Timberline
Sri Srinivasa Constructions · Hyderabad · RERA P02500001021
Timberline is a residential apartment project in Rajendra Nagar, Hyderabad; the mandal is not disclosed in the RERA identity record. The registered promoter developing it is Sri Srinivasa Constructions, recorded as a Partnership. The project occupies 1635.09 sq m and comprises one residential building with 2Cellar + Ground + 5 and 18 units; the RERA schedule records saleable areas of 268.0 sqm, 280.0 sqm and 293.0 sqm, without bedroom configurations. Its TG-RERA registration is P02500001021, and the proposed completion date recorded in the project information is 31/12/2021.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
10 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Item | Record |
|---|---|
| Registered project name | Timberline RERA record |
| Project type | Residential apartment project RERA record RERA filing |
| Phase / registered portion | The registration identifies the project and survey 308/PART; a separate phase designation is not disclosed. |
| TG-RERA registration | P02500001021, granted under section 5; valid from 12/07/2019 to 31/12/2020. The certificate records no extension. Registration validity is distinct from the completion undertaking and from occupancy certification. |
| Registered promoter | Sri Srinivasa Constructions; the RERA record identifies the organization type as Partnership. RERA record RERA filing |
| RERA status | The supplied certificate establishes registration for the stated validity period. The supplied materials do not establish a current registration status or an occupancy certificate. Document index |
Land and geographic identity
| Item | Record |
|---|---|
| Locality | Rajendra Nagar; the building permit describes the site locality as BUDVEL. RERA record RERA filing |
| Revenue village | Rajendra Nagar in the RERA identity fields; the title opinion and permit refer to Budvel Village. RERA record Land records |
| Mandal | Not disclosed in the supplied RERA identity record. Land records |
| District / PIN | Hyderabad / 500030. RERA record RERA filing |
| Survey number / subdivision | 308/PART; the title materials also refer to Sy.No.308/Part, Sy.No.308(Part) and 3O8/Part. RERA record Land records |
| Registered site extent | RERA land details record total area and net area as 1635.09 sq m, with 0 affected area. The permit extract also gives extent as 1635.09 m2. RERA filing |
| Boundaries (RERA filing) | East: Plot no 178; West: 40 Ft ROAD; North: 50 ft ROAD; South: Plot no 202 and 203. RERA filing |
| Plot identifiers | 176 & 177. RERA filing |
Development identity
| Item | Record |
|---|---|
| Sanctioning authority | Greater Hyderabad Municipal Corporation (GHMC). Approvals record |
| Principal building approval | Permit No. 1/C11/15286/2018, approved 23 September, 2018; file No. 1/C6/03963/2018. Approvals record |
| Approved building | One residential building, described in the permit as “Building - BLDG (RESIDENTIAL)”; the sanctioned configuration is 2Cellar + Ground + 5. |
| Height / approved area | Permit extract states height 17.97 m and “Proposed Covered builtup area 365,826.00.” The supplied extract does not clarify the scale or unit of that covered-built-up-area figure; it is therefore reproduced as recorded, not treated as a verified area measurement. Separately, the RERA filing records approved built-up area as 4572 sqmts. RERA filing |
| Parking / ancillary sanctioned provision | The permit says cellar and stilt parking shown in the plan are to be used exclusively for vehicle parking. A parking-space count and a separate stilt level are not established by the supplied extract. |
| Unit count | The RERA unit record lists 18 units. The supplied permit extract does not state a sanctioned unit count. RERA unit table RERA unit details |
Offering and status
| Item | Record |
|---|---|
| RERA-filed unit identifiers and saleable area | Unit identifiers and filed saleable areas range from 268.0 sqm to 293.0 sqm; the filing does not classify these entries by bedroom configuration. RERA unit details RERA unit table |
| Bookings / availability | The portal-derived unit record indicates 14 booked and 4 available units. No as-of date accompanies these counts, so they are indicative. RERA unit table RERA unit details |
| Construction stage | The supplied RERA amenity/status record includes progress percentages for listed works, but does not establish an independently verified overall construction stage or current site condition. RERA amenities |
| Completion dates | The registration certificate records validity through 31/12/2020. The RERA project information and Form-B declaration state a completion date/undertaking of 31/12/2020; another project-information field records 31/12/2021 as a proposed completion date. RERA filing |
| Occupancy / completion certificate | No occupancy certificate or completion certificate is included in the supplied materials. Document index |
2. The project story
Timberline is registered with TG-RERA as a residential apartment project on land recorded as survey 308/PART, with plot numbers 176 & 177, in Rajendra Nagar, Hyderabad. The permit identifies the site as Budvel and sanctions one residential building in a 2Cellar + Ground + 5 configuration. RERA record RERA filing
The RERA unit schedule contains 18 individually identified entries. Its booking and availability counts are portal-derived and lack an as-of date. Although the filed unit schedule supplies areas and identifiers, it does not label the units by bedroom configuration. Drawing-based software measurements indicate layouts labelled 3BHK and 6BHK, but those measurements are not RERA-filed configuration disclosures. RERA unit details RERA unit table Floor plans
The supplied record does not establish a current overall completion percentage, a completed or occupied building, or an issued occupancy certificate. RERA’s filed amenity schedule reports differing progress percentages for particular site works; these are reported progress figures, not independent verification of delivery. RERA amenities Document index
3. Master plan, architecture & building design
The site is recorded as 1635.09 sq m total and net area, with 0 affected area. The RERA filing separately records 4572 sqmts as approved built-up area. The permit extraction records “Proposed Covered builtup area 365,826.00”; because the supplied extraction does not identify its unit or scale, that figure cannot be reconciled or used as an area measurement here. RERA filing RERA filing
The building permit describes one residential building with a height of 17.97 m and configuration 2Cellar + Ground + 5. It records 84.68 m2 for the tot-lot and 12 rain-water-harvesting structures (RWHPs), and lists transformer space, garbage house and ETP among the site provisions. The permit extract does not provide a detailed floor-by-floor flat schedule, building footprint, lift or stair count, internal circulation plan, or a breakdown of FSI-counted, gross, saleable and carpet areas.
A layout/subdivision identifier, LRS/668/CR-6/SOUTH ZONE/GHMC/2008, appears in the building-permit record. The supplied material does not include a readable layout drawing or a detailed site plan that would establish internal-road arrangement or the distribution of open and common areas beyond the stated tot-lot. Document index
4. Homes, configurations & floor plans
The RERA schedule records unit identifiers rather than bedroom configurations. The table below groups the filed units by their stated saleable area; the record does not establish a bedroom type for any group. Unit booking figures are portal-derived, with no as-of date. RERA unit table RERA unit details RERA unit table
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| Homes with filed saleable area 268.0 sqm | 6 | 5 | 1 | 268.0 sqm | Not measured as a RERA-filed configuration | Not supplied |
| Homes with filed saleable area 280.0 sqm | 6 | 5 | 1 | 280.0 sqm | Not measured as a RERA-filed configuration | Not supplied |
| Homes with filed saleable area 293.0 sqm | 6 | 4 | 2 | 293.0 sqm | Not measured as a RERA-filed configuration | Not supplied |
The approved-plan drawings supplied for measurement include layouts labelled 3BHK and 6BHK. Software measurement of the drawings reports 3BHK carpet areas of 157.0–179.0 sqm (median 161.5 sqm) across four measured designs, and 6BHK carpet areas of 163.7–175.1 sqm (median 169.4 sqm) across two measured designs. These are drawing-based, software-measured figures requiring review, not RERA disclosures; the drawing-derived configurations are not matched to the RERA unit schedule. Floor plans RERA unit details
The measured 3BHK drawing includes living, dining, kitchen, foyer, bedrooms, toilets and two utility areas. The measured 6BHK drawing shows bedrooms, living areas, a foyer, dress space and toilets; some room labels in the supplied measurement record have no dimensions. Utility areas are marked excluded from carpet area in the 3BHK measurement. Carpet area, saleable area and any common-area loading are distinct; no loading figure is supplied. RERA unit details
5. Parking & vehicle circulation
The building permit states that cellar and stilt parking shown in the sanctioned plan are to be used exclusively for vehicle parking. The supplied extract does not state the number of parking spaces, a floor-by-floor parking allocation, visitor or accessible parking provision, a ramp or driveway arrangement, EV charging, or unit-specific parking allotments. A drawn or sanctioned parking space does not by itself establish exclusive ownership.
6. Amenities, recreation & open spaces
The RERA amenity schedule reports the following facilities and progress. The percentages are filed progress data; they do not independently verify completion. RERA amenities
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Green Strip/TOT LOT/Park | Permit specifies tot-lot 84.68 m2. | RERA amenity schedule; GHMC permit | 90% in RERA schedule; not independently verified complete. |
| Aggregate area of recreational Open Space | Area not stated in the supplied amenity schedule. | RERA amenity schedule RERA amenities | 50%; not independently verified complete. |
| Community Buildings | No description or size supplied. | RERA amenity schedule RERA amenities | 0% reported. |
| Internal Roads & Footpaths | No description or size supplied. | RERA amenity schedule RERA amenities | 0% reported. |
| Street Lighting | No quantity or specifications supplied. | RERA amenity schedule RERA amenities | 0% reported. |
The building permit also lists a tot-lot, but the supplied documents do not establish clubhouse, indoor recreation or sports facilities as sanctioned or delivered project amenities. Third-party amenity listings are not used as evidence of RERA-filed or completed facilities. RERA amenities Promoter website
7. Utilities, building services & safety
| Service | Supplied evidence |
|---|---|
| Water | RERA amenity schedule marks Water Supply “YES” and reports 90% progress. The source, storage capacity and treatment arrangements are not stated. RERA amenities |
| Sewerage / drainage | The RERA schedule marks sewerage and treatment/disposal of sewage and sullage “YES,” each at 25%. The building permit lists an ETP and requires its provision to standard specification. The schedule also reports storm-water drains “YES” at 100%. No STP capacity, reuse quantity or system specification is supplied. RERA amenities |
| Rain-water harvesting | The RERA schedule reports water conservation/rain-water harvesting “YES” at 90%; the permit lists 12 RWHPs. RERA amenities |
| Electrical | The permit requires space for a transformer. The RERA schedule lists electrical meter room/sub-station/receiving station at 0%. Supply capacity and backup arrangements are not established. RERA amenities |
| Fire and life safety | The RERA schedule marks fire protection and fire safety requirements “YES” at 50%. The supplied materials do not establish specific fire systems, clearances or independent compliance verification. RERA amenities |
| Waste | The RERA schedule marks solid-waste management and disposal “YES” at 25%; the permit lists a garbage house. No waste-processing capacity or operating status is supplied. RERA amenities |
| Lifts and accessibility | Lift count, lift capacity, accessible circulation and ramp provision are not disclosed in the supplied project records. Document index |
8. Location, access & connectivity
The registered project location is Rajendra Nagar, Hyderabad, PIN 500030; the land and permit records identify the site as survey 308/PART, Budvel, with plot numbers 176 & 177. The RERA filing records the site boundaries as Plot no 178 to the east, 40 Ft ROAD to the west, 50 ft ROAD to the north, and Plot no 202 and 203 to the south. RERA record RERA filing
The building permit records 18 mt. road widths and identifies an 18 mt. road as the relevant road-width provision in its extracted data. The supplied geocoded connectivity record gives distances from a cadastral parcel centroid: Financial District (Nanakramguda) 1.2 km; IndusInd Bank 0.4 km; (unnamed bus_station) 2.2 km; Manuu Polytechnic Hyderabad 1.6 km; Sankaraya Eye Hospital 1.6 km; ADP 0.0 km; South india shopping mall 2.6 km; (unnamed park) 1.2 km; Nanakramguda Govt primary school 0.5 km. These are recorded distances, not travel-time estimates. Location record
9. Developer & development status
The registered promoter is Sri Srinivasa Constructions, recorded as a partnership. The RERA filing lists Nishitha Menneni as partner and authorized signatory and Janaki Bontha as partner. The project record also identifies B Janaki and S Satheesh Kumar as landowners under area-share arrangements. RERA record RERA filing Parties record
The RERA Form-B declaration, made by B Nishitha as authorized signatory, states that the project would be completed by 31-12-2020 and includes declarations concerning title basis, approvals, project funds and accounts. Those are promoter declarations, not independent verification of performance or completion.
The supplied records do not disclose a registered office contact number, official project website, or independently verified construction status. The RERA amenity schedule supplies item-specific progress percentages; no independently verified overall percentage is provided. RERA filing RERA amenities Corporate record
10. Approvals, official records & documents
| Record | Supplied evidence |
|---|---|
| TG-RERA registration | Form ‘C’ certificate for Timberline, registration P02500001021, issued 12/07/2019, valid through 31/12/2020; no extension is recorded in the supplied certificate. |
| GHMC building permit | Building Permit Order 1/C11/15286/2018, dated 23 September, 2018, for a residential building at Budvel, survey 308/PART; file No. 1/C6/03963/2018. |
| Layout/subdivision reference | LRS/668/CR-6/SOUTH ZONE/GHMC/2008 is recorded in the permit; a separate readable approved-layout document is not supplied. Document index |
| Title report | Advocate’s title opinion dated 31-O5-2019, concerning land described as 1956 sq.yds in Sy.No.308/Part, Budvel Village, Plot Nos. 176 and 177; it describes the owners’ development-agreement-cum-GPAs and refers to a GHMC mortgage over proposed built-up area. This is an index of the filed opinion, not an independent title determination. |
| Form-B declaration | Promoter affidavit/declaration by B Nishitha as authorized signatory, with completion undertaking of 31-12-2020. |
| Occupancy/completion certificate | Not included in the supplied documents. Document index |
| Other filed references in permit | Notarised Affidavit No. 8996/2018 dated 08/06/2018; Contractor’s all Risk Policy No. 3211-500101-17-1000020-00-000 dated 16 November, 2017. |
1. Project at a glance
Project identity
Registered project name: Timberline
Project type: Residential apartment project
Phase / registered portion: The registration identifies the project and survey 308/PART; a separate phase designation is not disclosed.
TG-RERA registration: P02500001021, granted under section 5; valid from 12/07/2019 to 31/12/2020. The certificate records no extension. Registration validity is distinct from the completion undertaking and from occupancy certification.
Registered promoter: Sri Srinivasa Constructions; the RERA record identifies the organization type as Partnership.
RERA status: The supplied certificate establishes registration for the stated validity period. The supplied materials do not establish a current registration status or an occupancy certificate.
Land and geographic identity
Locality: Rajendra Nagar; the building permit describes the site locality as BUDVEL.
Revenue village: Rajendra Nagar in the RERA identity fields; the title opinion and permit refer to Budvel Village.
Mandal: Not disclosed in the supplied RERA identity record.
District / PIN: Hyderabad / 500030.
Survey number / subdivision: 308/PART; the title materials also refer to Sy.No.308/Part, Sy.No.308(Part) and 3O8/Part.
Registered site extent: RERA land details record total area and net area as 1635.09 sq m, with 0 affected area. The permit extract also gives extent as 1635.09 m2.
Boundaries (RERA filing): East: Plot no 178; West: 40 Ft ROAD; North: 50 ft ROAD; South: Plot no 202 and 203.
Plot identifiers: 176 & 177.
Development identity
Sanctioning authority: Greater Hyderabad Municipal Corporation (GHMC).
Principal building approval: Permit No. 1/C11/15286/2018, approved 23 September, 2018; file No. 1/C6/03963/2018.
Approved building: One residential building, described in the permit as “Building - BLDG (RESIDENTIAL)”; the sanctioned configuration is 2Cellar + Ground + 5.
Height / approved area: Permit extract states height 17.97 m and “Proposed Covered builtup area 365,826.00.” The supplied extract does not clarify the scale or unit of that covered-built-up-area figure; it is therefore reproduced as recorded, not treated as a verified area measurement. Separately, the RERA filing records approved built-up area as 4572 sqmts.
Parking / ancillary sanctioned provision: The permit says cellar and stilt parking shown in the plan are to be used exclusively for vehicle parking. A parking-space count and a separate stilt level are not established by the supplied extract.
Unit count: The RERA unit record lists 18 units. The supplied permit extract does not state a sanctioned unit count.
Offering and status
RERA-filed unit identifiers and saleable area: Unit identifiers and filed saleable areas range from 268.0 sqm to 293.0 sqm; the filing does not classify these entries by bedroom configuration.
Bookings / availability: The portal-derived unit record indicates 14 booked and 4 available units. No as-of date accompanies these counts, so they are indicative.
Construction stage: The supplied RERA amenity/status record includes progress percentages for listed works, but does not establish an independently verified overall construction stage or current site condition.
Completion dates: The registration certificate records validity through 31/12/2020. The RERA project information and Form-B declaration state a completion date/undertaking of 31/12/2020; another project-information field records 31/12/2021 as a proposed completion date.
Occupancy / completion certificate: No occupancy certificate or completion certificate is included in the supplied materials.
2. The project story
Timberline is registered with TG-RERA as a residential apartment project on land recorded as survey 308/PART, with plot numbers 176 & 177, in Rajendra Nagar, Hyderabad. The permit identifies the site as Budvel and sanctions one residential building in a 2Cellar + Ground + 5 configuration.
The RERA unit schedule contains 18 individually identified entries. Its booking and availability counts are portal-derived and lack an as-of date. Although the filed unit schedule supplies areas and identifiers, it does not label the units by bedroom configuration. Drawing-based software measurements indicate layouts labelled 3BHK and 6BHK, but those measurements are not RERA-filed configuration disclosures.
The supplied record does not establish a current overall completion percentage, a completed or occupied building, or an issued occupancy certificate. RERA’s filed amenity schedule reports differing progress percentages for particular site works; these are reported progress figures, not independent verification of delivery.
3. Master plan, architecture & building design
The site is recorded as 1635.09 sq m total and net area, with 0 affected area. The RERA filing separately records 4572 sqmts as approved built-up area. The permit extraction records “Proposed Covered builtup area 365,826.00”; because the supplied extraction does not identify its unit or scale, that figure cannot be reconciled or used as an area measurement here.
The building permit describes one residential building with a height of 17.97 m and configuration 2Cellar + Ground + 5. It records 84.68 m2 for the tot-lot and 12 rain-water-harvesting structures (RWHPs), and lists transformer space, garbage house and ETP among the site provisions. The permit extract does not provide a detailed floor-by-floor flat schedule, building footprint, lift or stair count, internal circulation plan, or a breakdown of FSI-counted, gross, saleable and carpet areas.
A layout/subdivision identifier, LRS/668/CR-6/SOUTH ZONE/GHMC/2008, appears in the building-permit record. The supplied material does not include a readable layout drawing or a detailed site plan that would establish internal-road arrangement or the distribution of open and common areas beyond the stated tot-lot.
4. Homes, configurations & floor plans
The RERA schedule records unit identifiers rather than bedroom configurations. The table below groups the filed units by their stated saleable area; the record does not establish a bedroom type for any group. Unit booking figures are portal-derived, with no as-of date.
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| Homes with filed saleable area 268.0 sqm | 6 | 5 | 1 | 268.0 sqm | Not measured as a RERA-filed configuration | Not supplied |
| Homes with filed saleable area 280.0 sqm | 6 | 5 | 1 | 280.0 sqm | Not measured as a RERA-filed configuration | Not supplied |
| Homes with filed saleable area 293.0 sqm | 6 | 4 | 2 | 293.0 sqm | Not measured as a RERA-filed configuration | Not supplied |
The approved-plan drawings supplied for measurement include layouts labelled 3BHK and 6BHK. Software measurement of the drawings reports 3BHK carpet areas of 157.0–179.0 sqm (median 161.5 sqm) across four measured designs, and 6BHK carpet areas of 163.7–175.1 sqm (median 169.4 sqm) across two measured designs. These are drawing-based, software-measured figures requiring review, not RERA disclosures; the drawing-derived configurations are not matched to the RERA unit schedule.
The measured 3BHK drawing includes living, dining, kitchen, foyer, bedrooms, toilets and two utility areas. The measured 6BHK drawing shows bedrooms, living areas, a foyer, dress space and toilets; some room labels in the supplied measurement record have no dimensions. Utility areas are marked excluded from carpet area in the 3BHK measurement. Carpet area, saleable area and any common-area loading are distinct; no loading figure is supplied.
5. Parking & vehicle circulation
The building permit states that cellar and stilt parking shown in the sanctioned plan are to be used exclusively for vehicle parking. The supplied extract does not state the number of parking spaces, a floor-by-floor parking allocation, visitor or accessible parking provision, a ramp or driveway arrangement, EV charging, or unit-specific parking allotments. A drawn or sanctioned parking space does not by itself establish exclusive ownership.
6. Amenities, recreation & open spaces
The RERA amenity schedule reports the following facilities and progress. The percentages are filed progress data; they do not independently verify completion.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Green Strip/TOT LOT/Park | Permit specifies tot-lot 84.68 m2. | RERA amenity schedule; GHMC permit | 90% in RERA schedule; not independently verified complete. |
| Aggregate area of recreational Open Space | Area not stated in the supplied amenity schedule. | RERA amenity schedule | 50%; not independently verified complete. |
| Community Buildings | No description or size supplied. | RERA amenity schedule | 0% reported. |
| Internal Roads & Footpaths | No description or size supplied. | RERA amenity schedule | 0% reported. |
| Street Lighting | No quantity or specifications supplied. | RERA amenity schedule | 0% reported. |
The building permit also lists a tot-lot, but the supplied documents do not establish clubhouse, indoor recreation or sports facilities as sanctioned or delivered project amenities. Third-party amenity listings are not used as evidence of RERA-filed or completed facilities.
7. Utilities, building services & safety
Water: RERA amenity schedule marks Water Supply “YES” and reports 90% progress. The source, storage capacity and treatment arrangements are not stated.
Sewerage / drainage: The RERA schedule marks sewerage and treatment/disposal of sewage and sullage “YES,” each at 25%. The building permit lists an ETP and requires its provision to standard specification. The schedule also reports storm-water drains “YES” at 100%. No STP capacity, reuse quantity or system specification is supplied.
Rain-water harvesting: The RERA schedule reports water conservation/rain-water harvesting “YES” at 90%; the permit lists 12 RWHPs.
Electrical: The permit requires space for a transformer. The RERA schedule lists electrical meter room/sub-station/receiving station at 0%. Supply capacity and backup arrangements are not established.
Fire and life safety: The RERA schedule marks fire protection and fire safety requirements “YES” at 50%. The supplied materials do not establish specific fire systems, clearances or independent compliance verification.
Waste: The RERA schedule marks solid-waste management and disposal “YES” at 25%; the permit lists a garbage house. No waste-processing capacity or operating status is supplied.
Lifts and accessibility: Lift count, lift capacity, accessible circulation and ramp provision are not disclosed in the supplied project records.
8. Location, access & connectivity
The registered project location is Rajendra Nagar, Hyderabad, PIN 500030; the land and permit records identify the site as survey 308/PART, Budvel, with plot numbers 176 & 177. The RERA filing records the site boundaries as Plot no 178 to the east, 40 Ft ROAD to the west, 50 ft ROAD to the north, and Plot no 202 and 203 to the south.
The building permit records 18 mt. road widths and identifies an 18 mt. road as the relevant road-width provision in its extracted data. The supplied geocoded connectivity record gives distances from a cadastral parcel centroid: Financial District (Nanakramguda) 1.2 km; IndusInd Bank 0.4 km; (unnamed bus_station) 2.2 km; Manuu Polytechnic Hyderabad 1.6 km; Sankaraya Eye Hospital 1.6 km; ADP 0.0 km; South india shopping mall 2.6 km; (unnamed park) 1.2 km; Nanakramguda Govt primary school 0.5 km. These are recorded distances, not travel-time estimates.
9. Developer & development status
The registered promoter is Sri Srinivasa Constructions, recorded as a partnership. The RERA filing lists Nishitha Menneni as partner and authorized signatory and Janaki Bontha as partner. The project record also identifies B Janaki and S Satheesh Kumar as landowners under area-share arrangements.
The RERA Form-B declaration, made by B Nishitha as authorized signatory, states that the project would be completed by 31-12-2020 and includes declarations concerning title basis, approvals, project funds and accounts. Those are promoter declarations, not independent verification of performance or completion.
The supplied records do not disclose a registered office contact number, official project website, or independently verified construction status. The RERA amenity schedule supplies item-specific progress percentages; no independently verified overall percentage is provided.
10. Approvals, official records & documents
TG-RERA registration: Form ‘C’ certificate for Timberline, registration P02500001021, issued 12/07/2019, valid through 31/12/2020; no extension is recorded in the supplied certificate.
GHMC building permit: Building Permit Order 1/C11/15286/2018, dated 23 September, 2018, for a residential building at Budvel, survey 308/PART; file No. 1/C6/03963/2018.
Layout/subdivision reference: LRS/668/CR-6/SOUTH ZONE/GHMC/2008 is recorded in the permit; a separate readable approved-layout document is not supplied.
Title report: Advocate’s title opinion dated 31-O5-2019, concerning land described as 1956 sq.yds in Sy.No.308/Part, Budvel Village, Plot Nos. 176 and 177; it describes the owners’ development-agreement-cum-GPAs and refers to a GHMC mortgage over proposed built-up area. This is an index of the filed opinion, not an independent title determination.
Form-B declaration: Promoter affidavit/declaration by B Nishitha as authorized signatory, with completion undertaking of 31-12-2020.
Occupancy/completion certificate: Not included in the supplied documents.
Other filed references in permit: Notarised Affidavit No. 8996/2018 dated 08/06/2018; Contractor’s all Risk Policy No. 3211-500101-17-1000020-00-000 dated 16 November, 2017.
Frequently asked questions
Is Timberline registered with Telangana RERA?
Yes. Timberline is registered with the Telangana Real Estate Regulatory Authority as P02500001021; the registration status is New Project.
Who is the developer of Timberline?
The promoter named in the RERA registration is Sri Srinivasa Constructions.
Where is Timberline located?
Timberline is in Rajendra Nagar, Hyderabad, Telangana (500030).
When will Timberline be completed?
The promoter's proposed date of completion filed with RERA is 31/12/2021. This is the promoter's declaration, not a guarantee.
More projects in Hyderabad