PLATINUM RESIDENCY is a residential apartment project in Miyapur, Hyderabad district; the mandal is not disclosed. The registered promoter is IREDDY CONSTRUCTIONS, and the project occupies 384.54 m², with one proposed residential building comprising 1 Stllt + 5 upper floors and 10 apartments: five 2BHK and five 3BHK. Its TG-RERA registration number is P02500003523, and the promoter’s Form-B declaration states a proposed completion date of 14/08/2023.

More from Ireddy Constructions · 2 projects →

01What we found

Period endedTG-RERA registration ran to 14 Aug 2023 - check its extension on TG-RERA
10documents on file - each fact links to its page
0court cases on this project's land in the court records searched
7items to check - 4 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

7 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

1. Project at a glance

Project identity

ItemRecord
Registered project namePLATINUM RESIDENCY RERA record
Project typeResidential apartment project RERA record RERA filing
Phase / registered portionPhase not separately identified in the supplied record; the registration is for this project.
TG-RERA registrationP02500003523; registration certificate issued 21/10/2021, valid through 14/08/2023. RERA record
Registered promoterIREDDY CONSTRUCTIONS RERA record
RERA statusCertificate records the validity period above; no extension is recorded in the supplied evidence.

Land and geographic identity

ItemRecord
Locality / revenue villageMiyapur / Miyapur Village RERA record Land records
MandalNot disclosed Land records
District / PINHyderabad / 500049 RERA record RERA filing
Survey number(s)Survey No. 111; no subdivision is stated in the supplied project identity record. RERA record Land records
Plot / registered site extentPart of Plot 173 and 174; site area 384.54 m². RERA filing
Total / net areaTotal area 384.54 m²; net area 384.54 m² in the RERA filing. The permit separately records a 5 m² road-affected portion surrendered to GHMC and also states net area 384.54 m². RERA filing
BoundariesEast: Plot No. 171 and 172; West: road width 9; North: Plot No. 175; South: Plot No. 173 part. RERA filing

Development identity

ItemRecord
Sanctioning authorityGreater Hyderabad Municipal Corporation (GHMC) Approvals record
Principal building approvalBuilding Permit Order 2/C21/09140/2021, approved 14 August 2021; associated file number 2/C21/07403/2021. Approvals record
Approved built-up areaThe RERA filing records approved built-up area as 1357.50 m². The permit extraction separately lists residential area 1,131.25 m² and parking area 212.15 m²; these are reproduced as recorded and are not treated as interchangeable area measures. RERA filing
Building count and floorsOne proposed residential building: 1 Stllt + 5 upper floors; permit records height 14.99 m.
Parking provisionPermit records 1 parking floor with area 212.15 m²; its condition says approved cellar/stilt parking is to be used exclusively for vehicle parking. No parking-space count is supplied.
Unit countGHMC permit extraction states num_units: 5; the RERA filing records 10 total building units, comprising five 2BHK and five 3BHK units. The scope of the permit’s extracted unit figure is not clarified here. RERA filing RERA unit table

Offering and status

ItemRecord
RERA-filed configurations2BHK: 5 units; 3BHK: 5 units RERA unit table RERA unit details
RERA-filed saleable area2BHK: 98.6 m²; 3BHK: 113.12 m² RERA unit table RERA unit details
Booked / availableRERA portal extract records 0 booked and 5 available for each configuration (10 available total). Counts are indicative: the portal record has no as-of date. RERA unit table RERA unit details
Construction stageNot disclosed in the supplied TG-RERA project evidence; no independently verified site-progress record is provided. Document index RERA amenities
Completion datePromoter’s Form-B declaration states 14/08/2023 as the completion undertaking; the registration certificate also ends 14/08/2023. These are distinct recorded dates serving different purposes.
Occupancy / completion certificateNo occupancy or completion certificate is included in the supplied evidence. The GHMC permit requires an occupancy certificate before occupation.

2. The project story

PLATINUM RESIDENCY is registered with TG-RERA as a residential apartment project on part of Plot 173 and 174 in Miyapur Village, Survey No. 111, Hyderabad. The project record describes one building on a 384.54 m² site, with the GHMC permit allowing one stilt and five upper floors. RERA record Land records

The RERA filing offers ten apartments: five 2BHK and five 3BHK units. The portal extract lists all ten as available and none as booked, but provides no as-of date. RERA unit table RERA unit details

The supplied documents establish the registration, permit and promoter’s proposed completion undertaking; they do not establish current construction progress, completed portions or an issued occupancy certificate.

3. Master plan, architecture & building design

The GHMC Building Permit Order identifies one proposed residential building on the Miyapur site, configured as 1 Stllt + 5 upper floors, with a recorded building height of 14.99 m. It also records one parking floor of 212.15 m². The permit extraction does not provide a reliable floor-by-floor apartment schedule, building footprint, lift or stair details, or measured open-space breakdown.

The RERA filing lists 1357.50 m² as approved built-up area. The permit extraction separately lists residential area 1,131.25 m² and parking area 212.15 m²; no further area reconciliation is supplied. These figures are reported in their recorded categories rather than converted into FSI-counted, gross, saleable or carpet area. RERA filing

GHMC permit conditions include a tot-lot, peripheral greenery and a transformer space, and require construction to follow the sanctioned plan. The supplied material does not give the tot-lot’s area or a detailed landscape, circulation or common-area plan.

4. Homes, configurations & floor plans

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
2BHK50598.6 m²Not established from the supplied drawing measurementsNot supplied
3BHK505113.12 m²Not established from the supplied drawing measurementsNot supplied

RERA saleable areas and unit counts are from the project filing; the booked/available figures have no portal as-of date and should be treated as indicative. No supported RERA carpet-area or loading figure is supplied. Saleable area and carpet area are different measures; the record does not provide the project-specific common-area loading calculation. RERA unit table RERA unit details

The available software-measured floor-plan record is not a usable measurement for the RERA-filed 2BHK and 3BHK configurations. The drawing-based measurements supplied are labelled 6BHK and are not matched to a RERA configuration, so they are not presented as this project’s filed apartment sizes. Floor plans RERA unit details

5. Parking & vehicle circulation

The GHMC permit records one parking floor with an area of 212.15 m² and states that approved cellar/stilt parking is to be used exclusively for vehicle parking, without partition walls or rolling shutters. It does not state the number of car or two-wheeler spaces, visitor or accessible provision, bay allocation, or a unit-wise parking entitlement. A parking area shown or permitted does not by itself establish exclusive ownership or allocation to a particular apartment.

The permit identifies a 9.00 MT WIDE MAIN ROAD and requires a service road wherever required; the supplied evidence does not describe a parking ramp, internal driveway layout, pedestrian separation or EV charging provision.

6. Amenities, recreation & open spaces

Tot-lot
Description / sizeArea not stated; permit condition says it is to be fenced and maintained as greenery.
Evidence sourceGHMC permit
Declared progress / verified statusPermit condition; completion not established
Peripheral greenery / tree planting
Description / sizePermit calls for tree planting along the periphery and in front; it records 15 Trees and a peripheral greenery strip.
Evidence sourceGHMC permit
Declared progress / verified statusPermit record/condition; completion not established
Community buildings
Description / sizeListed in the RERA amenity record; no size or description supplied.
Evidence sourceRERA amenity record RERA amenities
Declared progress / verified statusPercentage shown as 0; completion not established
Aggregate recreational open space
Description / sizeListed in the RERA amenity record; area not supplied.
Evidence sourceRERA amenity record RERA amenities
Declared progress / verified statusPercentage shown as 0; completion not established

The supplied amenity record does not document a clubhouse or specific indoor or sports facilities. The GHMC permit’s tot-lot, tree and greenery requirements are approval conditions, not evidence that those features have been delivered. RERA amenities

7. Utilities, building services & safety

Water
Evidence in the recordRERA amenity record lists water supply as available “YES”; the GHMC permit says public water connections are provided only on production of an occupancy certificate.
Status / limitationFiling entry does not establish a source, storage capacity or completed connection. RERA amenities
Sewerage and drainage
Evidence in the recordRERA amenity record lists sewerage (including STP), storm-water drains, and treatment/disposal of sewage and sullage water.
Status / limitationThe supplied record gives no STP capacity, design or completion verification; amenity progress is recorded as 0%. RERA amenities
Rainwater harvesting
Evidence in the recordPermit requires a rainwater-harvesting structure/percolation pit and records 4 RWHPs.
Status / limitationPermit provision; installation is not verified.
Electricity
Evidence in the recordAmenity record lists energy management; permit requires transformer space and says public electricity connections are provided only on production of an occupancy certificate.
Status / limitationSupply capacity, backup and completed connections are not disclosed. RERA amenities
Fire and life safety
Evidence in the recordRERA amenity record lists fire protection and fire-safety requirements. The GHMC permit requires a fire NOC from the Director (EV&DM) before issue of an occupancy certificate.
Status / limitationNo fire NOC or completed fire-system evidence is supplied. RERA amenities
Waste
Evidence in the recordPermit requires a garbage house within the premises; the RERA amenity record lists solid-waste management and disposal.
Status / limitationFacility completion and operating arrangements are not established. RERA amenities
Lifts, accessibility and security
Evidence in the recordThe permit refers generally to lifts and services being executed under qualified technical supervision; the supplied record gives no lift count or capacity, accessible-route details, CCTV or access-control specification.
Status / limitationNot established by the supplied evidence.

8. Location, access & connectivity

The registered location is Miyapur, Miyapur Village, Hyderabad district, Telangana, PIN 500049; the project site is identified as part of Plot 173 and 174 in Survey No. 111. The GHMC permit records a 9.00 MT WIDE MAIN ROAD. RERA record RERA filing RERA filing

The project’s cadastral parcel-centroid coordinate is recorded as 17.41528, 78.35459. The supplied structured location data lists Financial District (Nanakramguda) at 1.2 km. This is a recorded distance, not a travel-time estimate. Location record

9. Developer & development status

The registered promoter is IREDDY CONSTRUCTIONS, identified in the RERA filing as a partnership. Its supplied GSTIN is 36AAGFI9969Q1Z6. The listed project address is B, SRIVANI NAGAR, MIYAPUR, MIYAPUR, Hyderabad, 500049. The registered office and official website/contact details are not established in the supplied evidence; the RERA certificate separately prints a promoter-office line reading “Village: Mandal: District: Sangareddy, Pin: 502032.” RERA record Corporate record Parties record

IREDDY SUMALATHA is identified as authorized signatory and ARIPIRALA KAVITHA as partner in the supplied party record. The Form-B affidavit signed by IREDDY SUMALATHA declares a completion date of 14/08/2023. No current construction progress, revised completion date or occupancy certificate is evidenced in the supplied documents. Parties record

10. Approvals, official records & documents

TG-RERA registration certificate, Form C
Identifier / dateP02500003523; issued 21/10/2021; valid through 14/08/2023
What it establishesRegistration of PLATINUM RESIDENCY and its stated conditions.
GHMC Building Permit Order
Identifier / dateApproval 2/C21/09140/2021; file 2/C21/07403/2021; approved 14 August, 2021
What it establishesPermit for the proposed residential building and recorded conditions.
RERA Form-B declaration
Identifier / dateDated SEP 07 2021
What it establishesPromoter declaration, including proposed completion date 14/08/2023 and statements concerning title, encumbrances, project funds and approvals.
Approved drawing / layout-plan filing
Identifier / dateDocument 184065; drawing stamp read as 2/C21/09140/2021, dated 16-08-2021
What it establishesDrawing record is identified in the filing, but the supplied document extraction is not available to establish further plan details.
Occupancy / completion certificate
Identifier / dateNot supplied
What it establishesThe GHMC permit requires an occupancy certificate before occupation; no issued certificate is evidenced here.

Frequently asked questions

Is PLATINUM RESIDENCY registered with Telangana RERA?

Yes. PLATINUM RESIDENCY is registered with the Telangana Real Estate Regulatory Authority as P02500003523; the registration status is New Project.

Who is the developer of PLATINUM RESIDENCY?

The promoter named in the RERA registration is IREDDY CONSTRUCTIONS.

Where is PLATINUM RESIDENCY located?

PLATINUM RESIDENCY is in MIYAPUR, Hyderabad, Telangana (500049).

When will PLATINUM RESIDENCY be completed?

The promoter's proposed date of completion filed with RERA is 14/08/2023. This is the promoter's declaration, not a guarantee.