. Amenities, recreation & open spaces
The permit extract identifies a tot-lot and several site features. The RERA amenity register records specified items as “YES,” but lists 0% progress for each item; that is a filed status, not independent confirmation of delivery.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Tot-lot / green strip | 85.97 sq m; permit requires fencing and maintenance as greenery | GHMC building permit | Permitted / required; completion not independently verified |
| Aggregate recreational open space | Size not stated | RERA amenity register | “YES”; 0% recorded |
| Internal roads and footpaths | Size not stated | RERA amenity register | “YES”; 0% recorded |
| Community buildings | No details supplied | RERA amenity register | No availability value stated; 0% recorded |
RERA amenities
The supplied records do not establish clubhouse or indoor facilities, sports facilities beyond the tot-lot, or additional community amenities. RERA amenities
7. Utilities, building services & safety
The RERA amenity register marks water supply, sewerage, storm-water drains, sewage and sullage treatment/disposal, rainwater harvesting, fire protection and safety, and an electrical meter room/substation/receiving station as “YES”; each entry shows 0% progress. The register does not provide system capacities or establish completion. RERA amenities
GHMC’s permit requires a rainwater-harvesting percolation pit, space for a transformer, and a garbage house within the premises. It also refers to an ETP, fire-safety requirements, lifts, electrical installations, and supervision by qualified technical personnel. These are permit conditions or listed requirements, not evidence that the works are complete or that statutory compliance has been independently verified. No water source or storage capacity, treatment capacity, lift count or capacity, backup power details, CCTV provision, accessibility arrangement, or waste-segregation system is established in the supplied RERA project evidence. RERA amenities
8. Location, access & connectivity
The registered project location is Begumpet, Hyderabad, PIN 500016. The permit’s site boundaries identify roads to the south and west. The supplied evidence does not establish a project-specific approach-road description beyond those boundaries, or public-transport connections and measured distances suitable for this project profile. RERA record RERA filing RERA filing
9. Developer & development status
The registered legal promoter is SRI DURGA DEVELOPERS, identified in the RERA record as a partnership. Its supplied address is Apurupa, Motilal Nehru Nagar, Chikoti Gardens, Begumpet, Hyderabad, 500016. Nikhil Paleja is listed as an authorized signatory; the supplied record does not establish a separate official project contact or promoter website. Corporate record Parties record RERA filing
The promoter’s Form-B affidavit dated 28 November 2018 declares that the project would be completed by 10 April 2024 and includes undertakings on project funds, audits and pending approvals. This is a promoter declaration, not independent confirmation of construction progress or completion. No phase-wise status or revised completion timetable is supplied. RERA record
10. Approvals, official records & documents
| Identifier / date | P02500000381; issued 2 March 2019; stated validity through 10 April 2024 unless extended |
|---|---|
| Scope and evidence | Project DURGA; registered promoter SRI DURGA DEVELOPERS; Survey Nos. 30, 39 & 40. The supplied certificate records no extension. |
| Identifier / date | Permit 1/18B/06189/2018; 10 April 2018; file 1/18B/15015/2017 |
|---|---|
| Scope and evidence | Building permission extract for the Begumpet site; identifies Building A (proposed) and its sanctioned configuration and conditions. |
| Identifier / date | 28 November 2018 |
|---|---|
| Scope and evidence | Promoter declaration including the 10 April 2024 completion undertaking. |
| Identifier / date | Not supplied |
|---|---|
| Scope and evidence | The GHMC permit states that an occupancy certificate is compulsory before occupation; issuance is not established by the documents provided. |
| Identifier / date | Not established in the supplied record |
|---|---|
| Scope and evidence | No layout approval number is disclosed in the project identity fields. RERA filing |
The GHMC permit extract states that the building plan is valid for three years from the issue date if work commences within one year, and requires a completion notice and occupancy certificate before occupation. The supplied evidence does not establish whether those requirements were subsequently met.
1. Project at a glance
Project identity
Registered project name: DURGA
Project type: Residential apartment project
Phase / registered portion: Not separately identified in the supplied record
TG-RERA registration: P02500000381
Registration validity: 2 March 2019 to 10 April 2024, unless extended by the Authority; the supplied certificate records no extension
Registered promoter: SRI DURGA DEVELOPERS
RERA status: The registration certificate’s stated validity ended on 10 April 2024. Current registration status is not established by the supplied certificate.
Registered project status: “New Project” in the RERA project record
Land and geographic identity
Locality: Begumpet; the building permit describes Cheekoti Garden, Begumpet
Revenue village: Begumpet
Mandal: Not disclosed
District / PIN: Hyderabad / 500016
Survey numbers: 30, 39 & 40; no subdivision numbers are specified in the supplied project identity record
Plot / premises references: 1-10-68/B & 1-10-68/C, Plot Nos. 14 & 15
Site extent: Total site area 1,084.78 sq m; road-affected area 59.52 sq m; net area 1,025.26 sq m
Boundaries: North: Plot Nos. 13 and 26; South: road; East: Plot No. 16; West: road
Development identity
Sanctioning authority: Greater Hyderabad Municipal Corporation (GHMC)
Building permit: Permit No. 1/18B/06189/2018, dated 10 April 2018; file No. 1/18B/15015/2017
Approved residential area: 2,642.85 sq m
Building count: One proposed residential building, identified in the permit as “Building - A (PROPOSED)”
Sanctioned configuration: Cellar + stilt + 5 residential upper floors; stated height 14.84 m
Parking levels: Cellar (614.28 sq m) and stilt (691.20 sq m), both identified in the permit for parking
Tot-lot: 85.97 sq m
Approved versus RERA-declared units: The supplied extract gives no numerical sanctioned unit count. The RERA filing records 10 units.
Offering and status
Configuration: 4BHK
Units / booking: 10 units; 0 booked and 10 available in the portal data supplied. No as-of date is stated, so counts are indicative.
RERA saleable area: 297.29 sq m per unit
Construction stage: Not established by the supplied evidence; no independently verified site-progress record is provided.
Completion date: Promoter’s Form-B declaration undertakes completion by 10-04-2024. No revised completion date is supplied.
Occupancy certificate: No occupancy certificate is included in the supplied records; its issuance or current status is not established.
2. The project story
DURGA is registered with TG-RERA as a residential apartment project for the Begumpet site identified by Survey Nos. 30, 39 & 40, at the premises described as 1-10-68/B & 1-10-68/C, Plot Nos. 14 & 15. The GHMC building-permit extract describes one proposed building, Building A, with a cellar, stilt and five upper floors, and a residential area of 2,642.85 sq m.
The RERA unit record describes ten 4BHK units, with 0 booked and 10 available in the supplied portal data; the portal data has no as-of date. The promoter’s Form-B affidavit, dated 28 November 2018, declared a completion undertaking of 10 April 2024. The evidence supplied here does not establish subsequent construction progress, completion, or issuance of an occupancy certificate. The GHMC permit states that an occupancy certificate is compulsory before occupation.
3. Master plan, architecture & building design
The GHMC building-permit extract records the building height as 14.84 m, residential area as 2,642.85 sq m, site area as 1,084.78 sq m, net area as 1,025.26 sq m, and road-affected area as 59.52 sq m. These are permit-extract figures; the supplied materials do not provide a separately labelled FSI-counted area or gross built-up area.
The permit lists cellar parking of 614.28 sq m, stilt parking of 691.20 sq m, and an 85.97 sq m tot-lot. It also refers to five rainwater-harvesting structures and 50 trees. The supplied material does not establish the building footprint, number of flats per floor, lifts or stair arrangements, entrances, internal circulation, or detailed common-area distribution.
The supplied RERA unit schedule records ten 4BHK units. No approved drawing extraction establishing the apartment-by-apartment arrangement is available in the evidence presented here.
4. Homes, configurations & floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 4BHK | 10 | 0 | 10 | 297.29 sq m | Not available in the supplied measurements | Not supplied |
The supplied drawing-measurement data covers 2BHK and 3BHK layouts, not the RERA-filed 4BHK configuration; it therefore does not provide a measured carpet area for the units reported in this table. In general, saleable area and carpet area are distinct measures; no project-specific loading figure is supplied.
5. Parking & vehicle circulation
The GHMC permit identifies a cellar parking level of 614.28 sq m and a stilt parking level of 691.20 sq m, and states that both are to be used exclusively for vehicle parking. It does not provide the number of parking spaces, their allocation by unit, visitor or accessible parking counts, or information about ramps, vehicle entries, or internal driveways. The supplied RERA unit record marks the units as mortgaged; it does not establish any buyer-specific parking allocation.
6. Amenities, recreation & open spaces
The permit extract identifies a tot-lot and several site features. The RERA amenity register records specified items as “YES,” but lists 0% progress for each item; that is a filed status, not independent confirmation of delivery.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Tot-lot / green strip | 85.97 sq m; permit requires fencing and maintenance as greenery | GHMC building permit | Permitted / required; completion not independently verified |
| Aggregate recreational open space | Size not stated | RERA amenity register | “YES”; 0% recorded |
| Internal roads and footpaths | Size not stated | RERA amenity register | “YES”; 0% recorded |
| Community buildings | No details supplied | RERA amenity register | No availability value stated; 0% recorded |
The supplied records do not establish clubhouse or indoor facilities, sports facilities beyond the tot-lot, or additional community amenities.
7. Utilities, building services & safety
The RERA amenity register marks water supply, sewerage, storm-water drains, sewage and sullage treatment/disposal, rainwater harvesting, fire protection and safety, and an electrical meter room/substation/receiving station as “YES”; each entry shows 0% progress. The register does not provide system capacities or establish completion.
GHMC’s permit requires a rainwater-harvesting percolation pit, space for a transformer, and a garbage house within the premises. It also refers to an ETP, fire-safety requirements, lifts, electrical installations, and supervision by qualified technical personnel. These are permit conditions or listed requirements, not evidence that the works are complete or that statutory compliance has been independently verified. No water source or storage capacity, treatment capacity, lift count or capacity, backup power details, CCTV provision, accessibility arrangement, or waste-segregation system is established in the supplied RERA project evidence.
8. Location, access & connectivity
The registered project location is Begumpet, Hyderabad, PIN 500016. The permit’s site boundaries identify roads to the south and west. The supplied evidence does not establish a project-specific approach-road description beyond those boundaries, or public-transport connections and measured distances suitable for this project profile.
9. Developer & development status
The registered legal promoter is SRI DURGA DEVELOPERS, identified in the RERA record as a partnership. Its supplied address is Apurupa, Motilal Nehru Nagar, Chikoti Gardens, Begumpet, Hyderabad, 500016. Nikhil Paleja is listed as an authorized signatory; the supplied record does not establish a separate official project contact or promoter website.
The promoter’s Form-B affidavit dated 28 November 2018 declares that the project would be completed by 10 April 2024 and includes undertakings on project funds, audits and pending approvals. This is a promoter declaration, not independent confirmation of construction progress or completion. No phase-wise status or revised completion timetable is supplied.
10. Approvals, official records & documents
| Identifier / date | P02500000381; issued 2 March 2019; stated validity through 10 April 2024 unless extended |
|---|---|
| Scope and evidence | Project DURGA; registered promoter SRI DURGA DEVELOPERS; Survey Nos. 30, 39 & 40. The supplied certificate records no extension. |
| Identifier / date | Permit 1/18B/06189/2018; 10 April 2018; file 1/18B/15015/2017 |
|---|---|
| Scope and evidence | Building permission extract for the Begumpet site; identifies Building A (proposed) and its sanctioned configuration and conditions. |
| Identifier / date | 28 November 2018 |
|---|---|
| Scope and evidence | Promoter declaration including the 10 April 2024 completion undertaking. |
| Identifier / date | Not supplied |
|---|---|
| Scope and evidence | The GHMC permit states that an occupancy certificate is compulsory before occupation; issuance is not established by the documents provided. |
| Identifier / date | Not established in the supplied record |
|---|---|
| Scope and evidence | No layout approval number is disclosed in the project identity fields. |
The GHMC permit extract states that the building plan is valid for three years from the issue date if work commences within one year, and requires a completion notice and occupancy certificate before occupation. The supplied evidence does not establish whether those requirements were subsequently met.
Other registrations of Durga
Frequently asked questions
Is DURGA registered with Telangana RERA?
Yes. DURGA is registered with the Telangana Real Estate Regulatory Authority as P02500000381; the registration status is New Project.
Who is the developer of DURGA?
The promoter named in the RERA registration is SRI DURGA DEVELOPERS.
Where is DURGA located?
DURGA is in BEGUMPET, Hyderabad, Telangana (500016).
When will DURGA be completed?
The promoter's proposed date of completion filed with RERA is 10/04/2024. This is the promoter's declaration, not a guarantee.
More projects in Hyderabad