Sign in

Laxmiramana Lake View Enclave

SUDARSHANAA CONSTRUCTIONS · Medchal-Malkajgiri · RERA P02200010530

LAXMIRAMANA LAKE VIEW ENCLAVE is a residential apartment project in Suraram Village, Qutballapur Mandal, Medchal-Malkajgiri District. It is being developed by registered promoter SUDARSHANAA CONSTRUCTIONS, a partnership, on Survey Nos. 117, 118 and 119. The project site area is 6,576.11 sq. m and the development comprises two residential blocks and one amenities building: Block A has 1 stilt + 5 upper floors, Block B has 1 cellar + 1 stilt + 5 upper floors, and the amenities building has ground + 4 upper floors. The GHMC permit records 120 dwelling units, while the TG-RERA unit record identifies 109 2BHKs and 10 3BHKs, with RERA-filed saleable areas of 111.35 sq. m and 142.61 sq. m respectively. The project is registered under TG-RERA P02200010530, and the promoter’s Form B states completion on or before 09/09/2028.

01What we found

RegisteredTG-RERA - valid till 9 Sep 2028
35documents on file - each fact links to its page
2court cases on this project's land (survey 117, Quthbullapur Mandal)
9items to check - 4 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

9 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

Project at a glance

Project identity

FieldProject record
Registered project nameLAXMIRAMANA LAKE VIEW ENCLAVE RERA record
Project typeResidential apartment project RERA record
Phase / registered portionPhase not separately identified in the supplied record; registration refers to the project on Survey Nos. 117, 118 and 119 RERA record
TG-RERA registrationP02200010530 RERA record
Registration validity10 September 2025 to 9 September 2028, unless extended by the Authority RERA record
Registered promoterSUDARSHANAA CONSTRUCTIONS, a partnership RERA record RERA filing Corporate record
RERA statusRecorded as a new project. Registration certificate supplied; no occupancy certificate is recorded in the supplied evidence. RERA record

Land and geographic identity

FieldProject record
Locality / revenue villageSuraram Village in the building-permit record; the TG-RERA registration certificate identifies the location as Qutballapur.
MandalQutballapur / Qutubullapur, as recorded in the project documents RERA record
DistrictMedchal-Malkajgiri; the building-permit extraction also records “MEDCHAL” RERA record
PIN500055 RERA record
Project survey numbers117, 118 and 119; no subdivision is specified in the project identity or principal permit extraction. RERA record
Site areaPermit records 6,576.11 sq. m plot area, 915.37 sq. m affected area and 5,660.74 sq. m net plot area.
Boundaries recorded in RERA project fieldsEast: land of Chandramma Educational Society and Sy. No. 117; West: 40-wide road; North: land of Kudali Pentaiah; South: 50-wide road. RERA filing

Development identity

FieldProject record
Sanctioning authorityGreater Hyderabad Municipal Corporation (GHMC)
Principal building permit5457/GHMC/KPL/2025-BP, dated 10 September 2025 RERA record
Approved built-up areaThe RERA-filed permit extraction records 6,398.00 sq. m for Block A residential upper floors, 6,444.85 sq. m for Block B residential upper floors, and 148.01 sq. m ground plus 592.04 sq. m upper floors for the amenities block. It separately records a total proposed built-up area excluding parking of 13,582.91 sq. m and including parking of 18,503.31 sq. m.
BuildingsTwo residential blocks (A and B) and one amenities building
Sanctioned floor configurationBlock A: 1 stilt + 5 upper floors. Block B: 1 cellar + 1 stilt + 5 upper floors. Amenities block: ground + 4 upper floors.
Parking provisionCellar/stilt parking is shown for the residential blocks; the permit extraction records 5,187.3 sq. m total parking area.
Unit countsGHMC permit extraction: 120 dwelling units—60 in Block A and 60 in Block B. TG-RERA unit record: 125 total rows, comprising 119 identified 2BHK/3BHK homes, one unclassified row, and five floor-label rows not treated as homes on sale. RERA unit table
HeightPermit extraction records building-height figures of 14.9 m, 14.88 m and 14.99 m; it does not map each figure to a specific building in the supplied extraction.

Offering and status

FieldProject record
RERA-filed configurations2BHK and 3BHK RERA unit table
RERA-filed saleable area2BHK: 111.35 sq. m; 3BHK: 142.61 sq. m RERA unit table
Booked / availablePortal-derived unit counts show 0 booked and 109 available 2BHKs, and 0 booked and 10 available 3BHKs. These counts have no supplied as-of date and are indicative. RERA unit table
Construction stageThe project is recorded as a new project; no independently verified construction-stage or site-progress evidence is supplied. RERA record RERA amenities
Completion datesGHMC permit extraction: construction to be completed before 10 September 2028. Promoter Form B declaration: completion on or before 09/09/2028.
Registration expiry9 September 2028, unless extended; this is the registration-validity date, distinct from the completion undertaking.
Occupancy certificateNo OC is included in the supplied project evidence. The permit requires an OC before occupation.

The project story

LAXMIRAMANA LAKE VIEW ENCLAVE is a residential apartment development in Suraram Village, recorded in the project registration as Qutballapur, Medchal-Malkajgiri. Its GHMC building permit describes two residential blocks and a separate amenities building, on the project land identified as Survey Nos. 117, 118 and 119.

The permit provides for five upper floors in each residential block, with stilt parking in Block A and cellar plus stilt parking in Block B. It provides a ground floor and four upper floors for the amenities building. GHMC’s permit extraction records 120 dwelling units, while the RERA portal’s unit table identifies 109 2BHKs and 10 3BHKs; the table also contains entries that are not classified as these home configurations. The portal counts are not dated in the supplied record. RERA unit table

The promoter’s Form B states completion on or before 09/09/2028, and the permit gives a completion date before 10 September 2028. Those are stated deadlines, not evidence that construction is complete. No independently verified progress report, completion certificate or occupancy certificate is supplied.

Master plan, architecture & building design

The permit record describes the site as 6,576.11 sq. m, with 915.37 sq. m recorded as affected area and a net plot area of 5,660.74 sq. m. It separately records 13,582.91 sq. m of proposed built-up area excluding parking and 18,503.31 sq. m including parking; it also lists total built-up area of 19,011.53 sq. m and net built-up area of 12,842.85 sq. m. These are separate permit-record figures and are not carpet or saleable areas.

BuildingUse recordedSanctioned configurationArea / other recorded details
Block AResidential1 stilt + 5 upper floors6,398.00 sq. m residential upper-floor area; 60 tenements; 1,513.10 sq. m parking area
Block BResidential1 cellar + 1 stilt + 5 upper floors6,444.85 sq. m residential upper-floor area; 60 tenements; 3,407.30 sq. m parking area
Amenities buildingAmenities / commercial in the permit extractionGround + 4 upper floorsGround-floor area 148.01 sq. m; upper-floor area 592.04 sq. m

The permit extraction records a 574.3 sq. m tot lot and requires a periphery greenery strip, tree planting and a fenced tot lot maintained as green space. It records road-affected and nala-affected areas among the site-area components.

Homes, configurations & floor plans

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
2BHK1090109111.35 sq. mSoftware-measured range: 63.2–88.6 sq. m; median 81.0 sq. m27%
3BHK10010142.61 sq. mNot suppliedNot supplied

RERA-filed saleable areas and unit counts are from the project unit record; booked and available counts are portal-derived and have no supplied as-of date. RERA unit table The 2BHK carpet measurements were software-measured from the approved-plan drawing extraction for 46 designs, with 16 flagged as needing review. They are not RERA-filed area disclosures and should be checked against the drawings. Floor plans

Carpet area is not the same as saleable area: the RERA filing’s saleable figure and the software-measured drawing carpet figure describe different area measures. The supplied evidence does not provide a drawing-based carpet measurement for the 3BHK configuration. RERA unit table Floor plans

The RERA unit table also contains one entry labelled “409 2BHLK” and five entries labelled by floor. These have not been treated as additional 2BHK/3BHK configurations or as homes available for sale. RERA unit table

Parking & vehicle circulation

The GHMC permit extraction records cellar/stilt parking for the residential buildings, 5,187.3 sq. m total parking area, and 144 proposed cars. Its separate building breakdown lists 1,513.10 sq. m parking area for Block A and 3,407.30 sq. m for Block B. The permit conditions state that cellar and stilt areas approved for parking must be used exclusively for vehicle parking and not partitioned or converted to another use.

The layout-plan extraction describes a vehicular ramp measuring 24.42 m long, 3.00 m high and 5.64 m wide, and a minimum clearance requirement for the ramp. The supplied evidence does not establish visitor or accessible parking counts, EV charger quantities, pedestrian–vehicle separation, or legally documented exclusive parking allocation to individual units. A drawn parking bay or overall parking provision does not by itself establish exclusive ownership.

Amenities, recreation & open spaces

Tot lot / green space
Description / sizePermit extraction records 574.3 sq. m; permit conditions require fencing and maintenance as greenery.
Declared progress / verified statusSanctioned/required; no completion verification supplied.
Community / amenities building
Description / sizeGround + 4 upper floors; ground area 148.01 sq. m and upper-floor area 592.04 sq. m in the permit extraction.
Declared progress / verified statusIncluded in permit; no progress or delivery verification supplied.
Green strip and tree planting
Description / sizePeriphery greenery strip and tree planting are required by the permit conditions.
Declared progress / verified statusRequired; no completion verification supplied.
Garden, park, children’s play areas, yoga area, indoor games, jogging/cycling track
Description / sizeListed in vendor-supplied amenity material, not established by the supplied permit extraction as sanctioned or delivered facilities.
Evidence sourcePromoter website
Declared progress / verified statusMarketing claims; no independent verification supplied.

Utilities, building services & safety

The building-permit extraction lists water supply, electricity connections, transformer space, a garbage house, rainwater-harvesting pits and fire-fighting installations. It records six rainwater-harvesting pits and water tanks, including a 25,000-litre underground static storage tank and a 25,000-litre terrace tank for residential buildings. These are permit-record provisions, not evidence of installation or operation.

The permit conditions also call for a dual-piping arrangement for qualifying group-housing buildings, a rainwater-harvesting structure, a garbage house, fire-safety installations and an automatic sprinkler system in the cellar. The permit states that an occupancy fire NOC is to be obtained before issue of an occupancy certificate. No completed-system inspection, water source, STP capacity, generator capacity, lift details, CCTV/access-control specification, accessibility provision or issued fire NOC is evidenced in the supplied material.

Location, access & connectivity

The project’s official record places it in Suraram Village, Qutballapur Mandal, Medchal-Malkajgiri District, PIN 500055, on Survey Nos. 117, 118 and 119. The GHMC building-permit extraction records an 18 m road and the RERA project fields describe 40-wide and 50-wide roads on the west and south boundaries respectively. The permit extraction also lists road-width references of 12.00 m and 30.00 m, but the supplied text does not identify their precise alignment to the project. RERA filing

A supplied location record lists HITEC City at 10.0 km from the cadastral parcel centroid. Location record The vendor lists nearby landmarks and road connections, but these are vendor-supplied claims and are not independently verified in the supplied records. Promoter website

Developer & development status

The registered promoter is SUDARSHANAA CONSTRUCTIONS, recorded as a partnership. The RERA record names RAMANAIAH SEELIGALLA and LAXMI DEVI SEELIGALLA as partners, and RAMANAIAH SEELIGALLA as an authorised signatory. The supplied corporate identifier is GSTIN 36ADZFS2027H1ZN. Corporate record Parties record

The project permit identifies the landowners/applicants as Rajala Narender and others and Sudarshanaa Constructions as their DAGPA holder/developer. The RERA record lists five landowners: KASIREDDY NARAYANA RAO, RAJALA NARENDER, RAJALA ASHOK, RAJALA SHOBA and RAJALA AMARAVATHI. Land records

The promoter’s Form B declares that the project will be completed on or before 09/09/2028. No independent site-progress verification or official contact details or promoter website are included in the supplied evidence. RERA record

Approvals, official records & documents

RecordSupplied evidence
TG-RERA registrationForm C registration certificate for P02200010530, project name LAXMIRAMANA LAKE VIEW ENCLAVE; validity 10 September 2025–9 September 2028 unless extended.
GHMC building permitBuilding Permit Order 5457/GHMC/KPL/2025-BP, dated 10 September 2025, for residential blocks and an amenities building on Survey Nos. 117, 118 and 119.
Plan / layout materialRERA-filed plan/layout extraction records file reference TS/024426/2024, applicant and site details, building configurations and permit conditions.
Promoter declarationForm B by the promoter’s authorised representative, including the completion undertaking and financial/account-management declarations.
Occupancy / completion evidenceNo occupancy or completion certificate is supplied. The permit requires an occupancy certificate before occupation and states that a fire NOC must be obtained before the OC.

Frequently asked questions

Is LAXMIRAMANA LAKE VIEW ENCLAVE registered with Telangana RERA?

Yes. LAXMIRAMANA LAKE VIEW ENCLAVE is registered with the Telangana Real Estate Regulatory Authority as P02200010530; the registration status is New Project.

Who is the developer of LAXMIRAMANA LAKE VIEW ENCLAVE?

The promoter named in the RERA registration is SUDARSHANAA CONSTRUCTIONS.

Where is LAXMIRAMANA LAKE VIEW ENCLAVE located?

LAXMIRAMANA LAKE VIEW ENCLAVE is in Quthbullapur Mandal, Qutballapur, Medchal-Malkajgiri, Telangana (500055).

When will LAXMIRAMANA LAKE VIEW ENCLAVE be completed?

The promoter's proposed date of completion filed with RERA is 09/01/2029. This is the promoter's declaration, not a guarantee.