Sree Nilayam
SREE DHAMA CONSTRUCTIONS · Rangareddy · RERA P02400004921
SREE NILAYAM is a residential apartment project in Manchirevula, Gandipet mandal, Ranga Reddy district, developed by the registered promoter SREE DHAMA CONSTRUCTIONS. The registered site extent is 1,669.79 Sq. Mt., with one proposed residential building comprising 1 Cellar + 1 Stilt + 5 upper floors. The project has 30 3BHK units, with a RERA saleable area of 151.13 sq.m per unit. Its TG-RERA registration is P02400004921, and the proposed completion date is 29/03/2025.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
13 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Item | Project record |
|---|---|
| Registered name | SREE NILAYAM RERA record |
| Project type | Residential apartment project RERA record RERA filing |
| Phase / registered portion | No phase name is disclosed. The registration and building permission identify plots S-44, S-45/A, S-45/B, S-46 and S-47 in Survey Nos. 254 and 256. |
| TG-RERA registration | P02400004921 Approvals record |
| Registration validity | 29/08/2022 to 29/03/2025; the certificate says extension is not recorded. This is registration validity, not a certificate of completion or occupancy. Approvals record |
| Registered promoter | SREE DHAMA CONSTRUCTIONS, identified as a partnership in the filing. RERA record RERA filing |
| RERA status in supplied record | Certificate issued under section 5; the recorded validity ended on 29/03/2025. No extension or current-status confirmation is supplied. |
Land and geographic identity
| Item | Project record |
|---|---|
| Locality | Manchirevula; the filing also gives locality as GANDIPET. RERA record RERA filing |
| Revenue village | Manchirevula Village RERA record |
| Mandal / district / PIN | Gandipet mandal; Ranga Reddy district; PIN 500075. RERA record |
| Project survey numbers | Survey Nos. 254 & 256; no project survey subdivisions are stated in the supplied project identity. RERA record Land records |
| Plots identified in filing and sanction | S-44, S-45/A, S-45/B, S-46 & S-47 RERA filing |
| Registered site extent | 1,669.79 Sq. Mt. RERA filing |
| Total / net area | Total area: 1669.79 sq.mts; net area: 1669.79 sq.mts. RERA filing |
| Boundaries in RERA filing | North: Plot No. S-43; south: 40 - 0 WIDE ROAD; east: 40 - 0 WIDE ROAD; west: Plot Nos. S-48 to S-51. RERA filing |
Development identity
| Item | Project record |
|---|---|
| Sanctioning authority | Hyderabad Metropolitan Development Authority (HMDA); building-permit order records delegation to Narsingi Municipality / Municipal Corporation. Approvals record |
| Principal approval | 005076/BP/HMDA/0729/SKP/2021, approved 29 March, 2022. Approvals record |
| Proceedings number | 000559/BP/HMDA/SKP/2022 Approvals record |
| Building count | One proposed residential building. RERA filing |
| Sanctioned configuration | 1 Cellar + 1 Stilt + 5 upper floors. |
| Approved built-up area | 6,186.58 sq.mts is stated as total built-up area in the supplied technical approval extraction. It separately lists 3,980.95 Sq.mts as built-up area; the supplied record does not label these figures as interchangeable. |
| Parking provision | Cellar and stilt are specified for vehicle parking, without partition walls or rolling shutters; parking-space counts are not supplied. |
| Units | The RERA filing records 30 3BHK units; the sanctioned-plan extraction supplied here does not provide a separate approved unit count. RERA unit table RERA unit details |
Offering and status
| Item | Project record |
|---|---|
| Configuration and RERA saleable area | 3BHK; 151.13 sq.m per unit. RERA unit table RERA unit table |
| Booked / available | 0 booked; 30 available in the portal data supplied. Counts are indicative: the record has no as-of date. RERA unit table |
| Construction stage | No independently verified or dated construction-progress measurement is supplied. The filing status is “New Project”; that label does not establish current site progress. RERA record RERA amenities |
| Completion deadline | Promoter’s Form B declares completion by 29/03/2025. This is separate from the TG-RERA registration validity end date. |
| Occupancy / completion certificate | No completion or occupancy certificate is supplied; the building-permit extraction records completion certification as false and states that occupancy requires an occupancy certificate. |
2. The project story
SREE NILAYAM is registered as a residential apartment project on plots S-44, S-45/A, S-45/B, S-46 and S-47 in Manchirevula Village, Gandipet mandal, Ranga Reddy district. The filed land area is 1,669.79 sq.m. RERA record RERA filing
HMDA’s building-permit record describes a single residential building with one cellar, one stilt and five upper floors. The RERA portal records 30 3BHK units, all shown as available in the supplied unit data. RERA unit table The file does not establish whether construction is presently under way or the extent of work completed; no independent site inspection or verified progress certificate is included.
The promoter declared 29/03/2025 as the completion deadline. No occupancy or completion certificate is provided, so completion and lawful occupation are not established by the materials supplied.
3. Master plan, architecture & building design
The filed site area is 1,669.79 sq.m, with net area also recorded as 1,669.79 sq.m. HMDA’s approval extraction identifies a proposed residential building and the configuration 1 Cellar + 1 Stilt + 5 upper floors. RERA filing
The approval extraction reports 6,186.58 sq.m as total built-up area and separately lists 3,980.95 sq.m as built-up area. These are presented as distinct figures as labelled in the supplied record; the materials do not provide a plan-based breakdown of floor areas, building footprint, floor-by-floor unit arrangement, or FSI-counted area.
The supplied drawing record identifies an approved floor-plan document, but no readable layout or architectural extraction is provided here to establish flat positions per floor, entry and exit locations, lifts, stairs, circulation, open-space arrangement or landscaping. The sanction specifies rainwater harvesting, an STP and a transformer among the required/proposed site provisions; further design detail is not supplied.
4. Homes, configurations & floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 3BHK | 30 | 0 | 30 | 151.13 sq.m | 80.3–111.5 sq.m; median 104.6 sq.m | 31% |
RERA records 30 3BHK units and saleable area of 151.13 sq.m. Booking and availability counts are the supplied portal snapshot, with no as-of date. RERA unit table RERA unit details
Carpet-area figures are software-measured from approved floor-plan drawing geometry, not RERA-filed disclosures, and are flagged for review. The measurement set covers 12 flat designs. Saleable area and carpet area are different measures; the supplied drawing record notes that saleable area also counts the home’s share of common areas. Balcony and utility areas are excluded from the measured carpet area. Floor plans RERA unit details
A representative measured plan labels three bedrooms, a living room, kitchen and three toilets, as well as two balconies and a utility. The drawing extraction gives room dimensions for this example, but it does not establish that every 3BHK has the same arrangement. RERA unit details
5. Parking & vehicle circulation
The sanctioned building-permit record designates the cellar and stilt exclusively for vehicle parking and states that these areas must not be converted or partitioned with walls or rolling shutters. It also prohibits parking or construction in setback areas.
The supplied records do not state the number of car or two-wheeler spaces, visitor or accessible parking, parking allocation by unit, ramp arrangement, or EV-charging provision. The sanction’s identification of parking levels does not itself establish an exclusive parking allocation to a particular apartment.
6. Amenities, recreation & open spaces
| Description / size | Listed in the project amenity schedule; no size or quantity stated. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | Progress recorded as 0%; no independent completion verification supplied. |
| Description / size | Listed as available “YES”; no source, storage capacity or completion evidence stated in the amenity schedule. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | Progress recorded as 0%; no independent completion verification supplied. |
| Description / size | Listed as available “YES” in the amenity schedule; HMDA approval conditions require an STP. No capacity is supplied. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | Progress recorded as 0%; no independent completion verification supplied. |
| Description / size | Listed in the project amenity schedule; no dimensions stated. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | Progress recorded as 0%; no independent completion verification supplied. |
| Description / size | Listed in the project amenity schedule; no area or facilities specified. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | Progress recorded as 0%; no independent completion verification supplied. |
| Description / size | Listed in the project amenity schedule; no quantity or specification stated. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | Progress recorded as 0%; no independent completion verification supplied. |
| Description / size | Listed in the project amenity schedule; no description or size stated. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | Progress recorded as 0%; no independent completion verification supplied. |
| Description / size | Listed in the project amenity schedule; no treatment capacity or reuse details stated. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | Progress recorded as 0%; no independent completion verification supplied. |
| Description / size | Listed in the project amenity schedule; no system details stated. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | Progress recorded as 0%; no independent completion verification supplied. |
| Description / size | Listed as available “YES”; HMDA’s technical approval requires rainwater-harvesting structures. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | Progress recorded as 0%; no independent completion verification supplied. |
| Description / size | Listed in the project amenity schedule; no equipment or performance detail stated. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | Progress recorded as 0%; no independent completion verification supplied. |
| Description / size | Listed in the project amenity schedule; no installation or completion evidence supplied. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | Progress recorded as 0%; no independent completion verification supplied. |
| Description / size | Listed as available “YES”; the building-permit extraction also identifies a transformer. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | Progress recorded as 0%; no independent completion verification supplied. |
| Description / size | Listed as an aggregate-area item; no area supplied. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | Progress recorded as 0%; no independent completion verification supplied. |
The amenity schedule is a filed status record, not independent confirmation that a facility has been installed or completed. RERA amenities
7. Utilities, building services & safety
Water and drainage: The project amenity schedule marks water supply, sewerage and rainwater harvesting “YES,” while HMDA’s technical approval requires rainwater-harvesting structures and an STP. The supplied records do not state the water source, storage capacity, STP capacity, treated-water reuse arrangements or completion status. RERA amenities
Electrical and energy: The amenity schedule marks the electrical meter room / sub-station / receiving station “YES”; the approval extraction also lists a transformer. No electrical capacity, backup-power provision or EV charging detail is supplied. RERA amenities
Fire and life safety: Fire protection and fire safety appear in the amenity schedule, but the supplied records do not establish installed systems or a fire clearance. The technical approval extraction lists a minimum of four fire extinguishers per floor. RERA amenities
Vertical transport, waste, security and accessibility: The supplied TG-RERA and sanction material does not establish lift counts or capacities, service lifts, CCTV, security arrangements, waste segregation details, or accessible circulation. Document index RERA amenities
8. Location, access & connectivity
The registered project location is Manchirevula Village, Gandipet mandal, Ranga Reddy district, PIN 500075. The RERA filing identifies the locality as GANDIPET; the site boundaries include roads on the east and south, each described in the filing as “40 - 0 WIDE ROAD.” RERA record RERA filing
The supplied location record gives these distances: Financial District (Nanakramguda), 4.4 km; ICICI Bank, 2.5 km; Holy Mary College, 1.6 km; Urban Primary Health Centre Narsingi, 1.1 km; an unnamed park, 1.0 km; and Rishi Public School, 2.0 km. These are record-supplied location distances; no travel times or public-transport details are provided. Location record
9. Developer & development status
The registered promoter is SREE DHAMA CONSTRUCTIONS, recorded as a partnership. The filing lists GSTIN 36AENFS5318E1ZV and authorized signatory TAKKALAPALLY MADHUSUDHAN RAO. RERA record RERA filing Corporate record Parties record
The promoter’s RERA Form B declares a completion deadline of 29/03/2025 and makes fund-management and approval undertakings. These are promoter declarations, not independent verification of completion or progress. No construction-progress report or occupancy/completion certificate is supplied. The RERA registration certificate records validity through 29/03/2025; no extension record is supplied.
10. Approvals, official records & documents
| Identifier / date | P02400004921; issued 29/08/2022; valid through 29/03/2025 |
|---|---|
| What the supplied record establishes | Form C registration for SREE NILAYAM, with the site identified in Manchirevula, plots S-44, S-45/A, S-45/B, S-46 and S-47, Survey Nos. 254 and 256. |
| Identifier / date | 005076/BP/HMDA/0729/SKP/2021; 29 March, 2022 |
|---|---|
| What the supplied record establishes | Technical approval for the proposed residential building and its recorded site and floor configuration. |
| Identifier / date | 000559/BP/HMDA/SKP/2022; 29 March, 2022 |
|---|---|
| What the supplied record establishes | Building-permit order for 1 Cellar + 1 Stilt + 5 upper floors. |
| Identifier / date | 242862 |
|---|---|
| What the supplied record establishes | Listed as a layout-plan document; drawing-based unit measurements are identified as software-measured and requiring review. No readable full drawing extraction is supplied here. Floor plans |
| Identifier / date | Dated 15-06-2022 |
|---|---|
| What the supplied record establishes | Promoter’s filed declarations include the proposed completion date of 29/03/2025 and fund-management undertakings. |
| Identifier / date | Not supplied |
|---|---|
| What the supplied record establishes | The building-permit extraction states occupancy is required before occupation; it does not certify completion. |
The supplied documents do not include a project occupancy certificate or a current confirmation of TG-RERA registration validity. The HMDA approval extraction identifies a building permit, while its stated conditions separately require completion and occupancy steps.
1. Project at a glance
Project identity
Registered name: SREE NILAYAM
Project type: Residential apartment project
Phase / registered portion: No phase name is disclosed. The registration and building permission identify plots S-44, S-45/A, S-45/B, S-46 and S-47 in Survey Nos. 254 and 256.
TG-RERA registration: P02400004921
Registration validity: 29/08/2022 to 29/03/2025; the certificate says extension is not recorded. This is registration validity, not a certificate of completion or occupancy.
Registered promoter: SREE DHAMA CONSTRUCTIONS, identified as a partnership in the filing.
RERA status in supplied record: Certificate issued under section 5; the recorded validity ended on 29/03/2025. No extension or current-status confirmation is supplied.
Land and geographic identity
Locality: Manchirevula; the filing also gives locality as GANDIPET.
Revenue village: Manchirevula Village
Mandal / district / PIN: Gandipet mandal; Ranga Reddy district; PIN 500075.
Project survey numbers: Survey Nos. 254 & 256; no project survey subdivisions are stated in the supplied project identity.
Plots identified in filing and sanction: S-44, S-45/A, S-45/B, S-46 & S-47
Registered site extent: 1,669.79 Sq. Mt.
Total / net area: Total area: 1669.79 sq.mts; net area: 1669.79 sq.mts.
Boundaries in RERA filing: North: Plot No. S-43; south: 40 - 0 WIDE ROAD; east: 40 - 0 WIDE ROAD; west: Plot Nos. S-48 to S-51.
Development identity
Sanctioning authority: Hyderabad Metropolitan Development Authority (HMDA); building-permit order records delegation to Narsingi Municipality / Municipal Corporation.
Principal approval: 005076/BP/HMDA/0729/SKP/2021, approved 29 March, 2022.
Proceedings number: 000559/BP/HMDA/SKP/2022
Building count: One proposed residential building.
Sanctioned configuration: 1 Cellar + 1 Stilt + 5 upper floors.
Approved built-up area: 6,186.58 sq.mts is stated as total built-up area in the supplied technical approval extraction. It separately lists 3,980.95 Sq.mts as built-up area; the supplied record does not label these figures as interchangeable.
Parking provision: Cellar and stilt are specified for vehicle parking, without partition walls or rolling shutters; parking-space counts are not supplied.
Units: The RERA filing records 30 3BHK units; the sanctioned-plan extraction supplied here does not provide a separate approved unit count.
Offering and status
Configuration and RERA saleable area: 3BHK; 151.13 sq.m per unit.
Booked / available: 0 booked; 30 available in the portal data supplied. Counts are indicative: the record has no as-of date.
Construction stage: No independently verified or dated construction-progress measurement is supplied. The filing status is “New Project”; that label does not establish current site progress.
Completion deadline: Promoter’s Form B declares completion by 29/03/2025. This is separate from the TG-RERA registration validity end date.
Occupancy / completion certificate: No completion or occupancy certificate is supplied; the building-permit extraction records completion certification as false and states that occupancy requires an occupancy certificate.
2. The project story
SREE NILAYAM is registered as a residential apartment project on plots S-44, S-45/A, S-45/B, S-46 and S-47 in Manchirevula Village, Gandipet mandal, Ranga Reddy district. The filed land area is 1,669.79 sq.m.
HMDA’s building-permit record describes a single residential building with one cellar, one stilt and five upper floors. The RERA portal records 30 3BHK units, all shown as available in the supplied unit data. The file does not establish whether construction is presently under way or the extent of work completed; no independent site inspection or verified progress certificate is included.
The promoter declared 29/03/2025 as the completion deadline. No occupancy or completion certificate is provided, so completion and lawful occupation are not established by the materials supplied.
3. Master plan, architecture & building design
The filed site area is 1,669.79 sq.m, with net area also recorded as 1,669.79 sq.m. HMDA’s approval extraction identifies a proposed residential building and the configuration 1 Cellar + 1 Stilt + 5 upper floors.
The approval extraction reports 6,186.58 sq.m as total built-up area and separately lists 3,980.95 sq.m as built-up area. These are presented as distinct figures as labelled in the supplied record; the materials do not provide a plan-based breakdown of floor areas, building footprint, floor-by-floor unit arrangement, or FSI-counted area.
The supplied drawing record identifies an approved floor-plan document, but no readable layout or architectural extraction is provided here to establish flat positions per floor, entry and exit locations, lifts, stairs, circulation, open-space arrangement or landscaping. The sanction specifies rainwater harvesting, an STP and a transformer among the required/proposed site provisions; further design detail is not supplied.
4. Homes, configurations & floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 3BHK | 30 | 0 | 30 | 151.13 sq.m | 80.3–111.5 sq.m; median 104.6 sq.m | 31% |
RERA records 30 3BHK units and saleable area of 151.13 sq.m. Booking and availability counts are the supplied portal snapshot, with no as-of date.
Carpet-area figures are software-measured from approved floor-plan drawing geometry, not RERA-filed disclosures, and are flagged for review. The measurement set covers 12 flat designs. Saleable area and carpet area are different measures; the supplied drawing record notes that saleable area also counts the home’s share of common areas. Balcony and utility areas are excluded from the measured carpet area.
A representative measured plan labels three bedrooms, a living room, kitchen and three toilets, as well as two balconies and a utility. The drawing extraction gives room dimensions for this example, but it does not establish that every 3BHK has the same arrangement.
5. Parking & vehicle circulation
The sanctioned building-permit record designates the cellar and stilt exclusively for vehicle parking and states that these areas must not be converted or partitioned with walls or rolling shutters. It also prohibits parking or construction in setback areas.
The supplied records do not state the number of car or two-wheeler spaces, visitor or accessible parking, parking allocation by unit, ramp arrangement, or EV-charging provision. The sanction’s identification of parking levels does not itself establish an exclusive parking allocation to a particular apartment.
6. Amenities, recreation & open spaces
| Description / size | Listed in the project amenity schedule; no size or quantity stated. |
|---|---|
| Declared progress / verified status | Progress recorded as 0%; no independent completion verification supplied. |
| Description / size | Listed as available “YES”; no source, storage capacity or completion evidence stated in the amenity schedule. |
|---|---|
| Declared progress / verified status | Progress recorded as 0%; no independent completion verification supplied. |
| Description / size | Listed as available “YES” in the amenity schedule; HMDA approval conditions require an STP. No capacity is supplied. |
|---|---|
| Declared progress / verified status | Progress recorded as 0%; no independent completion verification supplied. |
| Description / size | Listed in the project amenity schedule; no dimensions stated. |
|---|---|
| Declared progress / verified status | Progress recorded as 0%; no independent completion verification supplied. |
| Description / size | Listed in the project amenity schedule; no area or facilities specified. |
|---|---|
| Declared progress / verified status | Progress recorded as 0%; no independent completion verification supplied. |
| Description / size | Listed in the project amenity schedule; no quantity or specification stated. |
|---|---|
| Declared progress / verified status | Progress recorded as 0%; no independent completion verification supplied. |
| Description / size | Listed in the project amenity schedule; no description or size stated. |
|---|---|
| Declared progress / verified status | Progress recorded as 0%; no independent completion verification supplied. |
| Description / size | Listed in the project amenity schedule; no treatment capacity or reuse details stated. |
|---|---|
| Declared progress / verified status | Progress recorded as 0%; no independent completion verification supplied. |
| Description / size | Listed in the project amenity schedule; no system details stated. |
|---|---|
| Declared progress / verified status | Progress recorded as 0%; no independent completion verification supplied. |
| Description / size | Listed as available “YES”; HMDA’s technical approval requires rainwater-harvesting structures. |
|---|---|
| Declared progress / verified status | Progress recorded as 0%; no independent completion verification supplied. |
| Description / size | Listed in the project amenity schedule; no equipment or performance detail stated. |
|---|---|
| Declared progress / verified status | Progress recorded as 0%; no independent completion verification supplied. |
| Description / size | Listed in the project amenity schedule; no installation or completion evidence supplied. |
|---|---|
| Declared progress / verified status | Progress recorded as 0%; no independent completion verification supplied. |
| Description / size | Listed as available “YES”; the building-permit extraction also identifies a transformer. |
|---|---|
| Declared progress / verified status | Progress recorded as 0%; no independent completion verification supplied. |
| Description / size | Listed as an aggregate-area item; no area supplied. |
|---|---|
| Declared progress / verified status | Progress recorded as 0%; no independent completion verification supplied. |
The amenity schedule is a filed status record, not independent confirmation that a facility has been installed or completed.
7. Utilities, building services & safety
Water and drainage: The project amenity schedule marks water supply, sewerage and rainwater harvesting “YES,” while HMDA’s technical approval requires rainwater-harvesting structures and an STP. The supplied records do not state the water source, storage capacity, STP capacity, treated-water reuse arrangements or completion status.
Electrical and energy: The amenity schedule marks the electrical meter room / sub-station / receiving station “YES”; the approval extraction also lists a transformer. No electrical capacity, backup-power provision or EV charging detail is supplied.
Fire and life safety: Fire protection and fire safety appear in the amenity schedule, but the supplied records do not establish installed systems or a fire clearance. The technical approval extraction lists a minimum of four fire extinguishers per floor.
Vertical transport, waste, security and accessibility: The supplied TG-RERA and sanction material does not establish lift counts or capacities, service lifts, CCTV, security arrangements, waste segregation details, or accessible circulation.
8. Location, access & connectivity
The registered project location is Manchirevula Village, Gandipet mandal, Ranga Reddy district, PIN 500075. The RERA filing identifies the locality as GANDIPET; the site boundaries include roads on the east and south, each described in the filing as “40 - 0 WIDE ROAD.”
The supplied location record gives these distances: Financial District (Nanakramguda), 4.4 km; ICICI Bank, 2.5 km; Holy Mary College, 1.6 km; Urban Primary Health Centre Narsingi, 1.1 km; an unnamed park, 1.0 km; and Rishi Public School, 2.0 km. These are record-supplied location distances; no travel times or public-transport details are provided.
9. Developer & development status
The registered promoter is SREE DHAMA CONSTRUCTIONS, recorded as a partnership. The filing lists GSTIN 36AENFS5318E1ZV and authorized signatory TAKKALAPALLY MADHUSUDHAN RAO.
The promoter’s RERA Form B declares a completion deadline of 29/03/2025 and makes fund-management and approval undertakings. These are promoter declarations, not independent verification of completion or progress. No construction-progress report or occupancy/completion certificate is supplied. The RERA registration certificate records validity through 29/03/2025; no extension record is supplied.
10. Approvals, official records & documents
| Identifier / date | P02400004921; issued 29/08/2022; valid through 29/03/2025 |
|---|---|
| What the supplied record establishes | Form C registration for SREE NILAYAM, with the site identified in Manchirevula, plots S-44, S-45/A, S-45/B, S-46 and S-47, Survey Nos. 254 and 256. |
| Identifier / date | 005076/BP/HMDA/0729/SKP/2021; 29 March, 2022 |
|---|---|
| What the supplied record establishes | Technical approval for the proposed residential building and its recorded site and floor configuration. |
| Identifier / date | 000559/BP/HMDA/SKP/2022; 29 March, 2022 |
|---|---|
| What the supplied record establishes | Building-permit order for 1 Cellar + 1 Stilt + 5 upper floors. |
| Identifier / date | 242862 |
|---|---|
| What the supplied record establishes | Listed as a layout-plan document; drawing-based unit measurements are identified as software-measured and requiring review. No readable full drawing extraction is supplied here. |
| Identifier / date | Dated 15-06-2022 |
|---|---|
| What the supplied record establishes | Promoter’s filed declarations include the proposed completion date of 29/03/2025 and fund-management undertakings. |
| Identifier / date | Not supplied |
|---|---|
| What the supplied record establishes | The building-permit extraction states occupancy is required before occupation; it does not certify completion. |
The supplied documents do not include a project occupancy certificate or a current confirmation of TG-RERA registration validity. The HMDA approval extraction identifies a building permit, while its stated conditions separately require completion and occupancy steps.
Frequently asked questions
Is SREE NILAYAM registered with Telangana RERA?
Yes. SREE NILAYAM is registered with the Telangana Real Estate Regulatory Authority as P02400004921; the registration status is New Project.
Who is the developer of SREE NILAYAM?
The promoter named in the RERA registration is SREE DHAMA CONSTRUCTIONS.
Where is SREE NILAYAM located?
SREE NILAYAM is in GANDIPET, Manchirevula, Rangareddy, Telangana (500075).
When will SREE NILAYAM be completed?
The promoter's proposed date of completion filed with RERA is 29/03/2025. This is the promoter's declaration, not a guarantee.
More projects in Manchirevula