VILLA HUB is a plotted development at Theegapur Village, Kothur Mandal, Ranga Reddy District, developed by the registered promoter SSV SAI INFRASTRUCTURE LLP. The registered site area is 23,151.56 sq.m, and the project is identified as a plotted layout; the supplied TG-RERA record does not disclose a plot count or plot-wise size schedule. Vendor-listed plot sizes are 1,351 Sq. Ft. and 3,207 Sq. Ft. TG-RERA registration number P02400006989 was issued 19/09/2023, and the project header lists proposed completion as 30/11/2026.

More from Ssv Sai Infrastructure LLP · 2 projects →

01What we found

Period endedTG-RERA registration ran to 24 May 2026 - check its extension on TG-RERA
21documents on file - each fact links to its page
1court case on this project's land (survey 131, Theegapur)
7items to check - 3 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

7 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

1. Project at a glance

Project identity

ItemProject record
Registered project nameVILLA HUB RERA record
Project typePlotted development / open-plot layout RERA record
Phase or registered portionA plotted project registered under P02400006989; no separate phase designation is disclosed RERA record
TG-RERA registrationP02400006989; certificate issued 19/09/2023 RERA record
Registration validityCertificate states validity from 19/09/2023 to 24/05/2026, unless extended by the Authority. The supplied record does not show an extension
Registered promoterSSV SAI INFRASTRUCTURE LLP RERA record Corporate record
RERA status in supplied recordRegistered under section 5; the supplied certificate gives the validity dates above

Land and geographic identity

ItemProject record
Locality / revenue villageTheegapur / Theegapur Village RERA record RERA filing
MandalKothur RERA record RERA filing
DistrictRanga Reddy RERA record RERA filing
PIN509325 RERA record
Project survey number and subdivision131/P; no further project subdivision is disclosed RERA record Land records
Registered site extent23,151.56 sq.m total site area; 21,316.42 sq.m net site area, after 1,835.14 sq.m affected by the master-plan road RERA filing
BoundariesEast: ROAD; West: NEIGHBOURS LAND; North: VILLAGE ROAD; South: ROAD RERA filing
Parcel referenceBhu Bharati cadastral record identifies survey 131/P in Theegapur; listed extent is 248,434.87 sq.m for the whole survey, not a project-area measurement Cadastral map

Development identity

ItemProject record
Sanctioning authorityHyderabad Metropolitan Development Authority (HMDA) Approvals record
Principal approvalDraft layout approval 000103/LO/Plg/HMDA/2023, dated 24 May 2023 Approvals record
Approval scopeDraft open-plot layout in survey 131/P, Theegapur Village; the letter forwards the layout to the local Executive Authority for further action and release of plans
Approved built-up area13,653.05 sq.m recorded as approved built-up area; the supplied material does not explain how this figure applies to this plotted-layout approval RERA filing
Buildings / floorsNo tower or building count, floor configuration, or parking levels disclosed for this plotted development RERA filing Document index
Layout land-use figuresPlotted area 13,653.03 sq.m; layout roads 5,384.27 sq.m; park/open space 1,746.03 sq.m; open-space entry 533.09 sq.m in the extracted approval record; amenities area 0 Layout record
Road-affected area1,835.14 sq.m, identified in the approval record as affected by a proposed 30 mtrs master-plan road and 30 ft road
Authority mortgagePlots 23–35 (13 plots), extent 2,180.99 sq.m, recorded as mortgaged to HMDA pending completion of required layout works and release

Offering and status

ItemProject record
Unit typePlots; no RERA unit inventory/count or plot-wise size schedule is provided in the supplied data RERA record RERA filing Document index
Plot-size informationA third-party vendor listing supplies two plot configurations: 1,351 Sq. Ft. and 3,207 Sq. Ft. These are vendor-supplied, not established as the TG-RERA plot inventory Promoter website
Booked / available countsNot disclosed in the supplied project evidence Document index
Construction stageThe supplied record does not establish independently verified site progress. The layout approval requires development works; no completion evidence is supplied
Completion datePromoter’s Form B states 24th May 2026; the project header lists proposed completion as 30/11/2026 RERA record
Occupancy / completion certificateNo occupancy or completion certificate is supplied. This is a plotted layout, and the available approval document is a draft layout letter rather than a final layout release Document index

2. The project story

VILLA HUB is registered with TG-RERA as a plotted development at Theegapur Village, Kothur Mandal, Ranga Reddy District, on survey 131/P. The registered site area is 23,151.56 sq.m; the approval record identifies 21,316.42 sq.m as net site area after the master-plan-road-affected area. The layout drawing’s recorded land-use figures allocate area to plots, roads and open space, with no amenities area shown RERA record RERA filing Layout record.

HMDA’s dated 24 May 2023 document is described as a draft layout letter. It sets out development and handover conditions, including completion of layout infrastructure, transfer of roads and open spaces to the local body, and release of the final layout. The supplied evidence does not establish that the final layout has been released or that the required works are complete.

The promoter’s Form B gives a completion undertaking of 24th May 2026; the project header separately records 30/11/2026 as proposed completion. The registration certificate gives a validity end date of 24/05/2026, unless extended. These are distinct record entries; the supplied documents do not confirm an extension, completion, or occupancy/completion certification RERA record.

3. Master plan, architecture & building design

This is a plotted layout, not a building or apartment project in the supplied RERA record.

Layout componentAreaEvidence / qualification
Total site area23,151.56 sq.mApproval record
Master-plan-road-affected area1,835.14 sq.mApproval record
Net site area21,316.42 sq.mApproval record
Plotted area13,653.03 sq.mApproval record
Layout road area5,384.27 sq.mApproval record
Park1,746.03 sq.mApproval record
Open-space entry533.09 sq.mApproval extraction; its relationship to the separately stated park figure is not specified in the supplied material
Amenities area0Approval record
Social infrastructureILLEGIBLEApproval extraction

The supplied layout drawing is one sheet and is identified as approved drawing material, but the plotted area and layout figures are drawing-derived. Plot count and plot sizes are not completely available from the drawing extraction; plot-wise sizes should therefore not be inferred from the layout totals Layout record.

The draft approval identifies internal roads and includes road widths of 30 mtrs and 30 ft. It also requires access to neighbouring sites and addresses roads, open spaces, utilities and infrastructure in its conditions. Building configuration, building footprints, floor levels and building design details are not disclosed.

4. Homes, configurations & floor plans

The RERA record identifies the offering as plots but the supplied evidence does not include RERA-filed plot counts, plot-wise sizes, or booked and available inventory. The following sizes appear in a third-party vendor listing only:

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading
PlotNot disclosedNot disclosedNot disclosedNot disclosedNot applicableNot supplied
Vendor-listed plot sizesCount not establishedNot disclosedNot disclosed1,351 Sq. Ft.; 3,207 Sq. Ft. (vendor-reported)Not applicableNot supplied

The vendor figures are not a RERA-filed plot schedule. The supplied floor-plan review records one layout sheet and no measured floor plans or apartment units, so there are no software-measured carpet or room measurements to report Promoter website Floor plans Document index.

5. Parking & vehicle circulation

The supplied evidence does not establish parking counts, visitor or accessible spaces, parking allocation to plots, or dedicated parking levels. The draft layout records that 13 plots, Nos. 23–35, measuring 2,180.99 sq.m in total, are mortgaged to HMDA. This is an approval-related mortgage entry, not evidence of buyer parking allocation.

The approval conditions refer to road access and layout roads, but the supplied records do not describe vehicle-entry arrangements, ramps, pedestrian separation, or a parking plan.

6. Amenities, recreation & open spaces

The approval record specifies or refers to layout infrastructure and facilities; the supplied evidence does not establish their completion or independent verification. The RERA amenity record lists progress as 0% where shown RERA amenities.

Park / open space
Description / sizePark 1,746.03 sq.m; a separate open-space entry is 533.09 sq.m in the extracted approval data
Evidence sourceLayout record
Declared progress / verified statusNo completion evidence supplied
Internal roads and footpaths
Description / sizeRequired layout infrastructure; approval records road area 5,384.27 sq.m
Evidence sourceRERA amenities
Declared progress / verified statusRERA amenity record: 0%; not independently verified complete
Community buildings
Description / sizeListed in the RERA amenity record, without a size or declared availability value
Evidence sourceRERA amenities
Declared progress / verified statusNo progress or completion evidence supplied
Recreation / common facilities
Description / sizeNo amenity area is recorded in the draft approval (0); no RERA-filed facility schedule with dimensions is supplied
Evidence sourceRERA amenities
Declared progress / verified statusNo completion evidence supplied

A third-party vendor lists a clubhouse, swimming pool, gym, children’s play area, sand pits and a large green area; those claims are vendor-supplied and are not established as approved, RERA-declared or delivered facilities in the project documents Promoter website.

7. Utilities, building services & safety

The draft layout approval and RERA amenity record identify several proposed or required infrastructure items, but the supplied record does not verify installation, commissioning or capacity.

Water
Evidence in the supplied recordWater supply and internal water-supply pipelines are listed; an overhead tank is also listed in the approval extraction RERA amenities
Status limitationSource, storage capacity and completion status not supplied
Sewerage / drainage
Evidence in the supplied recordSewerage, chambers, lines, septic tank/STP and storm-water drains appear in the RERA amenity record; the draft approval includes a common septic tank/STP requirement and underground storm-water drainage RERA amenities
Status limitationNo capacity, operating status or completion evidence supplied
Rainwater
Evidence in the supplied recordWater conservation and rainwater harvesting are listed RERA amenities
Status limitationNo system details or completion evidence supplied
Electrical / lighting
Evidence in the supplied recordElectrical meter room, sub-station/receiving station and street lighting are listed; the approval requires LED street lighting and underground utility ducting RERA amenities
Status limitationNo capacity, supply arrangement or completion evidence supplied
Solid waste
Evidence in the supplied recordSolid-waste management/disposal is listed; the approval specifies solid-waste disposal space, a bio-compost unit and source segregation RERA amenities
Status limitationNo operating or completion evidence supplied
Fire / life safety
Evidence in the supplied recordFire protection and fire-safety requirements appear in the RERA amenity record RERA amenities
Status limitationNo system details or compliance evidence supplied
Other layout works
Evidence in the supplied recordApproval conditions refer to cycling tracks and underground ducting for utilities and services
Status limitationNo completion evidence supplied

The third-party vendor listing also mentions 24×7 water supply, power backup, CCTV and security; these are vendor claims, not project completion evidence Promoter website.

8. Location, access & connectivity

The registered location is Theegapur Village, Kothur Mandal, Ranga Reddy District, Telangana 509325. The parcel centroid supplied for survey 131/P is 17.160214627400723, 78.27505471885274 RERA record RERA filing Cadastral map.

The project boundaries recorded in the land details are east: ROAD; west: NEIGHBOURS LAND; north: VILLAGE ROAD; south: ROAD RERA filing. The location evidence lists the nearest sampled Outer Ring Road interchange at approximately 18.2 km Location record. The vendor listing describes nearby bus stops and railway stations but gives no verified distances Promoter website.

9. Developer & development status

The registered legal promoter is SSV SAI INFRASTRUCTURE LLP, identified as an LLP, with GSTIN 36ADKFS8497C1Z1. The project record lists the promoter address as Flat No 404, 4th Floor, NAGASURI PLAZA, Gayatri Nagar, Plot No 8, Kothur, Theegapur, Kothur, Ranga Reddy, 509325; the registration certificate separately prints the promoter office as “Village: Mandal: District: Hyderabad, Pin: 500038” Corporate record RERA filing.

Gorantla Venkateswara Rao is identified as authorised signatory; Gorantla Subhashini is listed as a partner Parties record. Form B is the promoter’s affidavit-cum-declaration and states a completion undertaking of 24th May 2026. The project header records proposed completion as 30/11/2026 RERA record. No independent construction-progress record, final layout release, or completion certificate is supplied.

10. Approvals, official records & documents

RecordSupplied evidence
TG-RERA registrationForm C for VILLA HUB, registration P02400006989, issued 19/09/2023; stated validity through 24/05/2026, unless extended
HMDA draft layout approval000103/LO/Plg/HMDA/2023, dated 24 May 2023, for the plotted layout in survey 131/P, Theegapur Village
Approval status described in documentDraft layout letter; it forwards the matter to the local Executive Authority for further action and addresses subsequent release of the final layout
Mortgage recorded in approvalDocument 2510/2023, dated 24/4/2023; plots 23–35, total 2,180.99 sq.m, in favour of Metropolitan Commissioner, HMDA
Road-affected-area gift deed referenceDocument 2509/2023, dated 24/04/2023, for 1,835.14 sq.m affected by the proposed master-plan road and 30 ft road, to the Executive Authority, Grampanchayath, Theegapur Village, as stated in the approval extraction
Promoter Form BAffidavit-cum-declaration by authorised signatory Gorantla Venkateswara Rao for SSV SAI INFRASTRUCTURE LLP; the OCR date is incomplete
Completion / occupancy evidenceNo final layout release, project completion certificate or occupancy certificate is included in the supplied documents Document index
Public layout lookupHMDA DPMS approved-layout lookup was not publicly reachable in the supplied record; this is a source-availability limitation, not a determination about approval status HMDA

Frequently asked questions

Is VILLA HUB registered with Telangana RERA?

Yes. VILLA HUB is registered with the Telangana Real Estate Regulatory Authority as P02400006989; the registration status is New Project.

Who is the developer of VILLA HUB?

The promoter named in the RERA registration is SSV SAI INFRASTRUCTURE LLP.

Where is VILLA HUB located?

VILLA HUB is in Theegapur, Kothur, Rangareddy, Telangana (509325).

When will VILLA HUB be completed?

The promoter's proposed date of completion filed with RERA is 30/11/2026. This is the promoter's declaration, not a guarantee.