Laxmipuram Smartcity
KONDA · Suryapet · RERA P01900010015
LAXMIPURAM SMARTCITY is a plotted development in Kodad, Kodad Mandal, Suryapet District. The registered promoter is KONDA ANNAPURNA. The project has a RERA land area of 13860.39 sqmts and a tentative residential layout of 47 plots, with drawing-derived plot sizes from 106.44 sq.m (127.3 sq.yd) to 338.0 sq.m (404.2 sq.yd). It is registered under TG-RERA number P01900010015, with proposed completion on 11/03/2024.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
12 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Field | Project record |
|---|---|
| Registered project name | LAXMIPURAM SMARTCITY RERA record |
| Project type | Plotted development RERA record RERA filing |
| Phase / registered portion | Phase not separately identified. TG-RERA registration covers the project identified against the listed survey numbers. RERA record |
| TG-RERA registration number | P01900010015 RERA record Approvals record |
| Registration validity | Certificate states validity from 11/03/2022 to 11/03/2024; no extension is recorded in the supplied certificate. This is registration validity, distinct from the completion deadline. |
| Registered promoter | KONDA ANNAPURNA (certificate); project filing header names promoter as KONDA. RERA record |
| RERA status | Filing identifies the project as On-Going Project. The supplied record does not establish a current registration extension or closure. RERA filing |
Land and geographic identity
| Field | Project record |
|---|---|
| Locality | Kodad RERA record |
| Revenue village | Kodad Revenue Village (also rendered “Kodada Revenue Village” in the layout approval) |
| Mandal / district / PIN | Kodad Mandal; Suryapet District; 508206 RERA record |
| Project survey numbers and subdivisions | 429/C3, 429/A6, 429/A4, 429/C1, 429/A2, 429/A5, 429/C2 RERA record |
| Registered site extent | Layout approval states 3 Acer 17 Gts 16577 Sq. Yds. |
| RERA land area | Total area 13860.39 sqmts; net area 13860.39 sqmts; affected area reported as 0 sqmts. RERA filing |
| Boundaries | East: INDHIRAMMA COLONY; West: LAND OF SAIDULU; North: ROAD; South: LAND OF MADASU SAIDAYYA RERA filing |
Development identity
| Field | Project record |
|---|---|
| Sanctioning authority | KODADA Municipality/Municipal Corporation |
| Principal approval | Tentative layout plan 0012/LO/3046/2022, dated 03/11/2022 8:11:54 PM in the extracted approval record Approvals record |
| Related application / receipt references | TS-bPASS application 004751/LO/DTCP/3046/0019/2021; receipt TS/12213/2021 |
| Development form and count | Tentative residential plotted layout; 47 plots |
| Approved built-up area | RERA filing reports 8156.66 sqmts as approved built-up area. For a plotted layout, the supplied record does not explain the basis or identify buildings to which this figure relates. RERA filing |
| Buildings / floors | Building count, floor configuration and parking levels are not disclosed in the supplied project record. RERA filing |
Offering and status
| Field | Project record |
|---|---|
| Unit type | Plots; the tentative layout approval identifies 47 plots. RERA record |
| Plot count and sizes | Drawing-derived layout record identifies 47 plots, with sizes from 106.44 sq.m (127.3 sq.yd) to 338.0 sq.m (404.2 sq.yd); these are software-read from the layout drawing and should be checked against it. Layout record |
| Booked / available counts | Not disclosed in the supplied data. RERA record RERA amenities |
| Completion dates | Promoter’s Form B declaration gives 11th March 2024 as the completion undertaking; the RERA header records proposed and revised completion as 11/03/2024. RERA record |
| Construction stage | No independently verified site-progress assessment is supplied. The project is labelled “On-Going Project” in the filing. RERA filing |
| Occupancy / completion certificate | No occupancy or completion certificate is identified in the supplied records. The layout approval is described as tentative. Document index |
2. The project story
LAXMIPURAM SMARTCITY is recorded with TG-RERA as a plotted development in Kodad, Suryapet District. Its registered land identity comprises survey subdivisions 429/C3, 429/A6, 429/A4, 429/C1, 429/A2, 429/A5 and 429/C2 in Kodad Revenue Village. The tentative layout approval identifies 47 plots and assigns land for plots, internal roads, open space, utilities and social infrastructure. RERA record Layout record
The filing records a proposed completion date of 11/03/2024, and the promoter’s Form B declaration makes the same completion undertaking. The project is still labelled “On-Going Project” in the filing; the evidence supplied does not independently establish the present physical stage or that the development works have been completed. No occupancy or completion certificate is included in the reviewed material. RERA filing Document index
The layout approval is expressly a tentative approval. It requires the applicant to undertake infrastructure and development works, and states that final layout release follows completion of the required works and release of mortgaged land. These are approval-record conditions, not evidence that the works have been completed.
3. Master plan, architecture & building design
The supplied design evidence is for a plotted layout, not a residential building or apartment scheme. The tentative layout approval identifies 47 plots and a land-use allocation; the layout drawing record also counts 47 plots, with plot areas read by software from the drawing. Layout record
| Layout component | Area / share recorded |
|---|---|
| Plotted area | 8156.66 sq.m; 58.85% Layout record |
| Roads | 3795.41 sq.m; 27.38% Layout record |
| Parks / open space | 1255.75 sq.m; 9.06% Layout record |
| Utilities | 139.09 sq.m; 1.00% Layout record |
| Social infrastructure | 512.47 sq.m; 3.70% Layout record |
| Amenities | 0.00 sq.m; 0.00% Layout record |
The approval extraction separately describes the site as 3 Acer 17 Gts 16577 Sq. Yds and lists the land-use components in traditional area units. The drawing-derived layout record describes its land-use table as having a base area of 13859.38 sq.m. The RERA filing reports total and net land area of 13860.39 sqmts. Layout record RERA filing
The approval identifies 0 Acer 0 Gts for common parking space. It also identifies a mortgage area of 0 Acer 14 Gts 1694 Sq. Yds, corresponding to plots 34–39 and 33, in favour of the Municipality/Municipal Corporation. The RERA filing separately reports mortgage area of 1416.64 sq.m. RERA filing
No building arrangement, building count, floors, heights, building footprint, lifts or stairs are evidenced in the supplied material. The approved built-up-area figure of 8156.66 sqmts is recorded in the RERA filing; the documents supplied do not define its building or measurement basis. RERA filing
4. Homes, configurations & floor plans
This is a plotted layout, not an apartment configuration. The layout approval identifies 47 plots. The drawing-derived plot record reports a smallest area of 106.44 sq.m (127.3 sq.yd), median area of 166.65 sq.m (199.3 sq.yd) and largest area of 338.0 sq.m (404.2 sq.yd). These sizes are software-read from the drawing; the source notes they should be verified against the drawing. Layout record
| Plot-size band | Plot count |
|---|---|
| 100–150 sq.yd (84–125 sq.m) | 1 |
| 150–200 sq.yd (125–167 sq.m) | 28 |
| 200–250 sq.yd (167–209 sq.m) | 12 |
| 250–300 sq.yd (209–251 sq.m) | 2 |
| 300–400 sq.yd (251–334 sq.m) | 3 |
| 400–500 sq.yd (334–418 sq.m) | 1 |
The band counts and sizes are drawing-derived, not RERA-filed unit measurements. The supplied floor-plan review records two layout sheets and no apartment floor plans with flats, so there are no RERA-filed apartment saleable areas, measured carpet areas or loading figures to report. Layout record Floor plans
5. Parking & vehicle circulation
The tentative layout approval allocates 0 Acer 0 Gts (0%) to common parking space. The supplied material does not establish individual plot parking allocations, visitor or accessible parking, vehicle-entry arrangements, ramps, EV charging or parking capacity.
The approval requires roads to be formed and opened for accessibility to neighbouring sites. The drawing-derived layout record identifies 3795.41 sq.m of road area. Neither the presence of a drawn road nor the approval establishes completion of the road works. Layout record
6. Amenities, recreation & open spaces
The RERA filing’s amenity data records the following facilities and progress fields. These are filing declarations; the supplied evidence does not independently verify completion at site. RERA amenities
| Description / size | Road area 3795.41 sq.m in the drawing-derived layout land-use table Layout record |
|---|---|
| Evidence source | RERA amenity record and layout RERA amenities Layout record |
| Declared progress / verified status | RERA amenity field: YES, 100%; independent completion verification not supplied |
| Description / size | Parks/open space 1255.75 sq.m in the layout land-use table Layout record |
|---|---|
| Evidence source | RERA amenity record and layout RERA amenities Layout record |
| Declared progress / verified status | RERA amenity field: YES, 100%; independent completion verification not supplied |
| Description / size | No size or facility details supplied |
|---|---|
| Evidence source | RERA amenity record RERA amenities |
| Declared progress / verified status | Progress recorded as 0% |
| Description / size | No separate facility detail supplied |
|---|---|
| Evidence source | RERA amenity record RERA amenities |
| Declared progress / verified status | Progress recorded as 0% |
The approval also reserves 512.47 sq.m for social infrastructure and 139.09 sq.m for utilities. These are land-use allocations; the supplied material does not identify a specific community facility or confirm delivery. Layout record
7. Utilities, building services & safety
The tentative layout approval requires the applicant to provide infrastructure including a protected water-supply system, sewerage disposal, storm-water drains, street lighting, electricity facilities, rainwater-harvesting pits and greenery. It lists a water reservoir, septic tank, sewerage treatment plant, electric transformer and solid-waste management among the proposed utility works. These requirements and listed works do not establish that the facilities have been built or are operational.
The RERA amenity record marks water supply, sewerage, storm-water drains, street lighting, water conservation/rainwater harvesting, and electrical meter room/sub-station/receiving station as YES, 100%. It records treatment and disposal of sewage and sullage water as 0%, solid-waste management and disposal as 0%, and fire protection and fire-safety requirements as 0%. These are filing progress fields, not independent verification. RERA amenities
The supplied records do not provide water source or capacity, storage or treatment capacity, STP capacity, drainage design, electrical-load details, backup power, fire-system specifications, accessibility arrangements, or security and waste-management operating details. RERA amenities
8. Location, access & connectivity
The registered location is Kodad, Kodad Mandal, Suryapet District, Telangana, PIN 508206. The project’s recorded boundaries are east INDHIRAMMA COLONY, west LAND OF SAIDULU, north ROAD, and south LAND OF MADASU SAIDAYYA. RERA record RERA filing RERA filing
The location data supplies one approximate mapped connectivity reference: the nearest sampled Outer Ring Road interchange is listed at 146.1 km. The supplied record does not identify a project approach-road name, public-transport service, travel time or additional landmark distances. Location record
9. Developer & development status
The TG-RERA certificate names KONDA ANNAPURNA as promoter; the project header uses KONDA. The supplied data does not establish the promoter’s legal entity type, company-registration number or registered-office details. RERA record Corporate record
The promoter’s Form B declaration, made by Smt. Konda Annapurna as an authorised signatory, states a completion undertaking of 11th March 2024. The RERA header records proposed and revised completion as 11/03/2024. The filing’s “On-Going Project” status and absence of an independently verified construction-progress report mean that the current physical development stage cannot be established from the supplied evidence. RERA record RERA filing
The registration certificate states a validity period ending 11/03/2024; this is separate from the declared project completion date. No extension is recorded in the supplied certificate, and no occupancy or completion certificate is supplied. Document index
10. Approvals, official records & documents
| Record | Supplied evidence |
|---|---|
| TG-RERA registration | Form C certificate for P01900010015, for LAXMIPURAM SMARTCITY; validity stated as 11/03/2022–11/03/2024. |
| Principal layout approval | Tentative residential layout approval 0012/LO/3046/2022, issued by KODADA Municipality/Municipal Corporation; the extraction records approval date 03/11/2022 8:11:54 PM. |
| Approval application references | TS-bPASS application 004751/LO/DTCP/3046/0019/2021; receipt TS/12213/2021. |
| Layout drawing | Two layout sheets; drawing-derived record identifies 47 plots and area allocations. Plot sizes are software-read and noted for verification against the drawing. Layout record |
| Promoter declaration | Form B affidavit-cum-declaration by Smt. Konda Annapurna, identified as authorised signatory; includes the completion undertaking and project disclosures. |
| Occupancy / completion certificate | Not identified in the supplied documents. Document index |
| Construction progress evidence | No independent site-progress evidence supplied; filing status is “On-Going Project.” RERA filing Document index |
The approval document is a tentative layout plan and includes conditions for infrastructure development and later final layout release. The supplied document set does not include evidence of final layout release or completion of those works.
1. Project at a glance
Project identity
Registered project name: LAXMIPURAM SMARTCITY
Project type: Plotted development
Phase / registered portion: Phase not separately identified. TG-RERA registration covers the project identified against the listed survey numbers.
TG-RERA registration number: P01900010015
Registration validity: Certificate states validity from 11/03/2022 to 11/03/2024; no extension is recorded in the supplied certificate. This is registration validity, distinct from the completion deadline.
Registered promoter: KONDA ANNAPURNA (certificate); project filing header names promoter as KONDA.
RERA status: Filing identifies the project as On-Going Project. The supplied record does not establish a current registration extension or closure.
Land and geographic identity
Locality: Kodad
Revenue village: Kodad Revenue Village (also rendered “Kodada Revenue Village” in the layout approval)
Mandal / district / PIN: Kodad Mandal; Suryapet District; 508206
Project survey numbers and subdivisions: 429/C3, 429/A6, 429/A4, 429/C1, 429/A2, 429/A5, 429/C2
Registered site extent: Layout approval states 3 Acer 17 Gts 16577 Sq. Yds.
RERA land area: Total area 13860.39 sqmts; net area 13860.39 sqmts; affected area reported as 0 sqmts.
Boundaries: East: INDHIRAMMA COLONY; West: LAND OF SAIDULU; North: ROAD; South: LAND OF MADASU SAIDAYYA
Development identity
Sanctioning authority: KODADA Municipality/Municipal Corporation
Principal approval: Tentative layout plan 0012/LO/3046/2022, dated 03/11/2022 8:11:54 PM in the extracted approval record
Related application / receipt references: TS-bPASS application 004751/LO/DTCP/3046/0019/2021; receipt TS/12213/2021
Development form and count: Tentative residential plotted layout; 47 plots
Approved built-up area: RERA filing reports 8156.66 sqmts as approved built-up area. For a plotted layout, the supplied record does not explain the basis or identify buildings to which this figure relates.
Buildings / floors: Building count, floor configuration and parking levels are not disclosed in the supplied project record.
Offering and status
Unit type: Plots; the tentative layout approval identifies 47 plots.
Plot count and sizes: Drawing-derived layout record identifies 47 plots, with sizes from 106.44 sq.m (127.3 sq.yd) to 338.0 sq.m (404.2 sq.yd); these are software-read from the layout drawing and should be checked against it.
Booked / available counts: Not disclosed in the supplied data.
Completion dates: Promoter’s Form B declaration gives 11th March 2024 as the completion undertaking; the RERA header records proposed and revised completion as 11/03/2024.
Construction stage: No independently verified site-progress assessment is supplied. The project is labelled “On-Going Project” in the filing.
Occupancy / completion certificate: No occupancy or completion certificate is identified in the supplied records. The layout approval is described as tentative.
2. The project story
LAXMIPURAM SMARTCITY is recorded with TG-RERA as a plotted development in Kodad, Suryapet District. Its registered land identity comprises survey subdivisions 429/C3, 429/A6, 429/A4, 429/C1, 429/A2, 429/A5 and 429/C2 in Kodad Revenue Village. The tentative layout approval identifies 47 plots and assigns land for plots, internal roads, open space, utilities and social infrastructure.
The filing records a proposed completion date of 11/03/2024, and the promoter’s Form B declaration makes the same completion undertaking. The project is still labelled “On-Going Project” in the filing; the evidence supplied does not independently establish the present physical stage or that the development works have been completed. No occupancy or completion certificate is included in the reviewed material.
The layout approval is expressly a tentative approval. It requires the applicant to undertake infrastructure and development works, and states that final layout release follows completion of the required works and release of mortgaged land. These are approval-record conditions, not evidence that the works have been completed.
3. Master plan, architecture & building design
The supplied design evidence is for a plotted layout, not a residential building or apartment scheme. The tentative layout approval identifies 47 plots and a land-use allocation; the layout drawing record also counts 47 plots, with plot areas read by software from the drawing.
Plotted area: 8156.66 sq.m; 58.85%
Roads: 3795.41 sq.m; 27.38%
Parks / open space: 1255.75 sq.m; 9.06%
Utilities: 139.09 sq.m; 1.00%
Social infrastructure: 512.47 sq.m; 3.70%
Amenities: 0.00 sq.m; 0.00%
The approval extraction separately describes the site as 3 Acer 17 Gts 16577 Sq. Yds and lists the land-use components in traditional area units. The drawing-derived layout record describes its land-use table as having a base area of 13859.38 sq.m. The RERA filing reports total and net land area of 13860.39 sqmts.
The approval identifies 0 Acer 0 Gts for common parking space. It also identifies a mortgage area of 0 Acer 14 Gts 1694 Sq. Yds, corresponding to plots 34–39 and 33, in favour of the Municipality/Municipal Corporation. The RERA filing separately reports mortgage area of 1416.64 sq.m.
No building arrangement, building count, floors, heights, building footprint, lifts or stairs are evidenced in the supplied material. The approved built-up-area figure of 8156.66 sqmts is recorded in the RERA filing; the documents supplied do not define its building or measurement basis.
4. Homes, configurations & floor plans
This is a plotted layout, not an apartment configuration. The layout approval identifies 47 plots. The drawing-derived plot record reports a smallest area of 106.44 sq.m (127.3 sq.yd), median area of 166.65 sq.m (199.3 sq.yd) and largest area of 338.0 sq.m (404.2 sq.yd). These sizes are software-read from the drawing; the source notes they should be verified against the drawing.
100–150 sq.yd (84–125 sq.m): 1
150–200 sq.yd (125–167 sq.m): 28
200–250 sq.yd (167–209 sq.m): 12
250–300 sq.yd (209–251 sq.m): 2
300–400 sq.yd (251–334 sq.m): 3
400–500 sq.yd (334–418 sq.m): 1
The band counts and sizes are drawing-derived, not RERA-filed unit measurements. The supplied floor-plan review records two layout sheets and no apartment floor plans with flats, so there are no RERA-filed apartment saleable areas, measured carpet areas or loading figures to report.
5. Parking & vehicle circulation
The tentative layout approval allocates 0 Acer 0 Gts (0%) to common parking space. The supplied material does not establish individual plot parking allocations, visitor or accessible parking, vehicle-entry arrangements, ramps, EV charging or parking capacity.
The approval requires roads to be formed and opened for accessibility to neighbouring sites. The drawing-derived layout record identifies 3795.41 sq.m of road area. Neither the presence of a drawn road nor the approval establishes completion of the road works.
6. Amenities, recreation & open spaces
The RERA filing’s amenity data records the following facilities and progress fields. These are filing declarations; the supplied evidence does not independently verify completion at site.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Internal roads and footpaths | Road area 3795.41 sq.m in the drawing-derived layout land-use table | RERA amenity record and layout | RERA amenity field: YES, 100%; independent completion verification not supplied |
| Green strip / tot lot / park | Parks/open space 1255.75 sq.m in the layout land-use table | RERA amenity record and layout | RERA amenity field: YES, 100%; independent completion verification not supplied |
| Community buildings | No size or facility details supplied | RERA amenity record | Progress recorded as 0% |
| Aggregate recreational open space | No separate facility detail supplied | RERA amenity record | Progress recorded as 0% |
The approval also reserves 512.47 sq.m for social infrastructure and 139.09 sq.m for utilities. These are land-use allocations; the supplied material does not identify a specific community facility or confirm delivery.
7. Utilities, building services & safety
The tentative layout approval requires the applicant to provide infrastructure including a protected water-supply system, sewerage disposal, storm-water drains, street lighting, electricity facilities, rainwater-harvesting pits and greenery. It lists a water reservoir, septic tank, sewerage treatment plant, electric transformer and solid-waste management among the proposed utility works. These requirements and listed works do not establish that the facilities have been built or are operational.
The RERA amenity record marks water supply, sewerage, storm-water drains, street lighting, water conservation/rainwater harvesting, and electrical meter room/sub-station/receiving station as YES, 100%. It records treatment and disposal of sewage and sullage water as 0%, solid-waste management and disposal as 0%, and fire protection and fire-safety requirements as 0%. These are filing progress fields, not independent verification.
The supplied records do not provide water source or capacity, storage or treatment capacity, STP capacity, drainage design, electrical-load details, backup power, fire-system specifications, accessibility arrangements, or security and waste-management operating details.
8. Location, access & connectivity
The registered location is Kodad, Kodad Mandal, Suryapet District, Telangana, PIN 508206. The project’s recorded boundaries are east INDHIRAMMA COLONY, west LAND OF SAIDULU, north ROAD, and south LAND OF MADASU SAIDAYYA.
The location data supplies one approximate mapped connectivity reference: the nearest sampled Outer Ring Road interchange is listed at 146.1 km. The supplied record does not identify a project approach-road name, public-transport service, travel time or additional landmark distances.
9. Developer & development status
The TG-RERA certificate names KONDA ANNAPURNA as promoter; the project header uses KONDA. The supplied data does not establish the promoter’s legal entity type, company-registration number or registered-office details.
The promoter’s Form B declaration, made by Smt. Konda Annapurna as an authorised signatory, states a completion undertaking of 11th March 2024. The RERA header records proposed and revised completion as 11/03/2024. The filing’s “On-Going Project” status and absence of an independently verified construction-progress report mean that the current physical development stage cannot be established from the supplied evidence.
The registration certificate states a validity period ending 11/03/2024; this is separate from the declared project completion date. No extension is recorded in the supplied certificate, and no occupancy or completion certificate is supplied.
10. Approvals, official records & documents
TG-RERA registration: Form C certificate for P01900010015, for LAXMIPURAM SMARTCITY; validity stated as 11/03/2022–11/03/2024.
Principal layout approval: Tentative residential layout approval 0012/LO/3046/2022, issued by KODADA Municipality/Municipal Corporation; the extraction records approval date 03/11/2022 8:11:54 PM.
Approval application references: TS-bPASS application 004751/LO/DTCP/3046/0019/2021; receipt TS/12213/2021.
Layout drawing: Two layout sheets; drawing-derived record identifies 47 plots and area allocations. Plot sizes are software-read and noted for verification against the drawing.
Promoter declaration: Form B affidavit-cum-declaration by Smt. Konda Annapurna, identified as authorised signatory; includes the completion undertaking and project disclosures.
Occupancy / completion certificate: Not identified in the supplied documents.
Construction progress evidence: No independent site-progress evidence supplied; filing status is “On-Going Project.”
The approval document is a tentative layout plan and includes conditions for infrastructure development and later final layout release. The supplied document set does not include evidence of final layout release or completion of those works.
Frequently asked questions
Is LAXMIPURAM SMARTCITY registered with Telangana RERA?
Yes. LAXMIPURAM SMARTCITY is registered with the Telangana Real Estate Regulatory Authority as P01900010015; the registration status is On-Going Project.
Who is the developer of LAXMIPURAM SMARTCITY?
The promoter named in the RERA registration is KONDA.
Where is LAXMIPURAM SMARTCITY located?
LAXMIPURAM SMARTCITY is in Kodad, Suryapet, Telangana (508206).
When will LAXMIPURAM SMARTCITY be completed?
The promoter's proposed date of completion filed with RERA is 11/03/2024. This is the promoter's declaration, not a guarantee.