Siri Varaa Kubera
KUBERA DEVELOPERS · Rangareddy · RERA P02400009710
SIRI VARAA KUBERA is a residential apartment project in Southend Park, Saroornagar, Ranga Reddy, developed by registered promoter KUBERA DEVELOPERS, a partnership. The site is Plot Nos. 378 and 379 in Survey Nos. 8 and 9, with a total and net plot area of 627.06 sq. m. The project comprises one residential building, A (SP), with 1 Stilt + 5 upper floors and 15 homes: 10 2BHK units and 5 3BHK units. It is registered under TG-RERA registration P02400009710, with completion undertaken by 09/02/2028.
More from Kubera Developers · 3 projects →
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
9 items to check before you pay, 2 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Item | Project record |
|---|---|
| Registered project name | SIRI VARAA KUBERA RERA record |
| Project type / phase | Residential apartment project; registered portion is described as the project on Survey Nos. 8 and 9. A separate phase name is not disclosed. RERA record |
| TG-RERA registration | P02400009710 RERA record |
| Registration validity | 10/02/2025 to 09/02/2028, unless extended by the Authority. This is registration validity, not an occupancy certificate or proof of completion. |
| Registered promoter | KUBERA DEVELOPERS, a partnership. RERA filing Corporate record |
| RERA status in supplied record | The project is registered. The certificate records quarterly update requirements; the supplied evidence does not establish current construction progress or completion. RERA record |
Land and geographic identity
| Item | Project record |
|---|---|
| Locality / plots | Southend Park; Plot Nos. 378 and 379. RERA filing |
| Revenue village | Registration record: Southand park; building-permit record: MANSOORABAD. RERA record |
| Mandal / district / PIN | Saroornagar, Ranga Reddy, 500068. RERA record |
| Survey numbers / subdivisions | Survey Nos. 8 and 9; no subdivision numbers are disclosed for the project parcel. RERA filing |
| Site extent | 627.06 sq. m total and net plot area in the filed building-permit extraction; no road- or nala-affected area is recorded there. |
| Boundaries | North: 9 MT WIDE EXISTING 9 MT WIDE PROPOSED ROAD; south: PARK; east: PLOT NO-380; west: PLOT NO-377. RERA filing |
| Registered location reference | Southend Park, Mansoorabad, Saroornagar, Ranga Reddy, Telangana, 500068. RERA record |
Development identity
| Item | Project record |
|---|---|
| Sanctioning authority | Greater Hyderabad Municipal Corporation (GHMC). |
| Principal building permit | 4727/GHMC/LBN/2025-BP, approved 10 February, 2025; the filing also identifies file no. 010973/GHMC/5062/LBN2/2024-BP. Approvals record |
| Layout reference in building-permit record | LRS/00698 AND 00697/TP-3/E-ZONE/GHMC/2008. |
| Building arrangement and sanctioned floors | One residential building, A (SP): 1 Stilt + 5 upper floors; building height 14.95 MT. |
| Approved built-up area | 1,579.10 Sq.Mt. for 5 upper floors; 317.2 Sq.Mt. for stilt; Total Parking Area 330.4. The other filed plan extraction separately states TOTAL PROPOSED BUILT UP AREA INCLUDING PARKING: 1909.54, TOTAL BUA: 1924.36, DEDUCTIONS: 14.82, and NET BUA: 1579.10. These are reproduced as labelled in the respective records. |
| Units | 15 units in the building-permit extraction; the RERA filing records 10 2BHK and 5 3BHK. RERA unit table |
| Parking arrangement | Stilt is approved for vehicle parking; a cellar is referenced in one extracted condition, but the supplied floor configuration and quantified permit parameters do not establish a cellar level or a count of parking spaces. |
| Building-plan conditions affecting occupancy | The permit requires an occupancy certificate before occupation and an Occupancy FIRE NOC before issue of the occupancy certificate. |
Offering and status
| Item | Project record |
|---|---|
| RERA-filed configurations | 2BHK: 10 units, saleable area 114.26 sq. m each; 3BHK: 5 units, saleable area 162.58 sq. m each. RERA unit table |
| Booked / available | Portal figures show 0 booked / 10 available for 2BHK and 0 booked / 5 available for 3BHK. The portal extract carries no as-of date; treat these counts as indicative, not current availability confirmation. RERA unit table |
| Construction stage | Current physical construction stage is not established by the supplied evidence. The approved permit records a construction commencement deadline of 10 August, 2025; that deadline does not establish whether construction commenced. |
| Completion dates | RERA certificate validity ends 09/02/2028; the Form-B declaration also undertakes completion by 09/02/2028. The GHMC permit states construction is to be completed before 10 February, 2028. |
| OC / completion certificate | No occupancy or completion certificate is supplied. The building permit requires one before occupation; the project’s OC status is therefore not evidenced as issued. |
2. The project story
SIRI VARAA KUBERA is a registered residential apartment development on Plot Nos. 378 and 379, in Survey Nos. 8 and 9, in the Southend Park / Mansoorabad area of Saroornagar, Ranga Reddy district. The supplied GHMC permit record describes one building, A (SP), with a stilt and five upper residential floors, and the RERA filing records 15 homes: 10 two-bedroom and 5 three-bedroom units. RERA record RERA filing RERA unit table
The project is registered as P02400009710. The evidence includes a GHMC building permit and a promoter-filed completion undertaking, but no site-progress report or issued occupancy/completion certificate. Accordingly, the record supports describing the sanctioned and proposed development, not its present construction stage or any completed, occupied or occupancy-certified portion.
3. Master plan, architecture & building design
The filed building-permit extraction identifies a single residential block and six building levels in total: 1 Stilt + 5 upper floors. It records a building height of 14.95 MT. and 627.06 Sq. Mtrs as plot and net plot area. No basement or podium configuration is established in the supplied floor description.
The plan extraction reports 1,579.10 Sq.Mt. for the five upper floors and 317.2 Sq.Mt. for the stilt, with 330.4 total parking area. A second filed plan extraction labels 1,909.54 as total proposed built-up area including parking, 1,924.36 as total BUA, 14.82 as deductions and 1,579.10 as net BUA. These figures are kept under the labels recorded in those documents; the supplied material does not provide a further area reconciliation.
The building-permit record also identifies a tot-lot, periphery greenery, a transformer space, a garbage house and a rainwater-harvesting structure. The extraction does not provide a site plan measurement for the tot-lot or open-space area, nor a building footprint, floor-by-floor unit schedule, lift or stair arrangement, or internal circulation dimensions.
4. Homes, configurations & floor plans
RERA-filed figures below give unit counts and saleable areas. Carpet figures are software measurements taken from the filed plan drawings, not RERA-filed areas; they remain subject to review against the drawings. Saleable area and measured carpet area are different measures: the drawing-based carpet measurement excludes identified balcony and utility spaces and does not represent a verified RERA carpet-area disclosure. RERA unit table Floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK | 10 | 0 | 10 | 114.26 sq. m | 65.3–68.4 sq. m; median 67.9 sq. m | 41% |
| 3BHK | 5 | 0 | 5 | 162.58 sq. m | 112.5–112.8 sq. m; median 112.7 sq. m | 31% |
The 2BHK drawing sample covers four measured designs; the 3BHK sample covers two. In the representative measured 2BHK drawing, the labelled spaces include a kitchen, hall, drawing room, two bedrooms, two toilets and a balcony. The representative 3BHK drawing labels a kitchen, dining area, hall, three bedrooms, a dressroom, puja space, toilet, utility and balcony. These are drawing-derived descriptions, not independent measurements of constructed units. RERA unit details Floor plans
5. Parking & vehicle circulation
The GHMC permit extraction records a stilt and Total Parking Area 330.4; the other filed plan extraction gives PARKING AREA: 330.44. The permit conditions state that cellar and stilt areas approved for parking are to be used exclusively for vehicle parking and not partitioned or converted. The supplied evidence does not establish a parking-space count, resident-versus-visitor allocation, accessible spaces, parking allotment for any particular home, or an EV charging installation.
The building-permit extraction also refers to a minimum width of 4.5mts. and height clearance of 5mts. No detailed ramp, driveway, vehicle-entry/exit or pedestrian-separation layout information is available in the supplied material. A drawn or sanctioned parking area alone does not establish exclusive ownership or allocation to an individual unit.
6. Amenities, recreation & open spaces
The following table separates facilities recorded in the filed GHMC permit/plan from portal amenity declarations. The amenity data show 0% progress for each listed RERA amenity; this is declared progress data, not independent verification of site condition. RERA amenities
| Description / size | Permit condition requires a fenced tot-lot maintained as greenery before issue of the occupancy certificate; no size supplied. |
|---|---|
| Evidence source | GHMC permit extraction; RERA amenities RERA amenities |
| Declared progress / verified status | RERA amenity progress shown as 0%; completion not independently verified. |
| Description / size | Permit conditions call for tree planting along the periphery and in front of the premises and maintenance of a greenery strip. |
|---|---|
| Evidence source | GHMC permit extraction |
| Declared progress / verified status | No completion evidence supplied. |
| Description / size | Listed as “Green Strip/TOT LOT/Park” in the RERA amenity record. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | 0%; not independently verified. |
| Description / size | Listed in the RERA amenity record; no dimensions supplied. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | 0%; not independently verified. |
| Description / size | Listed in the RERA amenity record; no description or size supplied. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | 0%; not independently verified. |
A third-party vendor listing mentions a clubhouse, swimming pool, gym, indoor games and children’s play area, among other facilities. Those are vendor claims, not established as GHMC-sanctioned or delivered facilities in the supplied project records, and are not treated as confirmed project provisions here. Promoter website
7. Utilities, building services & safety
The building-permit extraction specifies a separate underground static water-storage tank of 25,000 litres and a separate residential terrace tank of 25,000 litres. The plan records water supply and a space for a transformer. The RERA amenity record marks water supply, sewerage, storm-water drains, rainwater harvesting and an electrical meter room/sub-station/receiving station as available, while showing 0% progress for each amenity item. The record does not establish commissioning, capacities beyond the stated tanks, water source, treatment method or current service status. RERA amenities
The permit/plan extraction lists a rainwater-harvesting structure (percolation pit), one rainwater-harvesting pit in the building-permit parameters, a garbage house, generator, emergency lighting, hose reel, down corner, automatic sprinkler system and fire-fighting installations. The permit requires an Occupancy FIRE NOC before issue of an occupancy certificate. These are approval-record provisions/conditions; no completion, testing or operational status is supplied.
No project-specific lift count or capacity, service lift, sewage-treatment capacity, reuse arrangement, power-backup capacity, CCTV installation, access-control system, or accessibility features are established in the supplied RERA/GHMC records. Vendor references to power backup, CCTV and an STP are not treated as verified project provisions. Promoter website
8. Location, access & connectivity
The registered location is Southend Park, Saroornagar, Ranga Reddy, Telangana, PIN 500068; the GHMC permit identifies the site as Plot Nos. 378 and 379 in Survey Nos. 8 and 9, Southend Park, Mansoorabad. The filed boundaries identify a park to the south, Plot Nos. 380 and 377 to the east and west, and a 9-metre existing/proposed road to the north. RERA record RERA filing
A supplied location record gives 6.8 km to the nearest sampled Outer Ring Road interchange (approx.). No other measured distances or verified public-transport connections are supplied. Location record The RERA filing and permit establish the project location; nearby transit, schools, hospitals and other destinations mentioned by a vendor are not independently substantiated in this evidence. Promoter website
9. Developer & development status
The registered legal promoter is KUBERA DEVELOPERS, recorded as a partnership. Its supplied GSTIN is 36AAYFK3092N1ZE. The partnership’s listed partners are SEELAM SRIDHAR and PATHIPAKA MURALI KRISHNA, with the latter identified as authorized signatory for the RERA filing. Corporate record Parties record
The project filing gives a promoter address in Southend Park, Mansoorabad, Saroornagar, Ranga Reddy, 500068; a separate registered-office address or official contact details are not established in the supplied material. RERA filing Parties record The promoter’s Form-B affidavit declares completion by 09/02/2028. This is a promoter undertaking, not evidence of construction progress or completion.
10. Approvals, official records & documents
| Reference and scope | P02400009710, SIRI VARAA KUBERA; KUBERA DEVELOPERS; Survey Nos. 8 and 9. |
|---|---|
| Evidence note | Form C certificate; validity 10/02/2025–09/02/2028, unless extended. |
| Reference and scope | Permit No. 4727/GHMC/LBN/2025-BP, approved 10 February, 2025; file no. 010973/GHMC/5062/LBN2/2024-BP. |
|---|---|
| Evidence note | Building permit for residential construction, 1 Stilt + 5 upper floors, at Plots 378 and 379, Survey Nos. 8 and 9. |
| Reference and scope | LRS/00698 AND 00697/TP-3/E-ZONE/GHMC/2008. |
|---|---|
| Evidence note | Reference recorded in the building-permit extraction. |
| Reference and scope | Document 563810. |
|---|---|
| Evidence note | Filed plan extraction includes building configuration, area labels, amenities/utilities and permit conditions. |
| Reference and scope | Dated 15th day of April, 2025. |
|---|---|
| Evidence note | Promoter’s authorized signatory declares a completion period ending 09/02/2028. |
| Reference and scope | Not supplied. |
|---|---|
| Evidence note | The permit requires an occupancy certificate before occupation; issuance is not evidenced in the materials reviewed. |
The supplied records identify the building-permit authority as GHMC. The evidence provided does not include an issued occupancy/completion certificate or a current construction-progress record.
1. Project at a glance
Project identity
Registered project name: SIRI VARAA KUBERA
Project type / phase: Residential apartment project; registered portion is described as the project on Survey Nos. 8 and 9. A separate phase name is not disclosed.
TG-RERA registration: P02400009710
Registration validity: 10/02/2025 to 09/02/2028, unless extended by the Authority. This is registration validity, not an occupancy certificate or proof of completion.
Registered promoter: KUBERA DEVELOPERS, a partnership.
RERA status in supplied record: The project is registered. The certificate records quarterly update requirements; the supplied evidence does not establish current construction progress or completion.
Land and geographic identity
Locality / plots: Southend Park; Plot Nos. 378 and 379.
Revenue village: Registration record: Southand park; building-permit record: MANSOORABAD.
Mandal / district / PIN: Saroornagar, Ranga Reddy, 500068.
Survey numbers / subdivisions: Survey Nos. 8 and 9; no subdivision numbers are disclosed for the project parcel.
Site extent: 627.06 sq. m total and net plot area in the filed building-permit extraction; no road- or nala-affected area is recorded there.
Boundaries: North: 9 MT WIDE EXISTING 9 MT WIDE PROPOSED ROAD; south: PARK; east: PLOT NO-380; west: PLOT NO-377.
Registered location reference: Southend Park, Mansoorabad, Saroornagar, Ranga Reddy, Telangana, 500068.
Development identity
Sanctioning authority: Greater Hyderabad Municipal Corporation (GHMC).
Principal building permit: 4727/GHMC/LBN/2025-BP, approved 10 February, 2025; the filing also identifies file no. 010973/GHMC/5062/LBN2/2024-BP.
Layout reference in building-permit record: LRS/00698 AND 00697/TP-3/E-ZONE/GHMC/2008.
Building arrangement and sanctioned floors: One residential building, A (SP): 1 Stilt + 5 upper floors; building height 14.95 MT.
Approved built-up area: 1,579.10 Sq.Mt. for 5 upper floors; 317.2 Sq.Mt. for stilt; Total Parking Area 330.4. The other filed plan extraction separately states TOTAL PROPOSED BUILT UP AREA INCLUDING PARKING: 1909.54, TOTAL BUA: 1924.36, DEDUCTIONS: 14.82, and NET BUA: 1579.10. These are reproduced as labelled in the respective records.
Units: 15 units in the building-permit extraction; the RERA filing records 10 2BHK and 5 3BHK.
Parking arrangement: Stilt is approved for vehicle parking; a cellar is referenced in one extracted condition, but the supplied floor configuration and quantified permit parameters do not establish a cellar level or a count of parking spaces.
Building-plan conditions affecting occupancy: The permit requires an occupancy certificate before occupation and an Occupancy FIRE NOC before issue of the occupancy certificate.
Offering and status
RERA-filed configurations: 2BHK: 10 units, saleable area 114.26 sq. m each; 3BHK: 5 units, saleable area 162.58 sq. m each.
Booked / available: Portal figures show 0 booked / 10 available for 2BHK and 0 booked / 5 available for 3BHK. The portal extract carries no as-of date; treat these counts as indicative, not current availability confirmation.
Construction stage: Current physical construction stage is not established by the supplied evidence. The approved permit records a construction commencement deadline of 10 August, 2025; that deadline does not establish whether construction commenced.
Completion dates: RERA certificate validity ends 09/02/2028; the Form-B declaration also undertakes completion by 09/02/2028. The GHMC permit states construction is to be completed before 10 February, 2028.
OC / completion certificate: No occupancy or completion certificate is supplied. The building permit requires one before occupation; the project’s OC status is therefore not evidenced as issued.
2. The project story
SIRI VARAA KUBERA is a registered residential apartment development on Plot Nos. 378 and 379, in Survey Nos. 8 and 9, in the Southend Park / Mansoorabad area of Saroornagar, Ranga Reddy district. The supplied GHMC permit record describes one building, A (SP), with a stilt and five upper residential floors, and the RERA filing records 15 homes: 10 two-bedroom and 5 three-bedroom units.
The project is registered as P02400009710. The evidence includes a GHMC building permit and a promoter-filed completion undertaking, but no site-progress report or issued occupancy/completion certificate. Accordingly, the record supports describing the sanctioned and proposed development, not its present construction stage or any completed, occupied or occupancy-certified portion.
3. Master plan, architecture & building design
The filed building-permit extraction identifies a single residential block and six building levels in total: 1 Stilt + 5 upper floors. It records a building height of 14.95 MT. and 627.06 Sq. Mtrs as plot and net plot area. No basement or podium configuration is established in the supplied floor description.
The plan extraction reports 1,579.10 Sq.Mt. for the five upper floors and 317.2 Sq.Mt. for the stilt, with 330.4 total parking area. A second filed plan extraction labels 1,909.54 as total proposed built-up area including parking, 1,924.36 as total BUA, 14.82 as deductions and 1,579.10 as net BUA. These figures are kept under the labels recorded in those documents; the supplied material does not provide a further area reconciliation.
The building-permit record also identifies a tot-lot, periphery greenery, a transformer space, a garbage house and a rainwater-harvesting structure. The extraction does not provide a site plan measurement for the tot-lot or open-space area, nor a building footprint, floor-by-floor unit schedule, lift or stair arrangement, or internal circulation dimensions.
4. Homes, configurations & floor plans
RERA-filed figures below give unit counts and saleable areas. Carpet figures are software measurements taken from the filed plan drawings, not RERA-filed areas; they remain subject to review against the drawings. Saleable area and measured carpet area are different measures: the drawing-based carpet measurement excludes identified balcony and utility spaces and does not represent a verified RERA carpet-area disclosure.
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK | 10 | 0 | 10 | 114.26 sq. m | 65.3–68.4 sq. m; median 67.9 sq. m | 41% |
| 3BHK | 5 | 0 | 5 | 162.58 sq. m | 112.5–112.8 sq. m; median 112.7 sq. m | 31% |
The 2BHK drawing sample covers four measured designs; the 3BHK sample covers two. In the representative measured 2BHK drawing, the labelled spaces include a kitchen, hall, drawing room, two bedrooms, two toilets and a balcony. The representative 3BHK drawing labels a kitchen, dining area, hall, three bedrooms, a dressroom, puja space, toilet, utility and balcony. These are drawing-derived descriptions, not independent measurements of constructed units.
5. Parking & vehicle circulation
The GHMC permit extraction records a stilt and Total Parking Area 330.4; the other filed plan extraction gives PARKING AREA: 330.44. The permit conditions state that cellar and stilt areas approved for parking are to be used exclusively for vehicle parking and not partitioned or converted. The supplied evidence does not establish a parking-space count, resident-versus-visitor allocation, accessible spaces, parking allotment for any particular home, or an EV charging installation.
The building-permit extraction also refers to a minimum width of 4.5mts. and height clearance of 5mts. No detailed ramp, driveway, vehicle-entry/exit or pedestrian-separation layout information is available in the supplied material. A drawn or sanctioned parking area alone does not establish exclusive ownership or allocation to an individual unit.
6. Amenities, recreation & open spaces
The following table separates facilities recorded in the filed GHMC permit/plan from portal amenity declarations. The amenity data show 0% progress for each listed RERA amenity; this is declared progress data, not independent verification of site condition.
| Description / size | Permit condition requires a fenced tot-lot maintained as greenery before issue of the occupancy certificate; no size supplied. |
|---|---|
| Evidence source | GHMC permit extraction; RERA amenities |
| Declared progress / verified status | RERA amenity progress shown as 0%; completion not independently verified. |
| Description / size | Permit conditions call for tree planting along the periphery and in front of the premises and maintenance of a greenery strip. |
|---|---|
| Evidence source | GHMC permit extraction |
| Declared progress / verified status | No completion evidence supplied. |
| Description / size | Listed as “Green Strip/TOT LOT/Park” in the RERA amenity record. |
|---|---|
| Declared progress / verified status | 0%; not independently verified. |
| Description / size | Listed in the RERA amenity record; no dimensions supplied. |
|---|---|
| Declared progress / verified status | 0%; not independently verified. |
| Description / size | Listed in the RERA amenity record; no description or size supplied. |
|---|---|
| Declared progress / verified status | 0%; not independently verified. |
A third-party vendor listing mentions a clubhouse, swimming pool, gym, indoor games and children’s play area, among other facilities. Those are vendor claims, not established as GHMC-sanctioned or delivered facilities in the supplied project records, and are not treated as confirmed project provisions here.
7. Utilities, building services & safety
The building-permit extraction specifies a separate underground static water-storage tank of 25,000 litres and a separate residential terrace tank of 25,000 litres. The plan records water supply and a space for a transformer. The RERA amenity record marks water supply, sewerage, storm-water drains, rainwater harvesting and an electrical meter room/sub-station/receiving station as available, while showing 0% progress for each amenity item. The record does not establish commissioning, capacities beyond the stated tanks, water source, treatment method or current service status.
The permit/plan extraction lists a rainwater-harvesting structure (percolation pit), one rainwater-harvesting pit in the building-permit parameters, a garbage house, generator, emergency lighting, hose reel, down corner, automatic sprinkler system and fire-fighting installations. The permit requires an Occupancy FIRE NOC before issue of an occupancy certificate. These are approval-record provisions/conditions; no completion, testing or operational status is supplied.
No project-specific lift count or capacity, service lift, sewage-treatment capacity, reuse arrangement, power-backup capacity, CCTV installation, access-control system, or accessibility features are established in the supplied RERA/GHMC records. Vendor references to power backup, CCTV and an STP are not treated as verified project provisions.
8. Location, access & connectivity
The registered location is Southend Park, Saroornagar, Ranga Reddy, Telangana, PIN 500068; the GHMC permit identifies the site as Plot Nos. 378 and 379 in Survey Nos. 8 and 9, Southend Park, Mansoorabad. The filed boundaries identify a park to the south, Plot Nos. 380 and 377 to the east and west, and a 9-metre existing/proposed road to the north.
A supplied location record gives 6.8 km to the nearest sampled Outer Ring Road interchange (approx.). No other measured distances or verified public-transport connections are supplied. The RERA filing and permit establish the project location; nearby transit, schools, hospitals and other destinations mentioned by a vendor are not independently substantiated in this evidence.
9. Developer & development status
The registered legal promoter is KUBERA DEVELOPERS, recorded as a partnership. Its supplied GSTIN is 36AAYFK3092N1ZE. The partnership’s listed partners are SEELAM SRIDHAR and PATHIPAKA MURALI KRISHNA, with the latter identified as authorized signatory for the RERA filing.
The project filing gives a promoter address in Southend Park, Mansoorabad, Saroornagar, Ranga Reddy, 500068; a separate registered-office address or official contact details are not established in the supplied material. The promoter’s Form-B affidavit declares completion by 09/02/2028. This is a promoter undertaking, not evidence of construction progress or completion.
10. Approvals, official records & documents
| Reference and scope | P02400009710, SIRI VARAA KUBERA; KUBERA DEVELOPERS; Survey Nos. 8 and 9. |
|---|---|
| Evidence note | Form C certificate; validity 10/02/2025–09/02/2028, unless extended. |
| Reference and scope | Permit No. 4727/GHMC/LBN/2025-BP, approved 10 February, 2025; file no. 010973/GHMC/5062/LBN2/2024-BP. |
|---|---|
| Evidence note | Building permit for residential construction, 1 Stilt + 5 upper floors, at Plots 378 and 379, Survey Nos. 8 and 9. |
| Reference and scope | LRS/00698 AND 00697/TP-3/E-ZONE/GHMC/2008. |
|---|---|
| Evidence note | Reference recorded in the building-permit extraction. |
| Reference and scope | Document 563810. |
|---|---|
| Evidence note | Filed plan extraction includes building configuration, area labels, amenities/utilities and permit conditions. |
| Reference and scope | Dated 15th day of April, 2025. |
|---|---|
| Evidence note | Promoter’s authorized signatory declares a completion period ending 09/02/2028. |
| Reference and scope | Not supplied. |
|---|---|
| Evidence note | The permit requires an occupancy certificate before occupation; issuance is not evidenced in the materials reviewed. |
The supplied records identify the building-permit authority as GHMC. The evidence provided does not include an issued occupancy/completion certificate or a current construction-progress record.
Frequently asked questions
Is SIRI VARAA KUBERA registered with Telangana RERA?
Yes. SIRI VARAA KUBERA is registered with the Telangana Real Estate Regulatory Authority as P02400009710; the registration status is New Project.
Who is the developer of SIRI VARAA KUBERA?
The promoter named in the RERA registration is KUBERA DEVELOPERS.
Where is SIRI VARAA KUBERA located?
SIRI VARAA KUBERA is in SOUTHEND PARK, Southand park, Saroornagar, Rangareddy, Telangana (500068).
When will SIRI VARAA KUBERA be completed?
The promoter's proposed date of completion filed with RERA is 09/06/2028. This is the promoter's declaration, not a guarantee.