TECHNO CITY is a plotted development / residential open-plot layout in Melaguda Tanda, Farooqnagar mandal, Ranga Reddy district. The registered promoter is MOHAMMED IMRANALI. The RERA land record gives a total and net area of 18105.6 sq.m, and the layout records 59 residential open plots; plot configurations are not disclosed. Its TG-RERA registration is P02400009171, and the promoter’s Form B undertakes completion by 10-02-2026.

01What we found

Period endedTG-RERA registration ran to 10 Feb 2026 - check its extension on TG-RERA
16documents on file - each fact links to its page
0court cases on this project's land in the court records searched
6items to check - 4 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

6 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

Project at a glance

Project identity

FieldRecord
Registered project nameTECHNO CITY
Project typePlotted development / residential open-plot layout RERA filing
Phase or registered portionThe registration identifies a project on Survey No. 9/P; a separate phase description is not disclosed
TG-RERA registrationP02400009171
Registration validity10/02/2024 to 10/02/2026, unless extended by the Authority
Registered promoterMOHAMMED IMRANALI
RERA statusRegistration certificate records a two-year validity period. A later extension or current registration status is not established by the supplied registration record.

Land and geographic identity

FieldRecord
LocalityMelaguda Tanda; the filed layout documents also identify Melaguda Gram Panchayat / Melaguda G.P. RERA filing
Revenue village(s)Kongaguda is identified in the layout documents; the registration record says “Farooqnagar” as village. The supplied records do not resolve the exact revenue-village identity.
MandalFarooqnagar RERA filing
DistrictRanga Reddy / Rangareddy RERA filing
PIN500531 RERA filing
Project survey reference(s)9/P; the final-layout document describes 09/PART. RERA filing
Site extentRERA land record: total and net area 18105.6 sq.m. RERA filing The filed DT&CP draft layout describes Ac.4-18.96 Gts; 21654.16 Sq.Yds.
BoundariesNot disclosed in the supplied project land record. Land records

Development identity

FieldRecord
Sanctioning authorityDT&CP; the filed draft technical layout document records delegated development to Melaguda Gram Panchayat.
Principal layout approvalDTLP NO. 07 / 2024 /HRO /H1, approved 10. 02.2024; file Lr.Roc.No. 107/2023/HRO/H1.
Other approval identifiersApplication / E. Panchayath No. 20043/31; proceedings TLP. No. 07/ 2024/ HRO/ H1; plan drawing C.NO. 107/ 2024 / HRO /H1.
Plots and land-use split in draft approval59 plots; plotted area Ac.2-31.56 Gts; 13498.76 Sq Yds. (62.34%); roads Ac. 1-09.51 Gts; 5989.98 Sq. Yds. (27.66%); park open space Ac.0-17.89 Gts; 2165.416 Sq. Yds. (10.00%).
Approved built-up areaNot disclosed for this plotted development. RERA filing
Buildings, floors and parking levelsNot applicable to the recorded plot layout; building-level or parking-level plans are not supplied.

Offering and status

FieldRecord
Unit typeResidential open plots; the draft approval records 59 plots.
Plot size rangeNot disclosed in the supplied records.
Booked / available countsNot disclosed.
Construction / development stageAn architect’s Form–1A dated 10-04-2026 reports internal and external development works as 100% complete where marked. This is a filed architect’s report, not independent site verification.
Completion datesPromoter’s Form B undertakes completion by 10-02-2026; this is separate from the registration-validity period.
Occupancy / completion certificate statusThe supplied records do not establish an occupancy certificate for a building. A final-layout document is supplied, and the architect’s certificate reports development completion; neither is described here as an occupancy certificate.

The project story

TECHNO CITY is registered as a plotted residential development on Survey No. 9/P in the Melaguda Tanda area of Farooqnagar mandal, Ranga Reddy district. The registration names MOHAMMED IMRANALI as promoter and records TG-RERA number P02400009171. RERA filing

The DT&CP-filed draft technical layout describes 59 residential plots, with internal roads and a park open space. It also identifies plots 11 to 13 and 20 to 22, measuring 2142.71 Sq. Yards, as mortgage land in favour of Melaguda Gram Panchayat; the approval states that this land is not for sale. The supplied Form–1A architect’s certificate, dated 10-04-2026, reports development works as 100% complete where marked. This is a professional certificate filed for the project, not independent verification of on-site completion.

The location and survey description are not fully specified as a single revenue-village identity in the supplied records: the layout documents name Kongaguda, while the registration record labels the village Farooqnagar.

Master plan, architecture & building design

This is a plotted layout, not a multi-storey residential building scheme in the records supplied. The DT&CP draft technical layout records a layout area of Ac.4-18.96 Gts; 21654.16 Sq.Yds. and provides for 59 plots. Its stated land-use allocation is 62.34% plotted area, 27.66% roads and 10.00% park open space.

The draft approval lists road widths of 33'-0" and 330 as extracted from the filed document; the second entry is reproduced as supplied, without an inferred unit. The same approval identifies the six plots reserved for mortgage to the Gram Panchayat. It also states that roads are to be accessible to neighbouring sites and that development and final release are subject to the approval conditions.

The supplied final-layout record describes a residential open-plot layout of 59 open plots and records an area of 18105.87 sq.m, with 11295.13 sq.m (62.38%) plotted area, 5000.08 sq.m (27.62%) road area and 1810.58 sq.m (10.00%) open space. No building footprint, floor configuration, tower arrangement, apartment mix or building-level architectural drawings are evidenced in the supplied material.

Homes, configurations & floor plans

The project record describes plots rather than apartments. The supplied layout approval records 59 plots, but the individual plot dimensions, plot-size bands, plot numbers offered for sale, and booked or available inventory are not established in the provided data.

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
Residential plots59 (layout count)Not disclosedNot disclosedNot disclosed by plotNot applicableNot supplied

Two drawing records are listed, but both remain unmeasured and are scans pending; no software-measured carpet or plot measurements are available. Floor plans For this plotted project, apartment carpet area and common-area loading are not applicable on the supplied evidence.

Parking & vehicle circulation

The supplied records do not establish a count or allocation of resident, visitor, accessible, two-wheeler or other parking spaces, nor a dedicated common-parking area. The final-layout record lists common parking area as 0.00 sq.m. The layout approval identifies internal roads, but does not provide vehicle-entry/exit arrangements, turning details, pedestrian separation or a parking-allocation schedule.

Amenities, recreation & open spaces

The filed draft layout approval lists a park open space, side drains, rain-water-harvesting pits, street lighting, electricity facilities, a sewerage disposal system and protected water supply. The RERA-filed amenity entries report progress percentages; these are reported project data, not independent verification.

FacilityDescription / sizeEvidence sourceDeclared progress / verified status
Clubhouse / indoorNo community building is recorded.RERA amenitiesCommunity Buildings: 0% recorded.
Sports / recreationNo separate sports facility is identified.RERA amenitiesNo progress figure for a sports facility is supplied.
Landscape / open spacePark open space: Ac.0-17.89 Gts; 2165.416 Sq. Yds. (10.00%) in the draft approval.Green Strip/TOT LOT/Park: 75% in the RERA amenity record; independent completion verification is not supplied. RERA amenities
Convenience / communityNo community buildings or separate convenience facilities are identified in the supplied layout records.RERA amenitiesCommunity Buildings: 0% recorded.

Utilities, building services & safety

The DT&CP draft layout approval lists side drains, rain-water-harvesting pits, street lighting, electricity facilities, sewerage disposal and protected water supply as layout works. A filed Form–1A architect’s certificate includes internal roads and footpaths, water supply, sewerage, storm-water drains, landscaping and tree planting, street lighting, solid-waste management, water conservation/rain-water harvesting, energy management, fire protection and an electrical meter room/sub-station/receiving station among its infrastructure categories.

RERA’s amenity record gives progress figures for several categories, including water supply (90%), sewerage (75%), storm-water drains (75%), street lighting (78%), solid-waste management (78%), water conservation/rain-water harvesting (80%), energy management (85%) and electrical meter room/sub-station/receiving station (85%). Fire protection and fire safety requirements are recorded at 0%. These are recorded project progress figures, not independent confirmation of delivery or statutory compliance. RERA amenities

Storage and treatment capacities, water source, sewerage-treatment capacity, reuse arrangements, electrical load, backup supply, firefighting equipment details, security systems and accessibility features are not established by the supplied project records. The vendor material mentions several services but is not used here as evidence of sanctioned or delivered facilities. Promoter website

Location, access & connectivity

The registered location is Melaguda Tanda, Farooqnagar mandal, Ranga Reddy district, PIN 500531, with Survey No. 9/P. RERA record RERA filing The layout documents identify Kongaguda village and Melaguda Gram Panchayat / Melaguda G.P.

A cadastral parcel-centroid geocode is supplied at 17.41528, 78.35459. Location record The supplied connectivity record lists Financial District (Nanakramguda) at 1.2 km as an anchor. Location record No approach-road name, public-transport route, or other independently measured landmark distance is supplied.

Developer & development status

The TG-RERA certificate names Mohammed Imranali as the registered promoter; the project fields identify the promoter as MOHAMMED IMRANALI and list the organization type as Proprietorship. RERA filing A promoter Form B is filed by MOHAMMED IMRAN ALI and declares a completion undertaking of 10-02-2026.

The registration certificate records validity from 10/02/2024 to 10/02/2026, unless extended by the Authority. The architect’s Form–1A dated 10-04-2026 reports development works as 100% complete where marked. The supplied material does not establish a later RERA extension, independent site inspection, or building occupancy certificate.

Approvals, official records & documents

RecordScope and identifying details
TG-RERA registration certificateForm C for TECHNO CITY, P02400009171; records the promoter and validity from 10/02/2024 to 10/02/2026 unless extended.
DT&CP draft technical layout approvalDTLP NO. 07 / 2024 /HRO /H1, dated 10. 02.2024; file Lr.Roc.No. 107/2023/HRO/H1; 59-plot layout on Sy. No. 9/P.
Final layout plan recordFinal-layout document for 59 residential open plots, identified as Sy. No. 09/PART at Melaguda G.P, Kongaguda Village; approval date recorded as 27/08/2026.
Architect’s Form–1A certificateDated 10-04-2026; identifies TG-RERA registration P02400009171 and Survey No. 9/P; reports development-work completion where marked.
Promoter’s Form B declarationPromoter declaration concerning title basis, encumbrances, fund handling, audits, approvals and completion undertaking by 10-02-2026.
Filed layout-plan materialAn additional supplied layout-plan file refers to Sy. Nos. 16/P, 15/P and 12/P and names Mondagonda Village, Sangareddy District. Its project-specific relationship is not established in the supplied record.

Frequently asked questions

Is TECHNO CITY registered with Telangana RERA?

Yes. TECHNO CITY is registered with the Telangana Real Estate Regulatory Authority as P02400009171; the registration status is New Project.

Who is the developer of TECHNO CITY?

The promoter named in the RERA registration is MOHAMMED IMRANALI.

Where is TECHNO CITY located?

TECHNO CITY is in MELAGUDA TANDA, Farooqnagar, Rangareddy, Telangana (500531).