Bhagyadeep Residency

JAIN PROJECTS · Hyderabad · RERA P02500004365

BHAGYADEEP RESIDENCY is a residential apartment project at BARKATPURA - 20, Amberpet, Hyderabad district. It is being developed by Jain Projects, a partnership. The RERA filing records a land area of 2087.53 sq m, one building with 1 Cellar + 2 Stilt + 9 upper floors, and 36 homes: 18 3BHK units and 18 4BHK units. Its TG-RERA registration number is P02500004365, and the project information field lists proposed completion as 11/06/2027.

01What we found

RegisteredTG-RERA - valid till 11 Feb 2027
14documents on file - each fact links to its page
0court cases on this project's land in the court records searched
7items to check - 3 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

7 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

Photo from nobroker.in

1. Project at a glance

Project identity

FieldRecord
Registered project nameBHAGYADEEP RESIDENCY
Project type / registered portionResidential apartment project; phase or separately registered portion is not disclosed. The RERA filing lists one building. RERA record RERA filing RERA filing
TG-RERA registrationP02500004365; granted under section 5 on 04/04/2022. The certificate states validity through 11/02/2027, unless extended by the Authority.
RERA statusListed as New Project in the project record. The registration certificate records that registration was granted; an extension is not recorded in the supplied material. RERA filing
Registered promoterJain Projects (also rendered “M/s. JAIN PROJECTS”); a partnership. RERA filing

Land and geographic identity

FieldRecord
Locality / site addressBARKATPURA - 20; plot/house numbers 3-4-2/1, 3-4-2/2, 3-4-2/3, 3-4-2/4 AND 3-4-2/5 OLD NO. 3-4-2. The filing’s address fields also state B, KACHIGUDA, Kachiguda Railway Station Road. RERA filing RERA filing
Revenue villageRERA identity lists Barkatpura; the GHMC building-permit extracts state Amberpet. A revenue-village identity is not consistently established in the supplied records. RERA record RERA filing
Mandal / district / PINMandal: not disclosed in the RERA identity; the permit extracts state Amberpet Mandal / Amberpet. District: Hyderabad. PIN: 500027. Land records
Survey numbers / subdivisionsNot disclosed in the supplied project identity or permit extracts. Land records
Registered site extentThe RERA filing records total area 2087.53 sq m, affected area 117.46 sq m, and net area 1970.07 sq m. RERA filing
BoundariesEast, west, north and south are each recorded as “OTHERS LAND -”; adjoining parcel identities are not provided. RERA filing

Development identity

FieldRecord
Sanctioning authorityGreater Hyderabad Municipal Corporation (GHMC).
Principal approvalRevised Building Permit Order 5862/GHMC/SEC/2023-BP, dated 13 July, 2023.
Approved built-up areaRERA filing: 8132.92 sq mts. RERA filing
Building countThe RERA filing records 1 total building unit; the plan extraction describes one residential building. RERA filing
Revised sanctioned configuration1 Cellar + 2 Stilt + 9 upper floors.
ParkingThe revised permit extract records Total Parking Area 2750.55; no parking-space count is supplied.
Unit count36 units in the RERA unit record; the RERA land-details field also records 1 proposed building unit, not a dwelling count. RERA unit table RERA filing

Offering and status

FieldRecord
RERA-filed configurations3BHK: 18 units, saleable area 206.47 sq m each; 4BHK: 18 units, saleable area 261.57 sq m each. RERA unit table
Booked / available12 booked / 24 available in total: 3BHK 7 / 11 and 4BHK 5 / 13. Counts are from the TG-RERA portal record, which supplies no as-of date; treat them as indicative. RERA unit table
Construction stageThe portal amenity-progress fields show some reported progress for water supply (50%) and sewerage (40%); they do not establish overall construction completion. No independently verified site-progress measurement is supplied. RERA amenities
Completion datesPromoter Form B undertakes completion by 11/02/2027. The project record separately lists proposed completion 11/06/2027. RERA filing
Occupancy / completion certificateNo occupancy or completion certificate is supplied. The revised permit requires an occupancy certificate before occupation.

2. The project story

BHAGYADEEP RESIDENCY is registered as a residential apartment project at BARKATPURA - 20, Hyderabad. The RERA record identifies one building and records 36 homes: 18 three-bedroom and 18 four-bedroom units. The filed saleable areas are 206.47 sq m and 261.57 sq m, respectively. RERA record RERA filing RERA filing RERA unit table

GHMC’s revised building permit describes a single residential building with 1 Cellar + 2 Stilt + 9 upper floors. The supplied material does not establish that construction is complete or independently verify the site’s overall construction stage. The RERA portal’s facility-progress entries show partial reported progress for water supply and sewerage, but are not a whole-project completion measure. RERA amenities

The promoter’s Form B undertaking gives 11/02/2027 as the completion date; the project information field separately states a proposed completion date of 11/06/2027. The supplied record contains no OC or completion certificate; the GHMC permit states that an occupancy certificate is compulsory before occupation. RERA filing

3. Master plan, architecture & building design

  • The project’s RERA land details record a total site area of 2087.53 sq m, an area affected by road widening/FTL/Nala widening of 117.46 sq m, and a net area of 1970.07 sq m. GHMC’s revised permit describes a net plot area of 1970.24 sq m. RERA filing
  • The revised GHMC permit sanctions one residential building comprising 1 Cellar + 2 Stilt + 9 upper floors. It records building height 26.92 and residential upper-floors area 7,812.09 Sq.Mt. The RERA filing separately records approved built-up area 8132.92 sq mts; these are distinct filed figures and should not be treated as interchangeable area measures. RERA filing
  • The revised permit records a Tot Lot 197.12, 4 rainwater-harvesting pits, transformer space and a garbage house. It states that the road-widening portion is to be left as per registered Gift Deed Doc.No. 97/2022, dated 07-01-2022. The supplied extracts do not establish flat counts per floor, building footprint, lift or stair arrangements, internal circulation, or a detailed residential/common-area schedule.

4. Homes, configurations & floor plans

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
3BHK18711206.47 sq m112.0–112.5 sq m; median 112.2 sq m46%
4BHK18513261.57 sq m148.1–148.2 sq m; median 148.1 sq m43%

RERA unit counts, bookings, availability and saleable areas are from the TG-RERA unit record; booked/available counts have no recorded as-of date. Carpet-area figures and loading are software measurements from approved floor-plan drawing geometry, not RERA disclosures, and the measurements need drawing review. Saleable area is not carpet area: it includes the home’s share of common areas, while balconies are excluded from the supplied drawing-based carpet measurements. RERA unit table Floor plans RERA unit details

The measured drawing sample includes 3BHK bedrooms, living/dining, kitchen, toilets and balconies; the 4BHK sample includes bedrooms, hall, dress area, kitchen, toilet and balcony. These room layouts are drawing-derived measurements, not a substitute for checking the relevant approved plan for a specific unit. RERA unit details

5. Parking & vehicle circulation

The revised GHMC permit records Total Parking Area 2750.55; it does not provide a number of car or two-wheeler spaces in the supplied extraction. The earlier permit describes the cellar and stilt floors as approved for parking and states they are to be used exclusively for vehicle parking without partition walls or rolling shutters.

No parking-space count, visitor or accessible-space allocation, EV provision, ramp/driveway details, or unit-specific parking allocation is established by the supplied record. The vendor material mentions dedicated bike parking, but provides no quantity or project-specific approved allocation. Promoter website

6. Amenities, recreation & open spaces

Tot Lot
Description / sizeRevised permit records 197.12; earlier permit requires the tot-lot to be fenced and maintained as greenery before OC.
Evidence sourceGHMC permit extraction
Declared progress / verified statusSanctioned; portal’s Green Strip/TOT LOT/Park progress field shows 0%. No independent completion verification. RERA amenities
Water supply
Description / sizeProject portal marks “YES”.
Evidence sourceTG-RERA portal amenity record
Declared progress / verified status50% reported progress; source and capacity are not stated. RERA amenities
Sewerage
Description / sizeProject portal marks “YES” for “Sewerage (Chamber, Lines, Septic Tank, STP)”.
Evidence sourceTG-RERA portal amenity record
Declared progress / verified status40% reported progress; specific system and capacity are not established. RERA amenities
Rainwater harvesting
Description / sizeRevised permit records 4 pits; permit also requires a rainwater-harvesting structure.
Evidence sourceGHMC permit extraction
Declared progress / verified statusSanctioned; portal progress field shows 0%. No independent completion verification. RERA amenities
Storm-water drains
Description / sizeListed in the portal facility record.
Evidence sourceTG-RERA portal amenity record
Declared progress / verified status0% reported progress. RERA amenities
Internal roads and footpaths
Description / sizeListed in the portal facility record.
Evidence sourceTG-RERA portal amenity record
Declared progress / verified status0% reported progress. RERA amenities
Street lighting
Description / sizeListed in the portal facility record.
Evidence sourceTG-RERA portal amenity record
Declared progress / verified status0% reported progress. RERA amenities
Community buildings
Description / sizeListed in the portal facility record.
Evidence sourceTG-RERA portal amenity record
Declared progress / verified status0% reported progress; no facility description or size supplied. RERA amenities
Solid-waste management and disposal
Description / sizeListed in the portal facility record; permit also identifies a garbage house.
Evidence sourceTG-RERA portal amenity record; GHMC permit extraction
Declared progress / verified statusPortal progress 0%; no independent completion verification. RERA amenities
Electrical meter room / sub-station / receiving station
Description / sizeListed in the portal facility record; permit requires transformer space.
Evidence sourceTG-RERA portal amenity record; GHMC permit extraction
Declared progress / verified statusPortal progress 0%; no completion verification. RERA amenities

The portal progress percentages are recorded facility-level declarations, not independent inspections. The supplied project-specific record does not describe a clubhouse or a distinct indoor or sports facility. RERA amenities

7. Utilities, building services & safety

  • The project record marks water supply and sewerage as available, with portal-reported progress of 50% and 40%, respectively. It does not specify water source, storage or treatment capacity, sewerage/STP configuration, or whether treated water is reused. The revised permit requires 4 rainwater-harvesting pits and a garbage house; the portal records rainwater harvesting at 0% progress. RERA amenities
  • The permit requires space for a transformer, and the portal lists an electrical meter room/sub-station/receiving station; its recorded progress is 0%. No electrical supply capacity or backup-power provision is established by the project-specific permit extraction. RERA amenities
  • The GHMC permit requires an occupancy Fire NOC from the Director (EV&DM) before issue of the Occupancy Certificate and states that an occupancy certificate is compulsory before occupation. The portal’s fire-protection/fire-safety progress is 0%. The supplied material does not detail fire systems, escape stairs, lift capacities, CCTV, access control or accessibility provisions. RERA amenities

8. Location, access & connectivity

  • The RERA record places the project at BARKATPURA - 20, with the address fields referring to 3-4-2 and Kachiguda Railway Station Road, Hyderabad, 500027. The GHMC permit describes the site as BARKATPURA -20, Amberpet, and records an 18 mt. road width. The supplied location record contains no verified road-network or public-transport details. RERA filing
  • The location dataset gives a distance of 1.2 km to Financial District (Nanakramguda). Its supplied geocode is labelled a cadastral parcel centroid; no other measured access distances or travel times are provided. Location record

9. Developer & development status

  • The registered promoter is Jain Projects, identified in the project record as a partnership, with GSTIN 36AAQFJ5304A1ZN. The promoter address is recorded as B, KACHIGUDA, AMBERPET VILLAGE, BARKATPURA - 20, Hyderabad, 500027. The supplied material does not provide a verified official website or contact details. RERA filing Corporate record Parties record
  • The promoter’s authorized signatory, Amit Kumar Shah, declared in Form B that the project would be completed by 11/02/2027. The project information field lists proposed completion as 11/06/2027; the supplied record does not establish an OC or independently verified overall construction progress. RERA filing

10. Approvals, official records & documents

TG-RERA registration certificate
Identifier / dateP02500004365; issued 04/04/2022; validity stated through 11/02/2027
What the supplied record establishesForm C records registration of BHAGYADEEP RESIDENCY under section 5 and includes a separate-account condition.
GHMC building permit
Identifier / date2145/GHMC/SEC/2022-BP; 11 February, 2022
What the supplied record establishesEarlier permit extraction describes 1 Cellar + 2 Stilt + 7 upper floors and sets conditions including OC before occupation.
Revised GHMC building permit
Identifier / date5862/GHMC/SEC/2023-BP; 13 July, 2023
What the supplied record establishesRevised permit extraction describes 1 Cellar + 2 Stilt + 9 upper floors and records the road-widening portion as to be left under Gift Deed Doc.No. 97/2022, dated 07-01-2022.
Form B promoter declaration
Identifier / dateL- 5 MAR 2022
What the supplied record establishesAuthorized signatory Amit Kumar Shah declared title, that the land was free from encumbrances, and completion by 11/02/2027, among other undertakings. These are promoter declarations.
Layout plan / layout approval documents
Identifier / dateDocument records 222097 and 342649
What the supplied record establishesListed as layout-related documents; no extracted layout approval particulars are supplied. Document index
Occupancy / completion certificate
Identifier / dateNot supplied
What the supplied record establishesThe revised permit states an occupancy certificate is required before occupation; the supplied pack contains no such certificate.

Frequently asked questions

Is BHAGYADEEP RESIDENCY registered with Telangana RERA?

Yes. BHAGYADEEP RESIDENCY is registered with the Telangana Real Estate Regulatory Authority as P02500004365; the registration status is New Project.

Who is the developer of BHAGYADEEP RESIDENCY?

The promoter named in the RERA registration is JAIN PROJECTS.

Where is BHAGYADEEP RESIDENCY located?

BHAGYADEEP RESIDENCY is in BARKATPURA - 20, Hyderabad, Telangana (500027).

When will BHAGYADEEP RESIDENCY be completed?

The promoter's proposed date of completion filed with RERA is 11/06/2027. This is the promoter's declaration, not a guarantee.