SRI OM ELITE is a residential apartment project in Dulapally, Dundigal Gandimaisamma mandal, Medchal-Malkajgiri district, being developed by the registered promoter Sri Om Builders. The project covers 668.8 sq. m and comprises one residential building with 1 Stilt + 5 upper floors and 20 2BHK apartments, each with a RERA-filed saleable area of 70.3 sq. m. Its TG-RERA registration number is P02200001894, and its proposed and revised proposed completion date is 19/10/2025.

More from Sri Om Builders · 3 projects →

01What we found

Period endedTG-RERA registration ran to 19 Oct 2025 - check its extension on TG-RERA
9documents on file - each fact links to its page
1court case on this project's land (survey 175, Dulapally)
13items to check - 2 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

13 items to check before you pay, 2 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

Project photoProject photoProject photo
▦ View all 3 photos
Dulapally, Dundigal Gandimaisamma, Medchal-Malkajgiri · geocoded — approximate.

1. Project at a glance

Project identity

ItemRecord
Registered project nameSRI OM ELITE
Project typeResidential apartment project RERA record
Phase / registered portionPhase designation not stated; the registration concerns the project on Plot No. 5 Part, Survey No. 175 Part
TG-RERA registrationP02200001894
Registration validity21/03/2020 to 19/10/2025; certificate states five years. Registration extension is not recorded in the supplied certificate
Registered promoterSri Om Builders
RERA statusThe project record describes it as “On-Going Project.” The recorded registration end date has passed; the evidence supplied does not establish a subsequent extension or current registration status RERA record

Land and geographic identity

ItemRecord
LocalityDulapally RERA record
Revenue villageDulapally; the HMDA approval also spells it “Dulapalle” RERA record
MandalDundigal Gandimaisamma; the approval states Dundigal/Gandimaisamma RERA record
DistrictMedchal-Malkajgiri RERA record
PIN500014 RERA record
Project survey number(s) and subdivision(s)175 Part; the building approval specifies 175 PART Land records
PlotPlot No. 5 Part Land records
Registered site extent668.8 sq. m (also stated as 668.80 sq. m in the HMDA approval) Land records
Net / total areaNet area 668.80 sq. m; total area 668.8 sq. m Land records
BoundariesNorth: Road; South: Plot No. 6; East and West: Plot No. 5 Part Land records

Development identity

ItemRecord
Sanctioning authorityHyderabad Metropolitan Development Authority (HMDA)
Principal building approval027938/MED/R1/U6/HMDA/10092019, approved 19/10/2019
Building configurationOne residential building: 1 Stilt + 5 upper floors
Approved built-up area1686.45 sq. m RERA record
Proposed built-up area stated in approval record2051.1 sq. m; the supplied approval extraction separately lists approved built-up area as 1686.45 sq. m
Building height14.5, as recorded in the approval extraction; the unit is not stated
Building / tower countOne building / one tower Land records RERA unit table
Units20 units are listed in the RERA unit record; the approval document’s extraction does not specify a sanctioned unit count RERA unit table
Parking levels / countA stilt level is shown in the building configuration. A parking-space count and allocation schedule are not established by the supplied records Document index

Offering and status

ItemRecord
Unit type2BHK apartments RERA unit table
RERA-filed saleable area70.3 sq. m per listed configuration RERA unit table
Booked / available0 booked / 20 available in the portal data; the record has no as-of date, so counts are indicative RERA unit table
Construction stageThe project is identified as “On-Going Project”; no independently verified site-progress report is supplied RERA record
Completion datesProposed and revised proposed completion: 19/10/2025 RERA record
Occupancy / completion certificateNot supplied in the evidence reviewed; the approval states that an Occupancy Certificate is compulsory before occupation Document index

2. The project story

SRI OM ELITE is recorded with TG-RERA as a residential apartment project on Plot No. 5 Part, Survey No. 175 Part, in Dulapally village, Dundigal Gandimaisamma mandal, Medchal-Malkajgiri district. The RERA and HMDA records describe a 668.8 sq. m site and a single residential building configured as one stilt level plus five upper floors. RERA record Land records

The RERA unit record lists 20 two-bedroom apartments, with 0 booked and 20 available in the portal data; no as-of date is provided for those counts. A measured drawing record covers four designs, but does not establish construction progress or the current physical state of the building. The project is labelled ongoing, while the supplied record gives 19/10/2025 as both the proposed and revised completion date. No occupancy or completion certificate is included in the supplied documents. RERA unit table Floor plans RERA record Document index

The promoter’s filed Form B declares that the project would be completed within six years. This is a promoter declaration in the registration file, not a site-verified progress finding.

3. Master plan, architecture & building design

The HMDA technical approval identifies one residential building on 668.80 sq. m in Plot No. 5 Part, Survey No. 175 Part, with a configuration of 1 stilt plus 5 upper floors. It records 1686.45 sq. m as built-up area and 2051.1 sq. m as proposed built-up area; these are the separate figures as presented in the supplied approval extraction. The extraction does not provide a floor-by-floor area schedule, footprint, flats per floor, lift or stair details, or internal circulation drawings.

The approval lists a 14.5 building height without a unit in the supplied extraction. It also specifies a 10% mortgage area of 168.645 sq. m and a provided mortgage area of 172.28 sq. m; the recorded mortgage deed concerns 168.64 sq. m on the second floor in favour of HMDA.

The building approval includes provisions for a transformer, garbage house, rainwater-harvesting structures and a tot-lot. The approval also requires a tot-lot to be fenced and maintained as greenery before issue of the occupancy certificate. These are approval conditions/provisions, not evidence that the facilities have been completed.

No approved layout drawing, landscape plan, open-space schedule or full set of floor plans is available in the supplied evidence. One of two floor-plan drawings is recorded as measured, with one further drawing scan pending. Document index Floor plans

4. Homes, configurations & floor plans

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
2BHK2002070.3 sq. m60.6 sq. m median; measured range 60.6–60.9 sq. mNot supplied

RERA records list 20 2BHK units at 70.3 sq. m saleable area each. The portal’s booked and available counts have no supplied as-of date and should be treated as indicative. RERA unit table RERA unit details

Software measurement of the approved floor-plan drawing gives a median carpet area of 60.6 sq. m (653 sq. ft), with a measured range of 60.6–60.9 sq. m (652–655 sq. ft) across four measured designs. This is drawing-based software measurement, not a RERA-filed carpet-area disclosure, and the extraction flags two designs for review. Floor plans RERA unit details

The drawing extraction for one second-floor flat identifies a kitchen, living room, dining area, two bedrooms and two toilets. Listed room dimensions are: kitchen 2.7 × 2.0 m; toilets 1.5 × 2.0 m and 1.4 × 2.0 m; bedrooms 3.12 × 3.6 m and 3.0 × 3.4 m; living room 3.12 × 5.02 m; dining area 3.11 × 3.22 m. These are drawing-derived measurements, not a site measurement. RERA unit details

Saleable area and carpet area are different area measures; the drawing-measurement record notes that saleable area includes the home’s share of common areas. Balcony, utility and loading figures are not supplied. Floor plans

5. Parking & vehicle circulation

The approved building configuration includes a stilt level, but the supplied records do not establish the number of parking spaces, whether they are for cars or two-wheelers, visitor or accessible parking, or how spaces are allocated to individual apartments. A stilt level alone does not establish a parking-space count or exclusive unit allocation. Document index

The approval refers to an 18 mt. road width. Details of the site entrance, ramps, internal driveways, pedestrian separation, EV charging or parking circulation are not supplied.

6. Amenities, recreation & open spaces

The following is the RERA project record’s amenity and infrastructure status. The percentages are portal-recorded progress figures; they are not independent verification of delivery. RERA amenities

FacilityDescription / sizeEvidence sourceDeclared progress / verified status
Water supplySize/capacity not statedRERA project recordYES; 100% recorded, not independently verified RERA amenities
Sewerage“Chamber, Lines, Septic Tank, STP”; specific system/capacity not statedRERA project recordYES; 100% recorded, not independently verified RERA amenities
Green strip / tot-lot / parkSize not stated; approval includes a tot-lotRERA project record; HMDA approvalYES; 100% recorded in RERA data; approval requires fencing and greenery before OC; completion not verified RERA amenities
Rainwater harvesting / water conservationDetails and capacity not statedRERA project record; HMDA approvalYES; 100% recorded in RERA data; completion not independently verified RERA amenities
Electrical meter room / sub-station / receiving stationSpecific equipment/capacity not stated; approval requires transformer provisionRERA project record; HMDA approvalYES; 100% recorded in RERA data; completion not independently verified RERA amenities
LiftNumber, type and capacity not statedRERA project recordYES; 100% recorded, not independently verified RERA amenities
Internal roads and footpathsDetails not statedRERA project record0% recorded RERA amenities
Storm-water drainsDetails not statedRERA project record0% recorded RERA amenities
Street lightingDetails not statedRERA project record0% recorded RERA amenities
Community buildingsNo size or facility details suppliedRERA project record0% recorded RERA amenities
Sewage / sullage treatment and disposalNo treatment details or capacity suppliedRERA project record0% recorded RERA amenities
Solid-waste management and disposalNo system details supplied; HMDA approval requires a garbage-house provisionRERA project record; HMDA approval0% recorded in RERA data; approval provision is not evidence of completion RERA amenities
Energy managementDetails not statedRERA project record0% recorded RERA amenities
Fire protection and fire-safety requirementsSystem details not statedRERA project record0% recorded RERA amenities
Recreational open-space aggregate areaArea not statedRERA project record0% recorded RERA amenities

The promoter’s website/listing information also names indoor games, kids’ play areas, power backup, security, CCTV and a common garden. These are promoter/vendor-provided claims and are not established as sanctioned or delivered facilities by the supplied RERA amenity record. Promoter website

7. Utilities, building services & safety

The RERA project record marks water supply, sewerage (chambers, lines, septic tank and STP), rainwater harvesting, an electrical meter room/sub-station/receiving station and a lift as available at 100%. Those are portal-declared progress values, not independent completion verification; system capacities and detailed designs are not supplied. RERA amenities

The HMDA approval requires rainwater-harvesting structures and provision for a transformer and garbage house within the premises. It also requires structural safety provisions in accordance with the National Building Code of 2005 and states that an Occupancy Certificate is compulsory before occupation. These approval conditions do not by themselves establish installation, testing or statutory compliance.

No detailed fire-system design, escape-stair information, emergency access plan, lift count or capacity, backup-power specification, water-storage or treatment capacity, storm-water design, waste-segregation system, CCTV/access-control specification, EV infrastructure or accessible-circulation details are supplied. The RERA record lists fire protection and fire safety at 0%. RERA amenities

8. Location, access & connectivity

The registered location is Dulapally, Dundigal Gandimaisamma mandal, Medchal-Malkajgiri district, PIN 500014; the site is identified as Survey No. 175 Part, Plot No. 5 Part. RERA record Land records

The supplied location record gives the nearest sampled Outer Ring Road interchange as approximately 9.4 km. This is a recorded distance, not a travel-time estimate. The HMDA approval lists an 18 mt. road width, but the supplied evidence does not identify the road name or provide further access, public-transport or landmark details. Location record

9. Developer & development status

The registered promoter is Sri Om Builders, described in the project filing as a partnership. The supplied evidence does not establish a corporate registration number or provide a separately verified registered-office address for the partnership. Corporate record

The registration certificate lists the promoter’s office as Village: Olb Bowenpally, Mandal: Balanagar, District: Medchal-Malkajgiri, PIN 500011. The project filing also identifies Dulapally as the project and promoter location. Parties record

The project is recorded as ongoing, with a proposed and revised completion date of 19/10/2025. No current site-progress inspection, completion certificate, occupancy certificate or registration-extension order is included in the supplied evidence. The RERA portal unit counts are indicative because no as-of date is stated. RERA record Document index RERA unit table

10. Approvals, official records & documents

RecordWhat the supplied evidence establishes
TG-RERA registration certificateForm C records project SRI OM ELITE, registration P02200001894, granted on 21/03/2020 and stated to be valid through 19/10/2025
HMDA technical building approvalApproval 027938/MED/R1/U6/HMDA/10092019, dated 19/10/2019, for a residential building at Plot No. 5 Part, Survey No. 175 Part, Dulapalle; the document describes technical approval and directs the applicant to approach the local Executive Authority for sanction and release
HMDA mortgage recordApproval extraction records mortgage deed document No. 14769, dated 10/10/2019; the mortgage schedule identifies 168.64 sq. m on the second floor in favour of HMDA
Form B declarationPromoter affidavit by Dr. CH. OMPRAKASHi as authorised partner for Sri Om Builders, including declarations about title, encumbrances, project funds, audits, approvals and completion within six years
Occupancy/completion certificateNot included in the supplied documents. The HMDA approval states that an Occupancy Certificate is compulsory before occupation Document index
Approved layout plan / complete drawing setThe RERA filing lists layout-plan and building-plan document entries, but the supplied evidence does not include an extracted approved layout. The floor-plan record reports two drawings, one measured and one scan pending Document index Floor plans

Frequently asked questions

Is SRI OM ELITE registered with Telangana RERA?

Yes. SRI OM ELITE is registered with the Telangana Real Estate Regulatory Authority as P02200001894; the registration status is On-Going Project.

Who is the developer of SRI OM ELITE?

The promoter named in the RERA registration is SRI OM BUILDERS.

Where is SRI OM ELITE located?

SRI OM ELITE is in Dulapally, Dundigal Gandimaisamma, Medchal-Malkajgiri, Telangana (500014).

When will SRI OM ELITE be completed?

The promoter's proposed date of completion filed with RERA is 19/10/2025. This is the promoter's declaration, not a guarantee.