Global City-V

GREATER INFRA PROJECTS · Sangareddy · RERA P01100003856

GLOBAL CITY-V is a plotted development at Indrakaran, Kandi mandal, Sangareddy district. It is being developed by GREATER INFRA PROJECTS, recorded as a partnership. The site area is 102880.02 sq.m; the software-read layout drawing shows plots numbered 1 to 332, and no building floors or RERA-filed plot-size schedule are disclosed. The project is registered under TG-RERA P01100003856, and the promoter’s Form B declaration undertakes completion by 21-08-2024.

More from Greater Infra Projects · 3 projects →

01What we found

Period endedTG-RERA registration ran to 21 Aug 2024 - check its extension on TG-RERA
11documents on file - each fact links to its page
0court cases on this project's land in the court records searched
7items to check - 4 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

7 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

1. Project at a glance

Project identity

ItemProject record
Registered project nameGLOBAL CITY-V RERA record
Project typePlotted development / open-plot layout RERA record
Phase or registered portionPhase not separately identified in the supplied record; TG-RERA registration is for GLOBAL CITY-V
TG-RERA registrationP01100003856; issued 03/01/2022, recorded validity from 03/01/2022 to 21/08/2024. The certificate says the term could be extended by the Authority; the supplied certificate records no extension
Registered promoterGREATER INFRA PROJECTS, recorded as a partnership RERA record RERA filing
RERA status in supplied recordNew Project; the registration validity date has passed. Current registration status is not established by the supplied certificate RERA record

Land and geographic identity

ItemProject record
Locality / revenue villageIndrakaran (also rendered “Inderkaran” in the HMDA draft layout letter); the RERA record identifies INDRAKARAN RERA record
Mandal / district / PINKandi / Sangareddy / 502329 RERA record
Project survey numbers357, 358, 369 and 370; no project subdivision schedule is disclosed in the supplied identity record RERA record
Total site area102880.02 sq.m RERA filing
Road-affected area6806.94 sq.m RERA filing
Net site area96073.08 sq.m RERA filing
Boundaries recordedNorth: neighbours’ land; South: road width 30; East: neighbours’ land; West: neighbours’ land RERA filing

Development identity

ItemProject record
Sanctioning authorityHyderabad Metropolitan Development Authority (HMDA) Approvals record
Principal approvalDraft layout approval / Layout Permit No. 000299/LO/Plg/HMDA/2021, dated 21 August 2021 Approvals record
Approved built-up area57290.37 sq.m is recorded as approved built-up area in the RERA fields; the layout drawing extraction identifies the same figure as plotted area. It is not a building-floor or apartment area schedule RERA filing Layout record
Building / floor configurationNot applicable to the filed open-plot layout; no tower, block, floor or apartment configuration is disclosed
ParkingNo project parking count or parking-level schedule is disclosed
Plot countLayout drawing software-read count: plots numbered 1 to 332; the drawing-derived count is not stated as a RERA-disclosed inventory count Layout record
Mortgaged plots in draft approvalPlots 149 to 209 are described as 60 plots in the approval condition, measuring 8653.08 sq.m; the drawing extraction counts 61 plot numbers in that range. This table reports the approval’s stated condition Layout record

Offering and status

ItemProject record
RERA-filed unit types and sizesUnit-level plot inventory and saleable-size schedule are not present in the supplied RERA data Document index
Marketed plot sizesA third-party vendor record lists plots of 167, 180, 200, 240, 260 and 300 sq.yd; these are marketing-source figures, not RERA-filed inventory Promoter website
Booked / available countsNot disclosed in the supplied evidence Document index
Construction / development stageRERA header records 70% completeness; the basis, date and independent verification of that figure are not supplied RERA record
Completion datePromoter’s Form B declaration undertakes completion by 21-08-2024; the supplied HMDA draft letter also directed completion of development works within three years
Registration validityThrough 21/08/2024, unless extended by the Authority; no extension is recorded in the supplied certificate
Completion / occupancy certificateNo completion certificate or occupancy certificate is included in the supplied documents. For this plotted layout, the supplied record does not establish a phase-wise or plot-wise certificate status Document index

2. The project story

GLOBAL CITY-V is registered as a plotted development at Indrakaran village, Kandi mandal, Sangareddy district, across survey numbers 357, 358, 369 and 370. The RERA-filed identity records a total site area of 102880.02 sq.m, of which 6806.94 sq.m is identified as road-affected and 96073.08 sq.m as net site area. The principal approval on file is an HMDA draft layout letter for an open-plot layout. RERA record RERA filing

The HMDA draft layout letter sets out layout-development conditions, including roads and open spaces to be handed over to the local body by registered gift deed before final layout release, underground utility ducting and storm-water drainage, footpath paving, cycling tracks and LED street lighting. It also states that the permission is not proof of land title and that construction on plots is not to be allowed until HMDA issues the final layout. The supplied record does not establish final layout release or independently verify on-site completion.

The RERA header reports 70% completeness, but no dated engineer, architect or other independent progress certification is supplied to establish what that percentage measures. The promoter’s completion undertaking and registration validity both run to 21 August 2024; the supplied certificate does not record an extension, and no completion or occupancy certificate is provided. RERA record Document index

3. Master plan, architecture & building design

This is a plotted layout, not an apartment or tower project. The HMDA draft layout letter records a total site area of 102880.02 sq.m, a master-plan-road-affected area of 6806.94 sq.m, and a net site area of 96073.08 sq.m. Its area schedule lists 57290.37 sq.m of plotted area, 26835.03 sq.m of layout road area, 9531.4 sq.m of park area, 2416.16 sq.m of open space, and 0 amenities area. The extracted drawing also records 7242.52 sq.m of organized open space/park, 760.03 sq.m utility area and 2416.40 sq.m social infrastructure area; these are drawing-extracted figures, not a separately verified site survey.

The software-read layout drawing shows plot numbers 1–332. Plot-size details were not successfully extracted, so a complete plot-size schedule cannot be provided from the drawing data. There are no supported building footprints, tower heights, floor configurations, or apartment/common-area plans for this plotted development. Layout record Floor plans

The draft approval identifies internal roads including 18 mts and above and 60 feet and above roads, and a 30.0mts wide master plan road. It requires roads to be opened for access to neighbouring sites and prohibits a compound wall or fencing around the site. These are approval terms; the evidence does not establish their completion on the ground.

4. Homes, configurations & floor plans

The registered offering is plotted land. The supplied RERA material does not include a plot-by-plot inventory with RERA-filed saleable areas, booking status or availability. The drawing software identified 332 plot numbers but could not produce a complete plot-size schedule. RERA record Layout record Document index

A third-party vendor record lists marketed plot sizes of 167, 180, 200, 240, 260 and 300 sq.yd. These are not a substitute for the registered plot schedule or an executed plot-specific agreement. Promoter website

The supplied floor-plan data contains two layout sheets and no apartment floor plans. No measured carpet area or loading figure is available. Floor plans

5. Parking & vehicle circulation

No sanctioned parking-space count, visitor or accessible parking provision, or plot-specific parking allocation is disclosed in the supplied project record. As this is a plotted layout, apartment-style parking levels and ramps are not evidenced. Document index

The HMDA draft letter requires internal road access, prohibits fencing or compound walls around the site, and identifies road widths including 18 mts and above and 60 feet and above roads. The supplied evidence does not establish the completed road layout, vehicle-entry arrangements or pedestrian separation.

6. Amenities, recreation & open spaces

The HMDA draft layout letter provides for parks and organized open space and lists development works and utilities. Its conditions and listed provisions are approval-record items; progress is not independently verified in the supplied evidence. RERA amenities

FacilityDescription / sizeEvidence sourceDeclared progress / verified status
Parks9531.4 sq.m in the layout area schedule; 7242.52 sq.m identified as organized open space/park area in the extracted approvalApproval/drawing record; no verified completion status supplied
Open space2416.16 sq.m in the layout area scheduleApproval/drawing record; no verified completion status supplied
Social infrastructure area2416.40 sq.mApproval/drawing record; no facility-specific completion status supplied
Cycling trackRequired within the layoutApproval condition; completion not verified
Park development and avenue plantationListed as layout provisionsProposed/required provision; completion not verified
Clubhouse, swimming pool, community hall, children’s play areas, landscaped gardens, fitness centres and indoor gamesListed in third-party vendor amenities; no dimensions or capacities suppliedPromoter websiteMarketing-source claims; not established as sanctioned or delivered

7. Utilities, building services & safety

The HMDA draft approval requires underground ducting of utilities and service lines, an underground storm-water drainage system, paved footpaths, LED street lighting and cycling tracks. Its listed provisions include a common septic tank/STP, internal water-supply pipelines and overhead tank, transformer, rainwater-harvesting pits, park development and avenue plantation. No capacities, as-built records or independently verified completion evidence are supplied.

Water
Evidence in the project recordInternal water-supply pipelines and overhead tank are listed; the approval extraction also lists a common septic tank/STP and rainwater-harvesting pits
Status evidencedListed in the draft approval; source, storage capacity and completion are not established
Sewerage / drainage
Evidence in the project recordCommon septic tank/STP and underground storm-water drainage are listed
Status evidencedApproval-record provisions; no capacity or completion evidence supplied
Electrical
Evidence in the project recordTransformer / transformer yard and LED street lighting are listed
Status evidencedApproval-record provisions; no supply capacity or completion evidence supplied
Waste and energy management
Evidence in the project recordRERA amenity extract marks energy management as available; no operational details are supplied RERA amenities
Status evidencedFiling-field status only; implementation not independently verified
Fire and life safety
Evidence in the project recordThe RERA amenity extract lists fire protection and fire-safety requirements, without a detailed system or clearance document RERA amenities
Status evidencedNo specific system, capacity or project-specific clearance is established
Security and accessibility
Evidence in the project recordNo project-specific security-system or accessibility details are supplied Document index
Status evidencedNot established

8. Location, access & connectivity

The official project identity is Indrakaran village, Kandi mandal, Sangareddy district, PIN 502329. The supplied cadastral coordinate is the parcel centroid at 17.529485662600457, 78.13672323421243. RERA record Cadastral map

The HMDA draft approval refers to a 30.0mts wide master plan road and internal roads, but the supplied evidence does not establish completed access conditions or public-transport links. The location record lists the nearest sampled Outer Ring Road interchange at 13.1 km (approx.). Location record

9. Developer & development status

The registered promoter is GREATER INFRA PROJECTS, recorded as a partnership, with GSTIN 36AARFG6014B1ZW. The supplied project information names KHAZMI YASMEEN as a partner and SAYYAD HIMAM as authorised signatory; the Form B declaration is made by Sayyad Himam for the promoter. A registered office address and official project contact details are not established in the supplied evidence. RERA filing Corporate record Parties record

The promoter declared a completion date of 21-08-2024 in Form B. The registration certificate states validity through 21/08/2024 unless extended by the Authority; no extension is recorded in that certificate. The RERA header reports 70% completeness, but the supplied evidence does not independently verify that progress figure or establish completion of the layout works. RERA record

10. Approvals, official records & documents

RecordWhat the supplied document establishes
TG-RERA registration certificate, P01100003856FORM C records GLOBAL CITY-V, promoter Greater Infra Projects, and validity from 03/01/2022 to 21/08/2024, unless extended by the Authority
HMDA draft layout letter, Layout Permit 000299/LO/Plg/HMDA/2021, dated 21 August 2021Draft approval for an open-plot layout in survey numbers 357, 358, 369 and 370, at Inderkaran village, Kandi mandal, Sangareddy district; includes area schedules and layout conditions
Form B declaration, dated 28thSEP, 2021Sayyad Himam for Greater Infra Projects declares title and freedom from encumbrances and undertakes completion by 21-08-2024
HMDA title-related mortgage and gift references in the draft letterReferences mortgage deeds 29237-2021, 29238/2021 and 29236/2021, and gift deed 29234/2021
Completion / occupancy documentsNo completion certificate or occupancy certificate is included in the supplied project documents Document index
Final layout releaseThe supplied HMDA document is identified as a Draft layout Letter and requires handover of roads, organized open space/park, utility and social-infrastructure areas before final layout release; final release is not established by the supplied evidence

Frequently asked questions

Is GLOBAL CITY-V registered with Telangana RERA?

Yes. GLOBAL CITY-V is registered with the Telangana Real Estate Regulatory Authority as P01100003856; the registration status is New Project.

Who is the developer of GLOBAL CITY-V?

The promoter named in the RERA registration is GREATER INFRA PROJECTS.

Where is GLOBAL CITY-V located?

GLOBAL CITY-V is in INDRAKARAN, KANDI, Sangareddy, Telangana (502329).

When will GLOBAL CITY-V be completed?

The promoter's proposed date of completion filed with RERA is 21/08/2024. This is the promoter's declaration, not a guarantee.

More projects in Indrakaran