RAVICHANDRA INFRA is a residential apartment project in NEW BAZAR, Mahabubabad, Mahabubabad District, developed by the registered promoter RAVICHANDRA INFRA. The project occupies 5048.22 m² and comprises one residential apartment building with 1 Stilt + 5 upper floors and 90 homes: 55 2BHK units of 30.27 m² each and 35 3BHK units of 44.0 m² each. It is registered with TG-RERA under P00700003424, and the promoter’s original completion undertaking was 31/03/2024.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
8 items to check before you pay, 2 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Field | Record |
|---|---|
| Registered project name | RAVICHANDRA INFRA RERA record |
| Project type | Residential apartment project RERA record |
| Phase / registered portion | Phase not separately identified; the registration and certificates refer to the project/building. Approvals record |
| TG-RERA registration | P00700003424 |
| Registration validity | 24/09/2021 to 31/03/2024; the supplied certificate says the registration was not extended. This is the registration period, not the construction deadline or OC date. |
| Registered promoter | RAVICHANDRA INFRA |
| RERA status | A later architect’s certificate and municipal Occupancy Certificate record completion and OC issuance in March 2026. |
Land and geographic identity
| Field | Record |
|---|---|
| Locality | NEW BAZAR; the building permit also describes the site as Salar Thanda W15. RERA record |
| Revenue village | New Bazar in the project/RERA identity; the filed title report describes the land as Bethole Village. RERA record |
| Mandal | Mahabubabad is stated in the title report and OC; the RERA identity does not disclose a mandal. |
| District / PIN | Mahabubabad / 506101 RERA record |
| Survey numbers and subdivisions in the project registration and building permit | 286/B/2/2/1, 286/A/4, 286/C/4/2, 286/A/2/1, 286/A/3/1, 286/A/3/2, 286/B/3/3/1, 286/B/2/2/2, 286/B/4/4/1 |
| Registered site extent | 5048.22 m² |
| Total / net site area | 5048.22 m²; road-affected area recorded as 0. |
| Boundaries in RERA land details | East: VACANT LAND; West: VACANT LAND; North: VACANT LAND; South: ROAD WIDTH-12. Land records |
Development identity
| Field | Record |
|---|---|
| Sanctioning authority | Mahabubabad Municipality |
| Principal building permit | 3003/W15/2021/2208, approved 15 July 2021 |
| Sanctioned building configuration | One residential apartment building; 1 Stilt + 5 upper floors |
| Sanctioned height | 14.95 m |
| Approved built-up area | The supplied building-permit extraction itemises 10,785.55 for residential upper floors and 3,318.27 for the stilt; it does not provide a single approved total built-up-area figure in the extracted fields. |
| Buildings / towers | One building / tower RERA record |
| Parking levels | Stilt approved for parking; a cellar is not identified in the supplied permit extraction. |
| Approved versus RERA-declared units | The RERA filing records 90 units: 55 2BHK and 35 3BHK. The permit requires the sanctioned unit count not be increased, but the supplied permit extraction does not state a unit total. RERA unit table |
Offering and status
| Field | Record |
|---|---|
| RERA-filed unit types and saleable areas | 2BHK: 55 units, 30.27 m² each; 3BHK: 35 units, 44.0 m² each. RERA unit table |
| Booked / available | 2BHK: 2 booked / 53 available; 3BHK: 2 booked / 33 available. These are portal counts with no supplied as-of date and are indicative. RERA unit table |
| Construction stage | An architect’s certificate dated 19.03.2026 certifies project completion; the municipal OC records building completion on 26/02/2026. These are documentary completion records, not a current site inspection. |
| Original completion undertaking | 31/03/2024, as declared in the promoter’s Form B. |
| Occupancy certificate | Municipal OC dated 09/03/2026; certificate reference 015596/MAHD/00019/SWOC/2026 is recorded in the filed OC document. The supplied architect certificate records 015596/MAHD/00019 VSWOC/2026. The OC is for the apartment building/project, not separately identified phases or towers. |
2. The project story
RAVICHANDRA INFRA is registered with TG-RERA as a residential apartment project on a 5048.22 m² site, with one apartment building sanctioned as 1 Stilt + 5 upper floors. The project is associated in the records with New Bazar and Salar Thanda W15, Mahabubabad; the filed title report and municipal OC describe the land as Bethole Village. RERA record
The RERA filing lists 90 homes—55 2BHK and 35 3BHK. The registration certificate ran from 24/09/2021 to 31/03/2024, and the promoter’s Form B undertook completion by 31/03/2024. A later architect’s certificate states the project was complete, and the municipality issued an OC dated 09/03/2026. The records therefore document a completed, occupancy-certified building after the original declared completion date; they do not provide independent on-site verification. RERA unit table
3. Master plan, architecture & building design
The building permit identifies one residential apartment building on a 5048.22 m² site, with 1 Stilt + 5 upper floors and a sanctioned height of 14.95 m. It records 10,785.55 for residential upper floors, 3,318.27 for the stilt and a 652.52 m² tot-lot. These are permit-extracted areas; the supplied material does not separately establish a floor-by-floor schedule, building footprint, FSI-counted area or carpet area at building level.
The permit records 14% open space and requires the tot-lot to be fenced and maintained as greenery. It also specifies peripheral tree planting and greenery, rainwater-harvesting structures, transformer space and a garbage house.
The supplied layout drawing extraction identifies 12 numbered plots, but does not provide plot sizes or a complete plot schedule; it is not enough to establish a detailed site arrangement for the apartment building. Layout record
4. Homes, configurations & floor plans
The TG-RERA filing lists the following unit counts and saleable areas. Booking figures are portal readings with no supplied as-of date. RERA unit table RERA unit table
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK | 55 | 2 | 53 | 30.27 m² | Not available | Not supplied |
| 3BHK | 35 | 2 | 33 | 44.0 m² | Not available | Not supplied |
The floor-plan dataset reports two drawings, one measured and one with no flats, but no usable measured flat designs or carpet-area results for either configuration. Accordingly, no drawing-based room layout or software-measured carpet area can be reported. The RERA-filed saleable area is not identified as carpet area in the supplied unit record. Floor plans RERA unit details
5. Parking & vehicle circulation
The building permit states that the stilt is approved for parking and requires it to be used exclusively for vehicle parking, without partition walls or rolling shutters. The municipal OC records a parking area of 3318.3 m². The supplied records do not establish the number of sanctioned parking bays, any visitor or accessible spaces, parking allocation to individual units, a vehicle ramp or pedestrian/vehicle separation. A parking-area figure does not by itself establish exclusive unit allocation.
6. Amenities, recreation & open spaces
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Tot-lot | 652.52 m²; permit requires fencing and maintenance as greenery | Building permit | Sanctioned; completion not independently verified. |
| Tree planting / peripheral greenery | Tree plantation along the periphery and in front; peripheral greenery to be maintained | Building permit | Required by permit; completion not independently verified. |
| Rainwater-harvesting structures | Permit specifies 6 rainwater-harvesting pits in the OC extraction | Building permit and OC | Sanctioned; OC records six pits. |
| Internal roads and footpaths | No size supplied | RERA amenity filing | 100% declared. RERA amenities |
| Water supply | No source or capacity supplied | RERA amenity filing | 100% declared. RERA amenities |
| Sewerage | Filing lists chambers, lines, septic tank and STP | RERA amenity filing | 100% declared for “Sewerage (Chamber, Lines, Septic Tank, STP)”. RERA amenities |
| Storm-water drains | No size supplied | RERA amenity filing | 50% declared. RERA amenities |
| Street lighting | No quantity supplied | RERA amenity filing | 100% declared. RERA amenities |
| Sewage and sullage treatment/disposal | No capacity supplied | RERA amenity filing | 40% declared. RERA amenities |
| Solid-waste management and disposal | No system details supplied | RERA amenity filing | 40% declared. RERA amenities |
| Energy management | No system details supplied | RERA amenity filing | 25% declared. RERA amenities |
| Fire protection and safety requirements | No system details supplied | RERA amenity filing | 10% declared. RERA amenities |
| Electrical meter room / sub-station / receiving station | No capacity supplied | RERA amenity filing | 25% declared. RERA amenities |
| Green strip / tot-lot / park; community buildings; aggregate recreational open space | No additional details supplied | RERA amenity filing | Each recorded at 0% in the amenity data. RERA amenities |
The amenity percentages are RERA-filed progress declarations, not independent verification of facility delivery. The permit also requires a garbage house and transformer space within the site. RERA amenities
7. Utilities, building services & safety
The permit requires rainwater harvesting, transformer space, a garbage house and execution of sanitation, plumbing, fire-safety requirements, lifts and electrical installations under qualified technical supervision. It also requires a completion notice and occupancy certificate before occupation. These are permit conditions; the supplied extracts do not provide system capacities or confirm each service’s as-built installation.
The RERA amenity data records water supply and sewerage at 100%, storm-water drains at 50%, sewage/sullage treatment and solid-waste management at 40%, energy management and electrical meter-room/sub-station/receiving-station facilities at 25%, and fire protection/safety at 10%. These are declared progress figures, not a technical inspection or certification of compliance. No water source or storage capacity, STP capacity, backup-power provision, lift count/capacity, CCTV, access-control system or accessibility details are supplied. RERA amenities
8. Location, access & connectivity
The registered project identity places the site in NEW BAZAR, Mahabubabad, Telangana, PIN 506101. The building permit calls the location Salar Thanda W15, and the title report and OC identify Bethole Village. The RERA land record gives the south boundary as ROAD WIDTH-12; the permit also refers to an 18M road and contains a road-related condition. RERA record Land records
No verified local public-transport details, approach-road route or nearby landmark distances are supplied. The available location dataset includes a geocode and an anchor labelled Financial District (Nanakramguda), 1.2 km away; the supplied records do not establish this as project-specific travel or road-network connectivity. Location record
9. Developer & development status
The registered promoter is RAVICHANDRA INFRA, identified in the RERA filing as a partnership. The supplied corporate identifier is GSTIN 36ABAFR9539C1Z4. The registration certificate gives the promoter’s office location only as Village: [blank], Mandal: [blank], District: Mahabubabad, PIN 506101; the project filing separately lists an address in Doctors Colony, New Bazar, Mahabubabad. Corporate record RERA filing RERA filing
The project’s RERA-filed completion undertaking was 31/03/2024. The architect’s certificate records completion and the municipal OC is dated 09/03/2026. The supplied records do not provide a revised completion undertaking or a current construction-progress inspection.
10. Approvals, official records & documents
| Identifier / date | P00700003424; issued 24/09/2021; valid to 31/03/2024 |
|---|---|
| What the supplied record establishes | Registration of RAVICHANDRA INFRA; certificate records the promoter’s registration conditions. |
| Identifier / date | 3003/W15/2021/2208; 15 July 2021 |
|---|---|
| What the supplied record establishes | Mahabubabad Municipality permit for one residential apartment building, 1 Stilt + 5 upper floors. |
| Identifier / date | August 2021; day not stated |
|---|---|
| What the supplied record establishes | Promoter declaration of title and no encumbrances, with a completion undertaking of 31/03/2024. |
| Identifier / date | 10-08-2021 |
|---|---|
| What the supplied record establishes | Advocate’s report concerning 6074 Sq. Yards of open land at Bethole Village, Mahabubabad Mandal. |
| Identifier / date | 19.03.2026; OC reference 015596/MAHD/00019 VSWOC/2026, dated 09/03/2026 |
|---|---|
| What the supplied record establishes | Architect certifies completion of the registered project and records an occupancy certificate. |
| Identifier / date | Issued 09/03/2026; file no. 015596/MAHD/00019/SWOC/2026 |
|---|---|
| What the supplied record establishes | Mahabubabad Municipality OC for the residential building; records completion details and parking area. |
| Identifier / date | Drawing document 182938 |
|---|---|
| What the supplied record establishes | One layout sheet is recorded; extracted plot count is 12, with no complete plot-size schedule. Layout record |
The supplied registration certificate, building permit, completion certificate and OC provide the principal project records summarized above. The supplied material does not include extracted floor-by-floor plans or a complete layout approval schedule.
1. Project at a glance
Project identity
Registered project name: RAVICHANDRA INFRA
Project type: Residential apartment project
Phase / registered portion: Phase not separately identified; the registration and certificates refer to the project/building.
TG-RERA registration: P00700003424
Registration validity: 24/09/2021 to 31/03/2024; the supplied certificate says the registration was not extended. This is the registration period, not the construction deadline or OC date.
Registered promoter: RAVICHANDRA INFRA
RERA status: A later architect’s certificate and municipal Occupancy Certificate record completion and OC issuance in March 2026.
Land and geographic identity
Locality: NEW BAZAR; the building permit also describes the site as Salar Thanda W15.
Revenue village: New Bazar in the project/RERA identity; the filed title report describes the land as Bethole Village.
Mandal: Mahabubabad is stated in the title report and OC; the RERA identity does not disclose a mandal.
District / PIN: Mahabubabad / 506101
Survey numbers and subdivisions in the project registration and building permit: 286/B/2/2/1, 286/A/4, 286/C/4/2, 286/A/2/1, 286/A/3/1, 286/A/3/2, 286/B/3/3/1, 286/B/2/2/2, 286/B/4/4/1
Registered site extent: 5048.22 m²
Total / net site area: 5048.22 m²; road-affected area recorded as 0.
Boundaries in RERA land details: East: VACANT LAND; West: VACANT LAND; North: VACANT LAND; South: ROAD WIDTH-12.
Development identity
Sanctioning authority: Mahabubabad Municipality
Principal building permit: 3003/W15/2021/2208, approved 15 July 2021
Sanctioned building configuration: One residential apartment building; 1 Stilt + 5 upper floors
Sanctioned height: 14.95 m
Approved built-up area: The supplied building-permit extraction itemises 10,785.55 for residential upper floors and 3,318.27 for the stilt; it does not provide a single approved total built-up-area figure in the extracted fields.
Buildings / towers: One building / tower
Parking levels: Stilt approved for parking; a cellar is not identified in the supplied permit extraction.
Approved versus RERA-declared units: The RERA filing records 90 units: 55 2BHK and 35 3BHK. The permit requires the sanctioned unit count not be increased, but the supplied permit extraction does not state a unit total.
Offering and status
RERA-filed unit types and saleable areas: 2BHK: 55 units, 30.27 m² each; 3BHK: 35 units, 44.0 m² each.
Booked / available: 2BHK: 2 booked / 53 available; 3BHK: 2 booked / 33 available. These are portal counts with no supplied as-of date and are indicative.
Construction stage: An architect’s certificate dated 19.03.2026 certifies project completion; the municipal OC records building completion on 26/02/2026. These are documentary completion records, not a current site inspection.
Original completion undertaking: 31/03/2024, as declared in the promoter’s Form B.
Occupancy certificate: Municipal OC dated 09/03/2026; certificate reference 015596/MAHD/00019/SWOC/2026 is recorded in the filed OC document. The supplied architect certificate records 015596/MAHD/00019 VSWOC/2026. The OC is for the apartment building/project, not separately identified phases or towers.
2. The project story
RAVICHANDRA INFRA is registered with TG-RERA as a residential apartment project on a 5048.22 m² site, with one apartment building sanctioned as 1 Stilt + 5 upper floors. The project is associated in the records with New Bazar and Salar Thanda W15, Mahabubabad; the filed title report and municipal OC describe the land as Bethole Village.
The RERA filing lists 90 homes—55 2BHK and 35 3BHK. The registration certificate ran from 24/09/2021 to 31/03/2024, and the promoter’s Form B undertook completion by 31/03/2024. A later architect’s certificate states the project was complete, and the municipality issued an OC dated 09/03/2026. The records therefore document a completed, occupancy-certified building after the original declared completion date; they do not provide independent on-site verification.
3. Master plan, architecture & building design
The building permit identifies one residential apartment building on a 5048.22 m² site, with 1 Stilt + 5 upper floors and a sanctioned height of 14.95 m. It records 10,785.55 for residential upper floors, 3,318.27 for the stilt and a 652.52 m² tot-lot. These are permit-extracted areas; the supplied material does not separately establish a floor-by-floor schedule, building footprint, FSI-counted area or carpet area at building level.
The permit records 14% open space and requires the tot-lot to be fenced and maintained as greenery. It also specifies peripheral tree planting and greenery, rainwater-harvesting structures, transformer space and a garbage house.
The supplied layout drawing extraction identifies 12 numbered plots, but does not provide plot sizes or a complete plot schedule; it is not enough to establish a detailed site arrangement for the apartment building.
4. Homes, configurations & floor plans
The TG-RERA filing lists the following unit counts and saleable areas. Booking figures are portal readings with no supplied as-of date.
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK | 55 | 2 | 53 | 30.27 m² | Not available | Not supplied |
| 3BHK | 35 | 2 | 33 | 44.0 m² | Not available | Not supplied |
The floor-plan dataset reports two drawings, one measured and one with no flats, but no usable measured flat designs or carpet-area results for either configuration. Accordingly, no drawing-based room layout or software-measured carpet area can be reported. The RERA-filed saleable area is not identified as carpet area in the supplied unit record.
5. Parking & vehicle circulation
The building permit states that the stilt is approved for parking and requires it to be used exclusively for vehicle parking, without partition walls or rolling shutters. The municipal OC records a parking area of 3318.3 m². The supplied records do not establish the number of sanctioned parking bays, any visitor or accessible spaces, parking allocation to individual units, a vehicle ramp or pedestrian/vehicle separation. A parking-area figure does not by itself establish exclusive unit allocation.
6. Amenities, recreation & open spaces
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Tot-lot | 652.52 m²; permit requires fencing and maintenance as greenery | Building permit | Sanctioned; completion not independently verified. |
| Tree planting / peripheral greenery | Tree plantation along the periphery and in front; peripheral greenery to be maintained | Building permit | Required by permit; completion not independently verified. |
| Rainwater-harvesting structures | Permit specifies 6 rainwater-harvesting pits in the OC extraction | Building permit and OC | Sanctioned; OC records six pits. |
| Internal roads and footpaths | No size supplied | RERA amenity filing | 100% declared. |
| Water supply | No source or capacity supplied | RERA amenity filing | 100% declared. |
| Sewerage | Filing lists chambers, lines, septic tank and STP | RERA amenity filing | 100% declared for “Sewerage (Chamber, Lines, Septic Tank, STP)”. |
| Storm-water drains | No size supplied | RERA amenity filing | 50% declared. |
| Street lighting | No quantity supplied | RERA amenity filing | 100% declared. |
| Sewage and sullage treatment/disposal | No capacity supplied | RERA amenity filing | 40% declared. |
| Solid-waste management and disposal | No system details supplied | RERA amenity filing | 40% declared. |
| Energy management | No system details supplied | RERA amenity filing | 25% declared. |
| Fire protection and safety requirements | No system details supplied | RERA amenity filing | 10% declared. |
| Electrical meter room / sub-station / receiving station | No capacity supplied | RERA amenity filing | 25% declared. |
| Green strip / tot-lot / park; community buildings; aggregate recreational open space | No additional details supplied | RERA amenity filing | Each recorded at 0% in the amenity data. |
The amenity percentages are RERA-filed progress declarations, not independent verification of facility delivery. The permit also requires a garbage house and transformer space within the site.
7. Utilities, building services & safety
The permit requires rainwater harvesting, transformer space, a garbage house and execution of sanitation, plumbing, fire-safety requirements, lifts and electrical installations under qualified technical supervision. It also requires a completion notice and occupancy certificate before occupation. These are permit conditions; the supplied extracts do not provide system capacities or confirm each service’s as-built installation.
The RERA amenity data records water supply and sewerage at 100%, storm-water drains at 50%, sewage/sullage treatment and solid-waste management at 40%, energy management and electrical meter-room/sub-station/receiving-station facilities at 25%, and fire protection/safety at 10%. These are declared progress figures, not a technical inspection or certification of compliance. No water source or storage capacity, STP capacity, backup-power provision, lift count/capacity, CCTV, access-control system or accessibility details are supplied.
8. Location, access & connectivity
The registered project identity places the site in NEW BAZAR, Mahabubabad, Telangana, PIN 506101. The building permit calls the location Salar Thanda W15, and the title report and OC identify Bethole Village. The RERA land record gives the south boundary as ROAD WIDTH-12; the permit also refers to an 18M road and contains a road-related condition.
No verified local public-transport details, approach-road route or nearby landmark distances are supplied. The available location dataset includes a geocode and an anchor labelled Financial District (Nanakramguda), 1.2 km away; the supplied records do not establish this as project-specific travel or road-network connectivity.
9. Developer & development status
The registered promoter is RAVICHANDRA INFRA, identified in the RERA filing as a partnership. The supplied corporate identifier is GSTIN 36ABAFR9539C1Z4. The registration certificate gives the promoter’s office location only as Village: [blank], Mandal: [blank], District: Mahabubabad, PIN 506101; the project filing separately lists an address in Doctors Colony, New Bazar, Mahabubabad.
The project’s RERA-filed completion undertaking was 31/03/2024. The architect’s certificate records completion and the municipal OC is dated 09/03/2026. The supplied records do not provide a revised completion undertaking or a current construction-progress inspection.
10. Approvals, official records & documents
| Identifier / date | P00700003424; issued 24/09/2021; valid to 31/03/2024 |
|---|---|
| What the supplied record establishes | Registration of RAVICHANDRA INFRA; certificate records the promoter’s registration conditions. |
| Identifier / date | 3003/W15/2021/2208; 15 July 2021 |
|---|---|
| What the supplied record establishes | Mahabubabad Municipality permit for one residential apartment building, 1 Stilt + 5 upper floors. |
| Identifier / date | August 2021; day not stated |
|---|---|
| What the supplied record establishes | Promoter declaration of title and no encumbrances, with a completion undertaking of 31/03/2024. |
| Identifier / date | 10-08-2021 |
|---|---|
| What the supplied record establishes | Advocate’s report concerning 6074 Sq. Yards of open land at Bethole Village, Mahabubabad Mandal. |
| Identifier / date | 19.03.2026; OC reference 015596/MAHD/00019 VSWOC/2026, dated 09/03/2026 |
|---|---|
| What the supplied record establishes | Architect certifies completion of the registered project and records an occupancy certificate. |
| Identifier / date | Issued 09/03/2026; file no. 015596/MAHD/00019/SWOC/2026 |
|---|---|
| What the supplied record establishes | Mahabubabad Municipality OC for the residential building; records completion details and parking area. |
| Identifier / date | Drawing document 182938 |
|---|---|
| What the supplied record establishes | One layout sheet is recorded; extracted plot count is 12, with no complete plot-size schedule. |
The supplied registration certificate, building permit, completion certificate and OC provide the principal project records summarized above. The supplied material does not include extracted floor-by-floor plans or a complete layout approval schedule.
Frequently asked questions
Is RAVICHANDRA INFRA registered with Telangana RERA?
Yes. RAVICHANDRA INFRA is registered with the Telangana Real Estate Regulatory Authority as P00700003424; the registration status is New Project.
Who is the developer of RAVICHANDRA INFRA?
The promoter named in the RERA registration is RAVICHANDRA INFRA.
Where is RAVICHANDRA INFRA located?
RAVICHANDRA INFRA is in NEW BAZAR, Mahabubabad, Telangana (506101).
When will RAVICHANDRA INFRA be completed?
The promoter's proposed date of completion filed with RERA is 31/03/2024. This is the promoter's declaration, not a guarantee.