LAXMI GANAPATHI AERO CITY is a plotted development in Mamnoor, Khila Warangal Mandal, Warangal Urban District, developed by the registered promoter LAXMI GANAPATHI AERO CITY. The registered site extent is 39,731.47 sq m, and the tentative layout covers 140 residential plots; buildings, floors and apartment configurations are not applicable to the filed plotted-layout offering. The project is registered under TG-RERA registration number P00300009647. The Form B completion undertaking states 11th APRIL 2026, while the shared project header records proposed completion as 30/11/2026.

01What we found

Period endedTG-RERA registration ran to 11 Apr 2026 - check its extension on TG-RERA
84documents on file - each fact links to its page
14court cases on this project's land (survey 289, 290, 292, 298, 299, 303 and 1 more, Mamnoor)
9items to check - 4 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

9 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

1. Project at a glance

Project identity

ItemProject record
Registered project nameLAXMI GANAPATHI AERO CITY RERA record
Project typePlotted development RERA record RERA filing
Phase / registered portionA registered plotted-layout project; no separate phase name is disclosed. The approved tentative layout covers 140 residential plots.
TG-RERA registrationP00300009647
Registration validity11/04/2023 to 11/04/2026; the supplied certificate records no extension. This is the registration period, not the completion deadline.
Registered promoterLAXMI GANAPATHI AERO CITY
RERA status in supplied recordThe project is registered. No current registration-status update or extension is supplied; the certificate’s stated validity ended on 11/04/2026.

Land and geographic identity

ItemProject record
LocalityMamnoor RERA record Land records
Revenue villageMamnoor (also described as Mamnoor Revenue Village in the tentative-layout approval) RERA record
MandalKhila Warangal RERA record
DistrictWarangal Urban RERA record
PIN506166 RERA record
Project survey numbers and subdivisions289, 290, 292/A/1, 292/B/1, 292/E, 298/A, 298/A1, 298/A/2, 298/B, 299/A, 299/B1/1, 299/B1, 299/B3, 299/B3/1, 299/B2, 299/B4, 299/C, 299/D, 303/A, 303/A/2, 303/B1, 303/B/1/2, 303/B2, 303/B3, 303/B4, 303/C, 303/D, 305/B/1, 305/B/3 Land records
Registered site extent39,731.47 sq m total; 39,602.51 sq m net after 128.96 sq m affected by road widening/FTL of tanks/nala, as recorded in the RERA land details. Land records
BoundariesNorth: 10M wide existing road and 18M wide proposed road; South: agriculture land of others; East: agriculture land of others; West: Sri Padmavathi Gardens and agriculture land. Land records

Development identity

ItemProject record
Approval authorityGWMC Municipality/Municipal Corporation, as stated in the tentative-layout approval
Principal approvalTentative Layout Plan 0046/LO/3006/2023, approved 04/11/2023; application no. 001535/LO/DTCP/3006/0057/2023
Approved developmentTentative layout for 140 residential plots
Approved built-up area24,045.35 sq m, as stated in RERA project information RERA filing
Buildings / floorsNot applicable to the filed plotted-layout offering; no building or floor configuration is supplied.
ParkingThe approval extract does not state a parking count or parking layout.

Offering and status

ItemProject record
Unit type and count140 residential plots in the tentative-layout approval
Plot sizesThe layout drawing’s plot schedule was software-read as 140 plots, with sizes from 151.85 to 372.24 sq m; the drawing-derived figures should be checked against the approved drawing. Layout record
Booked / availableNot disclosed in the supplied project evidence. RERA filing
Construction stageRERA project information records “New Project”; no independently verified site-progress evidence is supplied. RERA filing
Completion datesRERA certificate Form B declares completion by 11th APRIL 2026; the shared project header records proposed completion as 30/11/2026. The evidence does not establish a revised TG-RERA deadline or extension. RERA record
Occupancy / completion certificateNo occupancy or completion certificate is supplied. This is a plotted layout, and the supplied approval is tentative layout approval.

2. The project story

LAXMI GANAPATHI AERO CITY is a plotted residential layout in Mamnoor Revenue Village, Khila Warangal Mandal, Warangal Urban District. The tentative-layout approval identifies 140 residential plots and provides for roads, parks/open space, utility land and social-infrastructure land.

The approval describes the layout as tentative and makes the developer responsible for completing the layout infrastructure and obtaining release of the mortgaged plots and final layout. The RERA filing labels the project “New Project”; the supplied materials do not independently establish construction progress or completion of the layout works. RERA filing

3. Master plan, architecture & building design

The approved drawing-derived land-use schedule is for a plotted layout rather than apartment buildings. The area statement records 39,602.37 sq m as its land-use-table base, with 24,044.72 sq m plotted area, 10,570.01 sq m roads, 3,577.24 sq m parks/open space, 400.45 sq m utilities and 1,009.95 sq m social infrastructure; amenities are shown as 0.00 sq m. These are software-read values from the layout drawing, not a separate measurement survey. Layout record

The tentative-layout approval states the following allocation: plotted area 60.72%, road area 26.69%, open space/park 9.03%, social infrastructure 2.55%, utilities 1.01%. It also identifies 0 Acer 36.26 Gts 4388 Sq. Yds as mortgage area, described as 15.23 % of plotted area.

The approval lists 140 plots and requires the developer to provide layout infrastructure. It does not provide building designs, residential floor plans, building heights or a building-wise development arrangement.

4. Homes, configurations & floor plans

This is a plotted development; the supplied record does not provide apartment configurations or apartment floor plans.

Plot informationSupplied figure
Approved layout plot count140 residential plots
Drawing-derived plot count140; software-read from the approved layout drawing Layout record
Software-read size range151.85–372.24 sq m (181.6–445.2 sq yd) Layout record
Booked / available plotsNot disclosed RERA filing

The layout drawing’s software-read size bands are: 58 plots in the 150–200 sq yd band, 75 in the 200–250 sq yd band, 6 in the 250–300 sq yd band and 1 in the 400–500 sq yd band. These are drawing-derived measurements, not RERA-filed saleable-area figures. Layout record

No plot-wise saleable area, allottee inventory status or plot allocation schedule is supplied in the evidence presented here. The floor-plan record contains two layout sheets and no measured apartment plans. Floor plans

5. Parking & vehicle circulation

The tentative-layout approval requires roads to be formed and opened for access to neighbouring sites, and requires the applicant to provide road formation with black top and storm-water drains. It does not state parking-space counts, visitor or accessible parking, EV charging, vehicle-entry arrangements, or exclusive parking allocations.

The vendor record mentions “Open Parking,” but gives no quantity or allocation details; it is not evidence of a sanctioned or individually allotted parking space. Promoter website

6. Amenities, recreation & open spaces

The approved layout approval describes works and areas to be provided as part of layout development. The separate amenity-status extract reports several items at 100% and others at 0%; that record does not establish independent on-site verification. RERA amenities

Park / open space
Description / sizeApproval area: 0 Acer 35.36 Gts 4278 Sq. Yds, 9.03%; drawing-derived area: 3,577.24 sq m Layout record
Evidence sourceTentative-layout approval and layout drawing
Declared progress / verified statusApproval requires the area to be handed over; amenity extract reports “Green Strip/TOT LOT/Park” at 0%. No independent completion verification supplied. RERA amenities
Social infrastructure
Description / size0 Acer 9.98 Gts 1208 Sq. Yds, 2.55%
Evidence sourceTentative-layout approval
Declared progress / verified statusReserved in the approval; community buildings are reported at 0% in the amenity extract. RERA amenities
Internal roads and footpaths
Description / sizeRoads: 2 Acer 24.48 Gts 12642 Sq. Yds, 26.69%; drawing-derived road area: 10,570.01 sq m Layout record
Evidence sourceTentative-layout approval and layout drawing
Declared progress / verified statusApproval requires road formation with black top and roads open for access. Amenity extract reports internal roads and footpaths at 100%; no independent verification supplied. RERA amenities
Water supply infrastructure
Description / sizeInternal water-supply pipelines, overhead tank, water reservoir and assured water-supply source are listed in approval conditions.
Evidence sourceTentative-layout approval
Declared progress / verified statusApproval requirement; amenity extract reports water supply at 100%. No independent verification supplied. RERA amenities
Sewerage and sullage infrastructure
Description / sizeUnderground drainage lines and common septic tank/STP are listed in approval conditions.
Evidence sourceTentative-layout approval
Declared progress / verified statusApproval requirement; amenity extract reports sewerage (chamber, lines, septic tank, STP) at 100%. Treatment and disposal of sewage/sullage is separately reported at 0%. No independent verification supplied. RERA amenities
Storm-water drainage
Description / sizeStorm-water drains are listed in approval conditions.
Evidence sourceTentative-layout approval
Declared progress / verified statusApproval requirement; amenity extract reports storm-water drains at 0%. RERA amenities
Street lighting and electricity infrastructure
Description / sizeStreet lights and an electric transformer are listed in approval conditions.
Evidence sourceTentative-layout approval
Declared progress / verified statusApproval requirement; amenity extract reports street lighting and electrical meter room/sub-station/receiving station at 100%. No independent verification supplied. RERA amenities
Avenue planting and rainwater harvesting
Description / sizeAvenue plantation and rainwater-harvesting pits are listed in approval conditions.
Evidence sourceTentative-layout approval
Declared progress / verified statusApproval requirement; amenity extract reports water conservation/rainwater harvesting at 100%. No independent verification supplied. RERA amenities
Solid-waste management
Description / sizeSolid Waste Management is listed among the utility works in the approval.
Evidence sourceTentative-layout approval
Declared progress / verified statusApproval requirement; amenity extract reports solid-waste management and disposal at 0%. RERA amenities

7. Utilities, building services & safety

The tentative-layout approval lists an assured water source, internal water-supply pipelines, an overhead tank, water reservoir, underground drainage, a common septic tank/STP, storm-water drains, electrical supply lines, street lights, transformer, solid-waste management and rainwater-harvesting pits. These are approval-specified works; the evidence does not independently confirm installed capacity or completion.

No water-storage capacity, STP capacity, electrical capacity, backup-power provision, security system, accessibility design or fire-safety system is stated in the supplied records. The amenity extract reports fire protection/fire-safety requirements at 0%; it does not establish a project-specific fire clearance. RERA amenities

8. Location, access & connectivity

The registered project location is Mamnoor, Khila Warangal Mandal, Warangal Urban District, Telangana, PIN 506166. The layout approval identifies the site as Mamnoor Revenue Village and describes its northern boundary as a 10M wide existing road and an 18M wide proposed road. It also requires layout roads to be opened for neighbouring-site access. RERA record

The supplied location record contains a project-location coordinate, but its connectivity list identifies Financial District (Nanakramguda) at 1.2 km; no supporting route or measurement context is supplied for that distance. It is therefore not used here as a verified project-access distance. Location record

9. Developer & development status

The registered promoter is LAXMI GANAPATHI AERO CITY, identified in the RERA filing as a partnership. The supplied office address is THIRUPATHI REDDY BUILDING, WARANGAL KHAMMAM HIGHWAY, MAMNOOR, Khila Warangal, Warangal Urban, PIN 506166. GSTIN: 36AAKFL1296K1ZV. RERA filing Parties record Corporate record

RERA project information identifies landowners/promoters with area-share arrangements; the project evidence names seven landowner entries, including the partnership itself. The promoter’s Form B affidavit declares a legal-title basis and states that the land is free from encumbrances; these are promoter declarations, not independent findings in this Overview. Parties record

The RERA certificate records registration from 11/04/2023 to 11/04/2026, while the Form B completion undertaking states 11th APRIL 2026. The supplied record does not include a registration extension or independently verified completion evidence.

10. Approvals, official records & documents

RecordWhat it establishes in the supplied materials
TG-RERA Form C, registration P00300009647Registration of LAXMI GANAPATHI AERO CITY for the stated period 11/04/2023–11/04/2026.
Tentative Layout Plan 0046/LO/3006/2023Approval for a tentative layout of 140 residential plots, with land-use allocations, mortgage-area details and development conditions; authority named as GWMC Municipality/Municipal Corporation.
Mortgage deed 2604/2023, dated 04 April 2023The approval extract identifies plots mortgaged to the Municipality/Municipal Corporation to secure completion of layout-development conditions.
Form B affidavit-cum-declarationPromoter declaration on title basis, encumbrance status, project obligations and completion undertaking; verification day and month are blank in the supplied extraction.
Layout drawing, document 557073Drawing-derived plot schedule and area allocations used for the layout summary; software-read figures should be verified against the drawing. Layout record
Layout lookupPublic HMDA DPMS approved-layout lookup was unavailable in the supplied research record; this is not evidence of approval refusal. HMDA

The supplied evidence includes no final-layout release, completion certificate or occupancy certificate. The tentative approval’s conditions describe the works and release process; the detailed conditions are not reproduced here.

Frequently asked questions

Is LAXMI GANAPATHI AERO CITY registered with Telangana RERA?

Yes. LAXMI GANAPATHI AERO CITY is registered with the Telangana Real Estate Regulatory Authority as P00300009647; the registration status is New Project.

Who is the developer of LAXMI GANAPATHI AERO CITY?

The promoter named in the RERA registration is LAXMI GANAPATHI AERO CITY.

Where is LAXMI GANAPATHI AERO CITY located?

LAXMI GANAPATHI AERO CITY is in MAMNOOR, Khila Warangal, Hanamkonda, Telangana (506166).

When will LAXMI GANAPATHI AERO CITY be completed?

The promoter's proposed date of completion filed with RERA is 30/11/2026. This is the promoter's declaration, not a guarantee.