Pearl City

SAI BALAJI PROJECTS · Sangareddy · RERA P01100001426

PEARL CITY is a plotted development in Indrakaran, Kandi mandal, Sangareddy district. The registered promoter is Sai Balaji Projects. The site area is 42435.35 sq.m, and the project is an open-plot layout; the supplied records do not state a plot count or individual plot sizes. It is registered under TG-RERA number P01100001426, with a proposed completion date of 22nd February 2022.

More from Sai Balaji Projects · 2 projects →

01What we found

Period endedTG-RERA registration ran to 22 Feb 2022 - check its extension on TG-RERA
11documents on file - each fact links to its page
0court cases on this project's land in the court records searched
9items to check - 3 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

9 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

1. Project at a glance

Project identity

ItemRecord
Registered project namePEARL CITY
Project typePlotted development / open-plot layout RERA record
Phase or registered portionA separate phase is not identified in the supplied record; the registration is for PEARL CITY
TG-RERA registrationP01100001426
Registration validity25/11/2019–22/02/2022; the certificate states two years and no extension is recorded in the supplied certificate
Registered promoterSai Balaji Projects; entity type stated as partnership Corporate record RERA filing
RERA statusThe supplied certificate records registration; its stated validity period has ended. Current portal status is not established by the supplied record.

Land and geographic identity

ItemRecord
LocalityIndrakaran RERA record
Revenue villageIndrakaran RERA record
Mandal / district / PINKandi / Sangareddy / 502329 RERA record
Project survey numbers441, 445 and 439; no subdivisions are specified in the project filing RERA record
Site area and deductionsTotal site area 42435.35 sq.m; road-widening area 253.59 sq.m; net layout area 42181.76 sq.m RERA filing
BoundariesEast: “VAGU SURVEY NO 439 AA 1”; West: “ROAD INDRAKARAN TO CHERIYAL”; North: “LAND OF OWNERS AND KANDI NARAYANA”; South: “NAGAIAH SURVAY NO 437 AND MALLAIAH” RERA filing

Development identity

ItemRecord
Sanctioning authorityHyderabad Metropolitan Development Authority (HMDA)
Principal layout approvalHMDA Layout Permit 000047/LO/Plg/HMDA/2019, dated 22 February 2019
Approved built-up areaNot stated in the supplied layout approval; the project is a plotted layout, and no building or residential tower configuration is provided Approvals record
Layout land-use figuresPlotted area 26022.80 sq.m; layout roads 11385.72 sq.m; organized open space/park/utility area 3381.66 sq.m; social infrastructure 1108.48 sq.m; amenity area 0.00 sq.m
HMDA-mortgaged plotsPlots 1 to 3, 5 to 7 and 150 to 161—18 plots, totaling 3946.82 sq.m—are identified as mortgaged to HMDA

Offering and status

ItemRecord
Unit typeOpen plots; the RERA registration identifies a plotted development RERA record
Plot count and sizesNot established by the supplied records. The layout extraction says the plot details are incomplete and no plot-size measurements are available. Layout record
Booked / available countsNot established in the supplied data. Layout record
Construction / development stageThe RERA-filed amenity progress data reports internal roads and footpaths at 80% and sewerage at 60%; other reported items are at 0%. These are filed progress figures, not independent site verification. RERA amenities
Completion deadlineThe promoter’s Form B states a completion undertaking of 22nd February 2022 for the open-plot layout.
Occupancy / completion certificateNo occupancy or completion certificate is identified in the supplied records. For this plotted layout, the supplied documents identify layout permission and development works, not a building-phase OC. Document index Approvals record

2. The project story

PEARL CITY is a proposed residential plotted layout in Indrakaran village, Kandi mandal, Sangareddy district. The RERA registration covers plots rather than apartments or villas, and the filed site identity comprises survey numbers 441, 445 and 439. RERA record

The HMDA layout plan allocates land to plots, internal roads, open space/parks and utility areas, and social infrastructure. It also identifies 18 plots mortgaged to HMDA. The approval describes required layout development works, including roads and open spaces; it does not establish that these works have since been completed.

The RERA-filed progress figures report 80% completion for internal roads and footpaths and 60% for sewerage; several other infrastructure categories are recorded at 0%. These are promoter-submitted progress indicators in the supplied RERA data and are not an independent inspection of the site. RERA amenities

3. Master plan, architecture & building design

The HMDA-approved layout is a plotted plan, not a building or floor plan. Its stated total site area is 42435.35 sq.m, with 253.59 sq.m identified as road-widening area and a net layout area of 42181.76 sq.m. The area statement allocates 26022.80 sq.m to plots, 11385.72 sq.m to layout roads, 3381.66 sq.m to organized open space/park/utility area, 1108.48 sq.m to social infrastructure and 0.00 sq.m to amenity area. Layout record

The plan identifies PARK-1 438.00 Sq.Mtrs, PARK-2 1885.74 Sq.Mtrs, and UTILITY AREAS 213.34 Sq. Mtrs within the open-space/utility description. The plan also specifies road widths of 9.00, 9.92 and 12.00 M. These are drawing-derived approval details; the supplied material does not provide a complete, verified plot schedule or individual plot dimensions.

No buildings, building footprints, floors, parking levels, apartment layouts or building count are evidenced in the supplied project record. Approvals record Document index

4. Homes, configurations & floor plans

This is a plotted development; apartment configuration, apartment saleable area and measured carpet area are not applicable based on the supplied RERA project record. RERA record

Open plots
CountNot established
BookedNot established
AvailableNot established
Plot area / size bandsIndividual plot sizes and size bands are not established in the supplied data. Layout record

The approved layout drawing extraction is incomplete for plot-by-plot measurements, and the supplied floor-plan dataset contains no measured homes. A third-party vendor record lists “Plot” with “built-up 1,313 - 4,068 sq ft,” but the RERA-filed record does not establish those as approved plot sizes or a complete plot schedule; this Overview therefore does not present them as the project’s verified offering. Layout record Floor plans Promoter website

5. Parking & vehicle circulation

The supplied records do not establish sanctioned parking counts, visitor or accessible parking, parking allocation to individual plots, or EV charging. The approval plan identifies internal layout roads and road widths of 9.00, 9.92 and 12.00 M; it does not establish individual parking rights or spaces.

6. Amenities, recreation & open spaces

The HMDA layout approval identifies parks and open-space/utility land. The progress percentages below are RERA-filed figures; a recorded percentage is not independent confirmation of completion. RERA amenities

FacilityDescription / sizeEvidence sourceDeclared progress / verified status
Park 1438.00 Sq.MtrsHMDA layout planRERA amenity category “Green Strip/TOT LOT/Park”: 0%; not independently verified RERA amenities
Park 21885.74 Sq.MtrsHMDA layout planRERA amenity category “Green Strip/TOT LOT/Park”: 0%; not independently verified RERA amenities
Organized open space / park / utility area3381.66 sq.m in the layout area statementHMDA layout planNo independent completion verification supplied
Utility areas213.34 Sq. MtrsHMDA layout planNo independent completion verification supplied
Social infrastructure1108.48 Sq. MtrsHMDA layout planRERA-filed “Community Buildings”: 0%; no facility-specific completion verification supplied RERA amenities
Amenity area0.00 sq.m in the layout area statementHMDA layout planNot applicable as a separately allocated amenity-area figure in that statement
Internal roads and footpathsLayout roads total 11385.72 sq.mHMDA layout planRERA-filed progress: 80%; not independently verified RERA amenities

A vendor record lists a clubhouse, power backup, security, reserved parking, water storage, street lighting, parks and other amenities. These are vendor-listed claims, not established here as HMDA-sanctioned or delivered facilities. Promoter website

7. Utilities, building services & safety

The HMDA approval-document extraction lists proposed layout infrastructure including storm-water drains, underground drainage lines, a common septic tank/STP, internal water-supply pipelines, an overhead tank, a transformer, avenue plantation, park development and rainwater-harvesting pits. The extracted approval information identifies these as layout provisions; the supplied record does not establish their capacities or independent completion.

Water
Evidence in the supplied recordInternal water-supply pipelines and an overhead tank are listed in the approval-document extraction.
Status limitationSource, storage capacity, treatment and independently verified operation are not established.
Sewerage and drainage
Evidence in the supplied recordUnderground drainage lines, a common septic tank/STP and storm-water drains are listed.
Status limitationRERA-filed sewerage progress is 60%; treatment/disposal is reported at 0%. No independent completion evidence is supplied. RERA amenities
Electrical
Evidence in the supplied recordA transformer is listed; the RERA progress record includes electrical meter room, sub-station and receiving station at 0%. RERA amenities
Status limitationInstalled capacity, backup and completion are not established.
Rainwater management
Evidence in the supplied recordRainwater-harvesting pits are listed; RERA-filed water conservation/rainwater harvesting progress is 0%. RERA amenities
Status limitationCompletion and operating details are not established.
Fire and life safety
Evidence in the supplied recordRERA-filed fire-protection and fire-safety progress is 0%. RERA amenities
Status limitationNo fire-system design, clearance or independent compliance evidence is supplied.
Waste, security and accessibility
Evidence in the supplied recordNo project-specific details are established in the supplied RERA or approval records. RERA amenities Document index
Status limitationNo verified facilities or capacities stated.

8. Location, access & connectivity

The registered project location is Indrakaran, Kandi, Sangareddy, 502329, in Indrakaran revenue village, Kandi mandal. RERA record

The layout plan describes an approach at the west boundary as “ROAD INDRAKARAN TO CHERIYAL” and identifies layout-road widths of 9.00, 9.92 and 12.00 M. A supplied location record reports the nearest sampled Outer Ring Road interchange at approximately 11.8 km; no travel time is supplied. RERA filing Location record

A vendor record separately lists two “Type 1 Bus Stop” points at 2.28 Km and 2.29 Km, HP Petrol Pump at 2.64 Km, and Ordnance Factory at 3.32 Km. These are vendor-supplied connectivity claims, not independently verified distances. Promoter website

9. Developer & development status

The registered promoter is Sai Balaji Projects, identified in the project record as a partnership. The listed partners are Prasad Sakhamuri and Manohar Shakamuri; Venkatadri Naidu Pothugunta is identified as the authorized signatory. Corporate record RERA filing

The project filing lists the promoter address as Madhura Residency, Rajeev Nagar, Indrakaran, Kandi, Sangareddy, 502329. No verified corporate registration number, official website or contact details are established in the supplied data. Corporate record

In Form B, the promoter’s authorized signatory declared a completion undertaking of 22nd February 2022 and described the project as an open-plot layout. RERA-filed progress data reports internal roads and footpaths at 80% and sewerage at 60%; these are filed declarations, not independent site findings. RERA amenities

10. Approvals, official records & documents

RecordSupplied evidence
TG-RERA registrationForm C records PEARL CITY, registration P01100001426, granted under section 5, valid from 25/11/2019 to 22/02/2022.
HMDA layout approvalLayout Permit 000047/LO/Plg/HMDA/2019, dated 22 February 2019, for the plotted layout on survey numbers 441, 445 and 439 in Indrakaran village, Kandi mandal.
HMDA draft layout letterDocument describes HMDA’s draft layout letter and layout conditions, including roads, open spaces and mortgage plots.
RERA Form BPromoter declaration dated 24th day of May 2019, naming the landowners and referring to Development Agreement-cum-GPA No. 10068/2019.
Completion / occupancy certificateNone is identified in the supplied project documents. Document index
Development agreementThe supplied title-report extraction identifies a registered Development Agreement-cum-GPA dated 01 March 2019, No. 10068 of 2019, relating to Ac. 10-20 Guntas in survey numbers 441, 445 and 439.

Frequently asked questions

Is PEARL CITY registered with Telangana RERA?

Yes. PEARL CITY is registered with the Telangana Real Estate Regulatory Authority as P01100001426; the registration status is New Project.

Who is the developer of PEARL CITY?

The promoter named in the RERA registration is SAI BALAJI PROJECTS.

Where is PEARL CITY located?

PEARL CITY is in INDRAKARAN, KANDI, Sangareddy, Telangana (502329).

When will PEARL CITY be completed?

The promoter's proposed date of completion filed with RERA is 22/02/2022. This is the promoter's declaration, not a guarantee.