Sree Sai Balaji Dwarakamayee Residency Block I
BANALA · Medchal-Malkajgiri · RERA P02200002015
SREE SAI BALAJI DWARAKAMAYEE RESIDENCY BLOCK I is a residential apartment project in Mamatha Nagar, Uppal, Medchal-Malkajgiri. The registered promoter is Banala Goverdhan. The project covers a total land area of 785.8 sq.m. and comprises one residential building with 1 stilt + 5 upper floors and 20 homes: 10 2BHK and 10 3BHK. Its TG-RERA registration number is P02200002015, and its proposed completion date is 01/09/2025.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
8 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
Project at a glance
Project identity
| Item | Project record |
|---|---|
| Registered project name | SREE SAI BALAJI DWARAKAMAYEE RESIDENCY BLOCK I RERA record |
| Project type | Residential apartment project RERA record Approvals record |
| Phase / registered portion | Block I; the registration certificate names Block I. |
| TG-RERA registration | P02200002015 |
| Registration validity | 06/07/2020 to 01/09/2025; certificate states five years, unless extended by the Authority. The supplied certificate records no extension. Registration validity is distinct from the project completion deadline. |
| Registered promoter | Banala Goverdhan (also shown in the RERA project record as BANALA); legal entity type not disclosed. RERA record |
| RERA status in supplied record | New Project; registration certificate validity ended 01/09/2025, with no extension recorded in the supplied certificate. Current portal status is not established by the supplied evidence. RERA record |
Land and geographic identity
| Item | Project record |
|---|---|
| Locality | Mamatha Nagar RERA record RERA filing |
| Revenue village | Mamatha Nagar in the project header and land record. RERA record Land records |
| Mandal / district / PIN | Uppal / Medchal-Malkajgiri / 500039 RERA record RERA filing |
| Survey number and subdivision | Survey No. 23 PART RERA record Land records |
| Plots | 42, 43, 44P, 53P, 54 AND 55 RERA filing |
| Site area | Total area 785.8 sq.m.; area affected in road widening 43.66 sq.m.; net area 742.14 sq.m. RERA filing |
| Boundaries | East: 25 WIDE ROAD; West: 25 WIDE ROAD; North: PLOT NO 44 AND 53 PART; South: 30 WIDE ROAD RERA filing |
Development identity
| Item | Project record |
|---|---|
| Sanctioning authority | Greater Hyderabad Municipal Corporation (GHMC) Approvals record |
| Principal building-permit approval | No. 2/C3/13251/2019; plan records approval dated 05-09-2019. Approvals record |
| Approved built-up area | 1,953.10 sq.m. is recorded as “BUILT UP AREA” on the filed plan. |
| Building count and configuration | One residential building; 1 stilt + 5 upper floors. RERA filing |
| Height / floor count | Filed plan records 6 floors and building height 14.99 MT.; it also lists 17.99 mt. from GL and 20.99 mt. total height. |
| Parking provision | Plan records “Proposed Number of Parkings 18”; stilt is identified for parking. |
| Dwelling units | GHMC plan records 20 units; RERA filing records 20 units across two configurations. RERA unit table |
Offering and status
| Item | Project record |
|---|---|
| Configurations | 2BHK (filed as “DOUBLE BEDROOM”) and 3BHK (filed as “TRIBLE BEDROOM”) RERA unit table |
| RERA-filed saleable area | 2BHK: 49.52 sq.m.; 3BHK: 127.6 sq.m. RERA unit table |
| Booked / available | 0 booked and 10 available in each configuration; 20 available in total, as last read from the TG-RERA portal. No as-of date is supplied, so counts are indicative. RERA unit table |
| Completion deadline | Project header records proposed completion 01/09/2025. Form B declares completion by 01-02:2025; the supplied evidence does not clarify this date’s notation. RERA record |
| Construction stage | No independently verified site progress or dated construction-stage report is supplied. RERA amenity progress entries show 0% where recorded. RERA amenities |
| Occupancy / completion certificate | No occupancy or completion certificate is supplied. The GHMC plan says an occupancy certificate is compulsory before occupation. |
The project story
This is a single-building residential apartment project registered as SREE SAI BALAJI DWARAKAMAYEE RESIDENCY BLOCK I, at Mamatha Nagar, Uppal, in Medchal-Malkajgiri district. The filed land identity is Survey No. 23 PART, covering plots 42, 43, 44P, 53P, 54 AND 55. The GHMC plan describes a stilt-plus-five-floor building, with 20 dwelling units. RERA record Land records
The RERA filing lists ten 2BHK and ten 3BHK units. Its portal-derived booked/available figures indicate all 20 as available and none booked, but the record supplies no date for that snapshot. The project’s completion date is recorded separately from the RERA registration-validity period; neither should be treated as evidence of completion. No site-verified construction progress or occupancy certificate is included in the supplied material. RERA unit table RERA record RERA amenities
Master plan, architecture & building design
The filed GHMC plan is for a proposed residential building on the identified plots in Survey No. 23 PART. It shows one building, one stilt level and five upper floors. The plan records an approved built-up area of 1,953.10 sq.m.; it separately lists residential net BUA as 1,939.35 sq.m. and proposed coverage area as 418.69 sq.m. (56.42%). These are plan-recorded area labels and should not be read as carpet or saleable area.
The plan describes four dwelling units on each of the first through fifth floors. It also records a 195.73 sq.m. built-up area to mortgage. The plan identifies a green strip, a watchman room, a garbage bin and water-related features; it does not provide evidence that these have been completed. No basement or podium is shown in the supplied floor configuration.
The plan lists a single entry and exit with minimum width 4.5 m and height clearance 5 m. It also states that the stilt approved for parking is to be used exclusively for vehicle parking, and that no construction or parking is permitted in setbacks. Detailed floor-by-floor architectural drawings sufficient to establish room arrangements across all configurations are not supplied here.
Homes, configurations & floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK (“DOUBLE BEDROOM”) | 10 | 0 | 10 | 49.52 sq.m. | Not measured in supplied drawings | Not supplied |
| 3BHK (“TRIBLE BEDROOM”) | 10 | 0 | 10 | 127.6 sq.m. | 88.1–93.0 sq.m.; median 88.6 sq.m. (software-measured from drawings) | 31% (software-measured) |
RERA saleable-area figures and the drawing-based carpet measurements are different measures. The supplied drawing analysis explains that carpet area is measured from drawing geometry and that saleable area also includes a share of common areas. The drawing-based figures are not RERA disclosures and require review against the drawings. For the measured 3BHK drawing identified as flat 03 on the “TYPICAL - 1, 3, 4& 5 FLOOR PLAN,” the listed spaces include living/dining, kitchen, three bedrooms, three toilets, sitout and wash area. RERA unit table Floor plans RERA unit details
Parking & vehicle circulation
The GHMC plan records 18 proposed parking spaces and identifies the stilt for parking. It requires the stilt parking area to remain in parking use, without partition walls or rolling shutters. The plan also records one entry and one exit, each with a minimum width of 4.5 m and height clearance of 5 m.
The supplied evidence does not specify separate resident, visitor or accessible parking counts, two-wheeler spaces, EV charging, parking allocation by apartment, or a legally documented exclusive parking entitlement for any unit.
Amenities, recreation & open spaces
The following are features recorded in the GHMC plan or RERA amenity filing. The progress entries available in the filing are shown as 0% where recorded; the material does not establish independent completion.
| Description / size | GHMC plan identifies a green strip and states a tot-lot is to be fenced and maintained as greenery before occupancy certificate; no size is established in the supplied plan extract. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | RERA amenity entry shows 0%; completion not independently verified. |
| Description / size | Listed in the RERA amenity schedule; no description or size supplied. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | 0%; no completion evidence supplied. |
| Description / size | Listed as an aggregate recreational open-space item; no area supplied. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | 0%; no completion evidence supplied. |
| Description / size | Listed in the RERA amenity schedule; no dimensions supplied. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | 0%; no completion evidence supplied. |
Utilities, building services & safety
Water and drainage: The plan lists a sump, overhead water tank and percolating well. A drawing entry specifies separate underground static water storage of 25,000 litres and a separate residential terrace tank of 25,000 litres. The RERA amenity schedule marks water supply and sewerage as “YES,” but does not establish source, treatment capacity, STP details, reuse arrangements or completed installation. RERA amenities
Electrical and waste: The plan identifies space for a transformer and a garbage house; it also lists a garbage bin. The RERA amenity schedule marks an electrical meter room, sub-station or receiving station “YES.” No electrical backup capacity or waste-processing details are supplied. RERA amenities
Fire safety and circulation: Fire protection and fire safety are listed in the RERA amenity schedule, with no percentage or system specification supplied. The GHMC plan states that fire-safety and related services are to be executed under qualified technical supervision. The supplied evidence does not establish completed systems or statutory clearance. RERA amenities
Access and vertical transportation: The plan lists a lift and a watchman room, but gives no lift capacity or number of lifts. It specifies one entry and one exit, each with minimum width 4.5 m and height clearance 5 m. No accessible-route or ramp details are supplied.
Location, access & connectivity
The official project identity places the site at Mamatha Nagar, Uppal mandal, Medchal-Malkajgiri district, PIN 500039. The filed land record identifies Survey No. 23 PART and plots 42, 43, 44P, 53P, 54 AND 55. The plan records roads adjoining the site boundaries, including 25 WIDE ROAD on the east and west and 30 WIDE ROAD on the south. RERA record RERA filing RERA filing
The supplied location data gives a distance of 1.2 km to Financial District (Nanakramguda). No public-transport details or further measured access distances are provided. Location record
Developer & development status
The registered promoter is Banala Goverdhan, shown in the project record as BANALA. The legal entity type, corporate identifier, registered office and official contact details are not established in the supplied material. The project’s Form B is a promoter declaration: it identifies BANALA GOVERDHAN as promoter and includes undertakings concerning title, project funds, audits, pending approvals and completion. RERA record Corporate record
The project record states a proposed completion date of 01/09/2025; Form B gives a completion undertaking written as “01-02:2025.” No dated progress report or independently verified construction status is supplied, and no occupancy or completion certificate appears in the available project documents. RERA record RERA amenities
Approvals, official records & documents
| Record | What the supplied evidence establishes |
|---|---|
| TG-RERA registration certificate, P02200002015 | Form C records registration under section 5 for SREE SAI BALAJI DWARAKAMAYEE RESIDENCY BLOCK I, issued 06/07/2020 and valid to 01/09/2025; no extension is recorded in the supplied certificate. |
| GHMC building permit, 2/C3/13251/2019 | Filed building-permit material identifies a residential stilt-plus-five-floor building on Survey No. 23 PART. The plan records approval date 05-09-2019; the building-permit order extract records 04 September, 2019. Approvals record |
| GHMC proposed building plan | Records 20 units, 18 proposed parking spaces, the building configuration, area labels and stated plan conditions. |
| Promoter Form B | Promoter declaration identifying BANALA GOVERDHAN and stating title, encumbrance, funds, audit, approval and completion undertakings. |
| Occupancy/completion certificate | None supplied. The GHMC plan states that an occupancy certificate is required before occupation. |
The supplied record does not include an independently verified site-progress report or an occupancy/completion certificate.
Project at a glance
Project identity
Registered project name: SREE SAI BALAJI DWARAKAMAYEE RESIDENCY BLOCK I
Project type: Residential apartment project
Phase / registered portion: Block I; the registration certificate names Block I.
TG-RERA registration: P02200002015
Registration validity: 06/07/2020 to 01/09/2025; certificate states five years, unless extended by the Authority. The supplied certificate records no extension. Registration validity is distinct from the project completion deadline.
Registered promoter: Banala Goverdhan (also shown in the RERA project record as BANALA); legal entity type not disclosed.
RERA status in supplied record: New Project; registration certificate validity ended 01/09/2025, with no extension recorded in the supplied certificate. Current portal status is not established by the supplied evidence.
Land and geographic identity
Locality: Mamatha Nagar
Revenue village: Mamatha Nagar in the project header and land record.
Mandal / district / PIN: Uppal / Medchal-Malkajgiri / 500039
Survey number and subdivision: Survey No. 23 PART
Plots: 42, 43, 44P, 53P, 54 AND 55
Site area: Total area 785.8 sq.m.; area affected in road widening 43.66 sq.m.; net area 742.14 sq.m.
Boundaries: East: 25 WIDE ROAD; West: 25 WIDE ROAD; North: PLOT NO 44 AND 53 PART; South: 30 WIDE ROAD
Development identity
Sanctioning authority: Greater Hyderabad Municipal Corporation (GHMC)
Principal building-permit approval: No. 2/C3/13251/2019; plan records approval dated 05-09-2019.
Approved built-up area: 1,953.10 sq.m. is recorded as “BUILT UP AREA” on the filed plan.
Building count and configuration: One residential building; 1 stilt + 5 upper floors.
Height / floor count: Filed plan records 6 floors and building height 14.99 MT.; it also lists 17.99 mt. from GL and 20.99 mt. total height.
Parking provision: Plan records “Proposed Number of Parkings 18”; stilt is identified for parking.
Dwelling units: GHMC plan records 20 units; RERA filing records 20 units across two configurations.
Offering and status
Configurations: 2BHK (filed as “DOUBLE BEDROOM”) and 3BHK (filed as “TRIBLE BEDROOM”)
RERA-filed saleable area: 2BHK: 49.52 sq.m.; 3BHK: 127.6 sq.m.
Booked / available: 0 booked and 10 available in each configuration; 20 available in total, as last read from the TG-RERA portal. No as-of date is supplied, so counts are indicative.
Completion deadline: Project header records proposed completion 01/09/2025. Form B declares completion by 01-02:2025; the supplied evidence does not clarify this date’s notation.
Construction stage: No independently verified site progress or dated construction-stage report is supplied. RERA amenity progress entries show 0% where recorded.
Occupancy / completion certificate: No occupancy or completion certificate is supplied. The GHMC plan says an occupancy certificate is compulsory before occupation.
The project story
This is a single-building residential apartment project registered as SREE SAI BALAJI DWARAKAMAYEE RESIDENCY BLOCK I, at Mamatha Nagar, Uppal, in Medchal-Malkajgiri district. The filed land identity is Survey No. 23 PART, covering plots 42, 43, 44P, 53P, 54 AND 55. The GHMC plan describes a stilt-plus-five-floor building, with 20 dwelling units.
The RERA filing lists ten 2BHK and ten 3BHK units. Its portal-derived booked/available figures indicate all 20 as available and none booked, but the record supplies no date for that snapshot. The project’s completion date is recorded separately from the RERA registration-validity period; neither should be treated as evidence of completion. No site-verified construction progress or occupancy certificate is included in the supplied material.
Master plan, architecture & building design
The filed GHMC plan is for a proposed residential building on the identified plots in Survey No. 23 PART. It shows one building, one stilt level and five upper floors. The plan records an approved built-up area of 1,953.10 sq.m.; it separately lists residential net BUA as 1,939.35 sq.m. and proposed coverage area as 418.69 sq.m. (56.42%). These are plan-recorded area labels and should not be read as carpet or saleable area.
The plan describes four dwelling units on each of the first through fifth floors. It also records a 195.73 sq.m. built-up area to mortgage. The plan identifies a green strip, a watchman room, a garbage bin and water-related features; it does not provide evidence that these have been completed. No basement or podium is shown in the supplied floor configuration.
The plan lists a single entry and exit with minimum width 4.5 m and height clearance 5 m. It also states that the stilt approved for parking is to be used exclusively for vehicle parking, and that no construction or parking is permitted in setbacks. Detailed floor-by-floor architectural drawings sufficient to establish room arrangements across all configurations are not supplied here.
Homes, configurations & floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK (“DOUBLE BEDROOM”) | 10 | 0 | 10 | 49.52 sq.m. | Not measured in supplied drawings | Not supplied |
| 3BHK (“TRIBLE BEDROOM”) | 10 | 0 | 10 | 127.6 sq.m. | 88.1–93.0 sq.m.; median 88.6 sq.m. (software-measured from drawings) | 31% (software-measured) |
RERA saleable-area figures and the drawing-based carpet measurements are different measures. The supplied drawing analysis explains that carpet area is measured from drawing geometry and that saleable area also includes a share of common areas. The drawing-based figures are not RERA disclosures and require review against the drawings. For the measured 3BHK drawing identified as flat 03 on the “TYPICAL - 1, 3, 4& 5 FLOOR PLAN,” the listed spaces include living/dining, kitchen, three bedrooms, three toilets, sitout and wash area.
Parking & vehicle circulation
The GHMC plan records 18 proposed parking spaces and identifies the stilt for parking. It requires the stilt parking area to remain in parking use, without partition walls or rolling shutters. The plan also records one entry and one exit, each with a minimum width of 4.5 m and height clearance of 5 m.
The supplied evidence does not specify separate resident, visitor or accessible parking counts, two-wheeler spaces, EV charging, parking allocation by apartment, or a legally documented exclusive parking entitlement for any unit.
Amenities, recreation & open spaces
The following are features recorded in the GHMC plan or RERA amenity filing. The progress entries available in the filing are shown as 0% where recorded; the material does not establish independent completion.
| Description / size | GHMC plan identifies a green strip and states a tot-lot is to be fenced and maintained as greenery before occupancy certificate; no size is established in the supplied plan extract. |
|---|---|
| Declared progress / verified status | RERA amenity entry shows 0%; completion not independently verified. |
| Description / size | Listed in the RERA amenity schedule; no description or size supplied. |
|---|---|
| Declared progress / verified status | 0%; no completion evidence supplied. |
| Description / size | Listed as an aggregate recreational open-space item; no area supplied. |
|---|---|
| Declared progress / verified status | 0%; no completion evidence supplied. |
| Description / size | Listed in the RERA amenity schedule; no dimensions supplied. |
|---|---|
| Declared progress / verified status | 0%; no completion evidence supplied. |
Utilities, building services & safety
Water and drainage: The plan lists a sump, overhead water tank and percolating well. A drawing entry specifies separate underground static water storage of 25,000 litres and a separate residential terrace tank of 25,000 litres. The RERA amenity schedule marks water supply and sewerage as “YES,” but does not establish source, treatment capacity, STP details, reuse arrangements or completed installation.
Electrical and waste: The plan identifies space for a transformer and a garbage house; it also lists a garbage bin. The RERA amenity schedule marks an electrical meter room, sub-station or receiving station “YES.” No electrical backup capacity or waste-processing details are supplied.
Fire safety and circulation: Fire protection and fire safety are listed in the RERA amenity schedule, with no percentage or system specification supplied. The GHMC plan states that fire-safety and related services are to be executed under qualified technical supervision. The supplied evidence does not establish completed systems or statutory clearance.
Access and vertical transportation: The plan lists a lift and a watchman room, but gives no lift capacity or number of lifts. It specifies one entry and one exit, each with minimum width 4.5 m and height clearance 5 m. No accessible-route or ramp details are supplied.
Location, access & connectivity
The official project identity places the site at Mamatha Nagar, Uppal mandal, Medchal-Malkajgiri district, PIN 500039. The filed land record identifies Survey No. 23 PART and plots 42, 43, 44P, 53P, 54 AND 55. The plan records roads adjoining the site boundaries, including 25 WIDE ROAD on the east and west and 30 WIDE ROAD on the south.
The supplied location data gives a distance of 1.2 km to Financial District (Nanakramguda). No public-transport details or further measured access distances are provided.
Developer & development status
The registered promoter is Banala Goverdhan, shown in the project record as BANALA. The legal entity type, corporate identifier, registered office and official contact details are not established in the supplied material. The project’s Form B is a promoter declaration: it identifies BANALA GOVERDHAN as promoter and includes undertakings concerning title, project funds, audits, pending approvals and completion.
The project record states a proposed completion date of 01/09/2025; Form B gives a completion undertaking written as “01-02:2025.” No dated progress report or independently verified construction status is supplied, and no occupancy or completion certificate appears in the available project documents.
Approvals, official records & documents
TG-RERA registration certificate, P02200002015: Form C records registration under section 5 for SREE SAI BALAJI DWARAKAMAYEE RESIDENCY BLOCK I, issued 06/07/2020 and valid to 01/09/2025; no extension is recorded in the supplied certificate.
GHMC building permit, 2/C3/13251/2019: Filed building-permit material identifies a residential stilt-plus-five-floor building on Survey No. 23 PART. The plan records approval date 05-09-2019; the building-permit order extract records 04 September, 2019.
GHMC proposed building plan: Records 20 units, 18 proposed parking spaces, the building configuration, area labels and stated plan conditions.
Promoter Form B: Promoter declaration identifying BANALA GOVERDHAN and stating title, encumbrance, funds, audit, approval and completion undertakings.
Occupancy/completion certificate: None supplied. The GHMC plan states that an occupancy certificate is required before occupation.
The supplied record does not include an independently verified site-progress report or an occupancy/completion certificate.
Other registrations of Sree Sai Balaji Dwarakamayee Residency
Frequently asked questions
Is SREE SAI BALAJI DWARAKAMAYEE RESIDENCY BLOCK I registered with Telangana RERA?
Yes. SREE SAI BALAJI DWARAKAMAYEE RESIDENCY BLOCK I is registered with the Telangana Real Estate Regulatory Authority as P02200002015; the registration status is New Project.
Who is the developer of SREE SAI BALAJI DWARAKAMAYEE RESIDENCY BLOCK I?
The promoter named in the RERA registration is BANALA.
Where is SREE SAI BALAJI DWARAKAMAYEE RESIDENCY BLOCK I located?
SREE SAI BALAJI DWARAKAMAYEE RESIDENCY BLOCK I is in MAMATHA NAGAR, Uppal, Medchal-Malkajgiri, Telangana (500039).
When will SREE SAI BALAJI DWARAKAMAYEE RESIDENCY BLOCK I be completed?
The promoter's proposed date of completion filed with RERA is 01/09/2025. This is the promoter's declaration, not a guarantee.
More projects in Uppal