CIVITAS PHASE - II is a residential development in Sanath Nagar, Hyderabad, Hyderabad district; the project-site mandal is not disclosed. The registered promoter is SHREE SAI TIRUMALA CONSTRUCTIONS. The site covers 16,248.04 sq m and comprises five residential blocks and a clubhouse block: Block 1 has Cellar + Stilt + 5 upper floors, Blocks 2–5 have Stilt + 5 upper floors each, and the clubhouse has Ground + 3 upper floors; the RERA filing records 188 total units, including 40 2BHK and 144 3BHK homes. It is registered with TG-RERA under P02500004965, with proposed completion 08/03/2028.

More from Shree Sai Tirumala Constructions · 2 projects →

01What we found

RegisteredTG-RERA - valid till 8 Nov 2027
27documents on file - each fact links to its page
0court cases on this project's land in the court records searched
7items to check - 3 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

7 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

Project at a glance

Project identity

ItemRecord
Registered project nameCIVITAS PHASE - II RERA record
Project type / registered portionResidential; Phase II. The RERA filing describes six building units, while the GHMC permit identifies five residential blocks and one clubhouse block. RERA record RERA filing
TG-RERA registrationP02500004965 RERA record
Registration validity29 August 2022 to 8 November 2027; the certificate says five years and permits extension in accordance with the Act and rules. This is registration validity, not a statement that the project is complete. Approvals record
Registered promoterSHREE SAI TIRUMALA CONSTRUCTIONS RERA record Corporate record
RERA record statusRegistered; certificate states registration under section 5.

Land and geographic identity

ItemRecord
Locality / revenue villageSanath Nagar / Sanathnagar, Hyderabad. The RERA and GHMC records use these spelling variants. RERA record RERA filing
MandalNot disclosed in the project land details. The RERA certificate’s promoter-office field lists Ameerpet as mandal; it is not identified there as the project-site mandal. Land records
District / PINHyderabad / 500018 RERA record
Survey numbers and subdivisionsNot disclosed in the supplied project identity or land details. The GHMC permit identifies municipal premises 7-2-1668/1 to 13; this is not stated as a survey-number list. RERA filing
Registered site extent16,248.04 sq m total area; 16,001.54 sq m net area in the RERA filing. RERA filing
GHMC permit area detailsSite area 16,248.04 m²; net area 16,001.54 m². Permit also records road-affected area 244.4 m² and nala-affected area 0 m².
Boundaries in RERA filingNorth: 40 Feet Wide Road; South: Existing Building; East: Existing Building; West: 40 Feet Wide Road. RERA filing
Plan/layout identifierGHMC building approval 1/C17/10130/2021; permit file 1/C17/05509/2021; layout/Sub Divn. No. 53282/HO/CZ/CIR-10/2016. Approvals record

Development identity

ItemRecord
Sanctioning authorityGreater Hyderabad Municipal Corporation (GHMC) Approvals record
Principal building approvalRevised Building Permit Order 1/C17/10130/2021, approved 08 November 2021. Approvals record
Approved built-up areaRERA filing states 26,467.13 sq m as approved built-up area. RERA filing
Building count and arrangementSix blocks in the permit: five residential blocks (Blocks 1–5) and a clubhouse block.
Sanctioned floor configurationsBlock 1: Cellar + Stilt + 5 upper floors; Blocks 2–5: Stilt + 5 upper floors each; Club House: Ground + 3 upper floors.
Parking levels in sanctionCellar and stilt areas are designated for parking under the permit; the permit says they are to be used exclusively for vehicle parking without partition walls or rolling shutters.
UnitsRERA filing records 188 total units; the project-information field records six building units as per the approved plan and six proposed building units as per agreement. The unit table lists 184 2BHK/3BHK homes plus four rows labelled by floor, which are not treated here as homes for sale. RERA unit table RERA filing RERA unit details
Construction stageThe supplied records do not establish current site construction progress or independently verify completion of any block or facility. RERA amenity progress fields contain reported percentages for some infrastructure items; these are not independent site verification. RERA amenities

Offering and status

ItemRecord
RERA-filed home configurations2BHK: 40 units; 3BHK: 144 units. RERA unit table
RERA-filed saleable areas2BHK: 112.4 sq m; 3BHK: 163.12 sq m. RERA unit table
Booked / available2BHK: 5 booked, 35 available; 3BHK: 36 booked, 108 available. Counts are from the TG-RERA portal as last read; the record gives no as-of date, so they are indicative. RERA unit table
Completion datesForm-B declaration undertakes completion by 08 November 2027; the project header separately gives proposed completion 08/03/2028. RERA record
Occupancy / completion certificateNo occupancy or completion certificate is identified in the supplied evidence. The GHMC permit requires an occupancy certificate before occupation and a completion notice after construction. The certificate status has not been independently checked.

The project story

CIVITAS PHASE - II is a registered residential apartment development in Sanath Nagar, Hyderabad. Its GHMC permit organizes the development into five residential blocks and a separate clubhouse block, with stilt parking in the residential blocks and a cellar level in Block 1. The clubhouse is sanctioned as Ground + 3 upper floors. RERA record

The RERA unit filing identifies 184 apartments for sale: 40 2BHK and 144 3BHK homes. The portal’s indicative booking figures show 41 booked homes across these configurations and 143 available; the four additional floor-labelled entries in the filing are not treated as sale homes. RERA unit table RERA unit details

The available evidence describes the permitted design and RERA-filed amenities, but does not establish the present physical construction stage, completion of individual blocks, or independently verified delivery of facilities. The promoter’s Form-B declaration gives a completion undertaking of 08 November 2027; registration validity runs through 8 November 2027. Neither date is evidence that the project has already been completed or that an occupancy certificate has issued.

Master plan, architecture & building design

The GHMC permit identifies a site area of 16,248.04 m² and net area of 16,001.54 m². The RERA filing separately reports approved built-up area of 26,467.13 sq m. The permit extraction includes block-level area and height entries, but its aggregate “proposed covered builtup area” and “TOTAL” figures are not sufficiently legible or consistently formatted in the supplied extraction to report as reliable totals. RERA filing RERA filing

Sanctioned blockUseSanctioned floorsPermit area / height information available
Block 1ResidentialCellar + Stilt + 5 upper floorsResidential upper floors: 6,089.60 m²; cellar: 6,562.60 m²; stilt: 1,343.80 m²; height entry: 15 m.
Block 2ResidentialStilt + 5 upper floorsResidential upper floors: 6,044.60 m²; stilt: 1,317.80 m²; height entry: 15 m.
Block 3ResidentialStilt + 5 upper floorsResidential upper floors: 1,274.80 m²; stilt parking: 242.12 m²; height entry: 11.96 m.
Block 4ResidentialStilt + 5 upper floorsResidential upper floors: 5,983.05 m²; stilt: 1,253.00 m²; height entry: 15 m.
Block 5ResidentialStilt + 5 upper floorsResidential upper floors: 6,223.05 m²; stilt: 1,312.60 m²; height entry: 14.95 m.
Club HouseCommercial/common facility in permit extractionGround + 3 upper floorsCommercial upper floors: 638.31 m²; height entry: 15 m.

The permit records an 18 m road-width entry, a tot-lot of 1,607.3 m², and 810 Trees. It also records a first-floor area of 3,842.26 m² for Blocks 1–4; the supplied extraction does not explain the area’s precise measurement category.

No approved floor-plan geometry suitable for apartment-by-apartment measurement is available in the supplied drawing records: two floor-plan records are listed, with no measured plans and no flats identified in those drawings. Accordingly, the evidence supplied here does not establish flats per floor, building footprints, lift/stair counts, internal circulation arrangements, or residential-versus-common-area distribution beyond the block uses and floor configurations stated above. Floor plans

The approved drawing/permit record is distinct from the RERA saleable-area figures. No carpet-area measurements are available; the floor-plan data says no drawings were measured. Floor plans RERA unit table

Homes, configurations & floor plans

The following are the RERA-filed configurations and unit counts. Booked and available figures are portal counts with no stated as-of date. The supplied floor-plan set has no measured apartment plans, so carpet area and loading are not reported. RERA unit table RERA unit details Floor plans

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
2BHK40535112.4 sq mNot availableNot supplied
3BHK14436108163.12 sq mNot availableNot supplied

The RERA filing also has four entries labelled First Floor, Ground Floor, Second Floor and Third Floor. These are floor-labelled rows, not identified as apartment configurations, and are excluded from the home table. RERA unit table RERA unit details

Carpet area is not established by the supplied drawings. RERA saleable area is the filed figure; no drawing-based room dimensions, balcony/utility measurements, or common-area loading figures are available to describe or compare. RERA unit table Floor plans

Parking & vehicle circulation

The GHMC permit designates cellar and stilt areas for vehicle parking and expressly requires those approved areas to be used exclusively for parking, without partition walls or rolling shutters. Block 1 has a sanctioned cellar and stilt; the other four residential blocks have stilt levels.

The permit extraction provides some stilt and cellar areas, but does not establish the number of car or two-wheeler spaces, visitor or accessible spaces, bay allocation to individual homes, parking ramps, or separate vehicle entries and exits. No unit-specific parking allocation is available in the supplied records. A drawn or sanctioned parking area does not by itself establish exclusive ownership or allocation. Document index

Amenities, recreation & open spaces

The GHMC permit includes a tot-lot and records site-level provisions for a transformer space, garbage house, rainwater-harvesting percolation pit and ETP. These are permit requirements/provisions, not evidence of completed facilities. RERA’s progress fields report percentages for certain items; those percentages are filed status data, not independently verified completion. RERA amenities

Clubhouse / indoor
FacilityClubhouse block
Description / sizeSanctioned Ground + 3 upper floors; no facility schedule or internal area breakdown is supplied beyond the permit’s commercial upper-floor area entry of 638.31 m².
Declared progress / verified statusSanctioned; completion not established.
Landscape / open space
FacilityTot-lot
Description / size1,607.3 m² in permit extraction.
Declared progress / verified statusSanctioned provision; RERA Green Strip/TOT LOT/Park progress: 0%.
Landscape / open space
FacilityTrees
Description / sizePermit extraction records 810 Trees.
Declared progress / verified statusRecorded in permit; planting/completion not verified.
Convenience / community
FacilityGarbage house
Description / sizeRequired within the premises in permit.
Declared progress / verified statusRequired provision; completion not established.
Convenience / community
FacilityCommunity buildings
Description / sizeRERA progress field: 0%.
Evidence sourceRERA amenities
Declared progress / verified statusReported progress only; facility completion not established.

A third-party vendor record lists a gym, courts, supermarket, indoor games, children’s play area, jogging/walking track, badminton and basketball courts, table tennis, chess and reception. These are vendor-listed claims, not established by the supplied TG-RERA amenity or permit evidence, and are not presented as sanctioned or delivered facilities. Promoter website

Utilities, building services & safety

The permit and RERA progress record identify the following provisions and reported status. “Available” in the RERA field is a filing entry; the percentages are reported progress, not an independent inspection. RERA amenities

Water supply
Evidence in supplied recordRERA amenity field says “YES.”
Reported progress / status100% reported; independent verification not supplied. RERA amenities
Sewerage / sewage treatment
Evidence in supplied recordRERA lists sewerage (chamber, lines, septic tank, STP) as “YES”; the permit requires an ETP.
Reported progress / statusSewerage: 30% reported; treatment/disposal of sewage and sullage: 0% reported. RERA amenities
Storm-water drainage
Evidence in supplied recordRERA field says “YES.”
Reported progress / status30% reported. RERA amenities
Rainwater harvesting / water conservation
Evidence in supplied recordPermit requires a rainwater-harvesting percolation pit; RERA field says “YES.”
Reported progress / status25% reported. RERA amenities
Electrical / transformer
Evidence in supplied recordPermit requires transformer space; RERA lists electrical meter room, sub-station and receiving station as “YES.”
Reported progress / status35% reported for the RERA electrical item. RERA amenities
Solid waste
Evidence in supplied recordPermit requires a garbage house; RERA lists solid-waste management and disposal as “YES.”
Reported progress / status0% reported for solid-waste management and disposal. RERA amenities
Fire and life safety
Evidence in supplied recordPermit requires automatic sprinklers in the cellar and other fire-safety systems as per Table 7 of Part 4 of the National Building Code of India, 2016; it also requires an Occupancy Fire NOC before issue of the occupancy certificate.
Reported progress / statusRERA fire-protection/fire-safety progress: 0%. No Fire NOC or completed-system evidence is supplied. RERA amenities
Energy management / street lighting / internal roads
Evidence in supplied recordRERA progress fields are present.
Reported progress / statusEach reported at 0%. RERA amenities
Lifts, backup power, CCTV, access control, accessibility
Evidence in supplied recordNo project-specific capacities or confirmed provisions are supplied.
Reported progress / statusNot established by the supplied evidence.

The permit also requires the tot-lot to be fenced and maintained as greenery before issue of the occupancy certificate. It states that an occupancy certificate is compulsory before occupation. These permit conditions do not establish that the required works or certificates have been completed.

Location, access & connectivity

The registered project location is Sanath Nagar, Hyderabad, Telangana, PIN 500018. The RERA filing gives the project address as 7-2-1668/1 to 13, Sanath Nagar; the permit identifies Sanathnagar and the same municipal premises range. The project boundaries recorded in the filing include 40 Feet Wide Roads to the north and west. RERA record RERA filing

The permit extraction records 18 mt. road widths. The supplied structured location data gives a cadastral-parcel centroid of 17.41528, 78.35459 and one connectivity point: Financial District (Nanakramguda), 1.2 km. Location record

A vendor record lists Police Lines 0.14 Km, Hetero Bus Stop 0.15 Km, Sanath Nagar Ps Bus Stop 0.15 Km, Sanath Nagar Rd 0.15 Km, and Allwyn Colony 0.35 Km. These are vendor-supplied distances, not independently verified measurements. Promoter website

Developer & development status

The registered legal promoter is SHREE SAI TIRUMALA CONSTRUCTIONS, identified in the RERA record as a partnership. Its GSTIN is 36ABUFS1510N1ZP. The RERA address is given as CIVITAS PROJECT, Czech Colony, Sanath Nagar, Hyderabad, Telangana, 500018; the registration certificate’s promoter-office field states Village: (blank), Mandal: Ameerpet, District: Hyderabad, PIN 500018. No official website or contact details are supplied in the evidence. RERA record Corporate record Parties record

The RERA filing names four landowners—Vijay Delhikar, Rajender Delhikar, Devender Delhikar and Mahender Delhikar—and identifies the promoter’s authorized signatory as Devender Yelagundula. The GHMC permit names the landowners as applicants represented by Shree Sai Tirumala Constructions and separately names Ms Shreemukh Spaces as developer/builder in the extracted permit text. Parties record

The promoter’s Form-B affidavit declares completion by 08 November 2027. The project header gives a proposed completion date of 08/03/2028. The supplied evidence does not establish a revised completion approval, current construction progress, completed tower scope, or an issued occupancy certificate. RERA record Document index

Approvals, official records & documents

TG-RERA registration certificate, Form C
Identifier / dateP02500004965; issued 29 August 2022
What the supplied evidence establishesRegistration for CIVITAS PHASE - II; stated validity through 8 November 2027.
GHMC Revised Building Permit Order
Identifier / dateApproval 1/C17/10130/2021; 08 November 2021
What the supplied evidence establishesPermit extraction identifies five residential blocks and a clubhouse block, floor configurations, site area and conditions.
GHMC file and application references
Identifier / dateFile 1/C17/05509/2021; application 120086/18/03/2017/HO
What the supplied evidence establishesReferences appearing in the building permit extraction.
Layout / subdivision reference in permit
Identifier / date53282/HO/CZ/CIR-10/2016
What the supplied evidence establishesListed in the permit’s other-number fields; no separate approved-layout drawing is supplied here.
RERA Form-B declaration
Identifier / dateDated 25 May 2022
What the supplied evidence establishesPromoter declaration concerning landowners, title documents, development agreement, project accounts and completion undertaking.
Completion / occupancy certificate
Identifier / dateNot present in supplied records
What the supplied evidence establishesThe GHMC permit requires a completion notice and occupancy certificate before occupation; certificate issuance is not established.

The supplied GHMC permit is conditional and states that permission does not confer ownership rights. The permit also lists technical and construction conditions; the full conditions and their applicability are addressed in the approvals review.

Frequently asked questions

Is CIVITAS PHASE - II registered with Telangana RERA?

Yes. CIVITAS PHASE - II is registered with the Telangana Real Estate Regulatory Authority as P02500004965; the registration status is New Project.

Who is the developer of CIVITAS PHASE - II?

The promoter named in the RERA registration is SHREE SAI TIRUMALA CONSTRUCTIONS.

Where is CIVITAS PHASE - II located?

CIVITAS PHASE - II is in Sanath Nagar, Hyderabad, Telangana (500018).

When will CIVITAS PHASE - II be completed?

The promoter's proposed date of completion filed with RERA is 08/03/2028. This is the promoter's declaration, not a guarantee.