Amogh Homes Lake View

AMOGH HOMES LLP · Hanamkonda · RERA P00300003921

AMOGH HOMES LAKE VIEW is a residential apartment project in Prashanth Nagar – Waddepally, Hanamkonda mandal, Warangal Urban district, developed by the registered promoter AMOGH HOMES LLP. The project covers a site area of 1,771.85 m² and comprises one building with 1 Stilt + 5 upper floors and 40 apartments: 20 2BHK and 20 3BHK units. It is registered under TG-RERA number P00300003921, with a proposed completion date of 11/10/2027.

01What we found

RegisteredTG-RERA - valid till 11 Jun 2027
12documents on file - each fact links to its page
0court cases on this project's land in the court records searched
9items to check - 3 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

9 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

1. Project at a glance

Project identity

FieldProject record
Registered project nameAMOGH HOMES LAKE VIEW RERA record
Project type / phaseResidential apartment project; the supplied record identifies one building and does not state a separate phase name or registered-portion description. RERA record
TG-RERA registrationP00300003921 RERA record
Registration status and validityThe record describes the project as “New Project.” Registration certificate Form C grants registration from 17/01/2022 to 11/06/2027; no extension is recorded in the supplied certificate. This is the registration-validity period, not a statement that the project is complete. RERA record
Registered promoterAMOGH HOMES LLP, an LLP. RERA record Corporate record

Land and geographic identity

FieldProject record
Locality / site descriptionPrashanth Nagar – Waddepally; the building-permit record identifies Ward 49, WADDEPALLY.
Revenue villageWaddepally Revenue Village. Land records
Mandal / district / PINHanamkonda / Warangal Urban / 506002. RERA record
Project survey numbersSurvey Nos. 721 and 722, Waddepally; no subdivision is supplied. Land records
Site area1,771.85 m² total site area and 1,771.85 m² net area in the building-permit record; road-affected area is recorded as 0 m².
Boundaries recorded in RERA project informationEast: LAND OF PAPAIAH K; West: OPEN LAND OF K NARSAIAH; North: LAND OF EXCISE OTHERS; South: 9MT ROAD. RERA filing
RERA certificate plot reference721 & 722.

Development identity

FieldProject record
Sanctioning authorityGreater Warangal Municipal Corporation (GWMC), as stated in the filed building permit. The project information also lists DTCP as the authority; the approval record indexed here is the GWMC permit. Approvals record
Principal building approvalBuilding Permit Order 3006/33155/W49/2021, dated 11 June, 2021. Approvals record
Approved building formOne residential building, 1 Stilt + 5 upper floors, height recorded as 14.25 m.
Approved area figuresApproved residential area: 4,525.45 m²; stilt area: 980.95 m². The permit separately records a 93.82 m² tot-lot.
Building and unit countsOne building. The project form records 40 apartments across two configurations; the permit condition says the sanctioned unit count must not be increased without prior approval. RERA record RERA unit table
Parking levels / provisionStilt is included in the approved building configuration, and the permit requires approved stilt/cellar parking to be used exclusively for parking. The supplied record does not provide parking-space counts; no cellar level is identified in the stated floor configuration.
Project approval statusA building permit is filed; a separate approved-layout document is not established in the supplied material. The RERA filing labels the approval number as 3006/33155/W49/2021. Approvals record HMDA

Offering and status

FieldProject record
RERA-filed configurations2BHK: 20 units; 3BHK: 20 units. RERA unit table RERA unit details
RERA-filed saleable area2BHK: 50.28 m²; 3BHK: 40.41 m². RERA unit table RERA unit details
Booked / availablePortal extract shows 0 booked and 20 available for each configuration, but supplies no “as of” date; figures are indicative only. RERA unit table RERA unit details
Construction stageNo independently verified construction-stage or site-progress evidence is supplied. The RERA filing completeness indicator is 70%, which is not a verified construction-progress measure. RERA record
Completion dateThe promoter’s Form B declaration undertakes completion by 11 June 2027. The project header gives a proposed completion date of 11/10/2027. These are recorded separately here; the supplied evidence does not establish a revised completion date. RERA record
Occupancy / completion certificateNo occupancy certificate or completion certificate is supplied; the building-permit extraction records completion_certified: false.

2. The project story

AMOGH HOMES LAKE VIEW is registered as a residential apartment project on Survey Nos. 721 and 722 in Waddepally Revenue Village, Hanamkonda mandal, Warangal Urban district. The registered site extent is 1,771.85 m². The filed building permit describes one residential building with a stilt level and five upper floors, for residential use. RERA record Land records

The RERA unit schedule lists 40 apartments: 20 2BHK and 20 3BHK. It records all 40 as available and none as booked, but the portal extract has no as-of date. No construction progress has been independently verified in the supplied material, so the project’s physical stage cannot be confirmed from this evidence. The completion undertaking, proposed completion date and registration-validity date are separate record items; none establishes that an occupancy certificate has been issued. RERA unit table RERA unit details RERA record

3. Master plan, architecture & building design

The filed building permit covers a single residential building on a 1,771.85 m² site, with 1 Stilt + 5 upper floors and a stated building height of 14.25 m. It records 4,525.45 m² as residential area and 980.95 m² as stilt area. These are the permit’s labelled figures; the supplied material does not separately establish FSI-counted area, gross built-up area, carpet area or a building footprint.

The permit records a 93.82 m² tot-lot and an open-space percentage of 14%. It also lists setbacks as Front 3.05, Rear 5.01, Side I 5, and Side II 5; the supplied extraction does not state units for these setback figures. No floor plans or drawing-derived records in the supplied data establish flats per floor, internal layouts, lift or stair counts, entrances, circulation, landscaping beyond the tot-lot, or a phase-wise arrangement. Floor plans

4. Homes, configurations & floor plans

The following counts and saleable areas are from the TG-RERA filing. The portal counts have no supplied as-of date. No measured carpet-area or room-dimension results are available: although two floor-plan drawings are recorded as measured, the configuration data reports 0 measured flat designs for both filed configurations. RERA unit table RERA unit details Floor plans

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
2BHK2002050.28 m²Not availableNot supplied
3BHK2002040.41 m²Not availableNot supplied

The filing labels the areas as saleable area. Carpet area is a different measurement; the supplied project data does not provide a verified carpet-area figure or quantify any common-area loading. The floor-plan extraction warns that any software-measured carpet-area result would be drawing-based rather than a RERA disclosure, but provides no usable measured flat designs for these configurations. RERA unit details Floor plans

5. Parking & vehicle circulation

The approved building configuration includes a stilt level. The permit states that cellar and stilt areas approved for parking must be used exclusively for vehicle parking and not partitioned or converted to another use. The supplied permit extraction does not establish a cellar in the approved floor configuration, and neither the RERA filing nor permit extraction provides a number of parking spaces, two-wheeler provision, visitor or accessible bays, parking allocation by apartment, or EV charging. RERA amenities

The filed building-permit condition is evidence of a required parking use for approved stilt/cellar areas, not proof of the as-built provision or of an exclusive parking right attached to any particular apartment. The supplied materials do not establish ramps, driveway arrangements, vehicle entry or exit points, or pedestrian separation.

6. Amenities, recreation & open spaces

The RERA amenity schedule lists 14 infrastructure or common-facility categories. Its available-status entries are shown below as filed; all entries with progress data show 0%. No independent completion verification is supplied. RERA amenities

FacilityDescription / sizeEvidence sourceDeclared progress / verified status
Internal Roads & FootpathsSize not suppliedRERA amenity schedule0%; not independently verified
Water SupplyStatus marked “YES”; capacity/source not suppliedRERA amenity schedule0%; not independently verified
Sewerage (Chamber, Lines, Septic Tank, STP)Status marked “YES”; components/capacity not specifiedRERA amenity schedule0%; not independently verified
Storm Water DrainsDetails not suppliedRERA amenity schedule0%; not independently verified
Green Strip/TOT LOT/ParkStatus marked “YES”; permit records a 93.82 m² tot-lotRERA amenity schedule; building permit0% in schedule; delivery not independently verified
Street LightingDetails not suppliedRERA amenity schedule0%; not independently verified
Community BuildingsDetails not suppliedRERA amenity schedule0%; not independently verified
Treatment and Disposal of Sewage and Sullage WaterDetails not suppliedRERA amenity schedule0%; not independently verified
Solid Waste Management and DisposalDetails not suppliedRERA amenity schedule0%; not independently verified
Water Conservation / Rain Water HarvestingStatus marked “YES”; permit requires a rainwater-harvesting structure (percolation pit) and records 13 RWHPsRERA amenity schedule; building permit0% in schedule; installation not independently verified
Energy managementDetails not suppliedRERA amenity schedule0%; not independently verified
Fire Protection and Fire Safety RequirementsDetails not suppliedRERA amenity schedule0%; not independently verified
Electrical Meter Room, Sub-Station, Receiving StationStatus marked “YES”; permit requires transformer spaceRERA amenity schedule; building permit0% in schedule; installation not independently verified
Aggregate area of recreational Open SpaceArea not supplied in the RERA schedule; permit separately records 93.82 m² tot-lotRERA amenity schedule; building permit0% in schedule; not independently verified

No clubhouse, indoor recreation facility or sports facility is identified in the supplied evidence. The permit also requires a garbage house within the premises and tree planting along the periphery and in front of the premises; these are permit conditions, not confirmation of completed works.

7. Utilities, building services & safety

The RERA amenity schedule marks water supply, sewerage, rainwater harvesting and the electrical meter room/sub-station/receiving-station category as “YES,” but records 0% progress for its listed items. The schedule does not state water source or storage capacity, an STP design or capacity, sewage-reuse arrangements, storm-water details, electrical supply or backup capacity, or waste-processing capacity. RERA amenities

The building permit requires a rainwater-harvesting structure (percolation pit), records 13 RWHPs, specifies space for a transformer, and requires a garbage house within the premises. It also requires services including sanitation, plumbing, fire-safety requirements, lifts and electrical installations to be executed under qualified technical supervision, and makes provision of necessary fire-fighting installations a responsibility of the owner/builder and technical team. These are permit requirements; the supplied evidence does not establish installation, capacity, commissioning or statutory clearance.

No lift count or capacity, fire-system specification, escape-stair details, accessibility arrangements, CCTV, access-control system, or backup-power provision is supplied. The permit contains a condition referring to facilities for physically handicapped persons for public and semi-public buildings above 300 m²; the supplied record does not establish that such facilities have been provided in this residential project.

8. Location, access & connectivity

The registered location is Prashanth Nagar – Waddepally, Waddepally Revenue Village, Hanamkonda mandal, Warangal Urban district, PIN 506002. The project is identified in the filed permit as being in Ward 49, WADDEPALLY. The permit lists the southern boundary as a 9MT ROAD and contains conditions concerning road frontage, road margins and a service road where required. The supplied evidence does not provide a verified project approach route, public-transport information or measured distances to local landmarks. RERA record Land records

The location dataset includes an approximate 155.4 km distance to the nearest sampled Outer Ring Road interchange; it is an approximate mapped anchor, not a supplied travel-time claim. No further connectivity distances are established in the project evidence. Location record

9. Developer & development status

The registered promoter is AMOGH HOMES LLP, an LLP. The corporate record gives GSTIN 36ABKFA5131DIZT. The project record names POTLABATHINI VIJAY KUMAR and PONNALA SRIKANTH as partners, with Potlabathini Vijay Kumar also listed as authorised signatory. RERA record Corporate record Parties record

The promoter’s RERA filing records a designated account at State Bank of India, Parimala Colony Warangal, with masked account number \\\\\\\*7876 and IFSC SBIN0022052. The supplied record does not provide an independently verified construction-stage assessment, current site photographs, or an occupancy/completion certificate. The Form B declaration states a completion undertaking of 11 June 2027; the project header separately lists a proposed completion date of 11/10/2027. Parties record RERA record

10. Approvals, official records & documents

TG-RERA registration certificate
DetailsForm C; project AMOGH HOMES LAKE VIEW; registration P00300003921, granted under section 5; valid 17/01/2022–11/06/2027
Building permit
DetailsGWMC Building Permit Order 3006/33155/W49/2021, dated 11 June, 2021; one residential building, 1 Stilt + 5 upper floors
EvidenceApprovals record
Building/layout drawing record
DetailsDrawing document 191664, page 1, carries the approval number 3006/33155/W49/2021 and a drawing stamp read from the drawing text layer; the extraction says it needs review. The separate layout-lookup status is unavailable.
EvidenceHMDA
Promoter declaration
DetailsForm B declaration filed for the project, including title and encumbrance declarations and completion undertaking; the extracted promoter-name text is imperfectly rendered.
Title material filed with RERA
DetailsTitle report 210412 and related title-document copies 191661, 191662 and 210414; detailed title-chain review is addressed separately.
Encumbrance material filed with RERA
DetailsEncumbrance statement 210415.
Occupancy/completion record
DetailsNo occupancy or completion certificate is supplied; the building-permit extraction records completion certification as false.
Official land-use / layout status
DetailsHMDA land-use sheet was not confidently assigned; the public layout lookup is reported unavailable in the supplied record. These are unavailable records, not evidence of refusal.
EvidenceHMDA

The building permit states that its permission does not confer ownership rights and requires adherence to the sanctioned plan, commencement/completion notices, and an occupancy certificate before occupation. Its full conditions and any further approval questions are addressed in the approvals review.

Frequently asked questions

Is AMOGH HOMES LAKE VIEW registered with Telangana RERA?

Yes. AMOGH HOMES LAKE VIEW is registered with the Telangana Real Estate Regulatory Authority as P00300003921; the registration status is New Project.

Who is the developer of AMOGH HOMES LAKE VIEW?

The promoter named in the RERA registration is AMOGH HOMES LLP.

Where is AMOGH HOMES LAKE VIEW located?

AMOGH HOMES LAKE VIEW is in HANAMKONDA, Waddepally, Telangana (506002).

When will AMOGH HOMES LAKE VIEW be completed?

The promoter's proposed date of completion filed with RERA is 11/10/2027. This is the promoter's declaration, not a guarantee.