Siris Inara
SIRI CONSTRUCTIONS · Hanamkonda · RERA P00300000641
SIRIS INARA is a residential project in GOPALPUR(V), Hanamkonda mandal, Warangal Urban district, developed by the registered promoter SIRI CONSTRUCTIONS, a partnership. The project is on Survey No. 22, with a total land area of 8559.13 sqmts and net area of 8528.20 sqmts, and comprises 27 villas in a G+1 gated-community development. The homes are 3BHK, with RERA-filed saleable areas of 216.06–219.45 sqm. Its TG-RERA registration number is P00300000641, and the proposed completion date is 08/01/2024.
More from Siri Constructions · 2 projects →
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
11 items to check before you pay, 5 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Field | Project record |
|---|---|
| Registered project name | SIRIS INARA RERA record |
| Project type | Residential; the RERA filing identifies it as residential and the filed offering is 27 villas. RERA filing RERA unit table |
| Phase / registered portion | No phase name or phase number is disclosed. The registration is for the project identified at Survey No. 22. Land records |
| TG-RERA registration | P00300000641. The Form C certificate states registration under section 5, valid from 25/04/2019 to 08/01/2024; the certificate records no extension. |
| Registered promoter | SIRI CONSTRUCTIONS, a partnership. RERA filing Corporate record |
| RERA status shown in the supplied record | New Project; the stated registration period has ended. The current registration status beyond the certificate’s end date is not established by the supplied record. RERA filing |
Land and geographic identity
| Field | Project record |
|---|---|
| Locality / revenue village | GOPALPUR(V); the approval proceeding identifies Gopalpur Village. The drawing also labels the locality as “GOPALPUR TO BHEEMARAM.” RERA record |
| Mandal | Hanamkonda; also recorded as HANAMKONDA(M). RERA record |
| District | Warangal Urban in the RERA project identity; the approval proceeding refers to Warangal District. RERA record |
| PIN | 506001. RERA record |
| Project survey number(s) | Survey No. 22. No subdivision is disclosed. Land records |
| RERA-recorded site area | Total area 8559.13 sqmts; net area 8528.20 sqmts; area affected in road widening/FTL of Tanks/Nala Widening 30.93 sqmts. RERA filing |
| Approval proceeding extent | The proceeding OCR renders the extent as “85,59. 138 ts”; it is not a clear, normalized extent in that document. |
| Boundaries recorded in the RERA fields | East: LAND OF THIRUPATHI; West: LAND OF SAROJA DEVI AND 30 FEET ROAD; North: LAND OF DAYAKAR; South: LAND OF VASTALA. RERA filing |
Development identity
| Field | Project record |
|---|---|
| Sanctioning authority | Kakatiya Urban Development Authority (KUDA); the proceeding says sanctioned plans were forwarded to Greater Warangal Municipal Corporation. |
| Principal proceeding / plan references | Proceeding C1/1193/2018; plan reference D.P. No. 02/2019 and plan number D.P. No. 02/1 to 7/2019. The proceeding’s OCR gives the approval date as 09 -1-2019. |
| Development described in the proceeding | Group Housing Development Scheme, G+1 floor as a gated community. |
| Approved built-up area | Not established as a project-wide total in the supplied record. The site-plan sheets contain figures, but they do not provide a reliable project-wide approved built-up-area total. RERA filing |
| Building / unit scale | RERA records 27 total building units and 27 proposed building units (as per agreement). The unit record classifies these as 27 homes/villas. RERA filing RERA unit table |
| Sanctioned floor configuration | The KUDA proceeding and site-plan record describe G+1 / ground-plus-one-floor development. No separate basement, stilt or podium level is established in the supplied material. |
| Parking | The proceeding refers to garages and stilts approved for parking, but the supplied record does not establish a parking count or allocation schedule. |
Offering and status
| Field | Project record |
|---|---|
| RERA-filed unit type | 3BHK, filed as “TRIPLE BED ROOM” and “TRIPLE BEDROOM”; 27 units. RERA unit table RERA unit details |
| RERA-filed saleable area | 216.06–219.45 sqm (filed unit entries are 216.06 sqm for 26 units and 219.45 sqm for 1 unit). RERA unit details RERA unit details |
| Booked / available | Portal-read counts: 0 booked / 27 available. The portal record has no as-of date, so these counts are indicative. RERA unit table |
| Construction stage | No dated, independently verified construction-progress report or site inspection is supplied. The registration record alone does not establish present physical progress. |
| Completion date | The RERA project field gives proposed completion as 08/01/2024; the promoter’s Form B undertaking states 01/01/2024. RERA filing |
| Registration validity | 25/04/2019–08/01/2024, as stated on the registration certificate; registration validity and construction completion are separate records. |
| Occupancy / completion certificate | No occupancy or completion certificate is included in the supplied project documents. The KUDA proceeding says an occupancy certificate is compulsory before occupation. |
2. The project story
- SIRIS INARA is registered as a residential gated-community development on Survey No. 22, Gopalpur Village, Hanamkonda, Warangal Urban District. The RERA filing records a site of 8559.13 sqmts total area and 8528.20 sqmts net area, with 30.93 sqmts identified as affected by road widening/FTL of Tanks/Nala Widening. RERA record RERA filing
- The filed offering is 27 three-bedroom villas/homes. The KUDA proceeding describes a group housing development scheme as a gated community, G+1 floor, and records open-space, road, utility and mortgage-area provisions. The supplied record does not establish the current construction stage, completion of individual homes, or an occupancy certificate for any phase or unit. RERA unit table
- The RERA portal’s unit snapshot lists all 27 as available and none booked, but has no as-of date; treat that as an undated portal reading rather than a current sales confirmation. RERA unit table
3. Master plan, architecture & building design
- The KUDA proceeding describes a gated group-housing scheme of G+1 floor on Survey No. 22 and identifies the land as belonging to Smt Pingili Sumithra Devi and six others, with Siri Constructions as developer. It records plans forwarded to Greater Warangal Municipal Corporation, subject to conditions.
- The site-plan material records 10% open space and 817.37 SQ MTS as provided open space; the proceeding separately refers to 816.00sq:mts of open space. It also identifies service/utility areas, including an overhead tank, septic tank and transformer area, and records plots 01 and 16 as mortgage plots. These are drawing/proceeding disclosures; the supplied material does not verify that these spaces or facilities have been completed.
- The RERA land fields record 8559.13 sqmts total and 8528.20 sqmts net site area, while the project’s approved built-up-area total is not established in the supplied material. Floor-plan scans are pending measurement, so there is no software-measured carpet-area or room-layout description available for this review. RERA filing RERA filing Floor plans
- The principal building-related record is the KUDA proceeding C1/1193/2018, with plan reference D.P. No. 02/2019. Other submitted plan sheets contain different drawing/file references and some are not sufficient, on their extracted text, to establish a project-wide sanction or approved design detail.
4. Homes, configurations & floor plans
- The RERA filing lists 27 three-bedroom homes/villas. The recorded saleable-area figures are from the RERA unit data; no measured carpet-area figures are available because the supplied floor-plan scans have not been measured. RERA unit details Floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 3BHK (filed as “TRIPLE BED ROOM” / “TRIPLE BEDROOM”) | 27 | 0 | 27* | 216.06–219.45 sqm | Not measured | Not supplied |
\*The portal-read booking count has no as-of date and is indicative. RERA unit table
- Carpet area is not available from the supplied drawing review. The RERA saleable-area figures are not carpet-area measurements; the available material does not provide a loading calculation or unit-by-unit carpet-area schedule. RERA unit details Floor plans
5. Parking & vehicle circulation
- The KUDA proceeding states that garages and stilts approved for parking are to be used exclusively for vehicle parking and not converted or partitioned for another use. It does not state a total number of car or two-wheeler spaces, visitor or accessible-space provision, or unit-wise parking allocations.
- The site-plan and proceeding records identify plots/villas No. 1 and 16 as mortgage area; a drawing bay or mortgage designation does not establish an individual buyer’s parking allocation. The internal driveway and parking circulation arrangements are not sufficiently described in the supplied evidence.
6. Amenities, recreation & open spaces
- The RERA amenity list marks several infrastructure and open-space categories as available in the filing, but supplies no completion percentages beyond 0 and no independent verification of delivery. The KUDA proceeding also sets out conditions relating to greenery, a tot-lot and utility provisions. RERA amenities
| Description / size | Open-space provision shown as 817.37 SQ MTS on the site-plan sheet; proceeding records 816.00sq:mts and a tot-lot condition. |
|---|---|
| Evidence source | Site plan and KUDA proceeding; RERA amenity list |
| Declared progress / verified status | Filed as available; progress shown as 0 in amenity record. Completion not independently verified. |
| Description / size | No size or specific building description supplied. |
|---|---|
| Evidence source | RERA amenity list |
| Declared progress / verified status | Marked available; progress 0. No independent completion verification. |
| Description / size | 10% stated in the plan/proceeding material. |
|---|---|
| Declared progress / verified status | Plan/proceeding disclosure; delivery not independently verified. |
| Description / size | No total length or detailed specification supplied. |
|---|---|
| Evidence source | RERA amenity list; KUDA proceeding |
| Declared progress / verified status | Marked available; progress 0. No independent completion verification. |
- No project-specific clubhouse, gym, sports facility or indoor-recreation provision is established by the supplied RERA documents.
7. Utilities, building services & safety
- The filed amenity record lists water supply, sewerage, storm-water drains, sewage/sullage treatment and disposal, rainwater harvesting, solid-waste management, energy management, fire protection, electrical meter room/sub-station/receiving station and street lighting. These are filing categories; the record does not provide capacities, technical design details or independently verified completion status. RERA amenities
- The site-plan/proceeding material identifies an overhead tank, septic tank and transformer area. The KUDA proceeding also requires a rainwater-harvesting structure (percolation pit), safe separation from overhead electrical lines and that building services—including sanitation, plumbing, fire safety, lifts and electrical installations—be executed under qualified technical supervision. These are recorded plan conditions, not proof of completed installation or statutory compliance.
- No supplied project record establishes water source or storage capacity, an STP capacity, backup-power capacity, lift count or capacity, CCTV/access-control arrangements, accessible circulation, or fire-system specifications. The KUDA proceeding states that occupancy certification is compulsory before occupation and that public amenities such as water and electricity connections will be provided only on production of an occupancy certificate.
8. Location, access & connectivity
- The registered location is GOPALPUR(V), HANAMKONDA(M), WARANGAL URBAN(D), PIN 506001. The approval proceeding identifies Gopalpur Village, Hanamkonda and Warangal District. RERA record
- The submitted plan material refers to a 30' road and to road widening from an existing 30' road to 50' under ADP 30/2009. The KUDA proceeding also refers to road provision and roads handed over to Greater Warangal Municipal Corporation. These are plan/proceeding references; no supplied source provides measured distances to nearby landmarks or public transport.
9. Developer & development status
- The registered promoter is SIRI CONSTRUCTIONS, recorded as a partnership. The RERA project record lists authorized signatories MANDALA RAVINDAR REDDY and MAMATHA MANDALA; the project proceeding identifies Siri Constructions, represented by Managing Partner Sri M. Ravinder Reddy, as developer. RERA filing Parties record
- The promoter’s Form B affidavit is dated 4 April 2019 and undertakes completion by 01/01/2024. The project field gives a proposed completion date of 08/01/2024. No supplied record establishes a revised completion date, current construction progress, or an occupancy/completion certificate. RERA filing
- The RERA registration certificate gives the promoter office as “Village: Mandal: District: Ranga Reddy, Pin: 500072.” The supplied evidence does not establish an official website or project contact details.
10. Approvals, official records & documents
| Supplied evidence | Form C, registration P00300000641, project SIRIS INARA, issued 25/04/2019, stated validity to 08/01/2024. |
|---|---|
| Scope / note | Project registration record; no extension is recorded in the supplied certificate. |
| Supplied evidence | Proceeding C1/1193/2018; plan reference D.P. No. 02/2019; OCR date 09 -1-2019. |
|---|---|
| Scope / note | Sanctions a gated group-housing scheme on Survey No. 22, Gopalpur, and records conditions and transfer of open-space/road areas. |
| Supplied evidence | Extracted as a proceeding of KUDA for the G+1 gated community. |
|---|---|
| Scope / note | The supplied document extraction records sanctioning and conditions; no separate building-by-building commencement certificate is identified. |
| Supplied evidence | Site-plan sheet FILE.NO.C1/1/93/2018, plan reference D.P.NO. 2 /20189, and associated drawing sheets. |
|---|---|
| Scope / note | Drawing extracts describe the proposed scheme and land-use/service areas; some individual sheets do not establish a sanction decision or date. |
| Supplied evidence | Form B by Mandala Ravindar Reddy for SIRI CONSTRUCTIONS, dated 4 April 2019. |
|---|---|
| Scope / note | Promoter declaration and completion undertaking. |
| Supplied evidence | Not supplied. Document index |
|---|---|
| Scope / note | The KUDA proceeding states an occupancy certificate is compulsory before occupation. |
- The plan sheets 46685, 46687–46691, 46698–46702 also appear in the supplied project file; their extracted text is incomplete or does not, by itself, establish an approval decision or full project-wide sanction particulars.
1. Project at a glance
Project identity
Registered project name: SIRIS INARA
Project type: Residential; the RERA filing identifies it as residential and the filed offering is 27 villas.
Phase / registered portion: No phase name or phase number is disclosed. The registration is for the project identified at Survey No. 22.
TG-RERA registration: P00300000641. The Form C certificate states registration under section 5, valid from 25/04/2019 to 08/01/2024; the certificate records no extension.
Registered promoter: SIRI CONSTRUCTIONS, a partnership.
RERA status shown in the supplied record: New Project; the stated registration period has ended. The current registration status beyond the certificate’s end date is not established by the supplied record.
Land and geographic identity
Locality / revenue village: GOPALPUR(V); the approval proceeding identifies Gopalpur Village. The drawing also labels the locality as “GOPALPUR TO BHEEMARAM.”
Mandal: Hanamkonda; also recorded as HANAMKONDA(M).
District: Warangal Urban in the RERA project identity; the approval proceeding refers to Warangal District.
PIN: 506001.
Project survey number(s): Survey No. 22. No subdivision is disclosed.
RERA-recorded site area: Total area 8559.13 sqmts; net area 8528.20 sqmts; area affected in road widening/FTL of Tanks/Nala Widening 30.93 sqmts.
Approval proceeding extent: The proceeding OCR renders the extent as “85,59. 138 ts”; it is not a clear, normalized extent in that document.
Boundaries recorded in the RERA fields: East: LAND OF THIRUPATHI; West: LAND OF SAROJA DEVI AND 30 FEET ROAD; North: LAND OF DAYAKAR; South: LAND OF VASTALA.
Development identity
Sanctioning authority: Kakatiya Urban Development Authority (KUDA); the proceeding says sanctioned plans were forwarded to Greater Warangal Municipal Corporation.
Principal proceeding / plan references: Proceeding C1/1193/2018; plan reference D.P. No. 02/2019 and plan number D.P. No. 02/1 to 7/2019. The proceeding’s OCR gives the approval date as 09 -1-2019.
Development described in the proceeding: Group Housing Development Scheme, G+1 floor as a gated community.
Approved built-up area: Not established as a project-wide total in the supplied record. The site-plan sheets contain figures, but they do not provide a reliable project-wide approved built-up-area total.
Building / unit scale: RERA records 27 total building units and 27 proposed building units (as per agreement). The unit record classifies these as 27 homes/villas.
Sanctioned floor configuration: The KUDA proceeding and site-plan record describe G+1 / ground-plus-one-floor development. No separate basement, stilt or podium level is established in the supplied material.
Parking: The proceeding refers to garages and stilts approved for parking, but the supplied record does not establish a parking count or allocation schedule.
Offering and status
RERA-filed unit type: 3BHK, filed as “TRIPLE BED ROOM” and “TRIPLE BEDROOM”; 27 units.
RERA-filed saleable area: 216.06–219.45 sqm (filed unit entries are 216.06 sqm for 26 units and 219.45 sqm for 1 unit).
Booked / available: Portal-read counts: 0 booked / 27 available. The portal record has no as-of date, so these counts are indicative.
Construction stage: No dated, independently verified construction-progress report or site inspection is supplied. The registration record alone does not establish present physical progress.
Completion date: The RERA project field gives proposed completion as 08/01/2024; the promoter’s Form B undertaking states 01/01/2024.
Registration validity: 25/04/2019–08/01/2024, as stated on the registration certificate; registration validity and construction completion are separate records.
Occupancy / completion certificate: No occupancy or completion certificate is included in the supplied project documents. The KUDA proceeding says an occupancy certificate is compulsory before occupation.
2. The project story
- SIRIS INARA is registered as a residential gated-community development on Survey No. 22, Gopalpur Village, Hanamkonda, Warangal Urban District. The RERA filing records a site of 8559.13 sqmts total area and 8528.20 sqmts net area, with 30.93 sqmts identified as affected by road widening/FTL of Tanks/Nala Widening.
- The filed offering is 27 three-bedroom villas/homes. The KUDA proceeding describes a group housing development scheme as a gated community, G+1 floor, and records open-space, road, utility and mortgage-area provisions. The supplied record does not establish the current construction stage, completion of individual homes, or an occupancy certificate for any phase or unit.
- The RERA portal’s unit snapshot lists all 27 as available and none booked, but has no as-of date; treat that as an undated portal reading rather than a current sales confirmation.
3. Master plan, architecture & building design
- The KUDA proceeding describes a gated group-housing scheme of G+1 floor on Survey No. 22 and identifies the land as belonging to Smt Pingili Sumithra Devi and six others, with Siri Constructions as developer. It records plans forwarded to Greater Warangal Municipal Corporation, subject to conditions.
- The site-plan material records 10% open space and 817.37 SQ MTS as provided open space; the proceeding separately refers to 816.00sq:mts of open space. It also identifies service/utility areas, including an overhead tank, septic tank and transformer area, and records plots 01 and 16 as mortgage plots. These are drawing/proceeding disclosures; the supplied material does not verify that these spaces or facilities have been completed.
- The RERA land fields record 8559.13 sqmts total and 8528.20 sqmts net site area, while the project’s approved built-up-area total is not established in the supplied material. Floor-plan scans are pending measurement, so there is no software-measured carpet-area or room-layout description available for this review.
- The principal building-related record is the KUDA proceeding C1/1193/2018, with plan reference D.P. No. 02/2019. Other submitted plan sheets contain different drawing/file references and some are not sufficient, on their extracted text, to establish a project-wide sanction or approved design detail.
4. Homes, configurations & floor plans
- The RERA filing lists 27 three-bedroom homes/villas. The recorded saleable-area figures are from the RERA unit data; no measured carpet-area figures are available because the supplied floor-plan scans have not been measured.
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 3BHK (filed as “TRIPLE BED ROOM” / “TRIPLE BEDROOM”) | 27 | 0 | 27* | 216.06–219.45 sqm | Not measured | Not supplied |
\*The portal-read booking count has no as-of date and is indicative.
- Carpet area is not available from the supplied drawing review. The RERA saleable-area figures are not carpet-area measurements; the available material does not provide a loading calculation or unit-by-unit carpet-area schedule.
5. Parking & vehicle circulation
- The KUDA proceeding states that garages and stilts approved for parking are to be used exclusively for vehicle parking and not converted or partitioned for another use. It does not state a total number of car or two-wheeler spaces, visitor or accessible-space provision, or unit-wise parking allocations.
- The site-plan and proceeding records identify plots/villas No. 1 and 16 as mortgage area; a drawing bay or mortgage designation does not establish an individual buyer’s parking allocation. The internal driveway and parking circulation arrangements are not sufficiently described in the supplied evidence.
6. Amenities, recreation & open spaces
- The RERA amenity list marks several infrastructure and open-space categories as available in the filing, but supplies no completion percentages beyond 0 and no independent verification of delivery. The KUDA proceeding also sets out conditions relating to greenery, a tot-lot and utility provisions.
| Description / size | Open-space provision shown as 817.37 SQ MTS on the site-plan sheet; proceeding records 816.00sq:mts and a tot-lot condition. |
|---|---|
| Evidence source | Site plan and KUDA proceeding; RERA amenity list |
| Declared progress / verified status | Filed as available; progress shown as 0 in amenity record. Completion not independently verified. |
| Description / size | No size or specific building description supplied. |
|---|---|
| Evidence source | RERA amenity list |
| Declared progress / verified status | Marked available; progress 0. No independent completion verification. |
| Description / size | 10% stated in the plan/proceeding material. |
|---|---|
| Declared progress / verified status | Plan/proceeding disclosure; delivery not independently verified. |
| Description / size | No total length or detailed specification supplied. |
|---|---|
| Evidence source | RERA amenity list; KUDA proceeding |
| Declared progress / verified status | Marked available; progress 0. No independent completion verification. |
- No project-specific clubhouse, gym, sports facility or indoor-recreation provision is established by the supplied RERA documents.
7. Utilities, building services & safety
- The filed amenity record lists water supply, sewerage, storm-water drains, sewage/sullage treatment and disposal, rainwater harvesting, solid-waste management, energy management, fire protection, electrical meter room/sub-station/receiving station and street lighting. These are filing categories; the record does not provide capacities, technical design details or independently verified completion status.
- The site-plan/proceeding material identifies an overhead tank, septic tank and transformer area. The KUDA proceeding also requires a rainwater-harvesting structure (percolation pit), safe separation from overhead electrical lines and that building services—including sanitation, plumbing, fire safety, lifts and electrical installations—be executed under qualified technical supervision. These are recorded plan conditions, not proof of completed installation or statutory compliance.
- No supplied project record establishes water source or storage capacity, an STP capacity, backup-power capacity, lift count or capacity, CCTV/access-control arrangements, accessible circulation, or fire-system specifications. The KUDA proceeding states that occupancy certification is compulsory before occupation and that public amenities such as water and electricity connections will be provided only on production of an occupancy certificate.
8. Location, access & connectivity
- The registered location is GOPALPUR(V), HANAMKONDA(M), WARANGAL URBAN(D), PIN 506001. The approval proceeding identifies Gopalpur Village, Hanamkonda and Warangal District.
- The submitted plan material refers to a 30' road and to road widening from an existing 30' road to 50' under ADP 30/2009. The KUDA proceeding also refers to road provision and roads handed over to Greater Warangal Municipal Corporation. These are plan/proceeding references; no supplied source provides measured distances to nearby landmarks or public transport.
9. Developer & development status
- The registered promoter is SIRI CONSTRUCTIONS, recorded as a partnership. The RERA project record lists authorized signatories MANDALA RAVINDAR REDDY and MAMATHA MANDALA; the project proceeding identifies Siri Constructions, represented by Managing Partner Sri M. Ravinder Reddy, as developer.
- The promoter’s Form B affidavit is dated 4 April 2019 and undertakes completion by 01/01/2024. The project field gives a proposed completion date of 08/01/2024. No supplied record establishes a revised completion date, current construction progress, or an occupancy/completion certificate.
- The RERA registration certificate gives the promoter office as “Village: Mandal: District: Ranga Reddy, Pin: 500072.” The supplied evidence does not establish an official website or project contact details.
10. Approvals, official records & documents
| Supplied evidence | Form C, registration P00300000641, project SIRIS INARA, issued 25/04/2019, stated validity to 08/01/2024. |
|---|---|
| Scope / note | Project registration record; no extension is recorded in the supplied certificate. |
| Supplied evidence | Proceeding C1/1193/2018; plan reference D.P. No. 02/2019; OCR date 09 -1-2019. |
|---|---|
| Scope / note | Sanctions a gated group-housing scheme on Survey No. 22, Gopalpur, and records conditions and transfer of open-space/road areas. |
| Supplied evidence | Extracted as a proceeding of KUDA for the G+1 gated community. |
|---|---|
| Scope / note | The supplied document extraction records sanctioning and conditions; no separate building-by-building commencement certificate is identified. |
| Supplied evidence | Site-plan sheet FILE.NO.C1/1/93/2018, plan reference D.P.NO. 2 /20189, and associated drawing sheets. |
|---|---|
| Scope / note | Drawing extracts describe the proposed scheme and land-use/service areas; some individual sheets do not establish a sanction decision or date. |
| Supplied evidence | Form B by Mandala Ravindar Reddy for SIRI CONSTRUCTIONS, dated 4 April 2019. |
|---|---|
| Scope / note | Promoter declaration and completion undertaking. |
| Supplied evidence | Not supplied. |
|---|---|
| Scope / note | The KUDA proceeding states an occupancy certificate is compulsory before occupation. |
- The plan sheets 46685, 46687–46691, 46698–46702 also appear in the supplied project file; their extracted text is incomplete or does not, by itself, establish an approval decision or full project-wide sanction particulars.
Frequently asked questions
Is SIRIS INARA registered with Telangana RERA?
Yes. SIRIS INARA is registered with the Telangana Real Estate Regulatory Authority as P00300000641; the registration status is New Project.
Who is the developer of SIRIS INARA?
The promoter named in the RERA registration is SIRI CONSTRUCTIONS.
Where is SIRIS INARA located?
SIRIS INARA is in GOPALPUR(V),HANAMKONDA(M),WARANGAL URBAN(D)., Hanamkonda, Telangana (506001).
When will SIRIS INARA be completed?
The promoter's proposed date of completion filed with RERA is 08/01/2024. This is the promoter's declaration, not a guarantee.
More projects in Gopalpur