NIRMAN H.M.T HEIGHTS is a residential apartment project in ANDHRA KESARI NAGAR, Hayathnagar mandal, Ranga Reddy district, developed by the registered promoter Nirman Builders And Developers, a partnership. The project records a land extent of 561.69 m2, one building with 1 Stilt + 5 upper floors, and 15 2BHK units. Its TG-RERA registration number is P02400002603, and the proposed and revised proposed completion date is 06/07/2025.

01What we found

Period endedTG-RERA registration ran to 6 Jul 2025 - check its extension on TG-RERA
13documents on file - each fact links to its page
60court cases on this project's land (survey 2, 3, 4, 6, 8, Saheb Nagar)
9items to check - 3 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

9 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

Photo from nobroker.inPhoto from brokernetwork.in
▦ View all 2 photos
Saheb Nagar, Hayathnagar, Ranga Reddy · geocoded — approximate.

1. Project at a glance

Project identity

ItemProject record
Registered project nameNIRMAN H.M.T HEIGHTS RERA record
Project type / registered portionResidential apartment project; one building is identified in the filed building permit. The evidence does not identify a separately named phase. RERA record
TG-RERA registrationP02400002603
Registration validityCertificate states validity from 23/02/2021 to 06/07/2025; the supplied record shows no extension. This is registration validity, not the completion deadline.
Registered promoter / entity typeNirman Builders And Developers; partnership. RERA record RERA filing Corporate record
TG-RERA statusThe filing identifies the project as “On-Going Project.” The supplied certificate records registration under section 5. RERA filing

Land and geographic identity

ItemProject record
LocalityANDHRA KESARI NAGAR RERA filing
Revenue villageSAHEB NAGAR in the RERA project identity; the filed approval and occupancy certificate identify SAHEBNAGAR KALAN. RERA record
Mandal / district / PINHayathnagar / Ranga Reddy / 500070 RERA record
Project survey numbers and subdivisionsRERA certificate: 2, 3, 4, 5, 6.7PART, 8 PART. Building-permit and OC extracts: 2, 3, 4, 5, 6, 7-PART, 8-PART. The supplied extracts do not explain the survey-number rendering.
Plot reference146, 147, 148 WEST PART
Site extent561.69 m2; the permit and OC extracts each record net area as 561.69 and road-affected area as 0.
BoundariesEast: PLOT NO 148 EAST; West: PLOT NO 145; North: NEIGHBOURS LAND; South: ROAD. RERA filing

Development identity

ItemProject record
Sanctioning authorityGreater Hyderabad Municipal Corporation (GHMC)
Principal building approval2/C3/10567/2019, dated 06 July, 2019 Approvals record
Approved building form1 Stilt + 5 upper floors in the building-permit extract
Approved built-up area1,667.11 sq m as recorded in the RERA filing RERA filing
Building / block countOne building is recorded in the project filing. RERA filing
Units15 units in the RERA unit record; the building-permit extract also records that the sanctioned number of units must not be increased without prior GHMC approval. RERA unit table
ParkingThe OC extract records parking area as 1,389.0 m2 in the sanctioned plan and 1309 2 in the site building plan; a car-space count or allocation is not established in the supplied record.

Offering and status

ItemProject record
RERA-filed configuration2BHK, 15 units RERA unit table
RERA-filed saleable area785.1 sq m for the recorded configuration RERA unit table
Booked / available8 booked / 7 available; portal record has no stated as-of date, so counts are indicative. RERA unit table
Construction stageNo independently verified current construction-progress assessment is supplied. The project is recorded as ongoing in the RERA filing. RERA filing
Completion datesRERA project record: proposed and revised proposed completion 06/07/2025. Form B declaration dated 02 March 2020 states an undertaking to complete by 02/07/2025. RERA filing
Occupancy certificateGHMC OC extract for the building records issue date 15 April, 2021, completion notice submission 07 March, 2021, and declares the building fit for occupation. Its stated scope is the building at Plot Nos. 146, 147 & 148 W-PART.

2. The project story

NIRMAN H.M.T HEIGHTS is registered as a residential apartment project in Andhra Kesari Nagar, Hayathnagar, Ranga Reddy district. The RERA record identifies one building and 15 apartments, all filed as 2BHK; it shows eight booked and seven available, with no booking-record as-of date supplied. RERA record RERA filing RERA filing RERA unit table

The GHMC building permit extract describes a proposed residential building of 1 Stilt + 5 upper floors. A later GHMC occupancy-certificate extract identifies the building at Plot Nos. 146, 147 & 148 W-PART and states it was inspected and declared fit for occupation. The certificate’s scope is that building; the evidence does not establish a separate OC for any other project portion.

The RERA filing’s proposed and revised completion date is 06/07/2025. The supplied evidence does not include a current, independently verified construction-progress report; the portal’s “On-Going Project” label should not be treated as a site inspection or current work-status confirmation. RERA filing

3. Master plan, architecture & building design

The RERA filing records a 561.69 sq m site and 1,667.11 sq m approved built-up area. The GHMC permit extract identifies one residential building, 1 Stilt + 5 upper floors, with building height stated as 15 m. These are approved or filed figures, not software measurements. RERA filing RERA filing

The occupancy-certificate extract describes the building as “Cellar + Stilt, Ground +Upper Floors, 5 Upper Floor.” The supplied material does not include a reviewable floor-plan drawing from which to describe typical floor layouts, flat placement, lifts, stairs, entries, circulation, or open-space arrangement. Document index

The permit extract lists a tot-lot, transformer space, garbage house and rainwater-harvesting percolation pit as requirements or site provisions. It also records 25 trees and 2 rainwater-harvesting structures. The OC extract records a sanctioned tot-lot area of 263.45 m2 and site-building-plan tot-sot area of 253.45 m2.

4. Homes, configurations & floor plans

The RERA filing records 15 2BHK units, with 8 booked and 7 available. The recorded saleable area is 785.1 sq m. This is the filed saleable-area figure; it is not a carpet-area measurement. The unit record has no booking-count as-of date. RERA unit table

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
2BHK1587785.1 sq mNot supplied for a configuration matched to the RERA filingNot supplied

The supplied drawing-measurement record does not provide a reliable carpet-area figure for the RERA-filed 2BHK configuration. Its measured drawing record is marked as an unmatched 4BHK configuration, with two implausible measurements held back; those figures are not used as the project’s RERA unit-area disclosure. Floor plans RERA unit details

Carpet area, balcony or utility space, common-area share and saleable area are distinct measurements. No project-specific carpet-area, balcony/utility-area or loading figure can be established from the supplied evidence.

5. Parking & vehicle circulation

The occupancy-certificate extract records 1,389.0 m2 of parking area in the sanctioned plan and 1309 2 in the site building plan. The supplied record does not establish the number or type of parking spaces, whether spaces are resident, visitor or accessible, any parking-level layout, ramps, EV charging, or unit-wise parking allocation. A parking area entry does not by itself establish exclusive ownership or allocation to a particular apartment. RERA filing

6. Amenities, recreation & open spaces

The project amenity record gives the following declared availability and progress percentages. These are RERA-recorded entries; they are not independent verification of present condition. RERA amenities

FacilityDescription / sizeEvidence sourceDeclared progress / verified status
Green Strip / TOT LOT / ParkSize not supplied in the amenity entry; permit extract records tot-lot area 263.45 m2 sanctioned and 253.45 m2 in the site building plan.RERA amenitiesRERA amenity entry: 100%; independent completion verification not supplied.
Aggregate recreational open spaceSize not suppliedRERA amenitiesRERA entry: 100%; independent completion verification not supplied.
Community buildingsSize and facilities not suppliedRERA amenities0% in RERA amenity entry.
Internal roads & footpathsDetails not suppliedRERA amenities0% in RERA amenity entry.

The permit extract also lists a garbage house, transformer space and rainwater-harvesting structure, addressed under utilities and services below. A third-party listing names a clubhouse, swimming pool, gym, children’s play area and covered car parking, but these are not established as RERA-filed or independently verified facilities and are not treated here as project-delivery commitments. Promoter website

7. Utilities, building services & safety

ServiceSupplied project evidence
WaterRERA amenity record marks Water Supply 100%. The third-party listing describes water supply as borewell; this is not stated in the supplied RERA project record. RERA amenities Promoter website
Sewerage and drainageRERA amenity record marks Sewerage (Chamber, Lines, Septic Tank, STP) 100%. Storm Water Drains are recorded at 0%; treatment and disposal of sewage and sullage water is recorded at 0%. RERA amenities
Rainwater harvestingRERA amenity record marks water conservation/rainwater harvesting 100%. The GHMC permit extract requires a rainwater-harvesting percolation pit and records 2 RWHPs. RERA amenities
ElectricalRERA amenity record marks Energy management and Electrical Meter Room, Sub-Station, Receiving Station 100%. The permit extract requires transformer space. Capacities and independent operational verification are not supplied. RERA amenities
Fire and life safetyRERA amenity record marks Fire Protection and Fire Safety Requirements 100%. The supplied material does not detail systems, capacities, escape stairs or fire-access arrangements. RERA amenities
WastePermit extract requires a garbage house. RERA amenity entry for Solid Waste Management and Disposal is 0%. RERA amenities
Lifts, backup, security and accessibilityNo project-specific information or capacities supplied. Document index

The amenity percentages are filing entries, not a substitute for commissioning records or statutory clearances.

8. Location, access & connectivity

The registered location is Andhra Kesari Nagar, revenue village SAHEB NAGAR, Hayathnagar mandal, Ranga Reddy district, Telangana 500070. The GHMC building-permit and OC extracts identify the site locality as Andhra Kesari Nagar and village as SAHEBNAGAR KALAN. RERA record RERA filing

The location record gives a sampled nearest Outer Ring Road interchange at approximately 4.8 km. This is a supplied distance estimate, not a travel-time claim. No verified public-transport routes, approach-road measurements or project-specific landmark distances are provided. Location record

9. Developer & development status

The registered promoter is Nirman Builders And Developers, recorded as a partnership. The supplied RERA identity names partner NAVEEN PUNARIYA and authorised signatory ANAND KUMAR SAKRIYA. The RERA certificate gives the promoter office as Village Champapet, Saroornagar mandal, Ranga Reddy district, PIN 500079. RERA filing Parties record

The RERA filing records five landowners with area-share arrangements: SHIV A KUMAR ROUTALYE, SAPNA, MANISHA, NANDLAL, and K MEGHANA. Parties record The Form B affidavit-cum-declaration is signed by ANAND KUMAR SAKRIYA on 02 March 2020 and states a completion undertaking of 02/07/2025. This is a promoter-side declaration, not independently verified progress.

The project record shows proposed and revised completion as 06/07/2025. No current construction-progress certificate is supplied. The supplied GHMC OC extract applies to the identified building at Plot Nos. 146, 147 & 148 W-PART. RERA filing

10. Approvals, official records & documents

TG-RERA registration certificate
Identifier / dateP02400002603; issued 23/02/2021; valid through 06/07/2025
What the supplied record establishesForm C registration for NIRMAN H.M.T HEIGHTS; certificate records separate-account and other promoter conditions.
GHMC building permit
Identifier / date2/C3/10567/2019; 06 July, 2019
What the supplied record establishesPermit extract for one proposed residential building, 1 Stilt + 5 upper floors, at site extent 561.69 m2.
GHMC occupancy certificate
Identifier / dateApplication 2/C3/05799/2021-OC; proceedings 2/C3/05535/2021; issued 15 April, 2021
What the supplied record establishesExtract records the building at Plot Nos. 146, 147 & 148 W-PART as inspected and fit for occupation; completion notice submission recorded as 07 March, 2021.
RERA Form B declaration
Identifier / date02 March 2020
What the supplied record establishesPromoter-side affidavit includes title, encumbrance, completion and fund-handling declarations.
Approved layout / floor-plan set
Identifier / dateNot available for review in the supplied material
What the supplied record establishesDetailed layout and drawing-derived room, circulation and parking information cannot be established here. Document index

Frequently asked questions

Is NIRMAN H.M.T HEIGHTS registered with Telangana RERA?

Yes. NIRMAN H.M.T HEIGHTS is registered with the Telangana Real Estate Regulatory Authority as P02400002603; the registration status is On-Going Project.

Who is the developer of NIRMAN H.M.T HEIGHTS?

The promoter named in the RERA registration is NIRMAN BUILDERS AND DEVELOPERS.

Where is NIRMAN H.M.T HEIGHTS located?

NIRMAN H.M.T HEIGHTS is in ANDHRA KESARI NAGAR, SAHEB NAGAR, Hayathnagar, Rangareddy, Telangana (500070).

When will NIRMAN H.M.T HEIGHTS be completed?

The promoter's proposed date of completion filed with RERA is 06/07/2025. This is the promoter's declaration, not a guarantee.