Tuxedo Park

Subba Rao · Rangareddy · RERA P01400001769

TUXEDO PARK is a plotted development with open plots in SHADNAGAR, Farooqnagar mandal, Ranga Reddy district. The TG-RERA certificate names Mr./Ms. Subba Rao Vedantham as the registered promoter developing the project. The registered land area is 117863.71 sqmts, with a net area of 114632.71 sqmts; the project offers plots, and tower or block counts, floors, plot counts and plot configurations are not disclosed. It is registered under TG-RERA number P01400001769, with proposed completion on 27/04/2021.

01What we found

Period endedTG-RERA registration ran to 27 Apr 2021 - check its extension on TG-RERA
14documents on file - each fact links to its page
0court cases on this project's land in the court records searched
8items to check - 5 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

8 items to check before you pay, 5 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

1. Project at a glance

Project identity

ItemProject record
Registered nameTUXEDO PARK RERA record
Project typePlotted development / layout with open plots RERA record RERA filing
Phase or registered portionPhase not disclosed. TG-RERA registration is for TUXEDO PARK; the certificate lists Survey Nos. 219, 220 and 221.
TG-RERA registrationP01400001769
Registration validity20/03/2020–27/04/2021; the certificate says the registration may be extended by the Authority under the Act and Rules.
Registered promoterMr./Ms. Subba Rao Vedantham on the certificate; the project header identifies the promoter as Subba Rao. RERA record
RERA statusThe project record labels it On-Going Project. The certificate’s stated validity ended on 27/04/2021; the supplied material does not establish a subsequent extension or current registration validity. RERA record

Land and geographic identity

ItemProject record
Locality / PINSHADNAGAR, PIN 509410 RERA record
Revenue villageElikatta RERA record RERA filing
Mandal / districtFarooqnagar, Ranga Reddy RERA record RERA filing
Project survey numbers219, 220 AND 221; no project subdivision is specified in the RERA identity. RERA record RERA filing
Registered land figuresTotal area 117863.71 sqmts; area affected in road widening/FTL of tanks/Nala widening 3231 sqmts; net area 114632.71 sqmts. RERA filing
Boundaries recordedEast: LAND OF SY NO 220; West: LAND OF SY NO 218; North: LAND OF SY 219; South: LAND OF SY NO 218. RERA filing

Development identity

ItemProject record
Sanctioning authorityHyderabad Metropolitan Development Authority (HMDA) Approvals record
Principal approvalDraft Layout Permit No. 16/LO/Plg/HMDA/2017, dated 27-04-2017 Approvals record
Approved built-up area77183.00 sqmts is recorded as “Approved Built up Area”; the supplied material does not clarify its precise area basis for this plotted layout. RERA filing
Buildings / floorsBuilding count, floor configuration and tower heights are not disclosed. This is a plotted layout, not a RERA-filed apartment or tower schedule. RERA record
ParkingParking counts, parking levels and unit-wise parking allocation are not disclosed. Document index
Plots / countsRERA plot inventory, plot-size schedule, and booked/available counts are not supplied. RERA unit table Layout record

Offering and status

ItemProject record
Offered productPlots in a plotted layout; unit-wise RERA plot types, sizes and inventory are not provided in the supplied records. RERA record RERA filing RERA unit table
RERA-declared progressThe project header records 80% completeness. This is a recorded progress figure, not independent site verification. RERA record
Completion datesOriginal and revised proposed completion dates are both 27/04/2021. RERA record RERA filing
Occupancy/completion certificateNo occupancy or completion certificate is identified in the supplied project material. The supplied RERA status is “On-Going Project.” RERA record Document index

2. The project story

  • TUXEDO PARK is registered as a plotted development in Elikatta village, Farooqnagar mandal, Ranga Reddy district. Its TG-RERA identity covers Survey Nos. 219, 220 and 221 and gives a site area of 117863.71 sqmts, with 3231 sqmts recorded as affected and a net area of 114632.71 sqmts. RERA record RERA filing
  • HMDA’s filed approval material describes a draft layout with open plots and provides for roads, open space and social-infrastructure land. It also identifies 24 plots as mortgaged to HMDA and not available for sale under the approval conditions. The supplied records do not include a complete RERA plot schedule or enough information to describe individual plot sizes, current availability or the layout’s plot-by-plot arrangement. RERA unit table
  • The RERA header records 80% completeness and a completion date of 27/04/2021. Those are project-record declarations; no independent site inspection or completion certificate is supplied here to confirm current physical progress or completion. RERA record Document index

3. Master plan, architecture & building design

  • This is a plotted layout rather than a tower or apartment development. The HMDA document is titled an approval of a draft layout with open plots for Survey Nos. 219, 220 and 221. It describes a layout with proposed roads and designated areas for plots, open space and social infrastructure.
  • The RERA land record states total area 117863.71 sqmts, affected area 3231 sqmts, and net area 114632.71 sqmts. The filed built-up-area field records 77183.00 sqmts; no further definition or area breakdown is supplied for that figure. RERA filing RERA filing
  • The HMDA material identifies road widths including a 30 m wide Master Plan road and proposed 40’, 60’, 30’, 45.00M, 100’, and 36.60m roads. The approval conditions also require road formation, drainage, street lighting and underground utility ducting. These are approval/document provisions and do not establish that the works have been completed.
  • The approved draft-layout material identifies 13,718.12 sq.yds of open space, 5561.40 sq.yards of social-infrastructure area and 32349.21 sq.yards of roads. No building-floor plans, apartment configurations, tower arrangement or final plot schedule is provided in the supplied records.

4. Homes, configurations & floor plans

The offering evidenced by the RERA record is a plotted development. No RERA plot inventory table, plot-size bands, plot counts, or booked/available counts are supplied, so a unit-configuration table cannot be completed from the available evidence. RERA record RERA unit table Layout record

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading
PlotsNot disclosedNot disclosedNot disclosedNot disclosedNot applicable / not suppliedNot disclosed

Four drawings are listed, but all four are scans pending measurement; no drawing-based measurements are available. The floor-plan data specifically cautions that software-measured carpet area would not be a RERA disclosure and that it differs from saleable area. Floor plans

5. Parking & vehicle circulation

The supplied RERA and approval extracts do not establish car or two-wheeler parking counts, visitor or accessible spaces, parking levels, vehicle-entry arrangements, ramps, EV charging, or plot-specific parking allocations. The HMDA approval refers to a road network and requires road development, but does not provide a parking schedule. A plot’s inclusion in a layout does not, on this evidence, establish a separately allocated parking space. Document index

6. Amenities, recreation & open spaces

The project record includes a range of layout infrastructure and amenities. In the table below, “not evidenced complete” means the supplied material does not independently establish completion. The RERA amenities extract marks internal roads and footpaths, green strip/park, and street lighting as available, but records 0% progress for those items; it does not provide a separate verified completion status. RERA amenities

Open space / greenery
Description / sizeHMDA material states 13,718.12 sq.yds of open space; the RERA amenity list includes Green Strip/TOT LOT/Park. RERA amenities
Evidence sourceHMDA draft-layout approval; RERA amenities
Declared progress / verified statusRERA extract shows 0%; no independent completion verification supplied.
Roads and footpaths
Description / sizeHMDA material states roads area 32349.21 sq.yards; RERA amenities include internal roads and footpaths. RERA amenities
Evidence sourceHMDA draft-layout approval; RERA amenities
Declared progress / verified statusRERA extract says “YES” and 0%; no independent completion verification supplied.
Street lighting
Description / sizeRequired in the HMDA approval conditions and listed in RERA amenities. RERA amenities
Evidence sourceHMDA draft-layout conditions; RERA amenities
Declared progress / verified statusRERA extract says “YES” and 0%; no independent completion verification supplied.
Social infrastructure / community buildings
Description / sizeHMDA material states 5561.40 sq.yards of social-infrastructure area; RERA amenities list community buildings. RERA amenities
Evidence sourceHMDA draft-layout approval; RERA amenities
Declared progress / verified statusNo delivered facility or completion status established.
Water conservation / rainwater harvesting
Description / sizeHMDA conditions require harvesting pits; RERA amenities include water conservation and rainwater harvesting. RERA amenities
Evidence sourceHMDA draft-layout conditions; RERA amenities
Declared progress / verified statusNo completion status supplied.
Recreation and other community features
Description / sizeThe RERA amenity list includes aggregate recreational open space. A third-party sales brochure claims a clubhouse, indoor games, swimming pool, multipurpose hall, park, children’s park and avenue plantation; these are promoter-marketed, not established here as sanctioned or delivered facilities. RERA amenities
Evidence sourceRERA amenities; promotional brochure
Declared progress / verified statusNo RERA progress or independent completion evidence supplied for these facilities.

7. Utilities, building services & safety

  • HMDA’s approval conditions call for harvesting pits, septic tank and sump/OHT, street lighting and electricity facilities, an independent sewerage-disposal system, protected water supply, underground utility ducting, and avenue planting. These are approval conditions, not evidence that each item has been installed or is operational.
  • The RERA amenities extract lists water supply, sewerage, storm-water drains, treatment and disposal of sewage and sullage water, solid-waste management, water conservation/rainwater harvesting, energy management, fire-protection and fire-safety requirements, and an electrical meter room/sub-station/receiving station. No capacities, implementation details, or independently verified completion records are supplied. The same extract records 0% progress for these entries. RERA amenities
  • No project-specific evidence supplied here establishes water source or storage capacity, treatment plant capacity, electrical backup, fire-system design or clearance, security/CCTV, accessible circulation, or operational status. RERA amenities Document index

8. Location, access & connectivity

  • The registered project location is Elikatta village, Farooqnagar mandal, Ranga Reddy district, locality SHADNAGAR, PIN 509410. The project boundaries recorded in the RERA land details are: east LAND OF SY NO 220; west LAND OF SY NO 218; north LAND OF SY 219; and south LAND OF SY NO 218. RERA record RERA filing RERA filing
  • A location dataset lists the nearest sampled Outer Ring Road interchange at approximately 102.4 km. The record labels this as approximate; no project approach-road description or public-transport schedule is supplied in the official project material. Location record

9. Developer & development status

  • The TG-RERA certificate names the promoter as Mr./Ms. Subba Rao Vedantham; the project header records Subba Rao. The legal entity type, corporate registration identifiers, registered office details, official project contact details, and official promoter website are not established in the supplied project data. RERA record Corporate record
  • The RERA header records 80% completeness and proposed completion dates of 27/04/2021 (original and revised). The registration certificate gives validity through 27/04/2021. No extension order, current project-status update, independent progress report, or occupancy/completion certificate is supplied; therefore, the available material does not establish current completion or certification status. RERA record Document index

10. Approvals, official records & documents

TG-RERA registration certificate
Identifier / dateP01400001769, issued 20/03/2020; validity stated through 27/04/2021
What the supplied material establishesForm C certificate for TUXEDO PARK, naming the promoter as Mr./Ms. Subba Rao Vedantham and listing Survey Nos. 219, 220 and 221.
HMDA draft-layout approval
Identifier / dateLayout Permit No. 16/LO/Plg/HMDA/2017, dated 27-04-2017; file no. 202376/LO/Plg./H/2015
What the supplied material establishesHMDA approval of a draft layout with open plots in Survey Nos. 219, 220 and 221, Elikatta village; includes approval conditions and reserved/mortgaged plots.
HMDA technical-approval layout plan
Identifier / dateApproval number recorded as 16 Lo Plq HM DA /2017, dated 27/04/2017
What the supplied material establishesTechnical approval of a draft layout plan; includes roads, land-use areas and restrictions concerning plots mortgaged to HMDA.
Draft-layout plan extract
Identifier / dateNo approval number identified in the extract
What the supplied material establishesDraft plan records proposed layout and land-use figures; it does not itself identify a sanctioning authority or approval number.
Additional commencement/layout document
Identifier / dateDocument 107467; OCR shows a Gram Panchayat reference and date 14-12-08
What the supplied material establishesThe supplied extraction does not legibly establish a layout or building approval, sanctioned land details, or approval conditions.
Occupancy / completion certificate
Identifier / dateNot supplied
What the supplied material establishesNo project occupancy or completion certificate is identified in the materials reviewed. Document index
Other filed project documents
Identifier / dateForm B declaration 42453; title report 104765; title-related documents 104795, 41859, 41860; encumbrance statements 104766, 42339, 42340
What the supplied material establishesThese are present in the supplied document register; this overview does not assess their legal effect. Document index

Frequently asked questions

Is TUXEDO PARK registered with Telangana RERA?

Yes. TUXEDO PARK is registered with the Telangana Real Estate Regulatory Authority as P01400001769; the registration status is On-Going Project.

Who is the developer of TUXEDO PARK?

The promoter named in the RERA registration is Subba Rao.

Where is TUXEDO PARK located?

TUXEDO PARK is in SHADNAGAR, Elikatta, Farooqnagar, Rangareddy, Telangana (509410).

When will TUXEDO PARK be completed?

The promoter's proposed date of completion filed with RERA is 27/04/2021. This is the promoter's declaration, not a guarantee.

More projects in Elikatta