Likhitha Residency

AMPLE CONSTRUCTIONS · Hyderabad · RERA P02500009675

LIKHITHA RESIDENCY is a residential apartment project in Bakaram, Musheerabad Mandal, Hyderabad District. The registered promoter developing it is AMPLE CONSTRUCTIONS, represented by MAJETI BHEEMA SHANKAR. The project is on 376.26 sq. m of land and comprises one building with 1 Stilt + 5 upper floors and 10 homes: five 2BHK units of 111.48 sq. m and five 3BHK units of 139.35 sq. m. Its TG-RERA registration number is P02500009675, and the proposed completion date is 10 January 2028.

More from Ample Constructions · 3 projects →

01What we found

RegisteredTG-RERA - valid till 10 Jan 2028
15documents on file - each fact links to its page
0court cases on this project's land in the court records searched
8items to check - 2 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

8 items to check before you pay, 2 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

1. Project at a glance

Project identity

FieldProject record
Registered project nameLIKHITHA RESIDENCY RERA record
Project typeResidential apartment project RERA record
Phase / registered portionNo phase name is disclosed; the RERA record describes one building RERA record
TG-RERA registrationP02500009675 RERA record
Registration validity10 January 2025 to 10 January 2028; the certificate states a three-year registration period, unless extended by the Authority RERA record
Registered promoterAMPLE CONSTRUCTIONS, represented by MAJETI BHEEMA SHANKAR RERA record
RERA statusThe supplied record identifies the project as a new project. Registration validity is distinct from the promoter’s declared completion date and from occupancy certification. RERA record

Land and geographic identity

FieldProject record
LocalityBakaram / BAKARAM RERA record RERA filing
Revenue villageBakaram RERA record Land records
MandalMusheerabad, as stated in the GHMC building permit
DistrictHyderabad RERA record Land records
PIN500080 RERA record
Project survey number(s)Survey No. 144; no subdivision is disclosed RERA filing Land records
Registered site extent376.26 sq. m
Total / net areaTotal plot area: 376.26 sq. m; net plot area: 376.26 sq. m
BoundariesEast: Plot No. 33; West: Plot No. 31; North: Plot No. 28; South: 40 feet road RERA filing Land records

Development identity

FieldProject record
Sanctioning authorityGreater Hyderabad Municipal Corporation (GHMC) Approvals record
Principal building permit4296/GHMC/SEC/2025-BP, approved 10 January 2025. File No.: 011068/GHMC/5100/SEC2/2024-BP. Approvals record
Building arrangement and floorsOne residential building, 1 Stilt + 5 upper floors; building height stated as 14.99 m in the permit parameters
Approved built-up areaTotal proposed built-up area including parking: 1305.30 sq. m; excluding parking: 1087.75 sq. m. The plan record separately states parking area of 217.55 sq. m.
Sanctioned versus RERA unit countThe plan record states 10 units; the RERA unit record lists 10 total units. RERA unit table
Parking provisionThe permit identifies parking area and requires the stilt/approved parking areas to be used for vehicle parking. A specific parking-space count is not supplied.

Offering and status

FieldProject record
RERA-filed configurations2BHK: 5 units; 3BHK: 5 units RERA unit table
RERA-filed saleable areas2BHK: 111.48 sq. m; 3BHK: 139.35 sq. m RERA unit table
Booked / available0 booked and 5 available in each configuration (10 available in total), according to the portal data; the record has no as-of date, so counts are indicative. RERA unit table
Construction stageNo construction-progress percentage or independently verified site-stage record is supplied. The RERA amenities register records water supply at 10% and the other listed infrastructure items at 0%; these are reported portal values, not independent site verification. RERA amenities
Completion deadlineThe promoter’s Form B declares completion by 10 January 2028. The building permit also sets a deadline to complete before 10 January 2028.
Occupancy / completion certificateThe supplied permit document records that completion is not certified; no occupancy or completion certificate for the building is supplied.

2. The project story

LIKHITHA RESIDENCY is registered as a residential apartment project in Bakaram, Hyderabad, on Survey No. 144. The project record describes a single residential building on a 376.26 sq. m site, sanctioned by GHMC for a stilt level and five upper floors. RERA record Land records

The RERA filing lists ten homes: five 2BHK and five 3BHK apartments. Its portal-derived booking figures show all ten as available and none booked, but those figures carry no as-of date. RERA unit table No verified construction-stage report is provided, so the project’s actual on-site progress cannot be stated from this evidence. The permit’s completion deadline and the promoter’s declared completion undertaking are both 10 January 2028; neither is evidence that construction is complete. No occupancy or completion certificate is supplied.

3. Master plan, architecture & building design

The GHMC building-permit record and filed plan identify one residential building, RESI (BUILDING), on a plot area of 376.26 sq. m. The plan states net plot area of 376.26 sq. m, total proposed built-up area of 1305.30 sq. m including parking, and 1087.75 sq. m excluding parking. It separately records 217.55 sq. m as parking area; these figures are not interchangeable with apartment saleable or carpet areas.

The sanctioned configuration is 1 Stilt + 5 upper floors, with a stated building height of 14.99 m in the permit parameters. The plan record identifies the fifth floor as TDR. It lists setbacks, a tot-lot, a lift, parking and service-related elements, but the supplied extraction does not establish the detailed floor-by-floor dwelling arrangement, building footprint, lift capacity, number of stairs, or a complete circulation plan.

The plan records a 25,000-litre underground static water storage tank and a separate 25,000-litre terrace tank. It also lists a sump, rainwater harvesting, septic tank, transformer, garbage house, generator, emergency lighting and firefighting installations. These are plan-record entries, not confirmation that the facilities have been completed or commissioned.

No separate approved-layout record, landscaping plan, or measured open-space area is supplied. The building-permit conditions refer to maintaining a tot-lot and greenery, and to rainwater harvesting; these are conditions or plan provisions rather than evidence of delivery.

4. Homes, configurations & floor plans

The RERA filing lists ten units across two configurations. Saleable areas and unit counts below are filing figures. Carpet areas and loading figures are software measurements from the filed floor-plan drawing, not RERA disclosures; the measurement record says the drawing geometry needs review and that saleable area includes the home’s share of common areas. RERA unit table Floor plans

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
2BHK505111.48 sq. m68.5 sq. m (737 sq. ft)39%
3BHK505139.35 sq. m94.7 sq. m (1019 sq. ft)32%

The measured 2BHK drawing identifies bedrooms, living, dining/kitchen, puja and toilets, with utility areas shown separately. The measured 3BHK drawing identifies bedrooms, living, dining, kitchen and toilets, with utility areas shown separately. Room dimensions are drawing-derived measurements, not RERA-filed areas. RERA unit details

The portal booking and availability counts have no recorded as-of date and should be treated as indicative. RERA unit table

5. Parking & vehicle circulation

The permit and filed plan provide for parking in the stilt/approved parking area. The plan record states a parking area of 217.55 sq. m; the building permit’s sanctioned parameters separately state “Total Parking Area 173.9”. The supplied record does not specify a sanctioned count of car or two-wheeler spaces, visitor or accessible spaces, or unit-by-unit parking allocations.

The permit conditions say cellar and stilt areas approved for parking must be used exclusively for vehicle parking and not converted or partitioned. The available material does not establish parking-space ownership or exclusive allocation to any apartment.

6. Amenities, recreation & open spaces

The RERA amenities register includes the facilities below. Its percentage figures are portal-recorded progress values, not independent verification of completion. RERA amenities

Tot-lot / green strip
Description / sizePermit condition requires the tot-lot to be fenced and maintained as greenery; no size supplied
Declared progress / verified statusRERA amenities register: Green Strip/TOT LOT/Park 0%; not independently verified RERA amenities
Water supply
Description / sizeNo source or capacity specified in the RERA amenities register
Evidence sourceRERA amenities
Declared progress / verified statusRERA register: “YES”, 10%; not independently verified RERA amenities
Sewerage
Description / sizeRegister groups chamber, lines, septic tank and STP; the filed plan lists a septic tank
Evidence sourceRERA amenities
Declared progress / verified statusRERA register: “YES”, 0%; not independently verified RERA amenities
Rainwater harvesting
Description / sizePlan lists rainwater harvesting; permit requires rainwater harvesting pits
Declared progress / verified statusRERA register: Water Conservation, Rain water Harvesting 0%; not independently verified RERA amenities
Community buildings
Description / sizeNo facility description or size supplied
Evidence sourceRERA amenities
Declared progress / verified statusRERA register: 0%; not independently verified RERA amenities
Recreational open space
Description / sizeNo area supplied
Evidence sourceRERA amenities
Declared progress / verified statusRERA register: 0%; not independently verified RERA amenities

No RERA-filed clubhouse, swimming pool, gym or children’s play area is documented in the supplied project records. The RERA amenities register also lists internal roads and footpaths, storm-water drains, street lighting, sewage and sullage treatment/disposal, solid-waste management, energy management, fire-safety requirements, an electrical meter room/substation/receiving station, and aggregate recreational open space; their recorded progress is 0%, except where stated above. RERA amenities

7. Utilities, building services & safety

The filed plan records a 25,000-litre underground static water storage tank and a separate 25,000-litre terrace tank, along with a sump. It does not specify the water source or a treatment system. The RERA amenities register marks water supply “YES” at 10% progress. RERA amenities

For wastewater, the plan lists a septic tank; the RERA amenities register lists sewerage facilities as “YES” at 0% progress and groups chambers, lines, septic tank and STP. The supplied record does not confirm an installed or operating STP, sewage reuse, storm-water drainage completion, or rainwater-harvesting capacity. RERA amenities

The plan lists a distribution transformer, generator, emergency lighting and electrical meter room/substation/receiving station. The permit requires transformer space and rainwater-harvesting pits; it also includes conditions relating to fire safety, CCTV installation, construction safety and a zero-ramp provision within the plot. The plan lists a lift and firefighting installations, but no lift capacity, generator capacity, specific fire-system capacity, or completion/commissioning evidence is supplied.

8. Location, access & connectivity

The registered project location is Bakaram, Hyderabad, Telangana 500080, in Bakaram revenue village, Survey No. 144; the GHMC building permit identifies Musheerabad Mandal and Hyderabad District. The permit records a 40-foot road along the southern boundary. RERA record Land records

No project-specific public-transport stops, approach-route description, or measured distance to a landmark is supplied in the project location record. The available location data includes a distance of 1.2 km to Financial District (Nanakramguda), but the supplied record does not establish a route or travel time. Location record

9. Developer & development status

The registered promoter is AMPLE CONSTRUCTIONS, recorded as a proprietorship, represented by MAJETI BHEEMA SHANKAR. The Form B declaration is made by Majeti Bheema Shankar as proprietor of M/s Ample Constructions and gives the promoter’s completion undertaking as 10 January 2028. RERA record Corporate record

A Udyam certificate identifies AMPLE CONSTRUCTION as a micro enterprise and records Majeti Bheema Shankar as its owner; Udyam Registration No. UDYAM-TS-02-0227087, dated 07/03/2025. This is an enterprise-registration record, not a building approval.

The supplied promoter address record is Vivek Nagar, Chikkadpally, Bakaram, Hyderabad, PIN 500080. No official promoter website or contact details are supplied. The available evidence does not establish construction progress independently or confirm completion or occupancy certification. Parties record RERA record RERA amenities

10. Approvals, official records & documents

RecordSupplied evidence and scope
TG-RERA registrationForm C registration certificate for LIKHITHA RESIDENCY, P02500009675, Survey No. 144, with validity from 10 January 2025 to 10 January 2028.
GHMC building permitBuilding Permit Order 4296/GHMC/SEC/2025-BP, File No. 011068/GHMC/5100/SEC2/2024-BP, approved 10 January 2025; covers the residential building at Bakaram on the stated 376.26 sq. m site.
Filed building-plan recordPlan for proposed residential construction of stilt plus five floors at House Nos. 1-4-879/75 and 1-4-879/75/1, Plot No. 32, Group II, Survey No. 144, Bakaram.
Form B promoter declarationAffidavit-cum-declaration dated 07 March 2025, including the promoter’s title and encumbrance declarations and completion undertaking.
Title-related documents filed with RERASale deed, release deed and title-search report are in the project file; these are title records rather than building approvals.
Occupancy / completion recordNo occupancy or completion certificate is supplied; the permit extraction records completion as not certified.

The GHMC permit states that permission does not confer ownership rights and sets conditions for construction, completion notice and obtaining an occupancy certificate before occupation.

Frequently asked questions

Is LIKHITHA RESIDENCY registered with Telangana RERA?

Yes. LIKHITHA RESIDENCY is registered with the Telangana Real Estate Regulatory Authority as P02500009675; the registration status is New Project.

Who is the developer of LIKHITHA RESIDENCY?

The promoter named in the RERA registration is AMPLE CONSTRUCTIONS.

Where is LIKHITHA RESIDENCY located?

LIKHITHA RESIDENCY is in BAKARAM, Hyderabad, Telangana (500080).

When will LIKHITHA RESIDENCY be completed?

The promoter's proposed date of completion filed with RERA is 10/05/2028. This is the promoter's declaration, not a guarantee.