H Emerald
EMERALD CONSTRUCTIONS · Rangareddy · RERA P02400001134
H Emerald is a plotted development at Raipole, Ibrahimpatnam, Ranga Reddy District, developed by its registered promoter, Emerald Constructions. The registered site extent is 49,673.06 Sqm, and the approved layout drawing is software-read as showing 131 residential plots ranging from 150.0 to 502.0 sqm. The project is registered with TG-RERA under P02400001134, and the promoter’s Form B declaration states a completion date of 06-05-2022.
More from Emerald Constructions · 4 projects →
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
8 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
Project at a glance
Project identity
| Field | Record |
|---|---|
| Registered project name | H Emerald |
| Project type | Plotted development / residential open-plot layout RERA record |
| Phase / registered portion | A separate phase is not identified; the TG-RERA certificate covers the project in survey numbers 496/P, 498/P and 499/P |
| TG-RERA registration | P02400001134 |
| Registration validity | 05/09/2019–06/05/2022; the certificate records two years’ validity and says extension would be by Authority action. The supplied certificate record says no extension |
| Registered promoter | Emerald Constructions |
| RERA status | The project is registered; the supplied certificate’s validity ended on 06/05/2022. Current registration status is not established by the supplied records |
Land and geographic identity
| Field | Record |
|---|---|
| Locality / revenue village | Raipole; the final layout letter identifies Raipole village RERA record |
| Mandal / district / PIN | Ibrahimpatnam / Ranga Reddy / 501508 RERA record |
| Project survey numbers | 496/P, 498/P, 499/P |
| Registered site extent | 49,673.06 Sqm |
| RERA land-area disclosure | Total area 49,673.06 sqmts; area affected in road widening/FTL of tanks/nala widening 21,666.70 sqmts; net area 28,006.36 sqmts RERA filing |
| Layout-letter area statement | The final layout letter states an extent of 49,673.06 Sqm |
| Boundaries in RERA filing | East: Neighbours Land; West: Dream City-II Layout; North: Neighbours Land; South: Dream City-II Layout RERA filing |
Development identity
| Field | Record |
|---|---|
| Sanctioning authority | Hyderabad Metropolitan Development Authority (HMDA) |
| Principal layout approval | 000108/LO/Plg/HMDA/2019, final layout letter dated 05 January, 2023 |
| Earlier draft layout approval | 000108/LO/Plg/HMDA/2019, dated 07 May, 2019 |
| Approved built-up area | RERA filing states 28,006.36 sqmts RERA filing |
| Buildings / floors | Not disclosed as a building project; the evidence identifies a plotted layout. Building-specific floor configuration and building count are not established |
| Parking | No project-wide parking count or parking-level information is supplied. The draft layout identifies 18 mortgaged plots |
Offering and status
| Field | Record |
|---|---|
| Unit type | Residential plots RERA record |
| Plot count and size range | The approved layout drawing is software-read as 131 plots, ranging from 150.0 to 502.0 sqm (179.4 to 600.4 sq yd); drawing-based figures should be checked against the plan Layout record |
| Booked / available | Not disclosed in the supplied project data RERA filing |
| Construction stage | No independently verified site-progress assessment is supplied. The RERA filing is identified as a “New Project”; a vendor listing describes it as ready-to-move, but that is third-party marketing information, not a verified project status RERA record Promoter website |
| Original declared completion | 06-05-2022, as stated in the promoter’s Form B declaration |
| Revised completion | Not supplied |
| Occupancy / completion certificate | No project completion or occupancy certificate is identified in the supplied documents. The HMDA record is a final layout approval, not an occupancy certificate |
The project story
H Emerald is recorded with TG-RERA as a residential plotted development at Raipole, Ibrahimpatnam Mandal, Ranga Reddy District. Its registered land identity is survey numbers 496/P, 498/P and 499/P. HMDA’s final layout letter describes a residential open-plot layout over 49,673.06 Sqm.
The layout drawing is software-read as showing 131 plots. That count and the plot-size range are drawing-derived, not RERA-disclosed inventory figures; the supplied data does not provide booked or available plot counts. The promoter declared a completion date of 06-05-2022 in Form B. The material supplied does not independently establish current physical progress, completed infrastructure, or project-wide completion Layout record.
Master plan, architecture & building design
This is a plotted layout rather than a multi-storey building scheme. The RERA filing records an approved built-up area of 28,006.36 sqmts; the final HMDA layout letter records a site extent of 49,673.06 Sqm RERA filing.
The approved layout drawing is software-read as containing 131 plots. Its area statement records 28,006.34 sqm as plotted area, 16,225.34 sqm as roads, 4,166.18 sqm as parks/open space, 1,275.22 sqm as social infrastructure, and 0.00 sqm as amenities. These are drawing-derived readings; the drawing data notes that the figures should be verified against the plan Layout record.
The final HMDA letter states that roads, open spaces and social infrastructure were taken over by the Local Authority under registered gift deed 12313/2020, dated 24.12.2020, and refers to relinquishment deed 18392/2022, dated 21/12/2022, for mortgaged plots. The draft layout letter identifies Plots 52–61 and 124–131, totalling 18 plots, as mortgaged to HMDA; it does not establish the current status of any individual plot for sale.
HMDA’s master-plan zoning sheet is available as an image, but the supplied records do not establish the exact zoning at the project surveys HMDA. No building footprints, floor plans, building heights, or plot-by-plot orientation details are supplied.
Homes, configurations & floor plans
The offering is plots, not apartments. No RERA-filed unit-type inventory, booked/available counts, or saleable-area schedule is supplied. The approved layout drawing is software-read as follows:
| Plot information | Drawing-derived reading |
|---|---|
| Plots shown | 131 |
| Smallest plot | 150.0 sqm / 179.4 sq yd |
| Median plot | 181.0 sqm / 216.5 sq yd |
| Largest plot | 502.0 sqm / 600.4 sq yd |
| Plot-size bands | 15 plots at 150–200 sq yd; 82 at 200–250 sq yd; 3 at 250–300 sq yd; 24 at 300–400 sq yd; 4 at 400–500 sq yd; 3 at 500–1000 sq yd |
These are software-measured readings from the approved layout drawing, not RERA-filed plot inventory or a plot-specific sale schedule Layout record. The supplied floor-plan record contains three layout sheets and no measured floor plans; carpet-area, room-dimension, balcony, and common-area-loading data are not applicable or not provided for the plotted offering Floor plans. The vendor data lists two plot configuration entries as “saleable 1621 Sq. Ft.” and “saleable 5402 Sq. Ft.”; these are third-party listing details, not TG-RERA inventory Promoter website.
Parking & vehicle circulation
The final layout approval describes internal roads and requires the roads to remain open for free access to the public; it also states that no compound wall is permitted. The draft approval records road widths of 18 mts and above and 60 feet and above. No separate vehicle-entry arrangement, visitor or accessible parking provision, EV charging, parking count, or plot-specific parking allocation is established by the supplied records. The draft approval identifies 18 mortgaged plots, but does not make them parking spaces.
Amenities, recreation & open spaces
| Description / size | Layout roads; drawing-read road area 16,225.34 sqm |
|---|---|
| Evidence source | Layout record RERA amenities |
| Declared progress / verified status | Marked available at 100% in the amenities data; this is a filed status, not independent site verification |
| Description / size | Drawing-read parks/open space 4,166.18 sqm |
|---|---|
| Evidence source | Layout record RERA amenities |
| Declared progress / verified status | Green strip/TOT LOT/park marked available at 100%; completion is not independently verified |
| Description / size | Drawing-read area 1,275.22 sqm |
|---|---|
| Evidence source | Layout record |
| Declared progress / verified status | Final layout letter says social infrastructure area was handed over to the Local Authority by registered gift deed; no facility type or delivered use is specified |
| Description / size | No quantity or area stated |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | Final layout conditions refer to street lighting; amenities data marks it available at 100%, without independent verification |
| Description / size | Layout provision; no capacity stated |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | Final layout conditions identify a rainwater-harvesting structure; amenities data marks water conservation/rainwater harvesting available at 100%, not independently verified |
The HMDA draft approval also lists a park, but its other listed facilities—such as a common septic tank/STP, internal water lines, overhead tank, transformer and bio-compost unit—are addressed under utilities and are not confirmed as independently completed. No clubhouse, pool, gym or children’s play area is established by the project’s supplied RERA/layout documents; such items appear only in third-party vendor amenities Promoter website.
Utilities, building services & safety
HMDA’s final layout conditions describe water supply, sewerage and drainage disposal systems, street lighting, rainwater-harvesting structure and other civic amenities, and assign the local body responsibility for maintenance of the services. The draft layout approval lists a common septic tank/STP, internal water-supply pipelines, an overhead tank, transformer, rainwater-harvesting pits and a bio-compost unit. Their capacities, operating status and completion are not established.
The RERA amenities data marks water supply, sewerage, storm-water drains, sewage treatment/disposal, solid-waste management, energy management, fire protection, electrical meter room/sub-station/receiving station, and aggregate recreational open-space fields at 0%; it marks roads, green strip/park, street lighting and rainwater harvesting at 100%. These are recorded progress fields, not independent inspection results RERA amenities. No lift, fire-system specification, emergency access arrangement, CCTV, access-control, backup-power, or accessibility provision is documented in the supplied project records. Third-party vendor claims about security, power backup and 24-hour water supply are not treated as verified project facilities Promoter website.
Location, access & connectivity
The registered location is Raipole, Ibrahimpatnam Mandal, Ranga Reddy District, Telangana, PIN 501508 RERA record. The HMDA layout documents identify the project at Raipole in survey numbers 496/P, 498/P and 499/P. The supplied data identifies Dream City-II Layout to the west and south, and neighbouring land to the east and north RERA filing.
The draft HMDA approval refers to internal layout roads of 18 mts and above and 60 feet and above. No measured distances to landmarks, public-transport information, or verified travel times are supplied. A third-party listing names Raipole as the nearest landmark but provides no measured connectivity information Promoter website.
Developer & development status
The TG-RERA certificate names Emerald Constructions as the registered promoter. The RERA filing identifies the organisation type as a Partnership and lists the promoter name as EMERALD CONSTRUCTIONS RERA filing. The supplied project records identify S. Durga Reddy as the Form B declarant/authorised signatory and HMDA applicant representative.
The promoter’s Form B declaration states a completion date of 06-05-2022 and declares that 70% of amounts realised would be deposited in a separate account for construction and land cost. The TG-RERA certificate also records the separate-account condition. The supplied records do not provide a revised completion date, verified site-progress report, current registration-status confirmation, or completion/occupancy certificate. The RERA filing gives a masked identifier xxxxxx872Q, but its type is not stated RERA filing.
Approvals, official records & documents
| Identifier / date | P02400001134; issued 05/09/2019 |
|---|---|
| What the supplied record establishes | Form C registers H Emerald under section 5 and records validity through 06/05/2022 |
| Identifier / date | 000108/LO/Plg/HMDA/2019; 07 May, 2019 |
|---|---|
| What the supplied record establishes | Draft open-plot layout approval for survey numbers 496/P, 498/P and 499/P, with stated development conditions |
| Identifier / date | 000108/LO/Plg/HMDA/2019; 05 January, 2023 |
|---|---|
| What the supplied record establishes | Final residential open-plot layout letter for the same survey numbers and site extent 49,673.06 Sqm |
| Identifier / date | Verified 7 August, 2019 |
|---|---|
| What the supplied record establishes | Promoter declaration of title basis, encumbrance disclosure, separate-account undertakings and completion date 06-05-2022 |
| Identifier / date | Not identified in supplied documents |
|---|---|
| What the supplied record establishes | No project completion or occupancy certificate is established by this evidence set |
The HMDA final layout letter records gift deed 12313/2020, dated 24.12.2020, for roads, open spaces and social infrastructure, and relinquishment deed 18392/2022, dated 21/12/2022, concerning mortgaged plots. No building-specific sanction, commencement certificate for buildings, or occupancy/completion certificate is identified in the supplied records.
Project at a glance
Project identity
Registered project name: H Emerald
Project type: Plotted development / residential open-plot layout
Phase / registered portion: A separate phase is not identified; the TG-RERA certificate covers the project in survey numbers 496/P, 498/P and 499/P
TG-RERA registration: P02400001134
Registration validity: 05/09/2019–06/05/2022; the certificate records two years’ validity and says extension would be by Authority action. The supplied certificate record says no extension
Registered promoter: Emerald Constructions
RERA status: The project is registered; the supplied certificate’s validity ended on 06/05/2022. Current registration status is not established by the supplied records
Land and geographic identity
Locality / revenue village: Raipole; the final layout letter identifies Raipole village
Mandal / district / PIN: Ibrahimpatnam / Ranga Reddy / 501508
Project survey numbers: 496/P, 498/P, 499/P
Registered site extent: 49,673.06 Sqm
RERA land-area disclosure: Total area 49,673.06 sqmts; area affected in road widening/FTL of tanks/nala widening 21,666.70 sqmts; net area 28,006.36 sqmts
Layout-letter area statement: The final layout letter states an extent of 49,673.06 Sqm
Boundaries in RERA filing: East: Neighbours Land; West: Dream City-II Layout; North: Neighbours Land; South: Dream City-II Layout
Development identity
Sanctioning authority: Hyderabad Metropolitan Development Authority (HMDA)
Principal layout approval: 000108/LO/Plg/HMDA/2019, final layout letter dated 05 January, 2023
Earlier draft layout approval: 000108/LO/Plg/HMDA/2019, dated 07 May, 2019
Approved built-up area: RERA filing states 28,006.36 sqmts
Buildings / floors: Not disclosed as a building project; the evidence identifies a plotted layout. Building-specific floor configuration and building count are not established
Parking: No project-wide parking count or parking-level information is supplied. The draft layout identifies 18 mortgaged plots
Offering and status
Unit type: Residential plots
Plot count and size range: The approved layout drawing is software-read as 131 plots, ranging from 150.0 to 502.0 sqm (179.4 to 600.4 sq yd); drawing-based figures should be checked against the plan
Booked / available: Not disclosed in the supplied project data
Construction stage: No independently verified site-progress assessment is supplied. The RERA filing is identified as a “New Project”; a vendor listing describes it as ready-to-move, but that is third-party marketing information, not a verified project status
Original declared completion: 06-05-2022, as stated in the promoter’s Form B declaration
Revised completion: Not supplied
Occupancy / completion certificate: No project completion or occupancy certificate is identified in the supplied documents. The HMDA record is a final layout approval, not an occupancy certificate
The project story
H Emerald is recorded with TG-RERA as a residential plotted development at Raipole, Ibrahimpatnam Mandal, Ranga Reddy District. Its registered land identity is survey numbers 496/P, 498/P and 499/P. HMDA’s final layout letter describes a residential open-plot layout over 49,673.06 Sqm.
The layout drawing is software-read as showing 131 plots. That count and the plot-size range are drawing-derived, not RERA-disclosed inventory figures; the supplied data does not provide booked or available plot counts. The promoter declared a completion date of 06-05-2022 in Form B. The material supplied does not independently establish current physical progress, completed infrastructure, or project-wide completion.
Master plan, architecture & building design
This is a plotted layout rather than a multi-storey building scheme. The RERA filing records an approved built-up area of 28,006.36 sqmts; the final HMDA layout letter records a site extent of 49,673.06 Sqm.
The approved layout drawing is software-read as containing 131 plots. Its area statement records 28,006.34 sqm as plotted area, 16,225.34 sqm as roads, 4,166.18 sqm as parks/open space, 1,275.22 sqm as social infrastructure, and 0.00 sqm as amenities. These are drawing-derived readings; the drawing data notes that the figures should be verified against the plan.
The final HMDA letter states that roads, open spaces and social infrastructure were taken over by the Local Authority under registered gift deed 12313/2020, dated 24.12.2020, and refers to relinquishment deed 18392/2022, dated 21/12/2022, for mortgaged plots. The draft layout letter identifies Plots 52–61 and 124–131, totalling 18 plots, as mortgaged to HMDA; it does not establish the current status of any individual plot for sale.
HMDA’s master-plan zoning sheet is available as an image, but the supplied records do not establish the exact zoning at the project surveys. No building footprints, floor plans, building heights, or plot-by-plot orientation details are supplied.
Homes, configurations & floor plans
The offering is plots, not apartments. No RERA-filed unit-type inventory, booked/available counts, or saleable-area schedule is supplied. The approved layout drawing is software-read as follows:
Plots shown: 131
Smallest plot: 150.0 sqm / 179.4 sq yd
Median plot: 181.0 sqm / 216.5 sq yd
Largest plot: 502.0 sqm / 600.4 sq yd
Plot-size bands: 15 plots at 150–200 sq yd; 82 at 200–250 sq yd; 3 at 250–300 sq yd; 24 at 300–400 sq yd; 4 at 400–500 sq yd; 3 at 500–1000 sq yd
These are software-measured readings from the approved layout drawing, not RERA-filed plot inventory or a plot-specific sale schedule. The supplied floor-plan record contains three layout sheets and no measured floor plans; carpet-area, room-dimension, balcony, and common-area-loading data are not applicable or not provided for the plotted offering. The vendor data lists two plot configuration entries as “saleable 1621 Sq. Ft.” and “saleable 5402 Sq. Ft.”; these are third-party listing details, not TG-RERA inventory.
Parking & vehicle circulation
The final layout approval describes internal roads and requires the roads to remain open for free access to the public; it also states that no compound wall is permitted. The draft approval records road widths of 18 mts and above and 60 feet and above. No separate vehicle-entry arrangement, visitor or accessible parking provision, EV charging, parking count, or plot-specific parking allocation is established by the supplied records. The draft approval identifies 18 mortgaged plots, but does not make them parking spaces.
Amenities, recreation & open spaces
| Description / size | Layout roads; drawing-read road area 16,225.34 sqm |
|---|---|
| Declared progress / verified status | Marked available at 100% in the amenities data; this is a filed status, not independent site verification |
| Description / size | Drawing-read parks/open space 4,166.18 sqm |
|---|---|
| Declared progress / verified status | Green strip/TOT LOT/park marked available at 100%; completion is not independently verified |
| Description / size | Drawing-read area 1,275.22 sqm |
|---|---|
| Declared progress / verified status | Final layout letter says social infrastructure area was handed over to the Local Authority by registered gift deed; no facility type or delivered use is specified |
| Description / size | No quantity or area stated |
|---|---|
| Declared progress / verified status | Final layout conditions refer to street lighting; amenities data marks it available at 100%, without independent verification |
| Description / size | Layout provision; no capacity stated |
|---|---|
| Declared progress / verified status | Final layout conditions identify a rainwater-harvesting structure; amenities data marks water conservation/rainwater harvesting available at 100%, not independently verified |
The HMDA draft approval also lists a park, but its other listed facilities—such as a common septic tank/STP, internal water lines, overhead tank, transformer and bio-compost unit—are addressed under utilities and are not confirmed as independently completed. No clubhouse, pool, gym or children’s play area is established by the project’s supplied RERA/layout documents; such items appear only in third-party vendor amenities.
Utilities, building services & safety
HMDA’s final layout conditions describe water supply, sewerage and drainage disposal systems, street lighting, rainwater-harvesting structure and other civic amenities, and assign the local body responsibility for maintenance of the services. The draft layout approval lists a common septic tank/STP, internal water-supply pipelines, an overhead tank, transformer, rainwater-harvesting pits and a bio-compost unit. Their capacities, operating status and completion are not established.
The RERA amenities data marks water supply, sewerage, storm-water drains, sewage treatment/disposal, solid-waste management, energy management, fire protection, electrical meter room/sub-station/receiving station, and aggregate recreational open-space fields at 0%; it marks roads, green strip/park, street lighting and rainwater harvesting at 100%. These are recorded progress fields, not independent inspection results. No lift, fire-system specification, emergency access arrangement, CCTV, access-control, backup-power, or accessibility provision is documented in the supplied project records. Third-party vendor claims about security, power backup and 24-hour water supply are not treated as verified project facilities.
Location, access & connectivity
The registered location is Raipole, Ibrahimpatnam Mandal, Ranga Reddy District, Telangana, PIN 501508. The HMDA layout documents identify the project at Raipole in survey numbers 496/P, 498/P and 499/P. The supplied data identifies Dream City-II Layout to the west and south, and neighbouring land to the east and north.
The draft HMDA approval refers to internal layout roads of 18 mts and above and 60 feet and above. No measured distances to landmarks, public-transport information, or verified travel times are supplied. A third-party listing names Raipole as the nearest landmark but provides no measured connectivity information.
Developer & development status
The TG-RERA certificate names Emerald Constructions as the registered promoter. The RERA filing identifies the organisation type as a Partnership and lists the promoter name as EMERALD CONSTRUCTIONS. The supplied project records identify S. Durga Reddy as the Form B declarant/authorised signatory and HMDA applicant representative.
The promoter’s Form B declaration states a completion date of 06-05-2022 and declares that 70% of amounts realised would be deposited in a separate account for construction and land cost. The TG-RERA certificate also records the separate-account condition. The supplied records do not provide a revised completion date, verified site-progress report, current registration-status confirmation, or completion/occupancy certificate. The RERA filing gives a masked identifier xxxxxx872Q, but its type is not stated.
Approvals, official records & documents
| Identifier / date | P02400001134; issued 05/09/2019 |
|---|---|
| What the supplied record establishes | Form C registers H Emerald under section 5 and records validity through 06/05/2022 |
| Identifier / date | 000108/LO/Plg/HMDA/2019; 07 May, 2019 |
|---|---|
| What the supplied record establishes | Draft open-plot layout approval for survey numbers 496/P, 498/P and 499/P, with stated development conditions |
| Identifier / date | 000108/LO/Plg/HMDA/2019; 05 January, 2023 |
|---|---|
| What the supplied record establishes | Final residential open-plot layout letter for the same survey numbers and site extent 49,673.06 Sqm |
| Identifier / date | Verified 7 August, 2019 |
|---|---|
| What the supplied record establishes | Promoter declaration of title basis, encumbrance disclosure, separate-account undertakings and completion date 06-05-2022 |
| Identifier / date | Not identified in supplied documents |
|---|---|
| What the supplied record establishes | No project completion or occupancy certificate is established by this evidence set |
The HMDA final layout letter records gift deed 12313/2020, dated 24.12.2020, for roads, open spaces and social infrastructure, and relinquishment deed 18392/2022, dated 21/12/2022, concerning mortgaged plots. No building-specific sanction, commencement certificate for buildings, or occupancy/completion certificate is identified in the supplied records.
Frequently asked questions
Is H Emerald registered with Telangana RERA?
Yes. H Emerald is registered with the Telangana Real Estate Regulatory Authority as P02400001134; the registration status is New Project.
Who is the developer of H Emerald?
The promoter named in the RERA registration is EMERALD CONSTRUCTIONS.
Where is H Emerald located?
H Emerald is in Raipole, Ibrahimpatnam, Rangareddy, Telangana (501508).
When will H Emerald be completed?
The promoter's proposed date of completion filed with RERA is 06/05/2022. This is the promoter's declaration, not a guarantee.