UMA RESIDENCY is a residential apartment project in PUNJAGUTTA HYDERABAD, KHAIRTABAD, Hyderabad district. The registered promoter is DANDE UMADEVI AND OTHERS. The project is on 601.39 sq.m of land and comprises one residential building with 1 Stilt + 5 upper floors and 10 3BHK units. It is registered with TG-RERA under P02500008256, with a proposed completion date of 27/08/2025.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
9 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
Project at a glance
Project identity
| Field | Record |
|---|---|
| Registered project name | UMA RESIDENCY RERA record |
| Project type | Residential apartment project RERA record RERA filing |
| Phase / registered portion | A single residential building is identified in the building-permit record; a separate phase name is not disclosed. |
| TG-RERA registration | P02500008256 RERA record |
| Registration validity | 17 May 2024 to 27 August 2025. This is the registration period, distinct from the declared completion deadline. RERA record |
| Registered promoter | DANDE UMADEVI AND OTHERS; promoter organization type is recorded as “Others,” described as a joint venture. RERA record RERA filing |
| RERA status | Listed as “On-Going Project” in the project record. RERA record RERA filing |
Land and geographic identity
| Field | Record |
|---|---|
| Registered locality / address | H Nos 6-3-347/7, 6-3-347/7/A AND 6-3-347/7/B; PUNJAGUTTA HYDERABAD; PIN 500082. RERA filing |
| Revenue village | Punjagutta Hyderabad in the RERA project record. The building-permit extract separately states “Khairatabad”; the supplied evidence does not establish a revenue-village name corresponding to the project survey parcel. RERA record RERA filing |
| Mandal / district | KHAIRTABAD / Hyderabad. RERA record RERA filing |
| Survey number / subdivision | RERA land identity says survey number(s) “not disclosed.” A survey number 123/27 appears in the separate layout-plan extraction; its relationship to the project parcel is not established in the supplied record. Land records |
| Registered site extent | Total area 601.39 sq.m; net area 601.39 sq.m; road-widening/FTL/Nala affected area recorded as 0. RERA filing |
| Boundaries | East: LAND BELONGING TO NIZAM INSTITUTE OF M SCIENCES; West: PART ROAD AND PLOT NO 1 H NO 6-3-347BY7; North: PLOT NO 2 H NO 6-3-347BY8; South: JB APURUPA ONE PARTMENT COMPLEX. RERA filing |
Development identity
| Field | Record |
|---|---|
| Sanctioning authority | Greater Hyderabad Municipal Corporation (GHMC). Approvals record |
| Principal building approval | 2869/GHMC/KHB/2022-BP, dated 27 August, 2022; file no. 005188/GHMC/2595/KHB2/2022-BP. Approvals record |
| Approved building form | One residential building, 1 Stilt + 5 upper floors. The permit also records building height 14.99 and a separate total height 19.99 mt.; the supplied extraction does not specify units for the first height figure. |
| Approved area figures | Building-permit extraction lists residential upper-floors area 1,513.50 Sq.Mt., stilt area 313.8, total parking area 313.85, and six rainwater-harvesting pits. These are the figures as recorded in the permit extraction, not carpet or saleable area. |
| Approved building / parking count | 1 building; proposed number of parkings 11 and total parking 10 are both recorded in the permit extraction. |
| Unit count | The approved-plan record states that sanctioned units must not be increased without GHMC approval but does not state the sanctioned unit count in the supplied extraction. RERA records 10 units. RERA unit table |
Offering and status
| Field | Record |
|---|---|
| RERA-filed configuration | 3BHK, 10 units; saleable area 205.78 sq.m per unit. RERA unit table |
| Booked / available | 2 booked / 8 available, as last read from the TG-RERA portal; no as-of date is supplied, so these counts are indicative. RERA unit table |
| Construction-stage record | RERA project data reports 90% completeness; this is a reported figure, not an independent site inspection. RERA record RERA amenities |
| Promoter-declared completion deadline | 27/08/2025; Form B records completion “on or before 27/08/2025.” RERA record |
| Revised completion date | 27/08/2025 in the project record. RERA record |
| Occupancy / completion certificate | No occupancy or completion certificate is included in the supplied documents. The GHMC permit states that an occupancy certificate is compulsory before occupation. |
The project story
UMA RESIDENCY is registered with TG-RERA as a residential apartment project under registration P02500008256, with the RERA project record locating it at H Nos 6-3-347/7, 6-3-347/7/A AND 6-3-347/7/B in the Punjagutta Hyderabad locality of Hyderabad, PIN 500082. RERA record The record describes one residential building; GHMC’s permit identifies it as 1 Stilt + 5 upper floors.
The RERA filing lists ten 3BHK units, of which two are recorded as booked and eight as available; the portal snapshot has no stated as-of date. RERA unit table The project record reports 90% completeness, but the supplied evidence does not include an independent inspection confirming construction progress or a certificate confirming completion or occupation. RERA record RERA amenities The declared completion date is 27 August 2025, while RERA registration validity is a separate period ending on that same date. RERA record
Master plan, architecture & building design
The project is recorded as a single residential building on a site of 601.39 sq.m, with net plot area also recorded as 601.39 sq.m and road- and Nala-affected areas recorded as 0.0 in the GHMC permit extraction. The permit describes 1 Stilt + 5 upper floors, with a stilt area of 313.8, residential upper-floors area of 1,513.50 Sq.Mt., and total parking area of 313.85.
The permit lists setbacks as Front 3, Rear 3.5, Side I 3.5 and Side II 3.5; the supplied extraction does not state units for these figures. It also lists a lift machine room, drinking-water sump, overhead water tank, distribution transformer, garbage pit and percolation pit among site/building provisions. The permit’s listed six rainwater-harvesting pits and other conditions are summarized under facilities and services below.
No usable floor-plan measurements are available: the supplied floor-plan data records two drawings, zero measured, and two with no flats. Consequently, room arrangements, floor-by-floor unit distribution, circulation, lift/stair counts and carpet areas cannot be established from the supplied drawing data. Floor plans
Homes, configurations & floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 3BHK | 10 | 2 | 8 | 205.78 sq.m | Not available | Not supplied |
The configuration, unit count, booking counts and saleable area are from the TG-RERA filing; the booking figures have no stated as-of date. RERA unit table Carpet area was not software-measured from the supplied drawings: the drawing record reports two drawings and no measured plans. Floor plans The RERA-filed saleable area is therefore presented separately; no carpet-area or loading figure can be confirmed from this evidence.
Parking & vehicle circulation
The GHMC permit extraction records proposed number of parkings: 11 and total parking: 10. It describes the stilt as parking space and states that the stilt/cellar approved for parking must be used exclusively for vehicle parking, without partition walls or rolling shutters. The permit extraction does not establish a separate cellar level, visitor or accessible spaces, EV charging, parking allocation to individual apartments, or the number of parking bays by level. No exclusive ownership or unit-specific parking allocation can be established from the supplied evidence.
Amenities, recreation & open spaces
| Description / size | RERA amenity record identifies a green strip/tot lot/park; GHMC conditions call for a fenced tot-lot maintained as greenery and peripheral tree planting/greenery. No area is supplied. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | RERA record reports 90%; not independently verified complete. |
| Description / size | Listed in the RERA amenity record; no size or detail supplied. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | 0% shown in the supplied RERA amenity data. |
| Description / size | Listed in the RERA amenity record; no building or size specified. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | 0% shown. |
| Description / size | Appears in third-party vendor amenity text only; no supporting project-specific sanctioned or RERA facility detail is supplied here. |
|---|---|
| Evidence source | Promoter website |
| Declared progress / verified status | Marketing/vendor claims only; delivery not verified. |
The supplied project record does not provide dimensions or capacities for recreational or open-space facilities. The permit also requires a garbage house and percolation pit; site utilities and related services are addressed below.
Utilities, building services & safety
The RERA amenity record marks water supply, sewerage and sewage-related infrastructure, water conservation/rainwater harvesting, and an electrical meter room/substation/receiving station as available, each with 90% progress. Those are portal-reported figures, not independently verified completion. RERA amenities The GHMC permit extraction lists a drinking-water sump, overhead water tank, distribution transformer and garbage pit; it also records 6 rainwater-harvesting pits.
The supplied evidence does not specify water source or storage capacity, STP capacity or reuse arrangements, storm-water drainage provision, backup-power capacity, lift count or capacity, CCTV/security arrangements, waste-segregation details, or accessible circulation. The permit states that a transformer space is to be provided and that sanitation, plumbing, fire-safety requirements, lifts and electrical installations are to be executed under qualified technical supervision. It also states that fire-safety installations are the responsibility of the owner, builder/developer and technical professionals, and that a fire NOC is to be obtained before an occupancy certificate.
Location, access & connectivity
The registered project location is H Nos 6-3-347/7, 6-3-347/7/A AND 6-3-347/7/B, locality PUNJAGUTTA HYDERABAD, mandal KHAIRTABAD, Hyderabad district, PIN 500082. RERA record RERA filing The project record gives site boundaries to the east, west, north and south as listed in the land identity table. RERA filing
A supplied connectivity record identifies Financial District (Nanakramguda), 1.2 km, from a cadastral parcel-centroid location entry. Location record No approach-road measurements, public-transport details or independently verified travel times are supplied.
Developer & development status
The registered promoter is DANDE UMADEVI AND OTHERS; the project filing describes the organization type as “Others” and the arrangement as a “JOINT VENTURE.” RERA record RERA filing The project record gives the promoter address as Sunrise Apartments, Dwarakapuri Colony, Punjagutta Hyderabad, KHAIRTABAD, Hyderabad, 500082. Parties record
Form B is a promoter affidavit made by SMT. DANDE UMA DEVI, dated 05.12.2023, which states that the owners have legal title to the land, declares the land free from encumbrances, and records project-fund undertakings and a completion undertaking of on or before 27/08/2025. These are promoter declarations. The RERA project record reports 90% completeness, but the supplied evidence contains no independent construction-progress inspection or occupancy/completion certificate. RERA record RERA amenities
Approvals, official records & documents
| Identifier / date | P02500008256; validity 17 May 2024–27 August 2025 |
|---|---|
| What the supplied record establishes | Registers UMA RESIDENCY under Dande Umadevi And Others and states registration conditions. |
| Identifier / date | 2869/GHMC/KHB/2022-BP; 27 August, 2022; file no. 005188/GHMC/2595/KHB2/2022-BP |
|---|---|
| What the supplied record establishes | Conditional building permission for a residential building of 1 Stilt + 5 upper floors; the order states that permission does not confer ownership rights. |
| Identifier / date | 497/35/100/TP5/CCP/95 |
|---|---|
| What the supplied record establishes | Listed as “Approved Layout No. / LRS Proceeding No. / Sub division No”; the supplied extract does not further identify its scope. |
| Identifier / date | TS/046416/2022; supplied layout-plan extraction dated 22-07-2022 |
|---|---|
| What the supplied record establishes | Extract identifies a residential building, records survey number 123/27, and lists plan conditions. The supplied evidence does not establish the relationship of that survey number to the RERA-identified project parcel. |
| Identifier / date | 05.12.2023 |
|---|---|
| What the supplied record establishes | Promoter declaration of title, encumbrance status, project-fund undertakings and completion deadline. |
The supplied records do not include an occupancy certificate or completion certificate. GHMC’s permit requires an occupancy certificate before occupation and states that public water and electricity connections will be provided only on production of that certificate.
Project at a glance
Project identity
Registered project name: UMA RESIDENCY
Project type: Residential apartment project
Phase / registered portion: A single residential building is identified in the building-permit record; a separate phase name is not disclosed.
TG-RERA registration: P02500008256
Registration validity: 17 May 2024 to 27 August 2025. This is the registration period, distinct from the declared completion deadline.
Registered promoter: DANDE UMADEVI AND OTHERS; promoter organization type is recorded as “Others,” described as a joint venture.
RERA status: Listed as “On-Going Project” in the project record.
Land and geographic identity
Registered locality / address: H Nos 6-3-347/7, 6-3-347/7/A AND 6-3-347/7/B; PUNJAGUTTA HYDERABAD; PIN 500082.
Revenue village: Punjagutta Hyderabad in the RERA project record. The building-permit extract separately states “Khairatabad”; the supplied evidence does not establish a revenue-village name corresponding to the project survey parcel.
Mandal / district: KHAIRTABAD / Hyderabad.
Survey number / subdivision: RERA land identity says survey number(s) “not disclosed.” A survey number 123/27 appears in the separate layout-plan extraction; its relationship to the project parcel is not established in the supplied record.
Registered site extent: Total area 601.39 sq.m; net area 601.39 sq.m; road-widening/FTL/Nala affected area recorded as 0.
Boundaries: East: LAND BELONGING TO NIZAM INSTITUTE OF M SCIENCES; West: PART ROAD AND PLOT NO 1 H NO 6-3-347BY7; North: PLOT NO 2 H NO 6-3-347BY8; South: JB APURUPA ONE PARTMENT COMPLEX.
Development identity
Sanctioning authority: Greater Hyderabad Municipal Corporation (GHMC).
Principal building approval: 2869/GHMC/KHB/2022-BP, dated 27 August, 2022; file no. 005188/GHMC/2595/KHB2/2022-BP.
Approved building form: One residential building, 1 Stilt + 5 upper floors. The permit also records building height 14.99 and a separate total height 19.99 mt.; the supplied extraction does not specify units for the first height figure.
Approved area figures: Building-permit extraction lists residential upper-floors area 1,513.50 Sq.Mt., stilt area 313.8, total parking area 313.85, and six rainwater-harvesting pits. These are the figures as recorded in the permit extraction, not carpet or saleable area.
Approved building / parking count: 1 building; proposed number of parkings 11 and total parking 10 are both recorded in the permit extraction.
Unit count: The approved-plan record states that sanctioned units must not be increased without GHMC approval but does not state the sanctioned unit count in the supplied extraction. RERA records 10 units.
Offering and status
RERA-filed configuration: 3BHK, 10 units; saleable area 205.78 sq.m per unit.
Booked / available: 2 booked / 8 available, as last read from the TG-RERA portal; no as-of date is supplied, so these counts are indicative.
Construction-stage record: RERA project data reports 90% completeness; this is a reported figure, not an independent site inspection.
Promoter-declared completion deadline: 27/08/2025; Form B records completion “on or before 27/08/2025.”
Revised completion date: 27/08/2025 in the project record.
Occupancy / completion certificate: No occupancy or completion certificate is included in the supplied documents. The GHMC permit states that an occupancy certificate is compulsory before occupation.
The project story
UMA RESIDENCY is registered with TG-RERA as a residential apartment project under registration P02500008256, with the RERA project record locating it at H Nos 6-3-347/7, 6-3-347/7/A AND 6-3-347/7/B in the Punjagutta Hyderabad locality of Hyderabad, PIN 500082. The record describes one residential building; GHMC’s permit identifies it as 1 Stilt + 5 upper floors.
The RERA filing lists ten 3BHK units, of which two are recorded as booked and eight as available; the portal snapshot has no stated as-of date. The project record reports 90% completeness, but the supplied evidence does not include an independent inspection confirming construction progress or a certificate confirming completion or occupation. The declared completion date is 27 August 2025, while RERA registration validity is a separate period ending on that same date.
Master plan, architecture & building design
The project is recorded as a single residential building on a site of 601.39 sq.m, with net plot area also recorded as 601.39 sq.m and road- and Nala-affected areas recorded as 0.0 in the GHMC permit extraction. The permit describes 1 Stilt + 5 upper floors, with a stilt area of 313.8, residential upper-floors area of 1,513.50 Sq.Mt., and total parking area of 313.85.
The permit lists setbacks as Front 3, Rear 3.5, Side I 3.5 and Side II 3.5; the supplied extraction does not state units for these figures. It also lists a lift machine room, drinking-water sump, overhead water tank, distribution transformer, garbage pit and percolation pit among site/building provisions. The permit’s listed six rainwater-harvesting pits and other conditions are summarized under facilities and services below.
No usable floor-plan measurements are available: the supplied floor-plan data records two drawings, zero measured, and two with no flats. Consequently, room arrangements, floor-by-floor unit distribution, circulation, lift/stair counts and carpet areas cannot be established from the supplied drawing data.
Homes, configurations & floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 3BHK | 10 | 2 | 8 | 205.78 sq.m | Not available | Not supplied |
The configuration, unit count, booking counts and saleable area are from the TG-RERA filing; the booking figures have no stated as-of date. Carpet area was not software-measured from the supplied drawings: the drawing record reports two drawings and no measured plans. The RERA-filed saleable area is therefore presented separately; no carpet-area or loading figure can be confirmed from this evidence.
Parking & vehicle circulation
The GHMC permit extraction records proposed number of parkings: 11 and total parking: 10. It describes the stilt as parking space and states that the stilt/cellar approved for parking must be used exclusively for vehicle parking, without partition walls or rolling shutters. The permit extraction does not establish a separate cellar level, visitor or accessible spaces, EV charging, parking allocation to individual apartments, or the number of parking bays by level. No exclusive ownership or unit-specific parking allocation can be established from the supplied evidence.
Amenities, recreation & open spaces
| Description / size | RERA amenity record identifies a green strip/tot lot/park; GHMC conditions call for a fenced tot-lot maintained as greenery and peripheral tree planting/greenery. No area is supplied. |
|---|---|
| Declared progress / verified status | RERA record reports 90%; not independently verified complete. |
| Description / size | Listed in the RERA amenity record; no size or detail supplied. |
|---|---|
| Declared progress / verified status | 0% shown in the supplied RERA amenity data. |
| Description / size | Listed in the RERA amenity record; no building or size specified. |
|---|---|
| Declared progress / verified status | 0% shown. |
| Description / size | Appears in third-party vendor amenity text only; no supporting project-specific sanctioned or RERA facility detail is supplied here. |
|---|---|
| Declared progress / verified status | Marketing/vendor claims only; delivery not verified. |
The supplied project record does not provide dimensions or capacities for recreational or open-space facilities. The permit also requires a garbage house and percolation pit; site utilities and related services are addressed below.
Utilities, building services & safety
The RERA amenity record marks water supply, sewerage and sewage-related infrastructure, water conservation/rainwater harvesting, and an electrical meter room/substation/receiving station as available, each with 90% progress. Those are portal-reported figures, not independently verified completion. The GHMC permit extraction lists a drinking-water sump, overhead water tank, distribution transformer and garbage pit; it also records 6 rainwater-harvesting pits.
The supplied evidence does not specify water source or storage capacity, STP capacity or reuse arrangements, storm-water drainage provision, backup-power capacity, lift count or capacity, CCTV/security arrangements, waste-segregation details, or accessible circulation. The permit states that a transformer space is to be provided and that sanitation, plumbing, fire-safety requirements, lifts and electrical installations are to be executed under qualified technical supervision. It also states that fire-safety installations are the responsibility of the owner, builder/developer and technical professionals, and that a fire NOC is to be obtained before an occupancy certificate.
Location, access & connectivity
The registered project location is H Nos 6-3-347/7, 6-3-347/7/A AND 6-3-347/7/B, locality PUNJAGUTTA HYDERABAD, mandal KHAIRTABAD, Hyderabad district, PIN 500082. The project record gives site boundaries to the east, west, north and south as listed in the land identity table.
A supplied connectivity record identifies Financial District (Nanakramguda), 1.2 km, from a cadastral parcel-centroid location entry. No approach-road measurements, public-transport details or independently verified travel times are supplied.
Developer & development status
The registered promoter is DANDE UMADEVI AND OTHERS; the project filing describes the organization type as “Others” and the arrangement as a “JOINT VENTURE.” The project record gives the promoter address as Sunrise Apartments, Dwarakapuri Colony, Punjagutta Hyderabad, KHAIRTABAD, Hyderabad, 500082.
Form B is a promoter affidavit made by SMT. DANDE UMA DEVI, dated 05.12.2023, which states that the owners have legal title to the land, declares the land free from encumbrances, and records project-fund undertakings and a completion undertaking of on or before 27/08/2025. These are promoter declarations. The RERA project record reports 90% completeness, but the supplied evidence contains no independent construction-progress inspection or occupancy/completion certificate.
Approvals, official records & documents
| Identifier / date | P02500008256; validity 17 May 2024–27 August 2025 |
|---|---|
| What the supplied record establishes | Registers UMA RESIDENCY under Dande Umadevi And Others and states registration conditions. |
| Identifier / date | 2869/GHMC/KHB/2022-BP; 27 August, 2022; file no. 005188/GHMC/2595/KHB2/2022-BP |
|---|---|
| What the supplied record establishes | Conditional building permission for a residential building of 1 Stilt + 5 upper floors; the order states that permission does not confer ownership rights. |
| Identifier / date | 497/35/100/TP5/CCP/95 |
|---|---|
| What the supplied record establishes | Listed as “Approved Layout No. / LRS Proceeding No. / Sub division No”; the supplied extract does not further identify its scope. |
| Identifier / date | TS/046416/2022; supplied layout-plan extraction dated 22-07-2022 |
|---|---|
| What the supplied record establishes | Extract identifies a residential building, records survey number 123/27, and lists plan conditions. The supplied evidence does not establish the relationship of that survey number to the RERA-identified project parcel. |
| Identifier / date | 05.12.2023 |
|---|---|
| What the supplied record establishes | Promoter declaration of title, encumbrance status, project-fund undertakings and completion deadline. |
The supplied records do not include an occupancy certificate or completion certificate. GHMC’s permit requires an occupancy certificate before occupation and states that public water and electricity connections will be provided only on production of that certificate.
Frequently asked questions
Is UMA RESIDENCY registered with Telangana RERA?
Yes. UMA RESIDENCY is registered with the Telangana Real Estate Regulatory Authority as P02500008256; the registration status is On-Going Project.
Who is the developer of UMA RESIDENCY?
The promoter named in the RERA registration is DANDE UMADEVI AND OTHERS.
Where is UMA RESIDENCY located?
UMA RESIDENCY is in PUNJAGUTTA HYDERABAD, KHAIRTABAD, Hyderabad, Telangana (500082).
When will UMA RESIDENCY be completed?
The promoter's proposed date of completion filed with RERA is 27/08/2025. This is the promoter's declaration, not a guarantee.