RK OXYGEN VALLEY is a residential apartment project in Bollaram Village, Jinnaram Mandal, Sangareddy District, developed by registered promoter IDREAM SAI RK INFRA. The project has a site extent of 12,894.09 sq. m. and comprises five buildings: residential Blocks A, B, C and D, each with 1 Stilt + 5 upper floors, and a Club House with 1 Ground + 3 upper floors. The RERA unit record lists 190 homes: 40 2BHK units with a saleable area of 48.07 sq. m. and 150 3BHK units with a saleable area of 126.76 sq. m. It is registered under TG-RERA number P01100005792, and the promoter’s Form B undertaking states completion by 08.12.2025.

More from Idream Sai Rk Infra · 3 projects →

01What we found

Period endedTG-RERA registration ran to 8 Dec 2025 - check its extension on TG-RERA
14documents on file - each fact links to its page
9court cases on this project's land (survey 37, 40, Bollaram)
11items to check - 5 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

11 items to check before you pay, 5 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

1. Project at a glance

Project identity

FieldProject record
Registered project nameRK OXYGEN VALLEY RERA record
Project typeResidential apartment project RERA record
Phase / registered portionPhase details are not separately identified in the supplied record; five buildings are listed in the building approval
TG-RERA registrationP01100005792; Form C issued 15/03/2023; stated validity 15/03/2023–08/12/2025. The certificate records no extension. Registration validity is separate from the completion undertaking and does not establish occupancy certification.
Registered promoterIDREAM SAI RK INFRA, a partnership RERA record RERA filing
RERA statusRegistration certificate on file. The supplied certificate states validity through 08/12/2025 and no extension; current registration status is not verified here.

Land and geographic identity

FieldProject record
Locality / revenue villageBollaram Village; locality is also recorded as BOLLARAM VILLAGE RERA record Land records
Mandal / district / PINJinnaram Mandal, Sangareddy District, PIN 502325 RERA record
All filed survey numbers37/A, 37/AA, 38/A, 38/AA, 40/A & 40/AA RERA record Land records
Registered site extent12,894.09 sq. m. Land records
Net / total areaRERA land record states total and net area each 12,894.09 sq. m. and affected area 0 sq. m. Land records
BoundariesEast: ROAD; West: NEIGHBORS LAND; North: NEIGHBORS LAND; South: ORR SERVICE ROAD RERA filing

Development identity

FieldProject record
Sanctioning authorityHyderabad Metropolitan Development Authority (HMDA); plans are to be sanctioned and released by the delegated Bollaram Municipality / Municipal Corporation. Approvals record
Principal building approval005720/BP/HMDA/1113/MED/2022, approved 08 December 2022 Approvals record
Approved built-up area160,636.25 sq. m. RERA filing
BuildingsFive listed: Blocks A, B, C and D (residential), plus a Club House building
Floor configurationBlocks A–D: 1 Stilt + 5 upper floors each. Club House: 1 Ground + 3 upper floors.
Parking levelsStilt is specified for vehicle parking; a separate parking count, visitor provision and allocation by unit are not established in the supplied record.
Unit countsSanctioned-plan total: 190 residential units in the RERA filing summary; RERA unit record: 150 3BHK and 40 2BHK, total 190. RERA unit table RERA unit details
RERA-declared buildings / unitsFive buildings are reported in the RERA project fields; the RERA unit table records 190 residential units. RERA filing RERA unit table

Offering and status

FieldProject record
Unit types and RERA-filed saleable areas2BHK: 48.07 sq. m.; 3BHK: 126.76 sq. m. RERA unit table RERA unit details
Booked / availablePortal-derived counts show 0 booked and 40 available 2BHK units, and 0 booked and 150 available 3BHK units. The portal record has no stated as-of date, so counts are indicative. RERA unit table RERA unit details
Construction stageCurrent physical construction progress is not established by the supplied evidence. Document index
Completion datePromoter’s Form B undertaking states completion by 08.12.2025.
Occupancy / completion certificateNo occupancy certificate or completion certificate is included in the supplied project documents. The building approval requires an occupancy certificate before occupation. Document index

2. The project story

RK OXYGEN VALLEY is registered as a residential apartment project on land recorded in Bollaram Village, Jinnaram Mandal, Sangareddy District. Its filed land identity covers survey numbers 37/A, 37/AA, 38/A, 38/AA, 40/A and 40/AA, with a site extent of 12,894.09 sq. m. The RERA record gives a total and net site area of 12,894.09 sq. m., affected area of 0 sq. m., and approved built-up area of 160,636.25 sq. m. RERA record Land records RERA filing

The HMDA building approval describes four residential blocks—A, B, C and D—each with one stilt level and five upper floors, together with a separate Club House building with one ground and three upper floors. The RERA unit record lists 190 homes: 150 3BHK and 40 2BHK. RERA unit table

The promoter’s Form B affidavit undertakes completion by 08.12.2025. That is a promoter declaration, not independent evidence of construction progress or completion. The supplied documents do not establish the present construction stage, nor do they include an occupancy or completion certificate. Document index

3. Master plan, architecture & building design

The approval’s building schedule reports a residential building built-up area of 32,127.25 sq. m. and height of 14.9; the source extract does not state a unit alongside the height figure. The approval also records 2,587.40 sq. m. of built-up area mortgaged to HMDA.

The supplied approval names internal roads and road widths of 4.5 m, 3.0 m and 1.5 m, but the available extract does not establish their precise layout or whether those widths refer to vehicular or pedestrian circulation. No reliable drawing-derived evidence is supplied here for building footprints, flats per floor, lift or stair counts, tower arrangement, landscape areas or phase-wise construction organization.

The RERA record gives saleable areas for the homes; it does not provide carpet areas as a filed value in the unit table. The drawing-measured carpet-area information is presented separately below. RERA unit details Floor plans

4. Homes, configurations & floor plans

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
2BHK4004048.07 sq. m.Not measuredNot supplied
3BHK1500150126.76 sq. m.79.8–113.4 sq. m.; median 97.2 sq. m. (software-measured from drawings)23% (software-derived)

RERA unit counts, booked/available counts and saleable areas are from the project unit record; the portal counts have no stated as-of date. The 3BHK drawing measurements are software measurements, not RERA-filed carpet-area disclosures; the measurement record notes seven designs needing review. One drawing sheet remains pending scan review, and no 2BHK design was measured. RERA unit table RERA unit details Floor plans

For one 3BHK drawing, the first-floor plan identifies bedrooms, living/dining, kitchen, toilets, a sit-out, balcony and utility. The extracted drawing measurements include a living/dining area of 25.6 sq. m., kitchen of 8.36 sq. m., and bedrooms of 9.8, 9.49 and 14.4 sq. m.; the utility is separately measured at 3.84 sq. m. and the balcony is shown as 0.90 m wide. These are drawing-derived measurements, not RERA disclosures.

Saleable area and carpet area are not interchangeable: the RERA-filed saleable area is the figure in the table; drawing-measured carpet area is a separate software measurement. The supplied materials do not provide a verified room-by-room measurement schedule for every unit design or a separately filed balcony-area schedule. RERA unit details Floor plans

5. Parking & vehicle circulation

The HMDA approval specifies that the stilt / cellar is to be used exclusively for vehicle parking, without partition walls or rolling shutters. It also states that parking or construction is not permitted in setback areas. The supplied project record does not establish the number of sanctioned parking spaces, two-wheeler or visitor spaces, accessible bays, parking allocation for individual units, or EV charging provision. The approval’s statement about stilt use is not evidence that a particular bay is exclusively owned or allocated to a purchaser. Document index

6. Amenities, recreation & open spaces

The following facilities appear in the RERA amenity record. Its progress fields show 0% for each listed item; this is a portal-reported figure, not an independent site inspection. RERA amenities

FacilityDescription / sizeEvidence sourceDeclared progress / verified status
Internal Roads & FootpathsSize not statedRERA amenity record0%; not independently verified
Green Strip/TOT LOT/ParkSize not statedRERA amenity record0%; not independently verified
Community BuildingsSize not statedRERA amenity record; HMDA approval separately lists a Club House building0%; not independently verified
Aggregate area of recreational Open SpaceArea not statedRERA amenity record0%; not independently verified

The RERA amenity record also identifies water supply, sewerage/STP, storm-water drains, street lighting, sewage treatment and disposal, solid-waste management, rainwater harvesting, energy management, fire protection and electrical meter/sub-station/receiving facilities. These are site services and are covered under Utilities below. RERA amenities

The HMDA approval lists a Club House building but does not specify its rooms, recreational facilities, size or capacity in the supplied extraction. Marketing-listed amenities such as a swimming pool, gymnasium, multipurpose hall, jogging track and children’s play area are not established as RERA-declared or delivered facilities by the supplied project evidence. Promoter website

7. Utilities, building services & safety

The RERA amenity record marks water supply, sewerage (including STP), storm-water drains, street lighting, sewage treatment/disposal, solid-waste management, rainwater harvesting, energy management, fire protection and electrical meter-room/sub-station/receiving facilities. The record does not provide system capacities, supply sources, storage volumes, treatment specifications or verified completion status. Its listed amenity progress fields are 0%. RERA amenities

The HMDA approval requires rainwater-harvesting structures, an STP, a transformer and a garbage house within the premises. It also requires the municipality to ensure water supply, drainage and sewerage-disposal requirements, and requires fire and structural safety to be addressed by the owner, builder/developer, architect and structural engineer. These are approval conditions; the supplied evidence does not establish completion or operational testing.

The approval requires CC cameras and specifies an occupancy certificate before a building may be occupied. It also requires the stilt/cellar to remain for parking use. No lift count or capacity, backup-power capacity, fire-system specification, accessibility measures, CCTV installation status or waste-management operating arrangements are established in the supplied project documents. Document index

8. Location, access & connectivity

The official project location is Bollaram Village, Jinnaram Mandal, Sangareddy District, Telangana, PIN 502325. The cadastral parcel centroid is recorded at 17.51301, 78.51536. The project boundary description identifies a road to the east and the ORR service road to the south. RERA record Location record RERA filing

The nearest sampled Outer Ring Road interchange is recorded at approximately 5.6 km. No other verified distances or travel times are supplied in the project-location evidence. Location record

9. Developer & development status

The registered promoter is IDREAM SAI RK INFRA, recorded as a partnership, with GSTIN 36AAIFI0975L1ZY. The RERA project record gives an address at SHAPOOR NAGAR, BOLLARAM, BOLLARAM VILLAGE, JINNARAM, Sangareddy, PIN 502325. The TG-RERA certificate separately records the promoter office as Jeedimetla Village, Qutballapur Mandal, Medchal-Malkajgiri District, PIN 500055. RERA filing Corporate record Parties record

The Form B affidavit was made by Pratap Reddy Sanapu as an authorized signatory and declares a completion undertaking of 08.12.2025. The project registration certificate states a validity period ending 08/12/2025 and records no extension. These dates concern different matters: the Form B date is the promoter’s completion undertaking, while the certificate states registration validity. The supplied record does not establish current construction progress, subsequent extension, completion or occupancy certification. Document index

10. Approvals, official records & documents

TG-RERA registration certificate
Available evidenceForm C; P01100005792, issued 15/03/2023; stated validity through 08/12/2025; no extension recorded in the certificate
Scope / noteRK OXYGEN VALLEY; survey numbers 37/A, 37/AA, 38/A, 38/AA, 40/A and 40/AA
HMDA building approval
Available evidenceApproval 005720/BP/HMDA/1113/MED/2022, dated 08 December 2022
Scope / noteResidential blocks A–D and Club House building; technical approval, with plans to be sanctioned and released by Bollaram Municipality / Municipal Corporation
Form B promoter declaration
Available evidenceDated 27 January 2023; signed by Pratap Reddy Sanapu as authorized signatory
Scope / notePromoter declaration covering project land, encumbrances, account arrangements and completion undertaking
Layout / detailed plans
Available evidenceA layout-plan document entry is present, but the supplied record does not contain an extracted approved layout drawing or LP number
Scope / noteDetailed layout and drawing contents not established in the available evidence Document index HMDA
Occupancy / completion certificate
Available evidenceNot present in the supplied project documents
Scope / noteHMDA approval states that an occupancy certificate is compulsory before occupation Document index

The HMDA approval refers to mortgage document 37199, dated 03 November 2022, and records 2,587.40 sq. m. of built-up area mortgaged in favour of HMDA. The approval requires an occupancy certificate before occupation and before the mortgaged built-up area may be registered.

Frequently asked questions

Is RK OXYGEN VALLEY registered with Telangana RERA?

Yes. RK OXYGEN VALLEY is registered with the Telangana Real Estate Regulatory Authority as P01100005792; the registration status is New Project.

Who is the developer of RK OXYGEN VALLEY?

The promoter named in the RERA registration is IDREAM SAI RK INFRA.

Where is RK OXYGEN VALLEY located?

RK OXYGEN VALLEY is in BOLLARAM VILLAGE, BOLLARAM, JINNARAM, Sangareddy, Telangana (502325).

When will RK OXYGEN VALLEY be completed?

The promoter's proposed date of completion filed with RERA is 08/12/2025. This is the promoter's declaration, not a guarantee.