Sai Mantara Towers
PAVAN ATTAL · Nizamabad · RERA P03100008841
SAI MANTARA TOWERS is a residential apartment project at Bypass Road, Goopanpally / Gopanpalle, NIZAMABAD RURAL (NEW), Nizamabad. The registered promoter is PAVAN ATTAL. The project has a land area of 1677.06 sq.m and comprises one residential building, Building A, with 1 Stilt + 5 upper floors and 60 apartments: 35 1BHK and 25 2BHK. Its TG-RERA registration number is P03100008841, and the promoter’s Form B declares completion by 19/07/2027.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
7 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Item | Project record |
|---|---|
| Registered name | SAI MANTARA TOWERS RERA record |
| Project type / phase | Residential apartment project; registered portion or phase is not separately named in the supplied record. The filed plan identifies one residential building, Building A. RERA record |
| TG-RERA registration | P03100008841 RERA record |
| Registration validity | 20/07/2024 to 19/07/2027, unless extended by the Authority. This is the registration-validity period, not a statement of construction progress or occupancy status. |
| Registered promoter | PAVAN ATTAL; the promoter is identified in the filed record as a proprietorship. RERA record Corporate record |
| RERA status | New Project; registration certificate on file. RERA record |
Land and geographic identity
| Item | Project record |
|---|---|
| Locality | Bypass Road, Goopanpally / Gopanpalle RERA record RERA filing |
| Revenue village | Gopanpalle (also rendered GOOPANPALLY in the approval-plan extraction) RERA record |
| Mandal / district / PIN | NIZAMABAD RURAL (NEW) / Nizamabad / 503001 RERA record RERA filing |
| Project survey numbers and subdivisions, as recorded | 411/B1, 411/B2, 411/B5, 411/B3, 411/B2 & 411/B3 AND PART OF SURVEY NOS. 411/C4/1/1/1/1/1/1 & 411/ C4/2/1/1/1 RERA filing |
| Survey references in the approval documents | 411/B1, 411/B2, 411/B5, 411/B3, 411/C4/1/1/1/1/1/1, 411/C4/2/1/1/1 |
| Registered site extent | 1677.06 sq.m RERA filing |
| Net / total land area | Net Area: 1677.06 sq.m; Total Area: 1677.06 sq.m RERA filing |
| Boundaries | East: Apartment of CNR Homes; West: Existing wide main road 10 MT; North: Part of open place of owners; South: Land of Sri Katipally Narendra Reddy. RERA filing |
Development identity
| Item | Project record |
|---|---|
| Sanctioning authority | Nizamabad Municipality/Municipal Corporation Approvals record |
| Principal building approval | 0037/BP/3072/2024, approved 20 July 2024 Approvals record |
| Related file number | 006060/BP/NIZA/3072/0050/2024 Approvals record |
| Approved building | One residential building: Building A, 1 Stilt + 5 upper floors |
| Approved area figures | Total proposed built-up area excluding parking: 4093.85 sq.m; total proposed built-up area including parking: 5014.25 sq.m; parking area: 920.40 sq.m. These are the filed plan’s labels; they are not carpet or saleable area. |
| Height figures in filed plan | BLDG HT: 14.50 MT; Total height: 20.20mt; Height excluding Stilt Floor: 14.50 mt; Height from GL: 17.20 mt |
| Units | 60 units in the approval-plan extraction and 60 RERA-filed units. RERA unit table |
| Parking | Filed plan states No of Cars Proposed: 29 and Proposed parking area: 920.40 sq.m. |
Offering and status
| Item | Project record |
|---|---|
| Filed configurations | 1BHK: 35 units; 2BHK: 25 units RERA unit table RERA unit details |
| RERA-filed saleable area | 1BHK: 84.27 sq.m; 2BHK: 84.72 sq.m RERA unit table RERA unit details |
| Booked / available | Portal-derived counts show 0 booked and 60 available (35 1BHK and 25 2BHK). The portal record has no as-of date; treat counts as indicative. RERA unit table RERA unit details |
| Construction stage | The project is recorded as a new project, with proposed development; no independently verified site-progress figure is supplied. RERA record RERA amenities |
| Completion dates | Promoter’s Form B declares completion by 19/07/2027. The RERA certificate is valid to 19/07/2027. |
| OC / completion certificate | No occupancy or completion certificate is supplied for the building. The commencement approval requires an OC before occupation. |
2. The project story
- SAI MANTARA TOWERS is registered as a residential apartment project at Bypass Road, Goopanpally, in Gopanpalle village, Nizamabad district. The filed plan describes a single residential building, Building A, with a stilt and five upper floors, on a site of 1677.06 sq.m. The approval-plan instrument describes the proposal as a residential apartment construction on part of Open Plot Nos. 12 and 13. RERA record RERA filing
- The registered offering comprises 60 apartments: 35 filed as 1BHK and 25 as 2BHK. Portal-derived booking figures show all 60 as available and none booked, but the source record does not carry a retrieval date. No construction-progress percentage or independent site inspection evidence is supplied, so the project’s physical stage cannot be confirmed from this material. RERA unit table RERA unit details
- The promoter’s Form B undertaking states a completion date of 19/07/2027. The registration certificate separately records registration validity through 19/07/2027, unless extended. No OC or completion certificate is included in the supplied documents; the building approval says an OC is required before occupation.
3. Master plan, architecture & building design
- The filed approval documents describe one residential building, Building A, on a site of 1677.06 sq.m, with 1 Stilt + 5 upper floors. The plan records 4,093.85 sq.m as proposed built-up area excluding parking and 5,014.25 sq.m including parking; it separately records 920.40 sq.m of parking area. These are approval-plan area labels, not RERA-filed carpet or saleable-area figures.
- The approval-plan extraction also records 756.70 sq.m as vacant plot area and lists a tot-lot and green strip. The commencement approval identifies setbacks of Front 3.00 m and 5.00 m, Rear 5.00 m, Side I 5.00 m and Side II 5.00 m. The supplied material does not establish floor-by-floor apartment arrangement, building footprint, lifts, stairs, or common-area dimensions.
- The approved building-permit record identifies Building A and its stilt-plus-five-floor configuration. It also lists the related layout permit 18/2013/DTCPO/NZB and LTP licence TS/030032/2024 in the project approval records.
4. Homes, configurations & floor plans
The TG-RERA filing lists 60 units in two configurations. Saleable area below is the RERA-filed figure. “Measured carpet area” and “Loading” are not available in the supplied drawing data. The floor-plan dataset reports two drawings but zero measured; it therefore supplies no software-measured room or carpet-area figures. RERA unit table RERA unit details Floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 1BHK | 35 | 0 | 35 | 84.27 sq.m | Not supplied | Not supplied |
| 2BHK | 25 | 0 | 25 | 84.72 sq.m | Not supplied | Not supplied |
The booking and availability figures are portal-derived and have no recorded as-of date, so they are indicative. The supplied drawings have not produced measured apartment layouts, room dimensions, orientation, balcony or utility measurements. RERA unit table RERA unit details Floor plans
5. Parking & vehicle circulation
- The filed approval plan records 920.40 sq.m of proposed parking area and 29 proposed cars. It also lists a required parking area of 900.65 sq.m. The commencement approval states that cellar and stilt areas approved for parking are to be used exclusively for vehicle parking, without partition walls or rolling shutters.
- The supplied records do not establish a separate visitor or accessible-parking count, two-wheeler count, parking allocation to individual apartments, or a verified spaces-per-home figure. A parking bay shown or counted in an approval plan does not, by itself, establish exclusive ownership or allocation to a buyer.
6. Amenities, recreation & open spaces
The filed approval and amenity records identify a tot-lot, green strip and rainwater harvesting; the commencement approval also requires a garbage house and space for a transformer. Amenity records show 0% progress for the listed items, and no independent completion verification is supplied. RERA amenities
| Description / size | Area recorded as 0 sq.m in the commencement-approval extraction; approval-plan conditions call for fencing and greenery before OC. |
|---|---|
| Declared progress / verified status | Amenity record: 0%; completion not independently verified. RERA amenities |
| Description / size | Green strip listed in the approval-plan extraction; periphery planting and maintenance are specified in its conditions. |
|---|---|
| Declared progress / verified status | Amenity record: 0%; completion not independently verified. RERA amenities |
| Description / size | Approval records list rainwater harvesting; commencement approval specifies 2 RWHPs and a rainwater-harvesting structure. |
|---|---|
| Declared progress / verified status | Amenity record: 0%; completion not independently verified. RERA amenities |
No clubhouse, indoor recreation facility, sports facility or community-building size is established by the supplied project evidence.
7. Utilities, building services & safety
- The RERA amenity record marks water supply, sewerage, storm-water drains, rainwater harvesting and an electrical meter room/sub-station/receiving station as available, while reporting 0% progress for the listed amenities. The commencement approval requires a rainwater-harvesting structure, transformer space and an on-site garbage house. These records describe filed or approved provisions; they do not establish that the facilities are complete or operational. RERA amenities
- The approval-plan conditions refer to dual piping and EV-charging infrastructure requirements, and specify that parking places are to have EV charging infrastructure in accordance with the cited standards. The supplied material does not confirm installation, capacity or operational status. The record does not provide water-source or storage capacity, STP capacity or reuse arrangements, electrical backup capacity, lift count or capacity, or detailed fire-safety systems and clearances.
- The commencement approval requires an occupancy certificate before occupation and states that the tot-lot is to be fenced and maintained as greenery before OC. No OC is present in the supplied documents.
8. Location, access & connectivity
- The registered location is BYPASS ROAD, GOOPANPALLY, Gopanpalle village, NIZAMABAD RURAL (NEW), Nizamabad, Telangana, PIN 503001. The approval-plan record describes a 10.00MT WIDE MAINROAD and also lists road and passage dimensions, including a 40'-0" wide east road, 33'-0" wide road, 80'-0" wide road, 150'-0" wide ring road, 2.00 M. wide passage and 4.50M driveway. These are plan-record references; the supplied data does not establish that each is a direct project access route. RERA record RERA filing
- The location dataset gives the nearest sampled Outer Ring Road interchange at approximately 123.0 km. No public-transport details or independently verified nearby-landmark distances are supplied. Location record
9. Developer & development status
- The registered promoter is PAVAN ATTAL, identified in the project record as a proprietorship. The listed promoter address is B, Nizamabad, Goopanpally, Bypass Road, Goopanpally, Nizamabad Rural (New), Nizamabad, 503001. ATTAL PAVAN is listed as authorized signatory. A separate corporate registration identifier is not supplied. Corporate record Parties record
- In Form B dated 22 Augnt 24, the promoter declares legal title to the land, states that it is free from encumbrances, and undertakes completion by 19/07/2027. These are promoter declarations, not independent findings about title or construction progress. No official project website or contact number is provided in the supplied project records.
10. Approvals, official records & documents
| Identifier / date | P03100008841; valid 20/07/2024–19/07/2027, unless extended |
|---|---|
| Scope and evidence | Form C certificate for SAI MANTARA TOWERS, with Pavan Attal identified as promoter. |
| Identifier / date | 0037/BP/3072/2024; 20 July 2024 |
|---|---|
| Scope and evidence | Nizamabad Municipality/Municipal Corporation approval for Building A, one stilt plus five upper floors. |
| Identifier / date | 006060/BP/NIZA/3072/0050/2024 |
|---|---|
| Scope and evidence | Approval record for the residential building. |
| Identifier / date | L/21/NUDA/2021; layout permit 18/2013/DTCPO/NZB |
|---|---|
| Scope and evidence | Filed plan record identifies the proposed apartment building, site extent and survey references. |
| Identifier / date | TS/030032/2024 |
|---|---|
| Scope and evidence | Listed in the approval-plan record. |
| Identifier / date | Dated 22 Augnt 24 |
|---|---|
| Scope and evidence | Promoter’s filed title, encumbrance, fund-management and completion declarations. |
| Identifier / date | 0037/BP/3072/2024 |
|---|---|
| Scope and evidence | Approval conditions require commencement notice and an occupancy certificate before occupation; no OC is supplied in the reviewed material. |
The supplied approvals establish the recorded building-permit details and the registration record. They do not include an occupancy or completion certificate, and the available floor-plan data contains no completed software measurements. Floor plans
1. Project at a glance
Project identity
Registered name: SAI MANTARA TOWERS
Project type / phase: Residential apartment project; registered portion or phase is not separately named in the supplied record. The filed plan identifies one residential building, Building A.
TG-RERA registration: P03100008841
Registration validity: 20/07/2024 to 19/07/2027, unless extended by the Authority. This is the registration-validity period, not a statement of construction progress or occupancy status.
Registered promoter: PAVAN ATTAL; the promoter is identified in the filed record as a proprietorship.
RERA status: New Project; registration certificate on file.
Land and geographic identity
Locality: Bypass Road, Goopanpally / Gopanpalle
Revenue village: Gopanpalle (also rendered GOOPANPALLY in the approval-plan extraction)
Mandal / district / PIN: NIZAMABAD RURAL (NEW) / Nizamabad / 503001
Project survey numbers and subdivisions, as recorded: 411/B1, 411/B2, 411/B5, 411/B3, 411/B2 & 411/B3 AND PART OF SURVEY NOS. 411/C4/1/1/1/1/1/1 & 411/ C4/2/1/1/1
Survey references in the approval documents: 411/B1, 411/B2, 411/B5, 411/B3, 411/C4/1/1/1/1/1/1, 411/C4/2/1/1/1
Registered site extent: 1677.06 sq.m
Net / total land area: Net Area: 1677.06 sq.m; Total Area: 1677.06 sq.m
Boundaries: East: Apartment of CNR Homes; West: Existing wide main road 10 MT; North: Part of open place of owners; South: Land of Sri Katipally Narendra Reddy.
Development identity
Sanctioning authority: Nizamabad Municipality/Municipal Corporation
Principal building approval: 0037/BP/3072/2024, approved 20 July 2024
Related file number: 006060/BP/NIZA/3072/0050/2024
Approved building: One residential building: Building A, 1 Stilt + 5 upper floors
Approved area figures: Total proposed built-up area excluding parking: 4093.85 sq.m; total proposed built-up area including parking: 5014.25 sq.m; parking area: 920.40 sq.m. These are the filed plan’s labels; they are not carpet or saleable area.
Height figures in filed plan: BLDG HT: 14.50 MT; Total height: 20.20mt; Height excluding Stilt Floor: 14.50 mt; Height from GL: 17.20 mt
Units: 60 units in the approval-plan extraction and 60 RERA-filed units.
Parking: Filed plan states No of Cars Proposed: 29 and Proposed parking area: 920.40 sq.m.
Offering and status
Filed configurations: 1BHK: 35 units; 2BHK: 25 units
RERA-filed saleable area: 1BHK: 84.27 sq.m; 2BHK: 84.72 sq.m
Booked / available: Portal-derived counts show 0 booked and 60 available (35 1BHK and 25 2BHK). The portal record has no as-of date; treat counts as indicative.
Construction stage: The project is recorded as a new project, with proposed development; no independently verified site-progress figure is supplied.
Completion dates: Promoter’s Form B declares completion by 19/07/2027. The RERA certificate is valid to 19/07/2027.
OC / completion certificate: No occupancy or completion certificate is supplied for the building. The commencement approval requires an OC before occupation.
2. The project story
- SAI MANTARA TOWERS is registered as a residential apartment project at Bypass Road, Goopanpally, in Gopanpalle village, Nizamabad district. The filed plan describes a single residential building, Building A, with a stilt and five upper floors, on a site of 1677.06 sq.m. The approval-plan instrument describes the proposal as a residential apartment construction on part of Open Plot Nos. 12 and 13.
- The registered offering comprises 60 apartments: 35 filed as 1BHK and 25 as 2BHK. Portal-derived booking figures show all 60 as available and none booked, but the source record does not carry a retrieval date. No construction-progress percentage or independent site inspection evidence is supplied, so the project’s physical stage cannot be confirmed from this material.
- The promoter’s Form B undertaking states a completion date of 19/07/2027. The registration certificate separately records registration validity through 19/07/2027, unless extended. No OC or completion certificate is included in the supplied documents; the building approval says an OC is required before occupation.
3. Master plan, architecture & building design
- The filed approval documents describe one residential building, Building A, on a site of 1677.06 sq.m, with 1 Stilt + 5 upper floors. The plan records 4,093.85 sq.m as proposed built-up area excluding parking and 5,014.25 sq.m including parking; it separately records 920.40 sq.m of parking area. These are approval-plan area labels, not RERA-filed carpet or saleable-area figures.
- The approval-plan extraction also records 756.70 sq.m as vacant plot area and lists a tot-lot and green strip. The commencement approval identifies setbacks of Front 3.00 m and 5.00 m, Rear 5.00 m, Side I 5.00 m and Side II 5.00 m. The supplied material does not establish floor-by-floor apartment arrangement, building footprint, lifts, stairs, or common-area dimensions.
- The approved building-permit record identifies Building A and its stilt-plus-five-floor configuration. It also lists the related layout permit 18/2013/DTCPO/NZB and LTP licence TS/030032/2024 in the project approval records.
4. Homes, configurations & floor plans
The TG-RERA filing lists 60 units in two configurations. Saleable area below is the RERA-filed figure. “Measured carpet area” and “Loading” are not available in the supplied drawing data. The floor-plan dataset reports two drawings but zero measured; it therefore supplies no software-measured room or carpet-area figures.
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 1BHK | 35 | 0 | 35 | 84.27 sq.m | Not supplied | Not supplied |
| 2BHK | 25 | 0 | 25 | 84.72 sq.m | Not supplied | Not supplied |
The booking and availability figures are portal-derived and have no recorded as-of date, so they are indicative. The supplied drawings have not produced measured apartment layouts, room dimensions, orientation, balcony or utility measurements.
5. Parking & vehicle circulation
- The filed approval plan records 920.40 sq.m of proposed parking area and 29 proposed cars. It also lists a required parking area of 900.65 sq.m. The commencement approval states that cellar and stilt areas approved for parking are to be used exclusively for vehicle parking, without partition walls or rolling shutters.
- The supplied records do not establish a separate visitor or accessible-parking count, two-wheeler count, parking allocation to individual apartments, or a verified spaces-per-home figure. A parking bay shown or counted in an approval plan does not, by itself, establish exclusive ownership or allocation to a buyer.
6. Amenities, recreation & open spaces
The filed approval and amenity records identify a tot-lot, green strip and rainwater harvesting; the commencement approval also requires a garbage house and space for a transformer. Amenity records show 0% progress for the listed items, and no independent completion verification is supplied.
| Description / size | Area recorded as 0 sq.m in the commencement-approval extraction; approval-plan conditions call for fencing and greenery before OC. |
|---|---|
| Declared progress / verified status | Amenity record: 0%; completion not independently verified. |
| Description / size | Green strip listed in the approval-plan extraction; periphery planting and maintenance are specified in its conditions. |
|---|---|
| Declared progress / verified status | Amenity record: 0%; completion not independently verified. |
| Description / size | Approval records list rainwater harvesting; commencement approval specifies 2 RWHPs and a rainwater-harvesting structure. |
|---|---|
| Declared progress / verified status | Amenity record: 0%; completion not independently verified. |
No clubhouse, indoor recreation facility, sports facility or community-building size is established by the supplied project evidence.
7. Utilities, building services & safety
- The RERA amenity record marks water supply, sewerage, storm-water drains, rainwater harvesting and an electrical meter room/sub-station/receiving station as available, while reporting 0% progress for the listed amenities. The commencement approval requires a rainwater-harvesting structure, transformer space and an on-site garbage house. These records describe filed or approved provisions; they do not establish that the facilities are complete or operational.
- The approval-plan conditions refer to dual piping and EV-charging infrastructure requirements, and specify that parking places are to have EV charging infrastructure in accordance with the cited standards. The supplied material does not confirm installation, capacity or operational status. The record does not provide water-source or storage capacity, STP capacity or reuse arrangements, electrical backup capacity, lift count or capacity, or detailed fire-safety systems and clearances.
- The commencement approval requires an occupancy certificate before occupation and states that the tot-lot is to be fenced and maintained as greenery before OC. No OC is present in the supplied documents.
8. Location, access & connectivity
- The registered location is BYPASS ROAD, GOOPANPALLY, Gopanpalle village, NIZAMABAD RURAL (NEW), Nizamabad, Telangana, PIN 503001. The approval-plan record describes a 10.00MT WIDE MAINROAD and also lists road and passage dimensions, including a 40'-0" wide east road, 33'-0" wide road, 80'-0" wide road, 150'-0" wide ring road, 2.00 M. wide passage and 4.50M driveway. These are plan-record references; the supplied data does not establish that each is a direct project access route.
- The location dataset gives the nearest sampled Outer Ring Road interchange at approximately 123.0 km. No public-transport details or independently verified nearby-landmark distances are supplied.
9. Developer & development status
- The registered promoter is PAVAN ATTAL, identified in the project record as a proprietorship. The listed promoter address is B, Nizamabad, Goopanpally, Bypass Road, Goopanpally, Nizamabad Rural (New), Nizamabad, 503001. ATTAL PAVAN is listed as authorized signatory. A separate corporate registration identifier is not supplied.
- In Form B dated 22 Augnt 24, the promoter declares legal title to the land, states that it is free from encumbrances, and undertakes completion by 19/07/2027. These are promoter declarations, not independent findings about title or construction progress. No official project website or contact number is provided in the supplied project records.
10. Approvals, official records & documents
| Identifier / date | P03100008841; valid 20/07/2024–19/07/2027, unless extended |
|---|---|
| Scope and evidence | Form C certificate for SAI MANTARA TOWERS, with Pavan Attal identified as promoter. |
| Identifier / date | 0037/BP/3072/2024; 20 July 2024 |
|---|---|
| Scope and evidence | Nizamabad Municipality/Municipal Corporation approval for Building A, one stilt plus five upper floors. |
| Identifier / date | 006060/BP/NIZA/3072/0050/2024 |
|---|---|
| Scope and evidence | Approval record for the residential building. |
| Identifier / date | L/21/NUDA/2021; layout permit 18/2013/DTCPO/NZB |
|---|---|
| Scope and evidence | Filed plan record identifies the proposed apartment building, site extent and survey references. |
| Identifier / date | TS/030032/2024 |
|---|---|
| Scope and evidence | Listed in the approval-plan record. |
| Identifier / date | Dated 22 Augnt 24 |
|---|---|
| Scope and evidence | Promoter’s filed title, encumbrance, fund-management and completion declarations. |
| Identifier / date | 0037/BP/3072/2024 |
|---|---|
| Scope and evidence | Approval conditions require commencement notice and an occupancy certificate before occupation; no OC is supplied in the reviewed material. |
The supplied approvals establish the recorded building-permit details and the registration record. They do not include an occupancy or completion certificate, and the available floor-plan data contains no completed software measurements.
Other registrations of Sai Mantara Towers
Frequently asked questions
Is SAI MANTARA TOWERS registered with Telangana RERA?
Yes. SAI MANTARA TOWERS is registered with the Telangana Real Estate Regulatory Authority as P03100008841; the registration status is New Project.
Who is the developer of SAI MANTARA TOWERS?
The promoter named in the RERA registration is PAVAN ATTAL.
Where is SAI MANTARA TOWERS located?
SAI MANTARA TOWERS is in BYPASS ROAD, GOOPANPALLY, Gopanpalle, NIZAMABAD RURAL (NEW), Nizamabad, Telangana (503001).
When will SAI MANTARA TOWERS be completed?
The promoter's proposed date of completion filed with RERA is 19/11/2027. This is the promoter's declaration, not a guarantee.