Shiva Estates
CHAPALAMADUGU SIVA PRASAD · Rangareddy · RERA P02400008564
SHIVA ESTATES is a plotted development in Burgula, Farooqnagar Mandal, Ranga Reddy District. The registered promoter is CHAPALAMADUGU SIVA PRASAD. The project covers 8,600 sq m and provides for 32 residential plots; tower, floor and plot-size configurations are not stated. It is registered under TG-RERA P02400008564, with a proposed completion date of 29/06/2026.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
9 items to check before you pay, 5 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Item | Record |
|---|---|
| Registered project name | SHIVA ESTATES RERA record |
| Project type | Plotted development / residential plot layout RERA record RERA filing |
| Phase or registered portion | Phase not separately identified; TG-RERA record describes the registered project on Survey No. 503/P RERA record |
| TG-RERA registration | P02400008564 RERA record |
| Registration validity | 29/06/2024 to 29/06/2026 RERA record |
| Registered promoter | CHAPALAMADUGU SIVA PRASAD; proprietor, identified in the RERA record as an individual promoter RERA filing Corporate record |
| RERA status in supplied record | “New Project”; certificate records registration for the stated validity period RERA filing |
Land and geographic identity
| Item | Record |
|---|---|
| Locality | BURGULA; the filed project documents also identify the site as Chintaguda RERA record RERA filing |
| Revenue village | Burgula Revenue Village; RERA project fields also state Chinthaguda as Village/City RERA filing |
| Mandal / district | Farooqnagar Mandal, Ranga Reddy District RERA record |
| PIN | 500132 RERA record RERA filing |
| Project survey identifiers | Survey No. 503/P; the final-layout letter identifies Survey No. 503/PART. The RERA registration certificate states Survey No. 503/P. RERA record Land records |
| Registered site extent | RERA land details: 8,600 sq m total and 8,600.00 sq m net RERA filing |
| Layout extent stated in approval records | Draft layout: Ac. 2.125 Cents; 10,285.00 sq yd. Final HMDA layout: 8,599.67 sq m. |
| Boundaries | North, south, east and west boundaries are recorded as “NA” in the supplied parcel record Land records |
Development identity
| Item | Record |
|---|---|
| Principal draft-layout approval | TLP.No. 07 2024 / DCPO / RR.; approved 29.06.2024 by the District Town and Country Planning Officer, R.R. District, with development delegated to Chintaguda Gram Panchayat Approvals record |
| Final layout release | HMDA final layout permit 0943/HMDA/SWFL/2025, dated 06/11/2025 Approvals record |
| Approved built-up area | 5,068 sq m recorded in the RERA fields; the supplied layout documents describe a plotted layout rather than buildings RERA filing |
| Plot count | 32 plots in the draft-layout approval and final-layout letter |
| Building / floor configuration | Not applicable as a recorded project-wide building configuration: the approvals concern a plotted layout. Individual dwelling permissions are not supplied. |
| Parking | No project-wide parking count or parking layout is supplied. The final-layout land-use schedule records common parking area as 0.0. |
Offering and status
| Item | Record |
|---|---|
| Unit type | Residential plots; the sanctioned layout provides 32 plots |
| Plot sizes / RERA-filed saleable-area range | Not available in the supplied unit schedule or extracted layout data RERA unit table Layout record |
| Booked / available counts | Not disclosed in the supplied records RERA unit table |
| Construction stage | The supplied approvals establish layout approvals and final layout release; no independently verified site-progress assessment is supplied. |
| RERA completion date | 29/06/2026, as recorded in the RERA project fields RERA filing |
| Occupancy / completion certificate | The file includes an architect’s completion certificate recording HMDA occupancy certificate No. 008497/HMDA/02502/SW FL/SKP1/2025 dated 06-11-2025, without a clearly specified tower or separate phase scope. |
| Registration validity versus completion | Registration validity ends 29/06/2026; this is distinct from the filed project completion date and the occupancy certificate recorded in the documents. RERA filing |
2. The project story
SHIVA ESTATES is registered as a plotted residential development in the Burgula Revenue Village / Chintaguda area of Farooqnagar Mandal, Ranga Reddy District. The RERA record identifies Survey No. 503/P, while the final-layout letter describes the land as Survey No. 503/PART. RERA record
The filed draft layout provides for 32 residential plots, roads and open space. It also identifies Plots 29–32, stated as 919.60 sq yd, as mortgage plots for the Gram Panchayat under the draft approval conditions. The final HMDA layout letter records a later final-layout release and refers to gift and relinquishment instruments concerning roads, open spaces, utilities and the mortgage plots.
The records support describing the project as a layout development, not as an apartment or multi-building scheme. An architect’s certificate and an HMDA occupancy certificate are present in the file; the supplied extracts do not establish the specific scope of the certificate by plot or phase, or provide an independent assessment of on-site progress.
3. Master plan, architecture & building design
The project’s approved physical organization is a residential plot layout. The draft technical layout records 32 plots on 10,285.00 sq yd, with 58.95% plotted area, 31.05% roads area and 10.00% open space. It specifies road widths of 33'-0" and 40'-0".
The final HMDA layout letter records a net layout of 8,599.67 sq m, comprising 5,053.81 sq m plotted area (58.77%), 2,676.17 sq m road area (31.12%) and 869.69 sq m open space (10.11%). The final schedule records 0 for buffer area, social infrastructure, common parking, utilities, amenities and green belt.
No individual dwelling designs, building footprints, floor configurations or architectural plans are supplied. The draft approval states that plots are for detached single-family dwelling houses; residential building permissions are to be considered under the applicable building rules.
4. Homes, configurations & floor plans
The project is a plotted layout, not an apartment configuration. The draft approval and final HMDA letter each record 32 plots. The supplied records do not provide a plot-by-plot schedule, plot-size bands, booked or available counts, or RERA-filed saleable areas. RERA unit table Layout record
The available drawing files are not measured: two drawings are listed, both with scans pending. Accordingly, no software-measured plot or dwelling areas can be reported. Floor plans
5. Parking & vehicle circulation
The final HMDA land-use schedule records common parking area as 0.0; no separate parking-space count, parking plan, visitor provision, accessible parking, vehicle ramp or plot-level parking allocation is supplied.
The draft approval specifies roads of 33'-0" and 40'-0" and requires roads to remain open for access to neighboring sites. The final-layout letter also states that roads are to remain open for free public access. These are layout-road conditions, not evidence of a particular parking arrangement.
6. Amenities, recreation & open spaces
| Description / size | Draft approval: 10.00%, Ac. 0.2125 Cents; final HMDA schedule: 869.69 sq m, 10.11% |
|---|---|
| Declared progress / verified status | Shown in layout records; physical completion not independently verified |
| Description / size | Draft approval records 31.05%, Ac. 0.66 Cents; final schedule records 2,676.17 sq m, 31.12%; road widths 33'-0" and 40'-0" |
|---|---|
| Declared progress / verified status | Shown in layout records; physical completion not independently verified |
| Description / size | No area or facility specified; final layout schedule records social infrastructure as 0 |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | No completed facility verified |
| Description / size | No project-specific RERA-filed facility or size supplied |
|---|---|
| Evidence source | RERA amenities Document index |
| Declared progress / verified status | Not established in the supplied project records |
The vendor record lists a swimming pool, gym, children’s play area and clubhouse, among other facilities. These are vendor-listed claims, not facilities established by the supplied RERA layout or final-layout schedule. Promoter website
7. Utilities, building services & safety
The final HMDA layout letter describes the layout as provided with water supply, sewerage and drainage-disposal systems, street lighting and a rainwater-harvesting structure, and states that these civic amenities are to be properly maintained. Its extract does not give capacities or establish independent verification of operation.
The draft approval requires the developer to undertake, under Gram Panchayat supervision, road formation, underground or side drains and nala channelization, greenery and avenue planting, rainwater-harvesting pits, open-space fencing, street lighting and electricity facilities, a sewerage-disposal system and protected water supply. These are approval conditions, not proof of completed works.
The RERA amenity fields mark water supply, sewerage, storm-water drains, street lighting, water conservation/rainwater harvesting, energy management and fire protection/safety as available (“YES”), but record 0% progress. No system capacities, fire-system details, electrical substation specifications, waste-management details, security arrangements or accessibility features are supplied. RERA amenities
8. Location, access & connectivity
The registered project location is Chinthaguda, Farooqnagar, Ranga Reddy, with Burgula recorded as the revenue village and PIN 500132. The approval documents describe the site as being at Chintaguda, in Burgula Revenue Village. RERA record RERA filing
The layout approvals specify internal road widths of 33'-0" and 40'-0". The supplied location data lists the nearest sampled Outer Ring Road interchange at approximately 38.4 km. No public-transport details or other verified approach-road distances are supplied. Location record
9. Developer & development status
The registered promoter is CHAPALAMADUGU SIVA PRASAD, identified in the RERA record as a proprietor. The supplied record does not provide a separate corporate registration number, official website or project contact details. RERA filing Corporate record
The RERA project fields give a proposed completion date of 29/06/2026 and registration validity through 29/06/2026. These dates describe separate matters. The file also contains an architect’s completion certificate and an HMDA occupancy certificate dated 06-11-2025; the supplied extract does not specify a plot-by-plot or phase-specific scope for that certificate. RERA filing
10. Approvals, official records & documents
| Identifier / date | P02400008564; valid 29/06/2024–29/06/2026 |
|---|---|
| What the supplied record establishes | Registration of SHIVA ESTATES and the registered promoter |
| Identifier / date | TLP.No. 07 2024 / DCPO / RR.; 29.06.2024 |
|---|---|
| What the supplied record establishes | Draft approval for a 32-plot residential layout in Survey No. 503/P, with conditions and mortgage plots |
| Identifier / date | 03/2024/DTCPO/RR; 24-06-2024 |
|---|---|
| What the supplied record establishes | Chintaguda Gram Panchayat layout-plan record for Survey No. 503; includes park/open-space and road information |
| Identifier / date | 0943/HMDA/SWFL/2025; 06/11/2025 |
|---|---|
| What the supplied record establishes | Final layout release for 32 plots, identified as Survey No. 503/PART |
| Identifier / date | Doc. No. 9200/2024; 08/07/2024 |
|---|---|
| What the supplied record establishes | Cited for roads, open spaces, social infrastructure and utilities handed to the local authority |
| Identifier / date | Doc. No. 13415/2024; 25/09/2024 |
|---|---|
| What the supplied record establishes | Cited in relation to relinquishment of the mortgage plots |
| Identifier / date | 008497/HMDA/02502/SW FL/SKP1/2025; 06-11-2025 |
|---|---|
| What the supplied record establishes | Architect’s certificate records completion and the stated HMDA occupancy certificate; certificate scope is not specified by plot or separate phase in the supplied extract |
The supplied evidence does not include the complete layout drawing sheets or a plot-by-plot schedule. The project profile above is therefore limited to the extracted RERA and approval records identified here. Document index Floor plans
1. Project at a glance
Project identity
Registered project name: SHIVA ESTATES
Project type: Plotted development / residential plot layout
Phase or registered portion: Phase not separately identified; TG-RERA record describes the registered project on Survey No. 503/P
TG-RERA registration: P02400008564
Registration validity: 29/06/2024 to 29/06/2026
Registered promoter: CHAPALAMADUGU SIVA PRASAD; proprietor, identified in the RERA record as an individual promoter
RERA status in supplied record: “New Project”; certificate records registration for the stated validity period
Land and geographic identity
Locality: BURGULA; the filed project documents also identify the site as Chintaguda
Revenue village: Burgula Revenue Village; RERA project fields also state Chinthaguda as Village/City
Mandal / district: Farooqnagar Mandal, Ranga Reddy District
PIN: 500132
Project survey identifiers: Survey No. 503/P; the final-layout letter identifies Survey No. 503/PART. The RERA registration certificate states Survey No. 503/P.
Registered site extent: RERA land details: 8,600 sq m total and 8,600.00 sq m net
Layout extent stated in approval records: Draft layout: Ac. 2.125 Cents; 10,285.00 sq yd. Final HMDA layout: 8,599.67 sq m.
Boundaries: North, south, east and west boundaries are recorded as “NA” in the supplied parcel record
Development identity
Principal draft-layout approval: TLP.No. 07 2024 / DCPO / RR.; approved 29.06.2024 by the District Town and Country Planning Officer, R.R. District, with development delegated to Chintaguda Gram Panchayat
Final layout release: HMDA final layout permit 0943/HMDA/SWFL/2025, dated 06/11/2025
Approved built-up area: 5,068 sq m recorded in the RERA fields; the supplied layout documents describe a plotted layout rather than buildings
Plot count: 32 plots in the draft-layout approval and final-layout letter
Building / floor configuration: Not applicable as a recorded project-wide building configuration: the approvals concern a plotted layout. Individual dwelling permissions are not supplied.
Parking: No project-wide parking count or parking layout is supplied. The final-layout land-use schedule records common parking area as 0.0.
Offering and status
Unit type: Residential plots; the sanctioned layout provides 32 plots
Plot sizes / RERA-filed saleable-area range: Not available in the supplied unit schedule or extracted layout data
Booked / available counts: Not disclosed in the supplied records
Construction stage: The supplied approvals establish layout approvals and final layout release; no independently verified site-progress assessment is supplied.
RERA completion date: 29/06/2026, as recorded in the RERA project fields
Occupancy / completion certificate: The file includes an architect’s completion certificate recording HMDA occupancy certificate No. 008497/HMDA/02502/SW FL/SKP1/2025 dated 06-11-2025, without a clearly specified tower or separate phase scope.
Registration validity versus completion: Registration validity ends 29/06/2026; this is distinct from the filed project completion date and the occupancy certificate recorded in the documents.
2. The project story
SHIVA ESTATES is registered as a plotted residential development in the Burgula Revenue Village / Chintaguda area of Farooqnagar Mandal, Ranga Reddy District. The RERA record identifies Survey No. 503/P, while the final-layout letter describes the land as Survey No. 503/PART.
The filed draft layout provides for 32 residential plots, roads and open space. It also identifies Plots 29–32, stated as 919.60 sq yd, as mortgage plots for the Gram Panchayat under the draft approval conditions. The final HMDA layout letter records a later final-layout release and refers to gift and relinquishment instruments concerning roads, open spaces, utilities and the mortgage plots.
The records support describing the project as a layout development, not as an apartment or multi-building scheme. An architect’s certificate and an HMDA occupancy certificate are present in the file; the supplied extracts do not establish the specific scope of the certificate by plot or phase, or provide an independent assessment of on-site progress.
3. Master plan, architecture & building design
The project’s approved physical organization is a residential plot layout. The draft technical layout records 32 plots on 10,285.00 sq yd, with 58.95% plotted area, 31.05% roads area and 10.00% open space. It specifies road widths of 33'-0" and 40'-0".
The final HMDA layout letter records a net layout of 8,599.67 sq m, comprising 5,053.81 sq m plotted area (58.77%), 2,676.17 sq m road area (31.12%) and 869.69 sq m open space (10.11%). The final schedule records 0 for buffer area, social infrastructure, common parking, utilities, amenities and green belt.
No individual dwelling designs, building footprints, floor configurations or architectural plans are supplied. The draft approval states that plots are for detached single-family dwelling houses; residential building permissions are to be considered under the applicable building rules.
4. Homes, configurations & floor plans
The project is a plotted layout, not an apartment configuration. The draft approval and final HMDA letter each record 32 plots. The supplied records do not provide a plot-by-plot schedule, plot-size bands, booked or available counts, or RERA-filed saleable areas.
The available drawing files are not measured: two drawings are listed, both with scans pending. Accordingly, no software-measured plot or dwelling areas can be reported.
5. Parking & vehicle circulation
The final HMDA land-use schedule records common parking area as 0.0; no separate parking-space count, parking plan, visitor provision, accessible parking, vehicle ramp or plot-level parking allocation is supplied.
The draft approval specifies roads of 33'-0" and 40'-0" and requires roads to remain open for access to neighboring sites. The final-layout letter also states that roads are to remain open for free public access. These are layout-road conditions, not evidence of a particular parking arrangement.
6. Amenities, recreation & open spaces
| Description / size | Draft approval: 10.00%, Ac. 0.2125 Cents; final HMDA schedule: 869.69 sq m, 10.11% |
|---|---|
| Declared progress / verified status | Shown in layout records; physical completion not independently verified |
| Description / size | Draft approval records 31.05%, Ac. 0.66 Cents; final schedule records 2,676.17 sq m, 31.12%; road widths 33'-0" and 40'-0" |
|---|---|
| Declared progress / verified status | Shown in layout records; physical completion not independently verified |
| Description / size | No area or facility specified; final layout schedule records social infrastructure as 0 |
|---|---|
| Declared progress / verified status | No completed facility verified |
| Description / size | No project-specific RERA-filed facility or size supplied |
|---|---|
| Declared progress / verified status | Not established in the supplied project records |
The vendor record lists a swimming pool, gym, children’s play area and clubhouse, among other facilities. These are vendor-listed claims, not facilities established by the supplied RERA layout or final-layout schedule.
7. Utilities, building services & safety
The final HMDA layout letter describes the layout as provided with water supply, sewerage and drainage-disposal systems, street lighting and a rainwater-harvesting structure, and states that these civic amenities are to be properly maintained. Its extract does not give capacities or establish independent verification of operation.
The draft approval requires the developer to undertake, under Gram Panchayat supervision, road formation, underground or side drains and nala channelization, greenery and avenue planting, rainwater-harvesting pits, open-space fencing, street lighting and electricity facilities, a sewerage-disposal system and protected water supply. These are approval conditions, not proof of completed works.
The RERA amenity fields mark water supply, sewerage, storm-water drains, street lighting, water conservation/rainwater harvesting, energy management and fire protection/safety as available (“YES”), but record 0% progress. No system capacities, fire-system details, electrical substation specifications, waste-management details, security arrangements or accessibility features are supplied.
8. Location, access & connectivity
The registered project location is Chinthaguda, Farooqnagar, Ranga Reddy, with Burgula recorded as the revenue village and PIN 500132. The approval documents describe the site as being at Chintaguda, in Burgula Revenue Village.
The layout approvals specify internal road widths of 33'-0" and 40'-0". The supplied location data lists the nearest sampled Outer Ring Road interchange at approximately 38.4 km. No public-transport details or other verified approach-road distances are supplied.
9. Developer & development status
The registered promoter is CHAPALAMADUGU SIVA PRASAD, identified in the RERA record as a proprietor. The supplied record does not provide a separate corporate registration number, official website or project contact details.
The RERA project fields give a proposed completion date of 29/06/2026 and registration validity through 29/06/2026. These dates describe separate matters. The file also contains an architect’s completion certificate and an HMDA occupancy certificate dated 06-11-2025; the supplied extract does not specify a plot-by-plot or phase-specific scope for that certificate.
10. Approvals, official records & documents
| Identifier / date | P02400008564; valid 29/06/2024–29/06/2026 |
|---|---|
| What the supplied record establishes | Registration of SHIVA ESTATES and the registered promoter |
| Identifier / date | TLP.No. 07 2024 / DCPO / RR.; 29.06.2024 |
|---|---|
| What the supplied record establishes | Draft approval for a 32-plot residential layout in Survey No. 503/P, with conditions and mortgage plots |
| Identifier / date | 03/2024/DTCPO/RR; 24-06-2024 |
|---|---|
| What the supplied record establishes | Chintaguda Gram Panchayat layout-plan record for Survey No. 503; includes park/open-space and road information |
| Identifier / date | 0943/HMDA/SWFL/2025; 06/11/2025 |
|---|---|
| What the supplied record establishes | Final layout release for 32 plots, identified as Survey No. 503/PART |
| Identifier / date | Doc. No. 9200/2024; 08/07/2024 |
|---|---|
| What the supplied record establishes | Cited for roads, open spaces, social infrastructure and utilities handed to the local authority |
| Identifier / date | Doc. No. 13415/2024; 25/09/2024 |
|---|---|
| What the supplied record establishes | Cited in relation to relinquishment of the mortgage plots |
| Identifier / date | 008497/HMDA/02502/SW FL/SKP1/2025; 06-11-2025 |
|---|---|
| What the supplied record establishes | Architect’s certificate records completion and the stated HMDA occupancy certificate; certificate scope is not specified by plot or separate phase in the supplied extract |
The supplied evidence does not include the complete layout drawing sheets or a plot-by-plot schedule. The project profile above is therefore limited to the extracted RERA and approval records identified here.
Frequently asked questions
Is SHIVA ESTATES registered with Telangana RERA?
Yes. SHIVA ESTATES is registered with the Telangana Real Estate Regulatory Authority as P02400008564; the registration status is New Project.
Who is the developer of SHIVA ESTATES?
The promoter named in the RERA registration is CHAPALAMADUGU SIVA PRASAD.
Where is SHIVA ESTATES located?
SHIVA ESTATES is in BURGULA, Chinthaguda, Farooqnagar, Rangareddy, Telangana (500132).
When will SHIVA ESTATES be completed?
The promoter's proposed date of completion filed with RERA is 29/06/2026. This is the promoter's declaration, not a guarantee.